IR 05000482/2019004

From kanterella
(Redirected from ML20035C736)
Jump to navigation Jump to search
Integrated Inspection Report 05000482/2019004
ML20035C736
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 02/03/2020
From: O'Keefe N
NRC/RGN-IV/DRP/RPB-B
To: Reasoner C
Wolf Creek
References
EPID L-2019-004-0012 IR 2019004
Preceding documents:
Download: ML20035C736 (32)


Text

February 3, 2020

SUBJECT:

WOLF CREEK GENERATING STATION - INTEGRATED INSPECTION REPORT 05000482/2019004

Dear Mr. Reasoner:

On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station. On January 9, 2020, the NRC inspectors discussed the results of this inspection with Mr. J. McCoy, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA Russell L. Bywater Acting for/

Neil F. O'Keefe, Chief Reactor Projects Branch B Division of Reactor Projects

Docket No. 05000482 License No. NPF-42

Enclosure:

As stated

Inspection Report

Docket Number:

05000482

License Number:

NPF-42

Report Number:

05000482/2019004

Enterprise Identifier: I-2019-004-0012

Licensee:

Wolf Creek Nuclear Operating Corporation

Facility:

Wolf Creek Generating Station

Location:

Burlington, KS 66839

Inspection Dates:

October 1, 2019, to December 31, 2019

Inspectors:

D. Dodson, Senior Resident Inspector

C. Alldredge, Allegations/Enforcement Specialist

I. Anchondo-Lopez, Reactor Inspector

R. Azua, Inspection Programs & Assessment Team Leader

B. Baca, Resident Inspector

R. Bywater, Acting Senior Project Engineer

P. Elkmann, Senior Emergency Preparedness Inspector

S. Hedger, Emergency Preparedness Inspector

P. Jayroe, Reactor Inspector

J. Melfi, Project Engineer

A. Meyen, Physical Security Inspector

W. Sifre, Senior Reactor Inspector

M. Stafford, Acting Senior Resident Inspector

F. Thomas, Reactor Inspector

J. Vera, Resident Inspector

Approved By:

Neil F. O'Keefe, Chief

Reactor Projects Branch B

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000482/2017-003-00

[Atmospheric Relief Valve] and

[Main Steam Safety Valve]

Tornado Missile Vulnerabilities Result in Unanalyzed Condition 71153 Discussed LER 05000482/2019-001-00 Loss of Startup Transformer Results in Emergency Diesel Generator Actuation 71153 Closed LER 05000482/2019-002-00 Emergency Diesel Generator Inoperable Due to Temperature Control Valve Failure 71153 Closed

PLANT STATUS

Wolf Creek Generating Station began the inspection period shutdown for Refueling Outage 23. The reactor was restarted on November 5, 2019, and power ascension was commenced. The unit was returned to approximately rated thermal power on November 9, 2019, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems:
  • Refueling water storage tank

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Component cooling water train A on October 3, 2019
(2) Spent fuel pool cooling train B on November 18, 2019
(3) Containment purge system on December 27, 2019

71111.04S - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the residual heat removal system on November 8, 2019.

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Auxiliary building, elevation 1,974 feet, fire areas A-2 and A-3, on October 2, 2019
(2) Essential service water vertical loop chase, elevation 1,974 feet through 2,087 feet, fire area ESWC, on November 29, 2019
(3) Auxiliary building, elevation 2,026 feet, fire areas A-17 and A-18, on December 30, 2019
(4) Essential service water pump house, elevation 2,000 feet, fire areas ESWA and ESWB, on December 31, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (2 Samples)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Residual heat removal pump A room on October 10, 2019
(2) Spent fuel pool cooling train B room on October 17, 2019

71111.07A - Heat Sink Performance

Annual Review (IP Section 02.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Component cooling water heat exchanger train B on October 24, 2019

===71111.08P - Inservice Inspection Activities (PWR)

PWR Inservice Inspection Activities Sample (IP Section 03.01)===

(1) The inspectors verified that the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from September 28, 2019, to October 3, 2019:

03.01.a - Nondestructive Examination and Welding Activities

  • Ultrasonic examination, main feedwater loop 2, AE-4S026-A pipe to elbow
  • Ultrasonic examination, main feedwater loop 2, AE-4S026-B elbow to pipe
  • Radiographic examination, boron thermal regeneration, 17-434419-004 pipe to pipe
  • Dye penetrant, boron injection, EM-02-R008, pipe to pipe

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities

  • Visual examination of reactor head penetrations 1 through 79

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities

  • The inspector reviewed the following work orders associated with boric acid leaks: 19-453764-000, 19-453325-000, 19-453324-000, 19-453323-000, 19-

===451840-000, and 19-451734-000.

03.01.d - No steam generator tube inspections were performed this inspection period.

03.01.e - Problem Identification and Resolution

  • The inspector reviewed 31 condition reports associated with inservice and operating experience issues and concluded that nondestructive evaluation/inservice inspection related issues and operating experience are put into the corrective action program at a low threshold to ensure conditions and problems are identified.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

=

(1) The inspectors observed and evaluated licensed operator performance in the control room during reactor startup on November 5, 2019.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated just-in-time training for reactor startup on October 24, 2019.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Station blackout diesel generator control failure sample completed on October 23, 2019
(2) Residual heat removal system performance review completed on October 25, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Planned essential service water train B maintenance during the refueling outage on October 7, 2019
(2) Planned train swap activity control during the refueling outage on October 11, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (7 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Boric acid leak from normal charging check valve on October 21, 2019
(2) Essential service water train B traveling screen elevated vibrations on October 22, 2019
(3) Fuel assembly containing foreign material on October 24, 2019
(4) Digital rod position indication alarms prior to reactor restart on October 27, 2019
(5) Component cooling water to rad waste relief valve failed as found/as left tests on November 4, 2019
(6) Load shedder and emergency load sequencer testing methodology questions identified on October 18, 2019
(7) Main steam isolation action circuitry issue on November 7, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the following post-maintenance tests:

(1) Emergency diesel generator train B post-maintenance testing following outage maintenance on October 10, 2019
(2) Component cooling water heat exchanger train B following eddy current testing on October 18, 2019
(3) Emergency diesel generator train A post-maintenance testing following outage maintenance on October 18, 2019
(4) Component cooling water train B check valve post-maintenance testing on October 20, 2019
(5) Essential service water train B post maintenance testing activities on October 22, 2019
(6) Residual heat removal train B post-maintenance valve testing on October 22, 2019
(7) Containment cooler B post maintenance testing on October 27, 2019
(8) South electrical penetration room cooler post-maintenance testing on December 30, 2019

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Refueling Outage 23 activities from October 1 to November 6, 2019. The inspectors completed IP Sections 03.01.c, 03.01.d, and 03.01.e.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) STS-KJ-001A, Integrated [Diesel Generator] and Safeguards Actuation Test - Train A, Revision 65, on October 29, 2019, and STS-KJ-001B, Integrated [Diesel Generator] and Safeguards Actuation Test - Train B, Revision 63, on October 30, 2019

