MONTHYEARML12181A3122012-06-27027 June 2012 License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds Project stage: Request ML1221600472012-08-0303 August 2012 License Amendment Request, ME9021, ME9022, & ME9023, Acceptance Review (E-mail) Project stage: Acceptance Review ML12314A4342012-11-13013 November 2012 Request for Additional Information Regarding Amendment Application for a Revision to the Technical Specification on the Emergency Power System Project stage: RAI ML12359A0392012-12-14014 December 2012 Additional Information License Amendment Request for Temporary Tech Spec Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License Amendment Request Project stage: Request ML13077A0192013-03-11011 March 2013 Notification of Registration for Use of General License Spent Fuel Cask Number 127 Project stage: Request ML13094A4312013-04-12012 April 2013 Request for Additional Information Regarding Amendment Application Related to Maintenance on the Onsite Standby Power Sources Project stage: RAI ML13151A0232013-05-28028 May 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Project stage: Request ML13171A2952013-06-26026 June 2013 Request for Additional Information Regarding Amendment Application for a Revision to the Technical Specification on the Emergency Power System Project stage: RAI ML13214A3842013-07-26026 July 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field. Project stage: Request ML13336A5452013-11-13013 November 2013 Presentation Slides from Meeting with Duke Energy Carolinas, LLC, Oconee Nuclear Station Units 1, 2, and 3, Keowee Hydro Unit Generator Field Pole Rewind Project - License Amendment Request Project stage: Meeting ML13326A7212013-11-22022 November 2013 Request for Additional Information - Protected Service Water System Project stage: RAI ONS-2013-029, Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License2013-11-26026 November 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License Project stage: Request ML13338A3742013-12-0303 December 2013 12/3/13 E-mail from R.Guzman to B.Shingleton - Follow-up Request for Additional Information Keowee LAR for Temp TS Change to Support Keowee Generator Pole Rewind Work Project stage: RAI ML13336A5982013-12-0404 December 2013 Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss the Proposed One-time TS Completion Time Change to Perform Khu Generator Field Pole Rewind Maintenance - Oconee Nuclear Station Units 1, 2, and 3 (TAC Nos. ME9021, ME9022, and M Project stage: Meeting ML13346A0202013-12-0606 December 2013 Additional Information Regarding License Amendment Request for Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable for Generator Field Pole Rewinds License.. Project stage: Request ML13349A0022013-12-12012 December 2013 E-mail from B.Shingleton to R.Guzman Revised TS 3.8.1 Markup Pages for License Amendment Request to Extend Khu Allowed Outage Time for Field Pole Rewind Work Project stage: Request ML13351A3172013-12-24024 December 2013 Safety Evaluation Input Regarding Temporary Technical Specification Change Request to Extend the Completion Time for an Inoperable Keowee Hydro Unit Project stage: Approval ML13357A6742014-01-0808 January 2014 Issuance of Amendments Regarding the Temporary Technical Specification Change to Extend the Completion Time for an Inoperable Keowee Hydro Unit Project stage: Approval ML14021A0022014-01-17017 January 2014 1/17/14 E-mail from R.Guzman to B. Shingleton - Minor Comments to Safety Evaluation for Amendment Temporary TS Change Request to Extend the Completion Time for an Inoperable Keowee Hydro Unit (TAC Nos. ME9021/22/23) Project stage: Approval 2013-12-03
[Table View] |
Text
From:
Guzman, Richard Sent:
Tuesday, December 03, 2013 3:39 PM To:
'Shingleton, Boyd'
Subject:
RE: Keowee LAR for Temp TS Change to support Keowee generator pole rewind work
- Boyd, The following is the information that is requested by the technical staff to support the completion of their review. Let me know when youd like to discuss for clarifications w/the tech staff via conference call.
In the event of a loss of offsite power in all three Oconee units and a loss of coolant accident in one of the units please explain the following:
(1) Actions (manual and automatic) that must be taken to mitigate the consequence of an accident in one unit and bring the other two units in safe shut down condition when both KHUs are inoperable during the 62-hour KHU outage and only power sources available are the power sources not credited in the accident analysis (Oconee FSAR Chapter 15).
(2) Operating procedures established and operator training provided for the above condition to ensure that this activity can be completed safely with all reactors at full power.
- Thanks, Rich From: Shingleton, Boyd [1]
Sent: Tuesday, December 03, 2013 1:51 PM To: Guzman, Richard
Subject:
Keowee LAR for Temp TS Change to support Keowee generator pole rewind work
- Rich, Just a reminder - Do you have any information you can send me on the NRC Tech Staff open issue associated with compensatory actions that we need to address?