Letter Sequence Approval |
---|
|
|
MONTHYEARML12181A3122012-06-27027 June 2012 (Ons), Units 1, 2, and 3, License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds Project stage: Request ML12314A4342012-11-13013 November 2012 Request for Additional Information Regarding Amendment Application for a Revision to the Technical Specification on the Emergency Power System Project stage: RAI ML13151A0232013-05-28028 May 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field.. Project stage: Request ML13171A2952013-06-26026 June 2013 Request for Additional Information Regarding Amendment Application for a Revision to the Technical Specification on the Emergency Power System Project stage: RAI ML13190A0162013-06-28028 June 2013 Licensing Basis for the Protected Service Water System - Responses to Request for Additional Information - Supplement 5 Project stage: Supplement ML13214A3842013-07-26026 July 2013 (Ons), Units 1, 2, & 3, Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field... Project stage: Request ML13228A2682013-08-0707 August 2013 Licensing Basis for Protected Service Water System - Updated Responses to Request for Additional Information Item Nos. 107, 109(a) and 109(b); License Amendment Request (LAR) 2008-07-Supplement 6 Project stage: Supplement ML13336A5452013-11-13013 November 2013 Presentation Slides from Meeting with Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3, Keowee Hydro Unit Generator Field Pole Rewind Project - License Amendment Request Project stage: Meeting ML13326A7212013-11-22022 November 2013 Request for Additional Information - Protected Service Water System Project stage: RAI ONS-2013-029, Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License.2013-11-26026 November 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License. Project stage: Request ML13338A3742013-12-0303 December 2013 12/3/13 E-mail from R.Guzman to B.Shingleton - Follow-up Request for Additional Information Keowee LAR for Temp TS Change to Support Keowee Generator Pole Rewind Work Project stage: RAI ML13336A5982013-12-0404 December 2013 Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss the Proposed One-time TS Completion Time Change to Perform Khu Generator Field Pole Rewind Maintenance - Oconee Nuclear Station Units 1, 2, and 3 (TAC Nos. ME9021, ME9022, and M Project stage: Meeting ML13346A0202013-12-0606 December 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License.... Project stage: Request ML13349A0022013-12-12012 December 2013 E-mail from B.Shingleton to R.Guzman Revised TS 3.8.1 Markup Pages for License Amendment Request to Extend Khu Allowed Outage Time for Field Pole Rewind Work Project stage: Request ML13351A3172013-12-24024 December 2013 Safety Evaluation Input Regarding Temporary Technical Specification Change Request to Extend the Completion Time for an Inoperable Keowee Hydro Unit Project stage: Approval ML13357A6742014-01-0808 January 2014 Issuance of Amendments Regarding the Temporary Technical Specification Change to Extend the Completion Time for an Inoperable Keowee Hydro Unit (TAC ME9021, ME9022, and ME9023) Project stage: Approval ML14021A0022014-01-17017 January 2014 1/17/14 E-mail from R.Guzman to B. Shingleton - Minor Comments to Safety Evaluation for Amendment Temporary TS Change Request to Extend the Completion Time for an Inoperable Keowee Hydro Unit (TAC Nos. ME9021/22/23) Project stage: Approval 2013-12-04
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24257A0212024-09-11011 September 2024 Document Request for Oconee Nuclear Station - Radiation Protection Inspection - Inspection Report 2024-04 ML24234A2972024-08-21021 August 2024 August 21, 2024 - Oconee Nuclear Station, Units 1, 2, and 3 - Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 3.7.7 ML24211A0872024-07-27027 July 2024 EN 57079 Paragon Energy Solutions Final - No Active Links ML24197A2292024-07-15015 July 2024 Email from Mark Yoo (NRC) to Steve Snider (Duke) - Oconee SLRA - RAI - 2024 Annual Update ML24190A0462024-07-0505 July 2024 Notification of Inspection and Request for Information ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24143A1322024-05-22022 May 2024 May 22, 2024, Verbal Authorization for Duke Energy Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI (RA-24-0152) (EPID L- 2024-LLR-0034) ML24127A0892024-05-0202 May 2024 57079-EN57079-1 - Redline Strikethrough e-mail Re Part 21 Interim Notification of Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24086A3772024-03-26026 March 2024 Request for Additional Information License Amendment Request to Revise Technical Specification 5.5.2 ML24036A1442024-02-27027 February 2024 NRC to Fws, NRC Request for Concurrence with Endangered Species Act Determinations for Oconee Nuclear Station, Units 1, 2, and 3, Proposed Subsequent License Renewal in Oconee County, South Carolina (Consultation Code: 2023-0054989) ML24054A0492024-02-21021 February 2024 Notification of Oconee