Inservice Testing (IP Section 03.01) (2 Samples)

(1) Train B essential service water vertical loop vacuum breaker valves (EF-V482 and EF-V484) inservice testing in accordance with STS KJ-001B, Integrated [Diesel Generator] and Safeguards Actuation Test - Train B, Revision 63, on October 29, 2019
(2) STS EF-100A, "[Essential Service Water] System Inservice Pump A & [Essential Service Water] A Check Valve Test," Revision 47, on November 2, 2019

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) STS PE-125, "[Local Leak Rate Test] Valve Lineup for Penetration 25," Revision 9, on October 17, 2019

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Sample)

(1) The inspectors evaluated the biennial emergency plan exercise conducted December 3, 2019. The exercise scenario simulated two seismic events, losses of vital safety-related electric buses, a partial loss of offsite power, a loss of coolant accident inside containment, and a containment penetration failure causing a filtered and monitored radiological release through the plant vent. The inspectors also observed the licensee's management critique on December 17, 2019, and participated at the Federal Emergency Management Agency Region VII public meeting conducted on December 6, 2019. The inspectors discussed the performance of the licensee emergency response organization and offsite responders with Federal Emergency Management Agency Region VII staff on December 6, 2019.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the Wolf Creek Radiological Emergency Response Plan, Revision 19, on December 4, 2019, and Revision 20, on December 11, 2019. These evaluations do not constitute NRC approval.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 02.01) (1 Sample)

The inspectors evaluated radiological hazards assessments and controls.

(1) The inspectors reviewed the following:

Radiological Surveys

  • Survey M-20190921-5, "Downpost Survey for Upper Cavity"
  • Survey M-20190924-21, "Bottom Mounted Instrumentation (BMI) Inspection,"

Under Vessel

Removal"

  • Survey M-20190927-25, "Refueling (RF) 23 Reactor Head Lift"
  • Survey M-20190930-3, "Valve Removal EM-V0212"
  • Survey M-20190930-22, "Reactor Head on Head Stand"
  • Survey M-20191002-18, "2047' Containment Weekly for Wednesday"
  • Survey M-20191003-14, "RadWaste Filter Change FEC01A"

Risk Significant Radiological Work Activities

  • Fuel building transfer canal entries for repair/inspection and decontamination activities
  • Radwaste filter change FEC01A
  • Reactor head lift
  • Reactor cavity activities
  • Under reactor vessel cavity ring and incore tunnel inspections

Air Sample Survey Records

  • Air Sample 19-0045, "Aux Building 2000' Filter (FBG06) Change Out"
  • Air Sample 19-0134, "Post Maintenance Survey inside Transfer Canal 2047' Fuel Building"
  • Air Sample 19-0143, "Grinding on SJHV0133 North Pipe Pen, Aux Building 2000' elevation"
  • Radwaste building filter pits
  • Train B safety injection pump room for EM-V0212 valve removal
  • Refueling outage (RF) 23 reactor head lift

Instructions to Workers (IP Section 02.02) (1 Sample)

The inspectors evaluated instructions to workers including radiation work permits used to access high radiation areas.

(1) The inspectors reviewed the following:

Radiation Work Packages

  • Radiation Work Permit 190061, "Fuel Building Transfer Canal Entry for Repair/Inspection and Decontamination of Fuel Building Transfer System and other work activities," Revision 1
  • Radiation Work Permit 191101, "Under Reactor Vessel (RV) Cavity Seal Ring Inspections (Annulus) Access," Revision 0
  • Radiation Work Permit 191102, "Incore Tunnel Inspections, Maintenance &

Decontamination," Revision 0

  • Radiation Work Permit 195001, "Reactor Cavity Decon Activities," Revision 0
  • Radiation Work Permit 196000, "Lower Refueling Cavity Pre & Post Flooding Maintenance Activities," Revision 1

Electronic Alarming Dosimeter Alarms The inspectors reviewed the licensee's corrective action program and selected five condition reports and associated documentation regarding electronic alarming dosimeter alarms for additional review:

  • Condition Report 120680
  • Condition Report 120975
  • Condition Report 121726
  • Condition Report 124071
  • Condition Report 131088

Labeling of Containers

  • Four radioactive material trash bags
  • Six barrels of steam generator sludge lancing material and TriNuke filters and hoses
  • Two dry active waste sealand containers

Contamination and Radioactive Material Control (IP Section 02.03) (1 Sample)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) The inspectors verified the following sealed sources are accounted for and are intact:
  • 98-CHL-041
  • 00-HPL-009
  • 03-HPL-028
  • 82-HPL-088/82-HPL-089
  • 84-HPL-326
  • 92-HPL-009

Radiological Hazards Control and Work Coverage (IP Section 02.04) (1 Sample)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) The inspectors also reviewed the following radiological work package for areas with airborne radioactivity:

Contaminated Systems Valve and Pump RWP," Revision 1

  • Radiation Work Permit 190061, "Fuel Building Transfer Canal Entry,"

Revision 1

  • Radiation Work Permit 194482, "Reactor Vessel (RV) Head Disassembly to include, Canopy Seal Clamp (Vendor Activities)," Revision 2
  • Radiation Work Permit 194483, "Reactor Vessel (RV) Head Reassembly to include, Canopy Seal Clamp (Vendor Activities)," Revision 1

High Radiation Area and Very High Radiation Area Controls (IP Section 02.05) (1 Sample)

(1) The inspectors evaluated risk-significant high radiation area and very high radiation area controls.

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 02.06) (1 Sample)

(1) The inspectors evaluated radiation worker performance and radiation protection technician proficiency.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Engineering Controls (IP Section 02.01) (1 Sample)

The inspectors evaluated airborne controls and radioactive monitoring.

(1) The inspectors reviewed the following:

Installed Ventilation Systems

  • Fuel building emergency exhaust system
  • Containment purge exhaust system

Temporary Ventilation System Setups

  • 500 cubic feet per minute high efficiency particulate air unit, Radiation Work Permit 194050

Portable or Installed Monitoring Systems

  • Containment 2047 feet
  • Containment 2000 feet

Use of Respiratory Protection Devices (IP Section 02.02) (1 Sample)

The inspectors evaluated the licensees use of respiratory protection devices by:

(1) Observing in-field applications; verifying the licensee validated the level of protection provided by the devices; inspecting the material condition of devices, reviewing records and certification of devices issued for use; reviewing the qualifications of workers that use the devices; and observing workers donning, doffing, and testing devices.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 02.03) (1 Sample)

The inspectors evaluated self-contained breathing apparatus program implementation.

(1) The inspectors reviewed the following:

Status and Surveillance Records for Self-Contained Breathing Apparatus

  • S/N 115S1543108008
  • S/N 115S1543016987
  • S/N 115S1543009024

Self-Contained Breathing Apparatus Fit for On-Shift Operators

  • On Shift Operators, Tuesday, October 1, 2019, Day Shift
  • On Shift Operators, Thursday, October 3, 2019, Day Shift

Self-Contained Breathing Apparatus Maintenance Check

  • S/N 115S1543108008
  • S/N 115S1543016987
  • S/N 115S1543009024

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicator submittals listed below:

EP01: Drill/Exercise Performance (IP Section 02.12)===

(1) The inspectors reviewed Drill/Exercise Performance opportunities conducted between April 2018 and September 2019.

