From:
Shingleton, Boyd To:
Guzman, Richard Cc:
Wasik, Christopher J; Patterson, Terry L
Subject:
RE: Retyped TS 3.8.1 pages for LAR 2012-01 ( 62 day Completion Time)
Date:
Thursday, December 12, 2013 3:18:59 PM Attachments:
ONS-TS-3.8.1_markup_with note change.pdf ONS-TS-3.8.1_retype_with note change.pdf
- Rich,
I discussed the TS reviewers proposed revision of Note 2 to the 45-day cumulative Completion Time with Chris Wasik (ONS Regulatory Affairs Manager) and Terry Patterson (ONS Safety Assurance Manager). ONS considers the proposed revision to Note 2 editorial and therefore, find it acceptable. Attached are the revised TS markup pages and TS retyped pages incorporating the proposed revision.
Boyd Shingleton ONS Regulatory Affairs 864-873-4716
From: Guzman, Richard [1]
Sent: Wednesday, December 11, 2013 8:20 AM To: Shingleton, Boyd
Subject:
RE: Retyped TS 3.8.1 pages for LAR 2012-01 ( 62 day Completion Time)
- This is an EXTERNAL email. Exercise caution. DO NOT open attachments or click links from unknown senders or unexpected email. ***
- Boyd,
The TS reviewers provided some comments on the proposed TS changes (shown below).
Let me know if you are in agreement w/the suggested change to the proposed TS. We can have a conference call to discuss, as needed.
The licensee proposes using or in the proposed TS Required Action 2.2.5, Completion Time NOTE. Use of and/or (logical) connectors in TS has specific meaning and understanding so, even though the licensees proposed use of or may be grammatically correct, NOTE 2 should be modified for Note clarity and because it does not use Oconee TS convention for logical connectors
Licensee proposed 2.2.5 TS Completion Time (new) Note 2 currently states:
- 2. Not applicable during generator field pole rewind work or until 1 year after KHU declared OPERABLE following rewind work.
The licensee should consider the following:
The proposed Note 2 be revised into Note 2 and Note 3 to clarify that the (current TS) 45-day cumulative CT is:
- 2. Not applicable during generator field pole rewind work.
- 3. Not applicable until 1 year after the KHU is declared OPERABLE following generator field pole rewind work.
The above Note 2 rewording is consistent with the licensees proposed NOTE preceding the 62 DAY one-time CT and Oconee TS Section 1.2, Logical Connectors.
Rich Guzman Sr. Project Manager NRR/DORL US NRC 301-415-1030
From: Shingleton, Boyd [2]
Sent: Tuesday, December 10, 2013 4:22 PM To: Guzman, Richard
Subject:
Retyped TS 3.8.1 pages for LAR 2012-01 ( 62 day Completion Time)
- Rich,
Attached are the retyped TS pages for TS 3.8.1 in Adobe format as you requested. The last page has no changes (but needs to be re-issued) other than some of Action D pushed over to this page due to the additional text added for the 62 day completion time.
Boyd Shingleton ONS Regulatory Affairs 864-873-4716
AC Sources - Operating 3.8.1 ACTIONS (continued)
OCONEE UNITS 1, 2, & 3 3.8.1-3 Amendment Nos. 347, 349, & 348 CONDITION REQUIRED ACTION COMPLETION TIME C.
KHU or its required overhead emergency power path inoperable due to reasons other than Condition A.
C.1 Perform SR 3.8.1.3 for OPERABLE KHU.
AND C.2.1 Restore the KHU and its required overhead emergency power path to OPERABLE status.
OR C.2.2.1 Energize both standby buses from LCT via isolated power path.
AND C.2.2.2 Suspend KHU generation to grid except for testing.
AND 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> AND Once per 7 days thereafter
NOTE-------------
An additional 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> can be added to the following completion times. This expires on August 27, 2005 @1058 hours 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from discovery of inoperable KHU 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized standby bus 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (continued)
AC Sources - Operating 3.8.1 ACTIONS OCONEE UNITS 1, 2, & 3 3.8.1-4 Amendment Nos. 353, 355, & 354 CONDITION REQUIRED ACTION COMPLETION TIME C.
(continued)
C.2.2.3 Verify by administrative means that the remaining KHU and its required underground emergency power path and both required offsite sources are OPERABLE and the requirements of LCO 3.8.3, "DC Sources-Operating," LCO 3.8.6, "Vital Inverters-Operating," LCO 3.8.8, "Distribution Systems-Operating," LCO 3.3.17, "EPSL Automatic Transfer Function," LCO 3.3.18, "EPSL Voltage Sensing Circuits," LCO 3.3.19, "EPSL 230 kV Switchyard DGVP,"
and LCO 3.3.21, "EPSL Keowee Emergency Start Function" are met.
AND 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (continued)
NOTE------------
Not applicable to remaining KHU and its required underground emergency power path or LCO 3.3.21 when in Condition H to perform generator field pole rewind work.
AC Sources - Operating 3.8.1 ACTIONS (continued)
OCONEE UNITS 1, 2, & 3 3.8.1-5 Amendment Nos. 382, 384, & 383 CONDITION REQUIRED ACTION COMPLETION TIME C. (continued)
C.2.2.4 Verify alternate power source capability by performing SR 3.8.1.16.
AND C.2.2.5 Restore KHU and its required overhead emergency power path to OPERABLE status.
72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> AND Every 31 days thereafter 28 days when Condition due to an inoperable Keowee main step-up transformer AND
NOTE------------
Not to exceed 45 days cumulative per rolling 3-year time period for each KHU 45 days from discovery of initial inoperability when Condition due to an inoperable KHU (continued)
AND
NOTE------------
- 2. Only applicable one time for each KHU due to generator field pole rewind work and expires on January 1, 2015.
- 3. Only applicable if the SSF and EFW are administratively verified OPERABLE prior to entering the extended Completion Time.
62 days from initial inoperability when Condition due to an inoperable KHU to perform generator field pole rewind work
- 2. Not applicable during generator field pole rewind work.
- 3. Not applicable until 1 year after the KHU is declared OPERABLE following generator field pole rewind work.
- 1.
.