Status Report on South Carolina Public Service Authority'S Position on the Termination of the COL for VCSNS Units 2 & 3
ML18213A155
Person / Time
Site: Summer  South Carolina Electric & Gas Company icon.png
Issue date: 07/23/2018
From: Crosby M
South Carolina Public Service Authority
To: Delores Greene, Paul Kallan, Renee Taylor
Document Control Desk, Office of New Reactors
References
Download: ML18213A155 (2)


Text

-.1

'ntee cooper' MichaelR.Crosby Senior Vice President Nuclear Energy (843) 761-4126 fax: (843) 761-7037 July 23, 2018 mrcrosby@santeecooper.com Mr. Robert Taylor Director of DLSE ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Via email to Robert.Taylor@nrc.gov, Paul.Kallan@nrc.gov, Delores.Greene@nrc.gov and U.S. mail Virgil C. Summer Nuclear Station (VCSNS) Units 2 & 3.

Combined License (COL) Nos. NPF-93 and NPF-94 Docket Nos.52-027 & 52-028

Subject:

Status Report on South Carolina Public Service Authority's Position on the Termination of the COL for VCSNS Units 2 & 3

References:

1. Letter from Jeffrey B. Archie to NRC, V.C. Summer, Units 2 and 3 -

Notification of Termination of Project.Construction, dated August 17, 2017 (ML172298487)

2. Letter from Jeffrey B. Archie to NRC, V.C. Summer Units 2 and 3 -

SCE&G Request for Withdrawal of VCSNS Unit 2 & 3 COLs, dated December 27, 2017 (ML17361A088)

3. Letter from Michael R. Crosby .to NRC, Response to South Carolina Electric & Gas Company (SCE&G) Request for Withdrawal of VCSNS Unit 2 & .3 COLs, dated January 8, 2018 (ML 1801 OA068)
4. Letter to Michael R. Crosby, Santee Cooper, from Frederick D. Brown, NRO, re: SCE&G and Santee Cooper Acknowledgement of VC Summer Termination Letter, dated April 18, 2018 (ML18108A265)
5. Letter to Jeffrey B. Archie, SCE&G, from Frederick D. Brown, NRO, re:

SCE&G and Santee Cooper Acknowledgement of VC Summer Termination Letter, dated April 18, 2018 (ML18107A081)

6. Letter from Michael R. Crosby to NRC, South Carolina Public Service Authority's Maintenan_ce, Preservation & Documentation Program for VCSNS Units 2 & 3, dated June 4, 2018 (ML18158A155)
7. Letter to Michael R. Crosby from NRC, South Carolina Public Service Authority's Maintenance, Preservation & Documentation Program for VCSNS Units 2 & 3, dated June 6, 2018 (ML18156A316)

One Riverwood Drive I Moncks Comer, SC 29461-2901 I (843) 761-8000 I P.O. Box 2946101 I Moncks Corner, SC 29461-6101 1

The purpose of this letter is to provide the NRC with a status update on the South Carolina Public Service Authority's (Santee Cooper's) position with respect to SCE&G's December 27, 2017 request to terminate the VCSNS Unit 2 & 3 COLs. Today, Monday July 23, 2018, the Santee Cooper's Board of Directors held a special meeting to further consider and discuss the issue of the termination of the COL.

When the Board resolved to suspend construction of VCSNS Unit 2 & 3, on July 31, 2017, it authorized management to pre*serve the site and components for a period of one year or until July 31, 2018. At today's meeting the Board adopted a resolution to continue such site and high-valued component preservation until December 31, 2018. In addition, the Board declared that the components and equipment at the VCSNS Units 2 & 3 site are surplus and authorized the Interim President and CEO to undertake efforts to sell the components and equipment to interested purchasers.

At today's meeting the Board was not asked to take any action with regard to the termination of the VCSNS Units 2 & 3 COLs. That issue is expected to be resolved by the Board at its next meeting currently scheduled for August 20, 2018. Senior Santee Cooper management is committed to recommending to the Board at that meeting that the VCSNS Units 2 & 3 COLs be terminated.

If you have any questions regarding this update, please contact me at (843) 761-7081 or via e-mail at michael.crosby@santeecooper.com

~Jj?~

Michael Crosby cc: James E. Brogdon J. Michael Baxley Stephen R. Pelcher Elizabeth H. Warner Wm. Marion Cherry Jason W. Williams Richard M. Lorenzo Jimmy E. Addison, President & CEO SCANA Jim 0. Stuckey, Esquire, General Counsel SCANA Jeffrey B. Archie, SVP & CNO SCE&G Paul Kallan, Senior Project Manager Delores Greene, Division Administrative Assistant 2