EP02: ERO Drill Participation (IP Section 02.13) (1 Sample)

(1) The inspectors reviewed ERO Drill Participation data for drills and exercises conducted between April 2018 and September 2019.

EP03: Alert & Notification System Reliability (IP Section 02.14) (1 Sample)

(1) The inspectors reviewed tests of offsite emergency warning sirens conducted between April 2018 and September 2019.

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)

(1) October 1, 2018, to September 30, 2019

MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)

(1) October 1, 2018, to September 30, 2019

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) October 1, 2018, to September 30, 2019

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) April 1, 2018, to September 30, 2019

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) April 1, 2018, to September 30, 2019

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in the area of safety conscious work environment (SCWE) and assessed the licensee's progress in addressing the SCWE theme.

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) NRC Operating Experience Smart Sample 2018/01, Evaluation of Licensee Actions Taken in Response to 10 CFR Part 21 Notification of the Potential Existence of Defects Related to Control Rod Drive Mechanism Thermal Sleeves
(2) Fuel identified with foreign material during the refueling outage

71153 - Followup of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000482/2019-001-00, "Loss of Startup Transformer Results in Emergency Diesel Generator Actuation" (ADAMS Accession: ML19281C061). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER; therefore, no performance deficiency was identified. The inspectors also concluded that no violation of NRC requirements occurred. This licensee event report is closed.
(2) LER 5000482/2019-002-00, "Emergency Diesel Generator Inoperable Due to Temperature Control Valve Failure" (ADAMS Accession: ML19295D729). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER; therefore, no performance deficiency was identified. The inspectors also concluded that no violation of NRC requirements occurred. This licensee event report is closed.

INSPECTION RESULTS

Observation: Semiannual Trend Review 71152 The inspectors reviewed the licensees corrective action program for potential adverse trends in the area of Safety-Conscious Work Environment (SCWE).

SCWE

The NRC conducted semiannual baseline inspections during this year to assess the corrective actions taken to address the existing SCWE cross-cutting theme. Based on these recent inspections and review of the licensees actions taken and planned in response to the issuance of a violation of 10 CFR 50.7, the NRC determined that a theme in the SCWE area continued to exist; however, recent survey results indicate an improvement in some areas, Engineering And Security, but mixed results in others.

Consistent with NRC guidance, the licensees progress in addressing the SCWE theme will continue to be reviewed on a semiannual basis. During the current inspection, the inspectors review included consideration of previous NRC reviews of the licensees progress in addressing the SCWE theme, recent actions that the licensee has completed or planned to address the cross-cutting theme in the SCWE area, and consideration of recent enforcement actions taken by the NRC.

The inspectors reviewed approximately 38 condition reports that were directly or potentially related to SCWE. The number of condition reports from January 2019 to June 2019 was compared against the number of SCWE condition reports that were written between July 2019 to December 2019. The specific content of the SCWE condition reports was evaluated and the number of anonymous SCWE condition reports was assessed. In addition, the inspectors reviewed and compared results of the licensee's September 2018 SCWE pulse survey and April 2019 site-wide SCWE survey. The inspectors also reviewed a June 2019 peer (STARs) assessment, a Nuclear Safety Culture Assessment conducted in August 2019, and a Level of Effort Evaluation completed in October 2019.

Assessment

With regard to actions taken to address the cross-cutting theme in the SCWE area, it appears that the licensee is applying the corrective actions as described in its improvement plan. Many of the corrective actions taken include senior management presentations to the staff (referred to as "blitzes"), group training for managers, group training for employees, and procedural changes. At the time of this inspection, the licensee had completed nearly three quarters of their planned actions. All the blitzes and planned procedure changes have been completed, and the licensee was expecting to complete all associated training by December 31, 2019. The licensee still had some actions remaining on their plan, including evaluating the effectiveness of the completed actions. The inspectors reviewed the licensees actions and did not identify any significant concerns.

During a previous inspection, the inspectors identified to the licensee that it appeared that the licensee's corrective action plan had a focus on staff level interactions with first line supervision. Specifically, the corrective action plan had a focus on identifying those behaviors in the first line supervision and mid-level management that might contribute to a chilled work environment. The inspectors, based on the cause of the violation in question, asked the licensee if there were any actions planned for senior management with regard to peer review and assessment (i.e., training that focused on mid-level management reporting on senior management behaviors that may contribute to a chilled work environment, or senior manager peer-to-peer reporting). The licensee wrote Condition Report 133982. The licensee indicated in this condition report that the training provided as part of the overall plan should be adequate, but the licensee noted that it would re-evaluate adequacy in 2020 to see if other actions were needed to address this question.

The inspectors reviewed the licensee's survey results and Level of Effort Evaluation, and it was noted that the results were mixed. Some priority groups, such as Security and Engineering, showed some improvement, while other groups, such as Maintenance Support, appeared to remain static. In addition, there were a couple of condition reports that raised concerns that some supervisors had not significantly altered their behaviors or communication styles following the "blitzes."

Regarding the trend of SCWE-related condition reports, the inspectors did note a slight decrease in number. However, with respect to anonymous condition reports, the inspectors noted that the quantity did not appear to decrease, which may indicate that there are still employees who do not feel comfortable bringing their concerns directly to their management. Finally, the licensee has made a change to the documenting process for anonymous condition reports. Specifically, anonymous condition reports cannot be entered electronically anymore, they can only be entered via paper. This resulted in a couple of condition reports critiquing this action.

Observation: Potential Existence of Defects Related to Control Rod Drive Mechanism Thermal Sleeves 71152 The inspectors completed a review of the licensees response to a Westinghouse 10 CFR Part 21 notification (ADAMS Accession No. ML18143B678) regarding the potential existence of defects related to control rod drive mechanism thermal sleeves. The inspection was performed in accordance with NRC Operating Experience Smart Sample (OpESS)2018/01 (ADAMS Accession No. ML18263A261).

The inspectors reviewed evaluation LTR-RIDA-18-223, Evaluation of Thermal Sleeve Flange and OD/ID Wear Conditions and Recommendations, Revision 0, and associated corrective actions taken by the licensee. The inspectors reviewed and verified the adequacy of identified assumptions (i.e., accuracy of measurement technique and applicable wear rates)and the use of plant specific information to identify the most limiting thermal sleeves given the present wear rates. The inspectors also reviewed the results of the licensees thermal sleeve flange wear inspections to verify that the licensee was using the correct thermal sleeve metal wastage in their evaluation. The inspectors verified that the recommended reinspection period of 7.5 effective full power years was aligned with the most limiting locations before reaching their yielding criteria (i.e., ASME Code allowable). Subsequently, the inspectors verified that the licensee had placed the reinspection of control rod drive mechanism thermal sleeves and the evaluation for possible repair or replacement of these components into their corrective action program.

