ML14329A479

From kanterella
Jump to navigation Jump to search

Schedule Revision for the Review of the Davis-Besse Nuclear Power Station License Renewal Application (TAC No. ME613)
ML14329A479
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/28/2014
From: Chris Miller
Division of License Renewal
To: Lieb R
FirstEnergy Nuclear Operating Co
Keegan E, 415-8517
References
TAC ME4613
Download: ML14329A479 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 28, 2014 Mr. Raymond A. Lieb, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

Dear Mr. Lieb:

By letter dated August 27, 2010, FirstEnergy Nuclear Operating Company submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR Part 51) and (10 CFR Part 54), to renew operating license NPF-003 for the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC) staff. This letter is to inform you of a change in the environmental review schedule for the Davis-Besse license renewal review.

Regarding the staffs environmental review, by letter dated September 30, 2014, the staff issued a letter revising the environmental review schedule. This revision established a November 2014 issuance date for the final Supplemental Environmental Impact Statement (SEIS). Due to issues related to technical editing of the SEIS, the staff needs additional time to complete the final SEIS. The new issuance date for the final SEIS is January 2015.

Enclosed is the NRC staff's revised review schedule for the Davis-Besse license renewal application. If you have any questions related to the revised environmental schedule, please contact Elaine Keegan at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.

Sincerely,

/RA Dennis Morey for/

Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

Revised Schedule cc w/encl: Listserv

ML14329A479 *concurred via email OFFICE LA:DLR* PM:RPB2:DLR BC:RPB2:DLR BC:RPB1:DLR D:DLR YDiaz-Sanabria NAME IBetts EKeegan BWittick CMiller (DMorey for)

(JMitchell for)

DATE 11/25/2014 11/26/14 11/26/14 11/28/14 11/28/14

DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - LICENSE RENEWAL APPLICATION SCHEDULE REVISION Schedule Actual Milestones Date Date Receive license renewal application (LRA) 08/30/10 08/30/10 Publish Federal Register Notice (FRN) - LRA receipt and 09/17/10 09/20/10 availability Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10 Publish FRN - intent to conduct environmental scoping 10/20/10 10/28/10 Public Meeting - license renewal process and environmental 11/04/10 11/04/10 scoping Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10 Environmental scoping periods ends 12/27/10 12/27/10 Audit - scoping and screening methodology 01/24/11 01/24/11 Audit - aging management programs (AMPs) 02/14/11 02/14/11 Audit - environmental 03/07/11 03/07/11 Inspection - scoping, screening, and AMPs 04/2011 04/25/11 Environmental Requests for Additional Information (RAIs) - Issued 04/08/11 02/23/11 Safety RAIs - Issued 04/29/11 04/29/11 Environmental RAIs - Response Received 05/13/11 03/23/11 Safety RAI - Responses Received 05/30/11 05/30/11 Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12 ACRS subcommittee meeting on SER with open item(s) 09/19/12 09/19/12 Issue SER 09/2013 09/03/13 Issue draft supplemental environmental impact statement (SEIS) 02/2014 02/26/14 ACRS second subcommittee meeting on SER TBD Public Meeting - draft SEIS 03/2014 03/25/14 End of comment period for the draft SEIS 04/2014 04/21/14 ACRS full committee meeting on SER TBD Issue final SEIS 01/2015 Decision - Director, Office of Nuclear Reactor Regulation TBD Commission decision (hearing pending) TBD ENCLOSURE

Letter to R. Lieb from C. Miller dated November 28, 2014

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource Listserv


Emmanuel.Sayoc@nrc.gov Elaine.Keegan@nrc.gov Richard.Plasse@nrc.gov Brian.Wittick@nrc.gov Yoira.Diaz-Sanabria@nrc.gov John.Lamb@nrc.gov David.McIntyre@nrc.gov Eva.Brown@nrc.gov Brian.Harris@nrc.gov Daniel.Kimble@nrc.gov Adam.Wilson@nrc.gov Jamnes.Cameron@nrc.gov Viktoria.Mitlyng@nrc.gov