Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Confirmation of Information 3.5.2.2.2.6-L
ML22112A007
Person / Time
Site: Oconee  Duke energy icon.png
Issue date: 04/20/2022
From: Mary Johnson
NRC/NRR/DNRL/NLRP
To: Snider S
Duke Energy Carolinas
Johnson M, (301) 415-5861
Shared Package
ML22112A004 List:
References
Download: ML22112A007 (1)


Text

From: Johnson, Marieliz To: Steve.Snider@duke-energy.com Cc: RidsNrrDnrl Resource; RidsNrrPMOconee Resource; Gibson, Lauren; Smith - NRR, Brian; Thomson, Bernie; Williams, Shawn; Markley, Michael; Woods, Mary Frances; Wright, Megan; Azeizat, Joseph; Nolan, Caty; Burnell, Scott; Wilkins, Lynnea; McIntyre, Dave; Screnci, Diane; Gasperson, Dave; Pelchat, John; Nadel, Jared; Baptist, James; Paul.Guill@duke-energy.com; Reene.Gambrell@duke-energy.com; Arun.Kapur@duke-energy.com; Wu, Angela

Subject:

Oconee SLRA - Request for Confirmation of Information 3.5.2.2.2.6-L Date: Wednesday, April 20, 2022 10:03:00 AM Mr. Snider, By letter dated June 7, 2021 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML21158A193), as supplemented by letters dated October 22, 2021 (ADAMS Accession No. ML21295A035), October 28, 2021 (ADAMS Accession No. ML21302A208), November 11, 2021 (ADAMS Accession No. ML21315A012),

December 2, 2021 (ADAMS Accession No. ML21336A001), December 15, 2021 (ADAMS Accession No. ML21349A005), December 17, 2021 (ADAMS Accession No. ML21351A000),

January 7, 2022 (ADAMS Accession No. ML22010A129), January 21, 2022 (ADAMS Accession No. ML22021A000), February 14, 2022 (ADAMS Accession No. ML22045A021), February 21, 2022 (ADAMS Accession No. ML22052A002), March 22, 2022 (ADAMS Accession No. ML22081A027), and March 31, 2022 (ADAMS Accession No. ML22090A046), Duke Energy Carolinas, LLC (Duke Energy) submitted to the U.S. Nuclear Regulatory Commission (NRC or staff) an application to renew the Renewed Facility Operating License Nos. DPR-38, DPR-47, and DPR-55 for the Oconee Nuclear Station (ONS), Units 1, 2, and 3. Duke Energy submitted the application pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal.

The NRC staff is in the process of reviewing your application. Based on the review, the NRC staff has identified the attached final request for additional information (RAI).

The schedule for your response to this RAI was discussed with Paul Guill of your staff, and a mutually agreeable date for the response is within 30 days from the date of this email, or as otherwise agreed upon with the NRC Project Manager.

If you have any questions, please contact me or Angela by e-mail at Marieliz.Vera@nrc.gov or Angela.Wu@nrc.gov.

Sincerely, Marieliz Johnson, Project Manager Division of New and Renewed Licenses (DNRL)

Office of Nuclear Reactor Regulation (NRR)

U.S. Nuclear Regulatory Commission (NRC)