The inspectors concluded that the licensee had used available operating experience and had adequately evaluated for the potential existence of defects in the control rod drive mechanism thermal sleeves. Furthermore, the inspectors verified that applicable corrective actions had been communicated to the appropriate organizations for implementation.

LER (Discussed)

[Atmospheric Relief Valve] and [Main Steam Safety Valve]

Tornado Missile Vulnerabilities Result in Unanalyzed Condition LER 05000482/2017-003-00 71153 Discussion: On September 7, 2017, the licensee identified that there was no retrievable analysis proving that a single tornado driven design basis missile is not capable of affecting more than two atmospheric relief valves. This vulnerability was identified as part of the licensees review of operating experience regarding potential nonconforming conditions related to tornado generated missile effects on main steam safety valves and atmospheric relief valves. These tornado missile vulnerabilities have existed since original plant construction. The licensee invoked Enforcement Guidance Memorandum 15-002, Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance, Revision 1, implemented initial compensatory measures, and returned the structure, system, and component to an operable-degraded/non-conforming status. NRC Inspection Report 05000482/2017003 (ADAMS Accession No. ML17311B223) dated November 7, 2017, documented that the NRC exercised enforcement discretion by not issuing an enforcement action and allowing continued reactor operation.

At the end of the inspection period, the inspectors had reviewed LER 2017-003-00 and the status of the licensee's corrective actions. The inspectors were unable to close the LER pending licensee action.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 3, 2019, the inspectors presented the IP 71124, Radiation Safety - Public and Occupational cornerstone inspection results to Mr. R. Bayer, Plant Manager, and other members of the licensee staff.
  • On October 3, 2019, the inspectors presented the IP 71111.08, Inservice Inspection Activities (PWR), inspection results to Mr. R. Bayer, Plant Manager, and other members of the licensee staff.
  • On December 18, 2019, the inspectors presented the 2019 emergency preparedness exercise inspection results to Mr. J. McCoy, Site Vice President, and other members of the licensee staff.
  • On January 9, 2020, the inspectors presented the integrated inspection results to Mr. J. McCoy, Site Vice President, and other members of the licensee staff.
  • On January 16, 2020, the inspectors presented the 2019 emergency preparedness exercise inspection results to Mr. M. Dekat, Superintendent Emergency Planning.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

SYS EC-121

Cold Weather Operations

7A

71111.01

Procedures

SYS EF-205

ESW/Circ Water Cold Weather Operations

2A

71111.01

Procedures

SYS OPS-008

Cold Weather Operations

7A

71111.04Q Corrective Action

Documents

Condition Reports 139565, 139569

71111.04Q Drawings

M-12EC01

Piping & Instrumentation Diagram Fuel Pool Cooling and

Clean-Up System

71111.04Q Drawings

M-12EC02

Piping & Instrumentation Diagram Fuel Pool Cooling and

Clean-Up System

71111.04Q Drawings

M-12EG01

Piping & Instrumentation Diagram Component Cooling

Water System

71111.04Q Drawings

M-12EG02

Piping & Instrumentation Diagram Component Cooling

Water System

71111.04Q Drawings

M-12GT01

Piping & Instrumentation Diagram Containment Purge

Systems HVAC

71111.04Q Miscellaneous

CO: D-OP-S-005

CO Coversheet: Secure System Per Procedure Before

Tagging Drawing Revisions Must Be Verified - GTHZ0007

2/26/2019

71111.04Q Procedures

AP 21G-001

Control of Locked Component Status

77A

71111.04Q Procedures

CKL EC-120

Fuel Pool Cooling and Cleanup System Normal Valve

Lineup/Breaker Checklist

18A

71111.04Q Procedures

CKL EG-120

Component Cooling Water System Valve, Switch and

Breaker Lineup

71111.04Q Procedures

CKL GT-131

Containment Purge System Elec Checklist

71111.04S

Corrective Action

Documents

Condition Reports 109111, 120554, 121018, 121296, 122457, 123146, 125123,

25273, 127207, 127305, 128264, 128659, 128851, 137260,

137268, 137321, 137369

71111.04S

Drawings

M-189-REK01

Piping and Instrumentation Diagram Residual Heat Removal

System

71111.04S

Procedures

CKL EJ-120

RHR System Lineup

71111.05Q Corrective Action

Documents

Condition Reports 136534, 136540

71111.05Q Miscellaneous

E-1F9905

Fire Hazard Analysis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05Q Procedures

AP 10-106

Fire Preplans

18A

71111.06

Drawings

10466-A-1319

Architectural Fuel Bldg. Floor Plan El. 2000'-0" & 2026'-0"

71111.06

Drawings

10466-A-1320

Fuel Building Floor Plan El. 2047'-6" and Roof Plan

71111.06

Drawings

C-1C1112

Auxiliary Building - Area 1 Concrete Neat Lines Plan - Base

Slab El. 1974' - 0"

71111.06

Drawings

C-1C1910

Auxiliary Building Conc. Neat Lines & Reinforcing Wall

Elevation - Sheet 10

71111.06

Drawings

E-1RII22(Q)

Embedded Conduit Auxiliary Building Area -2 El. 1974' - 0"

71111.06

Drawings

M-12EC01

Piping & Instrumentation Diagram Fuel Pool Cooling System

71111.06

Drawings

M-12EJ01

Piping and Instrumentation Diagram Residual Heat Removal

System

71111.06

Drawings

M-12LF05

Piping & Instrumentation Diagram Auxiliary Building Floor &

Equip. Drain System

71111.06

Drawings

M-13EC05

Piping Isometric Fuel Pool Cooling & Clean-Up Sys. Fuel

Building

71111.06

Drawings

M-13EC07

Piping Isometric Fuel Pool Cooling & Clean-Up Sys.

Radwaste Building

71111.06

Drawings

M-1P1121

Embedded Drainage Systems (LF) Auxiliary Building El.

