ML13136A133

From kanterella
Jump to navigation Jump to search

Schedule Revision for the Environmental Review of the Davis-Besse Nuclear Power Station, License Renewal Application
ML13136A133
Person / Time
Site: Davis Besse 
Issue date: 05/23/2013
From: John Lubinski
Division of License Renewal
To: Lieb R
Davis-Besse Review Group
Elaine Keegan 301-415-8517
References
TAC ME4613
Download: ML13136A133 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 23,2013 Mr. Raymond A. Lieb, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-30S0 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

Dear Mr. Lieb:

By letter dated August 27, 2010, FirstEnergy Nuclear Operating Company (FENOC) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-003 for the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC).

This letter is to inform you of a change in the environmental review schedule for the Davis Besse license renewal review.

Enclosed is the NRC staff's revised environmental review schedule for the Davis-Besse license renewal application (LRA). The schedule is being revised because the NRC staff requires the additional time to allow for internal review of the Supplemental Environmental Impact Statement (SEIS) in a manner which balances the internal workload across numerous ongoing reviews.

Enclosed is the revised schedule for the review of the Davis-Besse LRA. The schedule has been updated to reflect a change in the date of the issuance of the draft SEIS and subsequent environmental review milestones.

R. Lieb

-2 If you have any questions on the revised schedule, Ms. Elaine Keegan, project manager for the Davis-Besse LRA environmental review by telephone at 301-415-8517 or bye-mail at Elaine. Keegan@nrc.gov.

W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

Revised safety review schedule cc w/encl: Listserv

R. Lieb

-2 If you have any questions on the revised schedule, Ms. Elaine Keegan, project manager for the Davis-Besse LRA environmental review by telephone at 301-415-8517 or bye-mail at Elaine. Keeg an@nrc.gov.

Sincerely, IRA!

John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

Revised safety review schedule cc w/encl: Listserv DISTRIBUTION: See next page ADAMS Accession No.: ML13136A133 OFFICE NAME DATE PM:DLR/RPB2 EKeegan 5/22/2013 LA:DLR/RPB1*

IKing 5/22/2013 BC:DLR/RPB2 ASimmons 5/22/2013 D:DLR JLubinski 5/23/2013 OFFICIAL RECORD COpy

Letter to R. Lieb from M. Wong dated May 23, 2013

SUBJECT:

SCHEDULE REVISION FOR THE SAFETY AND ENVIRONMENTAL REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource EKeegan ASimmons MWong BHarris, OGC AWang MMahoney DMclntyre, OPA VMitlyng, OPA TRiley,OCA EWilliamson, OGC RRihm, EDO JCameron, Rill

DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 LICENSE RENEWAL APPLICATION UPDATED SAFETY REVIEW SCHEDULE Milestones Schedule Date Actual Date Receive license renewal application (LRA) 08/30/10 08/30/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/17/10 09/20/10 Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10 Public Meeting - license renewal process and environmental scoping 11/04/10 11/04/10 Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10 Audit - scoping and screening methodology 01/24/11 01/24/11 Audit - aging management programs (AMPs) 02/14/11 02/14/11 Inspection - scoping, screening, and AMPs 04/2011 04/25/11 Safety Requests for Additional Information (RAls) - Issued 04/29/11 04/29/11 Safety RAls - First Round Responses Received 05/30/11 05/30/11 Issue draft supplemental environmental impact statement (SEIS) 7/2013 Public Meeting-draft SEIS 8/2013 End of comment period for the draft SEIS 9/2013 Issue safety evaluation report (SER) with open items(s) 7/2012 7/31/12 Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting on SER with open item(s) 9/19/12 9/19/12 Issue SER 7/2013 ACRS full committee meeting on SER 9/2013 Issue final SEIS 3/2014 NRR Decision TBD Commission Decision (hearing pending)

TBD ENCLOSURE