ML13120A584

From kanterella
Jump to navigation Jump to search
Request for Information for an NRC Triennial Baseline Component Design Bases Inspection (CDBI) Inspection Report 05000456-13-007 05000457-13-007
ML13120A584
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 04/29/2013
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Pacilio M
Exelon Generation Co, Exelon Nuclear
Caroline Tilton
References
IR-13-007
Download: ML13120A584 (8)


See also: IR 05000456/2013007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

April 29, 2013

Mr. Michael J. Pacilio

Senior Vice President, Exelon Generation Company, LLC

President and Chief Nuclear Officer, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2 REQUEST FOR INFORMATION FOR

AN NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION

(CDBI) INSPECTION REPORT 05000456/2013007/05000457/2013007

Dear Mr. Pacilio:

On July 29, 2013, the U. S. Nuclear Regulatory Commission (NRC) will begin a triennial

baseline Component Design Bases Inspection (CDBI) at Braidwood Station. A team of six

inspectors will perform this 3-week inspection. This inspection will be performed in accordance

with NRC Baseline Inspection Procedure (IP) 71111.21.

The CDBI focuses on the design, maintenance, and operation of risk significant components

associated with one or more accident scenario. The components to be reviewed during this

baseline inspection will be identified during the inoffice preparation week that occurs prior to the

first on-site inspection week. In addition, operating experience issues, associated with the

component samples, will also be selected for review. The inspection team may request

scenarios to be performed on the simulator. This request would require support from your

simulator staff to validate scenarios, simulator time, and a crew to perform the actions which

would most likely occur during the second on-site week. The team will work closely with your

staff early on during the inspection process to ensure this activity can be accomplished with

minimal impact.

The inspection will include three weeks on-site. The inspection team will consist of six NRC

inspectors, of which five will focus on engineering/maintenance and one on operations. The

current inspection schedule is as follows:

  • On-site weeks: July 29, 2013;

August 12, 2013; and

August 26, 2013.

The team will be preparing for the inspection, mainly during the week of July 22, 2013, as

discussed in the attached enclosure.

M. Pacilio -2-

Experience with previous baseline design inspections of similar depth and length has shown

that this type of inspection is extremely resource intensive, both for the NRC inspectors and the

licensee staff. In order to minimize the inspection impact on the site and to ensure a productive

inspection for both parties, we have enclosed a request for information needed for the

inspection.

It is important that all of these documents are up to date and complete in order to minimize the

number of additional documents requested during the preparation and/or the on-site portions of

the inspection. Insofar as possible, this information should be provided electronically to the lead

inspector. The information request has been divided into three groups:

  • The first group lists information necessary for our initial inspection scoping activities.

This information should be provided to the lead inspector no later than June 10, 2013. By

June 24, 2013, the lead inspector will communicate the initial selected set of approximately

20 components.

  • The second group of documents requested is those items needed to support our in-office

preparation activities. This set of documents, including the calculations associated with the

initial selected components, should be provided to the lead inspector at the Regional Office

no later than July 15, 2013. During the in-office preparation activities, the team may identify

additional information needed to support the inspection.

  • The last group includes the additional information above, as well as plant specific reference

material. This information should be available to the team onsite on July 29, 2013. It is also

requested that corrective action documents and/or questions developed during the

inspection be provided to the lead inspector as the documents are generated.

The lead inspector for this inspection is Caroline Tilton. We understand that our licensing

contact for this inspection is Murtaza Abbas of your organization. If there are any questions

about the inspection or the material requested in the enclosure, please contact the lead

inspector at (630) 829-9718 or via e-mail at caroline.tilton@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number 3150-

0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a

request for information or an information collection requirement unless the requesting document

displays a currently valid Office of Management and Budget control number.

M. Pacilio -3-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosures will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide

Documents Access and Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos.: 50-456 and 50-457

License Nos.: NPF-72 and NPF-77

Enclosure: Information Request for Component Design Bases Inspection (CDBI)

cc w/encl: Distribution via ListServ'

INFORMATION REQUEST FOR COMPONENT DESIGN BASES INSPECTION (CDBI)

Inspection Report: 05000456/2013007/05000457/2013007

Inspection Dates: July 29, 2013;

August 12, 2013; and

August 26, 2013.

Inspection Procedure: IP 71111.21 Component Design Bases Inspection

Lead Inspector: Caroline Tilton, Senior Reactor Engineer, DRS

(630) 829-9718

caroline.tilton@nrc.gov

I. Information Requested Prior to the On-site Information Gathering/Inspection Week

The following information is requested by June 10, 2013, or sooner, to facilitate

inspection preparation. If you have any questions regarding this information, please call

the team leader as soon as possible. (Please provide the information electronically in

pdf files, Excel, or other searchable formats, preferably on some portable electronic

media (e.g., CDROM, DVD, flash drive, etc.). The portable electronic media should

contain descriptive names, and be indexed and hyperlinked to facilitate ease of use.

Information in lists should contain enough information to be easily understood by

someone who has knowledge of light water reactor technology).

1. Risk-ranking of top 250 components from your site specific probabilistic safety

analysis (PSA) sorted by Risk-Achievement Worth (RAW). Include values for

Birnbaum Importance, Risk-Reduction Worth (RRW), and Fussell-Veseley (FV)

(as applicable).

2. Risk-ranking of top 100 containment-related components from your site specific

PSA sorted by Large Early Release Frequency (LERF).

3. Provide a list of the top 200 cut-sets from your PSA.

4. Provide a list of the top 100 cut-sets for each initiator modeled in the PSA that

contributes more than five percent to the baseline plant core damage frequency

(CDF).