1967' - 0" & 1974' - 0" Area 2

71111.06

Drawings

M-663-00017

Wolf Creek Nuclear Operating Corporation Penetration Seal

Typical Details

W22

71111.06

Drawings

M-OT1261

Fuel Bldg/Hot Mach. Shop Trench Piping Plan & Sections

71111.06

Miscellaneous

APF 05D-001-01

Calculation Sheet: Calculation No. FL-02

71111.06

Miscellaneous

APF 05D-001-01

Calculation Cover Sheet: Flooding of Fuel Building EL 2000'-

0" Rooms - Calculation No. FL-09

71111.06

Miscellaneous

M-12LF05

Piping & Instrumentation Diagram Auxiliary Building Floor &

Equip. Drain System

71111.07A

Procedures

STS PE-033

CCW Heat Exchanger Performance Test

71111.07A

Work Orders

18-443630-000

71111.08P

Corrective Action

Documents

Condition Reports 121793, 122185, 122379, 122440, 122447, 122485, 122562,

2710, 122802, 123098,123902, 124064, 124279, 124647,

24966, 126010, 126046, 128153, 128246, 128716, 129065,

29501, 129758, 130114, 130292, 130775, 130851, 130910,

131148, 132260, 133009, 133424

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P

Miscellaneous

L-2018-LLR-0068

Wolf Creek Generating Station, Unit 1 - Request for Relief

14R-06 from American Society of Mechanical Engineers

Boiler and Pressure Vessel Code Visual Examination

Requirements for Reactor Vessel Head Penetration Nozzle

Weld Specified by Code Case N-729-4

10/18/2018

71111.08P

Miscellaneous

MF7423

Wolf Creek Generating Station-Request for Relief 14R-01 to

Continue Use of an Alternative Risk-Informed Methodology

in Selecting Class 1 and Class 2 Piping Welds for Inservice

Inspection During the Forth 10-Year Interval

11/30/2016

71111.08P

Miscellaneous

MF7425

Wolf Creek Generating Station-Request for Relief 14R-02

for Alternative to ASME Code Inspection Requirements for

Class 1 Reactor Pressure Vessel Supports

08/23/2016

71111.08P

Miscellaneous

L-2018-LLR-0101

Wolf Creek Generation Station, Unit 1 - Request for Relief

from Requirements of the American Society of Mechanical

Engineers Boiler and Pressure Vessel Code, Code Case

N-666-1

2/12/2018

71111.08P

Miscellaneous

MF8456

Wolf Creek Generating Station-Relief from Certain

American Society of Mechanical Engineers Boiler and

Pressure Vessel Code Inservice Inspection Requirements

for Reactor Vessel Closure Head Penetration Nozzles

During Refueling Outage 21 and the Fourth 10-Year

Inservice Inspection Interval

05/01/2017

71111.08P

Miscellaneous

MF9639

Wolf Creek Generating Station - Request for Relief 14R-05

from Certain Pressure Test Requirements of the American

Society of Mechanical Engineers Boiler and Pressure Vessel

Code for Reactor Pressure Vessel Leak-Off Lines for the

Fourth 10-Year Inservice Inspection Interval

08/02/2017

71111.08P

Miscellaneous

WCRE-30

Inservice Inspection Program Plan, Wolf Creek Generating

Station, Interval 4

2/22/2018

71111.08P

Procedures

AI 16F-001

Evaluation of Boric Acid Leakage

71111.08P

Procedures

AI 16F-002

Boric Acid Leakage Management

71111.08P

Procedures

AP 16F-001

Boric Acid Corrosion Control Program

71111.08P

Procedures

DC24 07/02/2019

Welding Program Manual

71111.08P

Procedures

LMT-08-PDI-UT-1 Ultrasonic Examination of Ferritic Piping Welds

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P

Procedures

LMT-08-PDI-UT-2 Ultrasonic Examination of Austenitic Piping Welds

71111.08P

Procedures

LMT-08-PDI-UT-3 Ultrasonic Through Wall Sizing in Piping Welds

71111.08P

Procedures

LMT-08-UT-004

Ultrasonic Examination of Vessel Welds and Adjacent Base

Metal > 2.0 in Thickness

71111.08P

Procedures

QCP-20-501

Visible Dye Penetrant Examination

10A

71111.08P

Procedures

QCP-20-502

Magnetic Particle Examination AC/DC Yoke and AC Coil

Techniques

71111.08P

Procedures

QCP-20-503

Ultrasonic Examination for Component Wall Thinning

71111.08P

Procedures

QCP-20-508

Radiographic Examination of Welds

4B

71111.08P

Procedures

QCP-20-541

VT-3 Visual Examination

71111.08P

Procedures

WPD-1

Welding Program Description

71111.08P

Self-Assessments QH-2019-1866

Assessment for NRC RF23 ISI inspection

06/06/2019

71111.08P

Self-Assessments QH-2019-1871

Boric Acid Program Assessment for NRC RF23 ISI

inspection

06/17/2019

71111.08P

Self-Assessments QH-2019-1875

RF23 Readiness for NRC ISI Inspection

06/19/2019

71111.08P

Self-Assessments SA-2018-0140

ISI Pressure Test Self Assessment

01/17/2019

71111.08P

Work Orders

14-387463, 17-422890, 17-422899, 17-426657, 18-438730,

18-438963, 18-439101, 18-439263, 18-440094,

71111.11Q Procedures

AP 21-001

Conduct of Operations

83A

71111.11Q Procedures

GEN 00-002

Cold Shutdown to Hot Standby

103

71111.11Q Procedures

GEN 00-003

Hot Standby to Minimum Load

2

71111.11Q Procedures

RXE 01-002

Reload Low Power Physics Testing

71111.12

Corrective Action

Documents

Condition Reports 125518, 125777, 126839, 129032, 135326, 136537, 136880,

137321

71111.12

Miscellaneous

Maintenance Rule Final Scope Evaluation: Shutdown Diesel

Generators - KU-01

10/09/2019

71111.12

Miscellaneous

Maintenance Rule Final Scope Evaluation: Shutdown Diesel

Generators - KU-02

10/09/2019

71111.12

Miscellaneous

Maintenance Rule Final Scope Evaluation: Residual Heat

Removal/MSPI Residual Heat Removal System - EJ-01

10/02/2019

71111.12

Miscellaneous

Maintenance Rule Final Scope Evaluation: Residual Heat

Removal/MSPI Residual Heat Removal System - EJ-02

10/02/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Miscellaneous

Maintenance Rule Final Scope Evaluation: Residual Heat

Removal/MSPI Residual Heat Removal System - EJ-06

10/02/2019

71111.12

Miscellaneous

AIF 28A-100-08

Equipment Performance Evaluation: CR Number - 125518

71111.12

Miscellaneous

APF 23M-001-01

Maintenance Rule (a)(1) Determination Section I: Station

Blackout Diesel Generation System (KU)

2/19/2018

71111.12

Miscellaneous

EDI 23M-050

Engineering Desktop Instruction Monitoring Performance to

Criteria and Goals: Function Failure Determination Checklist

- System: KU

11/29/2018

71111.12

Procedures

AI 28A-100

Condition Report Resolution

71111.12

Procedures

AP 23M-001

WCGS Maintenance Rule Program

71111.13

Miscellaneous

APF 22B-001

Shutdown Safety Function Status & Assessment Summary

2A

71111.13

Procedures

AP 22B-001

Outage Risk Management

71111.13

Work Orders

13-372401-018

71111.15

Calculations

P-254

Normal Charging Loop 1 Snubber Reduction Analysis -

Reactor Building

005

71111.15

Corrective Action

Documents

Condition Reports 136012, 136383, 136412, 136553, 136672, 136709, 136749,

136750, 136752, 136790, 136851, 136940, 137333, 137389,

137826, 139619

71111.15

Drawings

J-104-00079

Schematic Input Buffer

2/22/1977

71111.15

Drawings

J-105A-00004

SA075A Main Steam (MS) One Line Diagram

W01

71111.15

Drawings

J-105A-00006

SA075B Main Steam (MS) One Line Diagram

W01

71111.15

Drawings

KL1909

Logic Block Diagram Load Shedding & Emergency Load

Sequencing System (LSELS)