Nuclear Station FEI Inspection and Information Request-Email ML23349A0272023-12-15015 December 2023 – Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 5.5.2 ML23284A3322023-10-11011 October 2023 Request for Additional Information Alternative Request (RA-22-0174) (L-2022-LLR-0060) ML23270B8362023-09-26026 September 2023 Code Case N-752 Audit September 26, 2023, E-mail Providing Additional Information Regarding the Use of Owners Requirements and Engineering Judgment in Lieu of Code and Standards ML23267A0032023-09-21021 September 2023 RP Inspection Document Request ML23269A0412023-08-22022 August 2023 Code Case N-752 Audit; August 22, 2023, E-mail Providing Additional Information Regarding Design and Quality Program Requirements ML23172A0132023-06-20020 June 2023 Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23153A1892023-06-0202 June 2023 Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23144A0862023-05-24024 May 2023 Acceptance of Requested Licensing Action Proposed Relief Request (RA-23-0018) to Use ASME Code Case 853 ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23125A1452023-05-0505 May 2023 Change in Estimated Review Schedule and Level of Effort for Proposed Alternative to Use Code Case N-752 ML23124A1212023-05-0404 May 2023 Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23095A0052023-04-0404 April 2023 002 Radiation Safety Baseline Inspection Information Request ML23086C0362023-03-27027 March 2023 Request for Additional Information Steam Generator Tube Inspection Report (03R31) ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML23038A1832023-02-0707 February 2023 Request for Additional Information Alternative Request (RA-22-0174) to Use ASME Code Case N-752 ML23031A1552023-01-17017 January 2023 1/17/2023 Email from John Moses, Deputy Director, Division of Rulemaking, Environmental, and Financial Support, to Diane Curran, Counsel to Beyond Nuclear and the Sierra Club, Request for Extension of Scoping Comment Period for Oconee EIS ML22294A0812022-10-21021 October 2022 Nrc/Duke Steam Generator Inspection Call for November 8, 2022 NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) ML22251A2902022-09-0808 September 2022 Request for Additional Information Additional Mode Change Limitations Applicable to the Adoption of Technical Specifications Tasks Force Traveler (TSTF) No. 359, Revision 9 ML22235A6552022-08-23023 August 2022 Acceptance of Requested Licensing Action Proposed Alternative to Use ASME Code Case N-752 NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22234A1262022-07-0808 July 2022 Email from NRC to Duke - Feedback on Trp 76 RAI Responses - July 8, 2022 ML22234A1272022-06-14014 June 2022 Email from NRC to Duke - Feedback on Trp 76 RAI Responses - June 14, 2022 ML22154A2142022-06-0101 June 2022 Email from NRC (Angela Wu) to Duke (Paul Guill) - Oconee SLRA - 2nd Round RAI B2.1.7-4b ML22157A0012022-06-0101 June 2022 Email from NRC (Angela Wu) to Duke (Paul Guill) - Oconee SLRA - Additional NRC Comments on RAI 4.6.1-1a ML22124A2052022-05-0404 May 2022 Summary of May 4, 2022, Clarification Call with Duke Energy Carolinas, LLC, Application to Revise TS 3.7.7, Low Pressure Service Water (LPSW) System ML22124A1612022-05-0303 May 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.7-4a ML22122A0192022-04-28028 April 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.9-2a ML22122A1322022-04-27027 April 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round Requests for Additional Information (FE 3.5.2.2.2.6 - Irradiation Structural) ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22130A0112022-04-25025 April 2022 Email: Oconee SLRA - RAI 4.6.1-1a - NRC Staff Comments ML22112A1892022-04-22022 April 2022 Acceptance Review for Additional Mode Change Limitations Applicable to the Adoption of TSTF- 359, Revision 9 ML22113A0082022-04-20020 April 2022 Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Additional Information 3.1.2-1 ML22112A0072022-04-20020 April 2022 Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Confirmation of Information 3.5.2.2.2.6-L ML22088A0452022-03-28028 March 2022 Radiation Safety Baseline Inspection Initial Information Request Inspection Report 2022002 2024-09-11
[Table view] |
Text
From: Guzman, Richard Sent: Friday, January 17, 2014 1:07 PM To: 'Shingleton, Boyd' Cc: Wasik, Christopher J
Subject:
RE: Minor comments on Safety Evaluation for Amendment Nos 383 385 &
384.docx
- Boyd, As we discussed, I have no objections to your comments; I agree these are minor errors, administrative in nature (see below) and do not impact the NRC staffs safety basis and reasonable assurance determination/conclusion. While I do not intend on issuing a correction letter, this email exchange will be added to ADAMS as an official agency record for staffs consideration for future reference/related applications. I do appreciate your quality read and review of the SE; thank you for your comments.
