Notifies That Util 801204 Request for Hearing Re Environ Qualification of safety-related Electrical Equipment Will Be Held in Abeyance for 30 Days After NRC Action on Industry Petition to Extend Deadline.Response Requested by 810901
ML20010E360
Person / Time
Site: Haddam Neck, Millstone  File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 08/14/1981
From: Eisenhut D
Office of Nuclear Reactor Regulation
To: Counsil W
NORTHEAST NUCLEAR ENERGY CO.
References
TAC-42493, NUDOCS 8109030391
Download: ML20010E360 (3)


Text

4

{

AUG 141981[6%'

Docket Hes. 50-213/245/336

%4

,'b b.y ^[k / '--

b fir. W. G. Counsil Senior Vice President 7

Northeast Huclear Energy Company D

--s Post Office Box 270 f.,-

Hartford, Connecticut 06101

.L e

/

k j 7g

Dear Mr. Counsil:

SUBJECT:

ENVIRONMENTAL QUALIFICATION OF SAFETY-RELATED ELECTRICAL EQUIPMENT RE: HADDAM NECK PLANT, MILLSTONE HFCLEAR POWER STATION, UNIT NOS. 1 & 2 Your letter of December 4,1980 requested a hearing concerning the subject.

As a result of our letter of June 12, 1981, your request has been held in abeyance until ninety days after the date of issuance of the Safety Evaluation for the facilities.

On July 31, 1981, the NRC staff recommended to the Conmission, in response to an industry petition, that the June 30, 1982 deadline for equipment qualification be extended to June 30, 1983, with limited pro risions for further extensions on a case-by-case basis. In addition, the NRC staff has provided clarifications on many of the technical issues in this area.

The underlying reasons for your original request, regarding a hearing, may be affected by the Commission's action on the staff's submittal or recent ts. Therefore, in order to allow staff interpretations of the you to consider all recent or ninent-velopnents, we will, upon your affirmation, hold your original in abeyance for up to thirty days after the Conmission has conpleted its action on the petition. By that time, we ask that you inforn us of your intent, and)f you pursue a hearing, of the specific issues you intend to raise in the-proceeding.

Your response to this letter, affirning or rejecting this course of action, is reqcsted by September 1,1981. We will continue to solicit your cooper-ation in the identification and resolution of disputed technical issues.

For additional inforrotion, contact Jin Liebernan (301-497-7267), Office of the Executive Legal Director, or Mark Williams (301-492-m8). Please send a copy of your resporse to Mr. Williams via telecopy (301-492-7617).

Sincerely,

/

Darrell G. Eisen D

or Division of Licensing Distribution:

Office of Huclear Reactor Regulation Docket File-NRC PDR-Local PDR-0RB#2 Rdng-D. Eisenhut-J. Heltemes T. Ippolito-S. Norris-M. Williams-0 ELD-I&E(3)-NSIC-TERA-ACRS(10),,[

ORgu2 ORB #2 noga2 nr n nFPDIR:DL Dl M D_L1 o rmo x

SNorri liiams Tipp6Mto RPurpie GEis6nhut

/,p T

~ B/""/8T "8/ %8P 8/ /BP 8/f/81-j

"]"87~ /81

,r svanw4 8109030391 sios14 UV

",,6 [Q, $ j.,,,,$[

PDR ADOCK 05000213

- P PDR J

1 anc rosu ms oo.eo,nacu mu O FICIAL RECORD COI.

.u m uw_3a m

~

~

Northeast Nuclear Energy Company cc:

William H. Cuddy, Esquire Mr. John Shediosky Day, Berry & Howard Resident Inspector / Millstone Counselors at Law c/o U.S.N.R.C.

One Constitution Plaza P. O. Drawer KK Hartford, Con:1ecticut 06103 Niantic, CT 06357 Mr. Charles Brinkman Natural Resources Defense Council Manager - Washington Nuclear 917 15th Street, N.W.

Operations Washington, D. C.

20005 C-E Power Systems Combustior Engineering, Inc.

Mr. Lawrence Bettencourt, First Seleccman 4853 Cordell Aven., Suite A-1 Town of Waterford Bethesda, MD 20014 Rail of Records - 200 Boston Post Road Waterford, Cennecticut 06385 Northeast Nuclear Energy Company ATTN:

Superintendent Millstone Plant Connecticut Energy Agency Post Office Box 128 AiTN:

Assistant Director, Research Wat'erford, Connecticut 06385 and Policy Development Department of Planning and Eriercy Waterford Public Library Policy Rope Ferry Road, Route 156 20 Grand Street Waterford, Connecticut 06385 Hartford, CT 06106 U. S. Envircnmental Protecticn Agnecy Region.I Office ATTN:

EIS COORDINATOR John F. Kennedy Feceral Building Boston, Massachusetts 02203 Northeast Utilities Service Ccmpany ATTN:

Mr. James R. Himmelwright Nuclear Engineering and Operations P. O. Box 270 Hartford, Connecticut,06101

HADDAM, NECK Docket No. 50-213 Mr. W. G. Counsil CC Day, Berry & Howard Counselors at Law One Constitution Plaza Hartford, Connecticut 06103 Superintendent Haddam Neck Plant RFD #1 Post Office Box 127E East Hampton, Connecticut 06424

~

Mr. Richard R. Laudenat Manager, Generation Facilities Licensing Northeast Utilities Service Company P. O. Box 270 Hartford, Connecticut 06101 Russell Library 119 Broad Street Middletown, Connecticut 06457 Board of Selectmen Town Hall Maddam, Connecticut 06103 Lonnecticut Energy Agency ATIN: Assistant Director Research and Policy Development Departnent of Planning and Energy Policy 20 Grand Street Hartford, Connecticut 06106 U. S. Environmental Protection Agency Region I Office ATTM: EIS COORDINATOR JFK Federal Building Boston, Massachusetts 02203 Resident Inspector Haddam Neck Nuclear Power Station c/o V. S. NRC East Haddam Post Office East Haddam, Connecticut 06423