09/29/1978

71111.15

Drawings

M-12AB02

Piping & Instrumentation Diagram Main Steam System

71111.15

Drawings

M-13HB33

Small Piping Isometric Liquid Radwaste System Radwaste

Building

71111.15

Drawings

M-151-00004

Nozzle Type Relief Valve

W07

71111.15

Miscellaneous

Engineering White Paper

2/17/2019

71111.15

Miscellaneous

Pictures of fuel assemblies: AA17, AA59, AC47, and AC53

71111.15

Miscellaneous

20322

Design Equivalent Change Package: Encapsulation to Seal

BB8378A Bonnet Boric Acid Leakage

71111.15

Miscellaneous

9002-DRPI-000

Principles of Operation (Figure 2-30)

71111.15

Miscellaneous

AIF 16F-001-01

Boric Acid Evaluation: CVCS Normal Charging to Loop 1

Check Valve

10/08/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Miscellaneous

APF 05C-004-01

Basic Engineering Disposition: ESW-B Traveling Screen

High Vibration 19-455350-001

10/15/2019

71111.15

Miscellaneous

APF 26A-001-01

RER Reportability Determination: RER No. 2019-021

10/22/2019

71111.15

Miscellaneous

Letter WO 96-

0068

Docket No. 50-482: Response to Generic Letter 96-01,

"Testing of Safety Related Logic Circuits"

04/18/1996

71111.15

Miscellaneous

TS Bases

Technical Specification Bases

71111.15

Miscellaneous

TS Bases

Technical Specification Bases

71111.15

Procedures

AP 26C-004

Operability Determination and Functionality Assessment

38A

71111.15

Procedures

EMG E-O

Reactor Trip or Safety Injection

41A

71111.15

Procedures

STS IC-208A

4KV Loss of Voltage & Degraded Voltage TADOT NB01 Bus

- SEP GRP 1

6B

71111.15

Procedures

STS IC-208B

4KV Loss of Voltage & Degraded Voltage TADOT NB02 Bus

- SEP GRP 4

71111.15

Procedures

STS RE-017

DRPI Operability Verification

10B

71111.15

Work Orders

Work Orders

17-426808-000, 19-454475

71111.19

Corrective Action

Documents

Condition Reports 114660, 139590

71111.19

Drawings

M-12GL01

Piping & Instrumentation Diagram Auxiliary Building HVAC

71111.19

Miscellaneous

APF 29B-003-01

Surveillance Test Routing Sheet: Train B RHR System

Inservice Valve Test

10/17/2019

71111.19

Procedures

MPE RC-001

Room Cooler Maintenance

71111.19

Procedures

QCP-20-514

Eddy Current Testing

71111.19

Procedures

STN EG-003B

CCW Train B Void Monitoring & Venting

71111.19

Procedures

STN PE-037B

ESW Train B Heat Exchanger Flow and DP Trending

71111.19

Procedures

STS EF-100B

ESW System Inservice Pump B & ESW B Check Valve Test

71111.19

Procedures

STS EJ-209B

Train B RHR System Inservice Valve Test

71111.19

Procedures

STS GN-001

CTMT Cooling Fans Operability Test

71111.19

Procedures

STS KJ-005B

Manual/Auto Start, Sync & Loading of EDG NE02

65A

71111.19

Procedures

STS KJ-011A

EDG NE01 24 Hour Run

71111.19

Procedures

STS MT-077

CCW Return to CCW Pumps Check Valve Inspection

71111.19

Procedures

SYS EF-201

ESW Screen Wash Operation

20A

71111.19

Procedures

SYS EG-400

Component Cooling Water System Fill and Vent

71111.19

Procedures

SYS GN-120

Containment Cooling System Operation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.19

Procedures

SYS KJ-124

Post Maintenance Run of Emergency Diesel Generator B

71111.19

Work Orders

Work Orders

13-364660, 13-372401, 15-399213-013, 15-402735,

15-406050, 16-418607, 17-432437-014, 18-441543-000,

18-441543-002, 18-442257, 18-442288, 18-442401,

18-443270, 18-443621-001, 18-443732, 18-443783,

19-451230-000

71111.20

Corrective Action

Documents

Condition Reports 137772, 138117, 138118, 139349

71111.20

Drawings

C-OC1211

Auxiliary Building Area 1 Concrete Neat Lines Plan Floor

EL. 1988'- 0"

71111.20

Drawings

C-OC1221

Auxiliary Building Area 2 Concrete Neat Lines Plan Floor

EL. 1988' - 0"

71111.20

Drawings

M-12BB01

Piping & Instrumentation Diagram Reactor Coolant System

71111.20

Drawings

M-12BG01

Piping & Instrumentation Diagram Chemical and Volume

Control System

71111.20

Drawings

M-OX1221

Auxiliary Building Area 2 Penetration Closure Plan Floor

EL. 1988' - 0"

71111.20

Miscellaneous

APF 15C-002-01

Procedure Cover Sheet: Reload Low Power Physics Testing

- RXE 01-002

71111.20

Miscellaneous

CO: D-OP-S-005

CO Coversheet: Secure System Per Procedure Before

Tagging Drawing Revisions Must Be Verified - GTHZ0007

2/26/2019

71111.20

Miscellaneous

CO: R-BG-L-001

CO Coversheet: Secure System Per Procedure Before

Tagging Drawing Revisions Must Be Verified - BGHV8149A

11/01/2019

71111.20

Miscellaneous

EmpCenter Data

(15 Workers)

