Letter Sequence Approval |
|---|
|
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: L-11-222, Ohio Department of Natural Resources Office of Coastal Management Concurrence with Federal Consistency Certification Related to the Review of License Renewal Application Environmental Report, L-12-244, Correction of Errors in the License Renewal Application Environmental Report Severe Accident Mitigation Alternatives Analysis, and License Renewal Application Amendment No. 29, L-14-206, License Renewal Application Amendment No. 50 - Annual Update, ML102450565, ML11193A093
|
MONTHYEARML1024505652010-08-27027 August 2010 License Renewal Application and Ohio Coastal Management Program Consistency Certification Project stage: Other 05000346/LER-2011-002, Regarding Containment Air Cooler Isolation Valve Disabled Due to Drawing Omission2011-03-23023 March 2011 Regarding Containment Air Cooler Isolation Valve Disabled Due to Drawing Omission Project stage: Request ML11193A0932011-05-27027 May 2011 Reply to RAI for the Review of the Davis-Besse Nuclear Power Station, Unit 1, License Renewal Application Environmental Report and Enclosure a - Environmental Audit Needs List Project stage: Other ML1108202762011-06-0303 June 2011 Summary of Site Audit Related to the Review of the License Renewal Application for Davis-Besse Nuclear Power Station, Unit 1 Project stage: Approval L-11-154, Reply to Request for Additional Information for the Review of License Renewal Application, Environmental Report Severe Accident Mitigation Alternatives Analysis, and License Renewal Application Amendment No. 102011-06-24024 June 2011 Reply to Request for Additional Information for the Review of License Renewal Application, Environmental Report Severe Accident Mitigation Alternatives Analysis, and License Renewal Application Amendment No. 10 Project stage: Response to RAI L-11-222, Ohio Department of Natural Resources Office of Coastal Management Concurrence with Federal Consistency Certification Related to the Review of License Renewal Application Environmental Report2011-07-11011 July 2011 Ohio Department of Natural Resources Office of Coastal Management Concurrence with Federal Consistency Certification Related to the Review of License Renewal Application Environmental Report Project stage: Other ML1122701392011-08-15015 August 2011 Request for Additional Information Response Clarification from Davis-Besse Nuclear Power Station in Support of License Renewal Application Review Project stage: RAI L-11-251, Reply to Supplemental Request for Additional Information for Review of License Renewal Application, Environmental Report Severe Accident Mitigation Alternatives Analysis2011-09-0101 September 2011 Reply to Supplemental Request for Additional Information for Review of License Renewal Application, Environmental Report Severe Accident Mitigation Alternatives Analysis Project stage: Supplement L-11-288, License Renewal Application Amendment No. 17, Supplemental Information for Environmental Report2011-09-19019 September 2011 License Renewal Application Amendment No. 17, Supplemental Information for Environmental Report Project stage: Supplement L-11-289, License Renewal Application Amendment No. 16, Supplemental Information for the Review of the License Renewal Application Environmental Report2011-09-19019 September 2011 License Renewal Application Amendment No. 16, Supplemental Information for the Review of the License Renewal Application Environmental Report Project stage: Supplement ML11256A1642011-10-31031 October 2011 Schedule Revision for the Environmental and Safety Review of the Davis-Besse Nuclear Power Station, Unit 1, License Renewal Application Project stage: Approval ML12032A1312012-01-31031 January 2012 Schedule Revision for the Environmental Review of the Davis-Besse Nuclear Power Station, Unit No. 1, LRA Project stage: Approval ML12025A1092012-01-31031 January 2012 Schedule Revision for the Environmental Review of the Davis-Besse Nuclear Power Station, Unit No. 1, License Renewal Application Project stage: Approval L-12-244, Correction of Errors in the License Renewal Application Environmental Report Severe Accident Mitigation Alternatives Analysis, and License Renewal Application Amendment No. 292012-07-16016 July 2012 Correction of Errors in the License Renewal Application Environmental Report Severe Accident Mitigation Alternatives Analysis, and License Renewal Application Amendment No. 29 Project stage: Other ML13136A1332013-05-23023 May 2013 Schedule Revision for the Environmental Review of the Davis-Besse Nuclear Power Station, License Renewal Application Project stage: Approval ML13205A0362013-07-31031 July 2013 Schedule Revision for the Environmental and Safety Review of the Davis-Besse Nuclear Power Station License Renewal Application Project stage: Approval ML13302C2072013-11-0606 November 2013 Schedule Revision for the Review of the Davis-Besse Nuclear Power Station License Renewal Application Project stage: Approval ML14027A2172014-01-30030 January 2014 Schedule Revision for Environmental Review of Davis-Besse Nuclear Power Station License Renewal Application Project stage: Approval ML14097A2722014-03-25025 March 2014 Slides for Davis-Besse Draft SEIS for License Renewal Public Meeting - Preliminary Site-Specific Results of the License Renewal Environmental Review for Davis-Besse Nuclear Power Station, March 25, 2014 Project stage: Draft Approval ML14097A2532014-03-25025 March 2014 Transcript of 03/25/2014 for Davis-Besse Nuclear Power Station Draft Environmental Impact Statement Public Meeting: Evening Session - Corrected. Pages 1-84 Project stage: Request ML14097A2542014-03-25025 March 2014 Draft Environmental Impact Statement Public