Minor comments on Safety Evaluation for Amendment Nos. 383, 385, & 384
- 1. In the description of the requested TS Change (Section 3.2), the last sentence on page 4 starting with The above note is added to avoid using up the 45 day CT concurrent should be below the note for TS RA C.2.2.5 on page 5 and should refer to Note 2 since these were broken into 3 notes. The Note above modifies RA C.2.2.3. This note modifies the 45 day CT of RA C.2.2.5.
Your comment is noted by the NRC staff. The quoted sentence should have read, The below above note is added
- 2. In the description of the requested TS Change (Section 3.2), while there is mention of notes being added below the 45 day CT, there is no mention of the 62 day completion time that they apply to.
Your comment is noted by the NRC staff. We agree the SE Section 3.2 would be more clear and improved with a description of how the notes are applicable to the 62-day completion time.
- 3. The last 4 sentences on page 6, while true, are not relevant to the pole rewind work.
Don't have to seal wicket gates to perform generator work, just need to dewater the penstock so we can install a shaft locking device.
This technicality is noted by the NRC staff; however, it does not affect the staffs reasonable assurance determination regarding the acceptability of the proposed Technical Specification change.
- 4. The first sentence on page 10 says that in letter dated December 14, 2012, the licensee stated that the generator field pole rewind work will be performed in January and July of 2014, to avoid performing the work during the peak tornado months of March, April, May, and June. The December 14, 2012 letter doesnt say this. In this letter (RAI 2 response), we said there was no need to avoid the peak tornado months based on the PRA assessment. We later (in phone conversations) said that by scheduling them as we had we were avoiding, for the most part, the peak tornado months.
The comment is noted by the NRC staff w/no objections or questions. We agree it is not a completely accurate statement.
- 5. Page 14, Section 3.7, first bullet: With two KHUs in allowed outage time for maintenance, in addition to LCT, other back-up power sources (a diesel generator at KHU Station, and a black-start capable Hydro Power Unit at Jocassee Station) are available and can provide power to safety system buses necessary to maintain all three ONS units in a safe shutdown condition, should a loss of all station power occur, until power can be restored. The diesel generator a the KHU station can restore the remaining operable KHU when in dual KHU outage - the KHU can get all three ONS unit in a safe shutdown condition. Note: Section 3.4, page 8, 2nd bullet characterizes the function of the backup DG at Keowee more complete so the shortened version in the conclusion section is okay.
The comment is noted by the NRC staff w/no objections or questions. The Section 3.4, page 8, 2nd bullet is a more appropriate characterization of the function of the backup DG at Keowee.
Rich Guzman Sr. Project Manager NRR/DORL/LPL1-1 US NRC 301-415-1030 From: Shingleton, Boyd [1]
Sent: Tuesday, January 14, 2014 8:05 AM To: Guzman, Richard Cc: Wasik, Christopher J
Subject:
Minor comments on Safety Evaluation for Amendment Nos 383 385 & 384.docx
- Rich, A few minor comments on the Safety Evaluation for the 62 day Keowee LAR. My opinion is they dont affect any of the conclusions and dont require any changes to the SE. Ill call you to discuss.
Boyd Shingleton ONS Regulatory Affairs 864-873-4716