Work Hour Reports

09/07/2019

to

11/15/2019

71111.20

Miscellaneous

M-663-00017

Wolf Creek Nuclear Operating Corporation Penetration Seal

Typical Details

W22

71111.20

Procedures

AP 13-001

Fatigue Management

20D

71111.20

Procedures

GEN 00-003

Hot Standby To Minimum Load

103

71111.20

Procedures

STN KU-001B

SBO DG to NB02 Functional Test

71111.20

Procedures

STS KJ-001A

Integrated D/G and Safeguards Actuation Test - Train A

71111.20

Procedures

STS KJ-001B

Integrated D/G and Safeguards Actuation Test - Train B

71111.22

Procedures

I-ENG-026

Local Leak Rate Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.22

Procedures

STS EF-001A

ESW System Inservice Pump A & ESW A Check Valve Test

71111.22

Procedures

STS KJ-001B

Integrated D/G and Safeguards Actuation Test - Train B

71111.22

Procedures

STS PE-125

LLRT Valve Lineup for Penetration 25

71114.01

Corrective Action

Documents

Condition Reports 119506,119507, 119869, 119911, 119915, 119941, 120109,

21171, 121173, 121729, 122130, 122348, 125976, 126201,

26213, 126222, 126240, 127643, 127649, 127651, 127665,

28016, 128018, 128019, 129197, 129586, 129774, 130241,

130282, 130286, 130296, 130301, 130306, 130313, 130321,

130440, 130679, 131782, 131802, 131821, 131822, 131851,

131944, 132067, 132249, 132417, 132424, 132430, 132450,

2772, 133765, 134128, 134497, 134924, 134930, 134933,

134946, 134948, 134953, 134964, 134966, 134967, 135038,

138628, 138707, 138723, 139116

71114.01

Corrective Action

Documents

Resulting from

Inspection

Condition Reports 138995, 139002, 139006, 139008, 139009, 139011, 139012,

139013, 139015, 139016, 139017, 139019, 139020, 139021,

139025, 139026, 139027, 139028, 139037, 139039, 139040,

139045, 139047, 139048, 139050, 139053, 139054, 139063,

139126, 139130

71114.01

Miscellaneous

TR 2018-215

Training Request

71114.01

Miscellaneous

Procedure Change Requests PCR 69855, PCR 69858,

PCR69859

71114.01

Miscellaneous

18-SA-02

Drill Type: Semi-Annual, Drill Requirements: Full Scope, HP,

PPX, Communications Drill, Radiological Monitoring

11/15/2018

71114.01

Miscellaneous

APF 06-002-02

Emergency Action Levels Technical Bases

0B

71114.01

Miscellaneous

EP-06-002

Radiological Emergency Response Plan, R20

9/11/2019

71114.01

Miscellaneous

EPF 06-018-11

Technical Support Center Inventory Checklist

71114.01

Miscellaneous

EPF 06-018-12

Emergency Operations Facility Inventory Checklist

71114.01

Miscellaneous

RA 19-0014

Docket No. 50-482: Revision of One Procedure that

Implements the Radiological Emergency Response Plan

(RERP) for Wolf Creek Generating Station (WCGS)

1/30/2019

71114.01

Miscellaneous

RA 19-0022

Docket No. 50-482: Revision of Two Forms that Implement

the Radiological Emergency Response Plan (RERP) for Wolf

Creek Generating Station (WCGS)

2/11/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71114.01

Miscellaneous

RA 19-0059

Docket No. 50-482: Revision of Two Procedures and Four

Forms that Implement the Radiological Emergency

Response Plan (RERP) for Wolf Creek Generating Station

(WCGS)

5/28/2019

71114.01

Procedures

AI 28A-010

Screening Condition Reports

71114.01

Procedures

AP 21-001

Conduct of Operations

83A

71114.01

Procedures

EPP 06-018

Maintenance of Emergency Facilities and Communications

Checks

71114.01

Procedures

EPP 06-019

Alert and Notification System Sirens

9B

71114.01

Procedures

EPP-06-001

Control Room Operations, R30A

11/82019

71114.01

Procedures

EPP-06-002

Technical Support Center Operations, R43

9/11/2019

71114.01

Procedures

EPP-06-003

Emergency Operations Facility Operations, R27

9/11/2019

71114.01

Procedures

EPP-06-005

Emergency Classification, R9A

2/14/2019

71114.01

Procedures

EPP-06-006

Protective Action Recommendations, R10

9/26/2019

71114.01

Procedures

EPP-06-007

Emergency Notifications, R26

9/26/2018

71114.01

Procedures

EPP-06-009

Drill and Exercise Requirements, R11A

11/13/2018

71114.01

Procedures

EPP-06-011

Emergency Team Formation and Control, R12

9/11/2019

71114.01

Procedures

EPP-06-013

Exposure Control and Personnel Protection, R6A

5/6/2018

71114.01

Procedures

EPP-06-015

Emergency Response Organization Callout, R14

9/30/2015

71114.04

Corrective Action

Documents

Condition

Reports-

26669, 129586

71114.04

Corrective Action

Documents

Resulting from

Inspection

Condition Reports 139133

71114.04

Miscellaneous

E-Plan Screening - Activity/Document Number: APF 06-002-

2, Revision: 0B

1/10/2019

71114.04

Miscellaneous

E-Plan Screening - Activity/Document Number: APF 06-002-

03, Revision: 0B

1/14/2019

71114.04

Miscellaneous

ML19052A546

Wolf Creek Generating Station, Unit 1 - Issuance of

Amendment Re: Revision to the Emergency Plan (EPID L-

2018-LLA-0138)

4/1/2019

71114.04

Miscellaneous

STARS 480

Changes to the Emergency Plan description that do not

reduce the commitments set forth in the previously-approved

7/1/2005

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Emergency Plan.

71114.04

Miscellaneous

WO 18-0016

Docket No. 50-482: License Amendment Request (LAR) for

Revision to the Emergency Plan

5/9/2018

71114.04

Miscellaneous

WO 18-0045

Docket No. 50-482: Response to Requests for Additional

Information (RAI) Regarding License Amendment Request

(LAR) for Revision to the Emergency Plan

11/19/2018

71114.04

Procedures

AP 26A-004

Communications with the Nuclear Regulatory Commission

71124.01

Corrective Action

Documents

Condition Reports 119737, 119739, 119754, 119762, 120567, 120680, 120708,

20975, 121099, 121159, 121281, 121282, 121495, 121601,

21726, 122202, 124071, 124104, 122444, 124823, 125181,

25880, 126557, 126571, 126577, 127145, 128132, 129523,

131088

71124.01

Procedures

AP 19C-002

Special Nuclear Material Safeguards and Accountability

71124.01

Procedures

AP 25B-100

Radiation Worker Guidelines

71124.01

Procedures

FHP 02-019

Spent Fuel Pool Exclusion Area

71124.01

Procedures

RPP 02-105

Radiation Work Permit (RWP)

71124.01

Procedures

RPP 02-210

Radiation Survey Methods

49B

71124.01

Procedures

RPP 02-215

Posting of Radiological Controlled Areas

34B

71124.01

Procedures

RPP 02-605

Control and Inventory of Radioactive Sources

71124.01

Radiation Work

Permits (RWPs)

2300

Crane Operators, Riggers, Iron Workers, Tool Crib Workers,

Fire Watch, Coatings, Housekeeping, and Cleaner Support

Personnel

71124.01

Radiation Work

Permits (RWPs)

194482

IRV Head Disassembly to include Canopy Seal Clamp

(Vendor Activities)

71124.01

Radiation Work

Permits (RWPs)

194483

RV Head Reassembly to include Canopy Seal Clamp

(Vendor Activities)

71124.01

Self-Assessments QS 2019-3094

Quality Assurance Review: Temporary Shielding Request

Packages

10/03/2019

71124.01

Self-Assessments Quick Hit 2019-

1893

NRC Inspection Procedure 71124.01, Radiological Hazard

Assessment and Exposure Controls

04/17/2019

71124.03

Corrective Action

Documents

Condition Reports 120334, 120975, 121159, 121281, 121282, 122130, 122348,

24071, 126557, 126577, 127145, 128131, 130911, 135180,

136261, 136365, 136370,

71124.03

Procedures

AI 14-009

Industrial Respiratory Protection Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.03