Meeting: Afternoon Session - Corrected. Pages 1-56 Project stage: Request ML14112A3152014-04-21021 April 2014 Review of Draft Plant-Specific Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding ML14099A3392014-04-22022 April 2014 March 27, 2014, Summary of Telephone Conference Call Held Between Nuclear Regulatory Commission and First Energy Nuclear Operating Company Concerning Commitment 13 of the Safety Evaluation Report Pertaining to the Davis Besse Unit 1, Licens Project stage: Request ML14099A4642014-05-0606 May 2014 Summary of Public Meetings to Discuss Draft Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Generating Station, Unit 1 L-14-206, License Renewal Application Amendment No. 50 - Annual Update2014-06-23023 June 2014 License Renewal Application Amendment No. 50 - Annual Update Project stage: Other ML14329A4792014-11-28028 November 2014 Schedule Revision for the Review of the Davis-Besse Nuclear Power Station License Renewal Application (TAC No. ME613) Project stage: Approval ML15022A2532015-01-29029 January 2015 Schedule Revision for the Review of the Davis-Besse Nuclear Power Station License Renewal Application TAC No. ME4613) Project stage: Approval ML15054A5342015-02-27027 February 2015 Schedule Revision and Project Manager Change for the Review of the Davis-Besse Nuclear Power Station License Renewal Application Project stage: Approval ML15083A0992015-03-31031 March 2015 Schedule Revision for the Review of the Davis-Besse Nuclear Power Station License Renewal Application Project stage: Approval ML15113A1072015-04-30030 April 2015 Schedule Revision for the Review of the Davis-Besse Nuclear Power Station License Renewal Application Project stage: Approval 2013-11-06
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 31, 2011 Mr. Barry S. Allen, Site Vice President, FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL AND SAFETY REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1, LICENSE RENEWAL APPLICATION (TAC NO. ME4613)
Dear Mr. Allen:
By letter dated August 27,2010, FirstEnergy Nuclear Operating Company (FENOC) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew the Operating License NPF-003 for the Davis-Besse Nuclear Power Station, Unit No.1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).
By two separate letters dated September 19, 2011, FENOC submitted additional information as supplements to the license renewal application (LRA), Appendix E, Environmental Report.
These supplements contained information relating to alternatives as well as a letter from the U.S. Fish and Wildlife Service identifying an endangered species within the transmission line corridor.
Enclosed is the NRC staffs revised environmental review schedule for the Davis-Besse LRA.
In developing the revised environmental review schedule, the staff took several factors into consideration, including additional review of the in-depth alternatives and additional coordination with Federal, State and local governments. The environmental schedule change has no impact on the planned license renewal decision date.
Based on the number of open items, the NRC staff is evaluating the impact and will issue a revised schedule for the safety evaluation and the date of a license renewal decision, as needed, in a separate letter.
B. Allen
- 2 We would like to emphasize that the NRC staff will make every effort to meet the revised schedule milestones. The NRC will continue to follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Parts 54 and 51.
If you have any questions on the revised schedule, please contact Ms. Paula Cooper, Project Manager for the review of the Davis-Besse LRA environmental review, by telephone at 301-415-2323 or bye-mail at paula.cooper@nrc.gov.
Sincerely, Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
As stated cc w/encl: Listserv
DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Milestones Schedule Date Actual Date Receive license renewal application (LRA) 08/30/10 08/30/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/17/10 09/20/10 Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10 Publish FRN - intent to conduct environmental scoping 10/20/10 10/28/10 Public Meeting - license renewal process and environmental scoping 11/04/10 11/04/10 Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10 Environmental scoping periods ends 12/27/10 12/27/10 Audit - scoping and screening methodology 01/24/11 01/24/11 Audit - aging management programs (AMPs) 02/14/11 02/14/11 Audit - environmental 03/07/11 03/07/11 Inspection - scoping, screening, and AMPs 04/2011 04/25/11 Environmental Requests for Additional Information (RAls) - Issued 04/08/11 Environmental RAls - Response Received 05/13/11 03/23/11 Safety RAls -Issued 04/29/11 04/29/11 Safety RAI - Responses Received 05/30/11 05/30/11 Issue draft supplemental environmental impact statement (SEIS) 01/2012 Public Meeting - draft SEIS 02/2012 End of comment period for the draft SEIS 04/2012 Issue final SEIS 07/2012 ENCLOSURE
"" ML11256A164
- concurrence via e-mail OFFICE LA:DLR/RPB2 PM:DLR/RPB2 PM:DLR/RPB1 BC:DLR/RPB2 BC:DLR/RPB1 NAME IKing PCooper SCuadrado DWrona (AI mboden for)
DMorey DATE 09/13/2011 10104/2011 10/14/2011 10/6/2011 10/10/2011 OFFICE BC: DLR/RERB LA: DLR/RPB2 AD:DLR NAME Almboden IKinQ MGaliowav DATE 10/6/2011 10131/2011 10/31/2011
Letter to Barry S. Allen from Melanie A. Galloway dated October 31,2011
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1, LICENSE RENEWAL APPLICATION (TAC NO. ME4613)
DISTRI BUTION:
HARD COPY:
DLR R/F E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource B. Harris B. Harris, OGC A. Wang M. Mahoney I. Couret, OPA V. Mitlyng, OPA T. Reilly, OCA E. Williamson, OGC R. Rihm, EDO J. Cameron, Rill