UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 31, 2011 Mr. Barry S. Allen, Site Vice President, FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL AND SAFETY REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1, LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

Dear Mr. Allen:

By letter dated August 27,2010, FirstEnergy Nuclear Operating Company (FENOC) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew the Operating License NPF-003 for the Davis-Besse Nuclear Power Station, Unit No.1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).

By two separate letters dated September 19, 2011, FENOC submitted additional information as supplements to the license renewal application (LRA), Appendix E, Environmental Report.

These supplements contained information relating to alternatives as well as a letter from the U.S. Fish and Wildlife Service identifying an endangered species within the transmission line corridor.

Enclosed is the NRC staffs revised environmental review schedule for the Davis-Besse LRA.

In developing the revised environmental review schedule, the staff took several factors into consideration, including additional review of the in-depth alternatives and additional coordination with Federal, State and local governments. The environmental schedule change has no impact on the planned license renewal decision date.

Based on the number of open items, the NRC staff is evaluating the impact and will issue a revised schedule for the safety evaluation and the date of a license renewal decision, as needed, in a separate letter.

B. Allen

- 2 We would like to emphasize that the NRC staff will make every effort to meet the revised schedule milestones. The NRC will continue to follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Parts 54 and 51.

If you have any questions on the revised schedule, please contact Ms. Paula Cooper, Project Manager for the review of the Davis-Besse LRA environmental review, by telephone at 301-415-2323 or bye-mail at paula.cooper@nrc.gov.

Sincerely, Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

As stated cc w/encl: Listserv

DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Milestones Schedule Date Actual Date Receive license renewal application (LRA) 08/30/10 08/30/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/17/10 09/20/10 Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10 Publish FRN - intent to conduct environmental scoping 10/20/10 10/28/10 Public Meeting - license renewal process and environmental scoping 11/04/10 11/04/10 Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10 Environmental scoping periods ends 12/27/10 12/27/10 Audit - scoping and screening methodology 01/24/11 01/24/11 Audit - aging management programs (AMPs) 02/14/11 02/14/11 Audit - environmental 03/07/11 03/07/11 Inspection - scoping, screening, and AMPs 04/2011 04/25/11 Environmental Requests for Additional Information (RAls) - Issued 04/08/11 Environmental RAls - Response Received 05/13/11 03/23/11 Safety RAls -Issued 04/29/11 04/29/11 Safety RAI - Responses Received 05/30/11 05/30/11 Issue draft supplemental environmental impact statement (SEIS) 01/2012 Public Meeting - draft SEIS 02/2012 End of comment period for the draft SEIS 04/2012 Issue final SEIS 07/2012 ENCLOSURE

"" ML11256A164

  • concurrence via e-mail OFFICE LA:DLR/RPB2 PM:DLR/RPB2 PM:DLR/RPB1 BC:DLR/RPB2 BC:DLR/RPB1 NAME IKing PCooper SCuadrado DWrona (AI mboden for)

DMorey DATE 09/13/2011 10104/2011 10/14/2011 10/6/2011 10/10/2011 OFFICE BC: DLR/RERB LA: DLR/RPB2 AD:DLR NAME Almboden IKinQ MGaliowav DATE 10/6/2011 10131/2011 10/31/2011

Letter to Barry S. Allen from Melanie A. Galloway dated October 31,2011

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1, LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

DISTRI BUTION:

HARD COPY:

DLR R/F E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource B. Harris B. Harris, OGC A. Wang M. Mahoney I. Couret, OPA V. Mitlyng, OPA T. Reilly, OCA E. Williamson, OGC R. Rihm, EDO J. Cameron, Rill