Procedures

AI-10-001

Fire Brigade Equipment Inventory, Maintenance and

Cleaning

71124.03

Procedures

AP 25B-100

Radiation Worker Guidelines

71124.03

Procedures

AP 25B-600

Respiratory Protection Program at Wolf Creek

71124.03

Procedures

GT1245302

Self-Contained Breathing Apparatus User

71124.03

Procedures

RPP 02-105

RWP

71124.03

Procedures

RPP-03-310

Respiratory Protection Equipment

71124.03

Procedures

SYS GG-201

Fuel Building HVAC System Operation

10A

71124.03

Procedures

SYS GT-121

Containment Shutdown Purge System Operation

71124.03

Radiation Work

Permits (RWPs)

180049

Decon Inside High Radiation Areas, High Contamination

Areas, Discrete Radioactive Particle Area, and Alpha Level 2

Areas

71124.03

Radiation Work

Permits (RWPs)

2300

Crane Operators, Riggers, Iron Workers, Tool Crib Workers,

Fire Watch, Coatings, Housekeeping & Cleaner Support

Personnel

71124.03

Radiation Work

Permits (RWPs)

194050

SI "B" Pump and Motor Work/Inspection 1974'Aux Room

1108

71124.03

Radiation Work

Permits (RWPs)

196000

Lower Refueling Cavity Pre and Post Flooding Maintenance

Activities

71124.03

Self-Assessments Quick Hit Number

2019-1894

NRC Inspection Procedure 71124.03, In-Plant Airborne

Radioactivity Control and Mitigation

71151

Corrective Action

Documents

Condition Reports 126201, 126533, 129679, 132774, 133765, 133805, 133901

71151

Miscellaneous

MSPI Derivation Report - MSPI Residual Heat Removal

System - Unavailability Index

2/11/2019

71151

Miscellaneous

MSPI Derivation Report - MSPI Residual Heat Removal

System - Unreliability Index

2/11/2019

71151

Miscellaneous

MSPI Derivation Report - MSPI Residual Heat Removal

System - Performance Limit Exceeded

2/11/2019

71151

Miscellaneous

MSPI Derivation Report - MSPI Heat Removal System -

Unreliability Index

2/11/2019

71151

Miscellaneous

MSPI Derivation Report - MSPI Heat Removal System -

Unavailability Index

2/11/2019

71151

Miscellaneous

MSPI Derivation Report - MSPI Residual Heat Removal

2/11/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

System - Performance Limit Exceeded

71151

Miscellaneous

LER 2018-001-00

Inappropriate Use of Blind Flange for Containment Isolation

Valve Results in Condition Prohibited by Technical

Specifications

10/04/2018

71151

Miscellaneous

LER 2018-002-00

Modification Activities Affected Control Room Envelope

Boundary Causing a Condition Prohibited by Technical

Specifications

2/27/2019

71151

Miscellaneous

LER 2019-001-00

Loss of Startup Transformer Results in Emergency Diesel

Generator Actuation

07/18/2019

71151

Miscellaneous

STN CH-024

Quarterly/Yearly Dose Projections: April 17, 2018, through

September 19, 2019

71151

Miscellaneous

WCNOC-163

Mitigating System Performance Index (MSPI) Basis

Document

71151

Procedures

AI 26A-008

INPO/NRC/STARS Performance Indicator Guidelines

71151

Procedures

AP 26A-007

NRC Performance Indicators

71151

Procedures

EPP-06-019

Alert and Notification Siren Systems, R9B

10/18/2018

71151

Procedures

EPP-06-022

Tone Alert Radio Maintenance/Compensatory Measures

11/13/2018

71151

Work Orders

WR19130402, WR19452760

71152

Corrective Action

Documents

Condition Reports 122351, 123083, 123084, 129698, 132017, 132610, 132652,

2744, 133430, 133543, 133907, 133935, 133979, 133982,

134101, 134102, 134103, 134106, 134722, 134889, 134984,

135205, 135873, 135891, 135950, 136226, 136383, 136412,

136640, 136641, 136672, 136683, 136688, 136709, 136744,

136749, 136750, 136752, 136790, 136801, 136802, 136803,

136804, 136805, 136810, 136851, 136924, 137699, 138224,

138754, 139225

71152

Drawings

1464F11

Thermal Sleeve

71152

Drawings

M-703-00055

Closure Head (SAP) General Assembly

W02

71152

Engineering

Evaluations

LTR-RIDA-18-223 Evaluation of Thermal Sleeve Flange and OD/ID Wear

Conditions and Recommendations

71152

Engineering

Evaluations

PWROG-16003-P Evaluation of Potential Thermal Sleeve Flange Wear

71152

Engineering

Evaluations

PWROG-16003-P Evaluation of Potential Thermal Sleeve Flange Wear

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71152

Miscellaneous

MRP 2018-010

Notification of Recent PWR CRDM Thermal Sleeve Flange

Wear and Control Rod Motion Stoppage Operating

Experience and Recommended Plant Actions

03/20/2018

71152

Miscellaneous

TB-07-2

Reactor Vessel Head Adapter Thermal Sleeve Wear

71153

Corrective Action

Documents

Condition Reports 13957, 15576, 18497, 20105, 32801, 132693, 134184,

134814

71153

Drawings

908 663

Valve, Thermostatic 3-Way ICW ASME Sect. III, CL 3

05/10/1977

71153

Drawings

908 664

Valve, Thermostatic 3-Way

J.W. ASME Sect. III, CL 3

05/10/1977

71153

Drawings

908 665

Valve, Thermostatic 3-Way

L.O. ASME Sect. III, CL 3

05/10/1977

71153

Drawings

N-84984-E2

5" 3-Way Temp. Regulatory ANSI Class 150 Steel

71153

Miscellaneous

APF 24G-001-01

Commercial Grade Dedication Package Number 009-P0002

71153

Miscellaneous

APF 28A-000-01

Performance Improvement Request Initiation:

PIR 2004-2160

08/21/2004

71153

Miscellaneous

APF 28A-001-01

Performance Improvement Request Initiation:

PIR 2004-2160

08/21/2004

71153

Miscellaneous

LER 2019-002-00

Emergency Diesel Generator Inoperable Due to

Temperature Control Valve Failure

10/14/2019

71153

Miscellaneous

Letter NO 92-

0195

Docket No. 50-482: Special Report 92-002

07/08/1992

71153

Miscellaneous

PIR 1999-1886

71153

Miscellaneous

PIR 2000-2462

71153

Miscellaneous

PIR 2004-2160

71153

Miscellaneous

Product

Specification I-

285-P, Q, S, T

Robertshaw Sales Manual Section 351

71153

Miscellaneous

WCNOC-67

Shelf Life Guidelines

71153

Miscellaneous

WM 93-0024

Docket No. 50-482; Special Report 89-003, WCNOC Letter

NO 90-0009 dated January 8, 1990, from

J.A. Bailey,

WCNOC to NRC

2/18/1993

71153

Procedures

ALR 501

Standby Diesel Engine System Control Panel KJ-121

71153

Procedures

AP 24E-007

Stored Item Maintenance, Shelf Life, Storage Level &

Storage Packaging

71153

Work Orders

00-220529-050, 01-227134-000, 01-230949-002,

19-450841-000, 19-453254-000, 19-453567-002

30