5. Copies of PSA system notebooks and latest PSA summary document.

6. List of time critical operator actions. Identify those actions that do not have job

performance measures (JPMs).

7. Provide copies of the emergency operating procedures (EOPs).

1 Enclosure

INFORMATION REQUEST FOR COMPONENT DESIGN BASES INSPECTION (CDBI)

8. If you have an External Events or Fire PSA Model, provide the information

requested in Items 1 and 2 for external events and fire. Provide narrative

description of each coded event (including fire, flood zone description).

9. Electronic copy of the site IPEEE, if available.

10. Any pre-existing evaluation or list of components and associated calculations

with low design margins, (i.e., pumps closest to the design limit for flow or

pressure, diesel generator close to design required output, heat exchangers

close to rated design heat removal etc.).

11. List of available design (setup) margins in both the open and closed direction

(identify safety-related direction) for valves in the motor-operated valve (MOV)

and air-operated valve (AOV) programs. Identify the basis for how the margin

was determined.

12. List of high risk Maintenance Rule systems/components based on engineering or

expert panel judgment (i.e., those systems/components not identified in the

PRA).

13. Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1)

category for the last three years.

14. Site top ten issues list (if applicable).

15. A list of operating experience evaluations for the last three years.

16. Information of any common cause failure of components experienced in the last

five years at your facility.

17. List of Root Cause Evaluations associated with component failures or design

issues initiated/completed in the last five years.

18. List of open operability evaluations.

19. List of components/systems considered operable but degraded/nonconforming.

20. Current management and engineering organizational chart.

21. Electronic copies of Updated Final Safety Analysis Report, Technical

Specifications, Technical Specifications Bases, and Technical Requirements

Manual.

22. Major one line electrical drawings (ac and dc) and key diagrams (paper copies).

23. Electronic copy of P&IDs (if available).

2 Enclosure

INFORMATION REQUEST FOR COMPONENT DESIGN BASES INSPECTION (CDBI)

II. Information Requested (for the approx. 20 selected components) to be Available

by July 15, 2013, Will be Reviewed by the Team in the Regional Office During the

Week of July 22, 2013.

This information should be separated for each selected component, especially if

provided electronically (e.g., folder with component name that includes calculations,

condition reports, maintenance history, etc.).

1. List of condition reports (corrective action documents) associated with each of

the selected components for the last four years.

2. The maintenance history (corrective, preventive, and elective) associated with

each of the selected components for the last 10 years. Identify frequency of

preventive maintenance activities.

3. Copies of calculations associated with each of the selected components (if not

previously provided), excluding data files. Please review the calculations and

also provide copies of important referenced material (such as drawings,

engineering requests, and vendor letters).

4. System Health Reports, System Descriptions, Design Basis Documents, and/or

Training Lesson Plans that are associated with each of the selected components.

5. A list of modifications, including equivalency evaluations and setpoint changes,

associated with each of the selected components. This list should include a

descriptive paragraph on the purpose of the modification. Please ensure this list

only includes design completed (not canceled) modifications.

6. Copies of operability evaluations (open/closed for last three years) associated

with each of the selected components and plans for restoring operability, if

applicable.

7. Copies of selected operator work-around evaluations associated with each of the

selected components and plans for resolution, if applicable.

8. Copies of any open temporary modifications associated with each of the selected

components, if applicable.

9. Trend data on the selected electrical/mechanical components performance for

last three years (For example, pumps performance including in-service testing,

other vibration monitoring, oil sample results, etc., for valves: stroke time and

leak rate results, etc.).

10. Copy of latest completed surveillance tests for each component (for example, for

pumps this would include: comprehensive test, quarterly test, flow balance, etc.

for valves: stroke time testing, diagnostic testing, leak testing, etc.). Acceptance

criteria basis calculations should also be included.

11. Provide copies of the normal and abnormal operating procedures associated with

the selected components and selected scenarios.

3 Enclosure

12. A copy of any internal/external self-assessments and associated corrective

action documents generated in preparation for the inspection.

13. A copy of engineering/operations related audits completed in the last two years.

III. Additional Information to be Provided on July 29, 2013, On-Site (for final selected

components)

1. During the in-office preparation activities, the team will be making final selections

and may identify additional information needed to support the inspection. The

lead inspector will provide a list of the additional information needed during the

week of July 22, 2013.

2. Schedule of any testing/maintenance activities to be conducted on the selected

components during the three onsite inspection weeks.

IV. Information Requested to be Provided Throughout the Inspection

1. Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection.

2. Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the inspection

to each team member).

3. One complete set of P&IDs (paper copies).

4. Reference materials. (make available if needed during all on-site weeks):

  • IPE/PRA report;
  • Procurement documents for components selected (verify retrievable);
  • Plant procedures (normal, abnormal, emergency, surveillance, etc.); and
  • Vendor manuals.

If you have questions regarding the information requested, please contact the lead inspector.

M. Pacilio -3-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosures will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide

Documents Access and Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos.: 50-456 and 50-457

License Nos.: NPF-72 and NPF-77

Enclosure: Information Request for Component Design Bases Inspection (CDBI)

cc w/encl: Distribution via ListServ'

DISTRIBUTION:

Doug Huyck

RidsNrrDorlLpl3-2 Resource

RidsNrrPMBraidwood Resource

RidsNrrDirsIrib Resource

Chuck Casto

Cynthia Pederson

Steven Orth

Allan Barker

DRPIII

DRSIII

Christine Lipa

Carole Ariano

Linda Linn

Patricia Buckley

Tammy Tomczak

DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\Ltr 042913 Braidwood CDBI RFI Letter CET.docx

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII

NAME CTilton:ls AMStone

DATE 4/29/13 4/29/13

OFFICIAL RECORD COPY