Changes to Technical Specification Bases - Revisions 55 and 56
ML13079A060
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 03/08/2013
From: Westman M
Wolf Creek
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA 13-0026
Download: ML13079A060 (33)


Text

W10.LF CREEKNUCLEAR OPERATING CORPORATION Michael J. Westman Manager Regulatory Affairs March 8, 2013 RA 13-0026 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

Subject:

Docket No. 50-482: Wolf Creek Generating Station Changes to Technical Specification Bases - Revisions 55 and 56 Gentlemen:

The Wolf Creek Generating Station (WCGS) Unit 1 Technical Specifications (TS), Section 5.5.14, "Technical Specifications (TS) Bases Control Program," provide the means for making changes to the Bases without prior Nuclear Regulatory Commission (NRC) approval. In addition, TS Section 5.5.14 requires that changes made without NRC approval be provided to the NRC on a frequency consistent with 10 CFR 50.71(e). The Enclosure provides those changes made to the WCGS TS Bases (Revisions 55 and 56) under the provisions to TS Section 5.5.14 and a List of Effective Pages. This submittal reflects changes from January 1, 2012 through December 31, 2012.

This letter contains no commitments. If you have any questions concerning this matter, please contact me at (620) 364-8831 ext. 4009.

Sincerely, Michael J. Westman MJW/rlt Enclosure cc: E. E. Collins (NRC), w/e C. F. Lyon (NRC), w/e N. F. O'Keefe (NRC), w/e Senior Resident Inspector (NRC), w/e P.O. Box 411 / Burlington, KS 66839 / Phone: (620) 364-8831 An Equal Opportunity Employer MIF/HCNET

Enclosure to RA 13-0026 Wolf Creek Generating Station Changes to the Technical Specification Bases (16 pages)

LTOP System B 3.4.12 B 3.4 REACTOR COOLANT SYSTEM (RCS)

B 3.4.12 Low Temperature Overpressure Protection (LTOP) System BASES BACKGROUND The LTOP System controls RCS pressure at low temperatures so the integrity of the reactor coolant pressure boundary (RCPB) is not compromised by violating the pressure and temperature (P/T) limits of 10 CFR 50, Appendix G (Ref. 1). The reactor vessel is the limiting RCPB component for demonstrating such protection. The PTLR provides the maximum allowable actuation logic setpoints for the power operated relief valves (PORVs) and the maximum RCS pressure for the existing RCS cold leg temperature during cooldown, shutdown, and heatup to meet the Reference 1 requirements during the LTOP MODES.

The reactor vessel material is less tough at low temperatures than at normal operating temperature. As the vessel neutron exposure accumulates, the material toughness decreases and becomes less resistant to pressure stress at low temperatures (Ref. 2). RCS pressure, therefore, is maintained low at low temperatures and is increased only as temperature is increased.

The potential for vessel overpressurization is most acute when the RCS is water solid, occurring only while shutdown; a pressure fluctuation can occur more quickly than an operator can react to relieve the condition.

Exceeding the RCS P/T limits by a significant amount could cause brittle cracking of the reactor vessel. LCO 3.4.3, "RCS Pressure and Temperature (P/T) Limits," requires administrative control of RCS pressure and temperature during heatup and cooldown to prevent exceeding the PTLR limits.

This LCO provides RCS overpressure protection by having a minimum coolant input capability and having adequate pressure relief capacity.

Limiting coolant input capability requires both safety injection pumps and one Emergency Core Cooling System (ECCS) centrifugal charging pump to be incapable of injection into the RCS and isolating the accumulators.

The normal charging pump (NCP), in addition to one ECCS centrifugal charging pump flow, has been included in the analysis of design basis mass input overpressure transient. The NCP shall not be capable of injecting into the RCS when this specification is applicable. The pressure relief capacity requires either two redundant RCS relief valves or a depressurized RCS and an RCS vent of sufficient size. One RCS relief valve or the open RCS vent is the overpressure protection device that acts to terminate an increasing pressure event.

Wolf Creek - Unit 1 B 3.4.12-1 Revision 56

LTOP System B 3.4.12 BASES BACKGROUND With minimum coolant input capability, the ability to provide core coolant (continued) addition is restricted. The LCO does not require the makeup control system deactivated or the safety injection (SI) actuation circuits blocked.

Due to the lower pressures in the LTOP MODES and the expected core decay heat levels, the makeup system can provide adequate flow via the makeup control valve. If conditions require the use of more than one ECCS centrifugal charging pump for makeup in the event of loss of inventory, other ECCS pumps can be made available through manual actions.

The LTOP System for pressure relief consists of two PORVs with reduced lift settings, or two residual heat removal (RHR) suction relief valves, or one PORV and one RHR suction relief valve, or a depressurized RCS and an RCS vent of sufficient size. Two RCS relief valves are required for redundancy. One RCS relief valve has adequate relieving capability to prevent overpressurization for the required coolant input capability.

PORV Requirements As designed for the LTOP System, each PORV is signaled to open ifthe RCS pressure approaches a limit determined by the LTOP actuation logic.

The LTOP actuation logic monitors both RCS temperature and RCS pressure and determines when a condition not acceptable with respect to the PTLR limits is approached. The wide range RCS temperature indications are auctioneered to select the lowest temperature signal.

The lowest temperature signal is processed through a function generator that calculates a pressure limit for that temperature. The calculated pressure limit is then compared with the indicated RCS pressure from a wide range pressure channel. If the indicated pressure meets or exceeds the calculated value,.a PORV is signaled to open.

The PTLR presents the PORV setpoints for LTOP. The setpoints are normally staggered so only one valve opens during a low temperature overpressure transient. Having the setpoints of both valves within the limits in the PTLR ensures that the Reference 1 limits will not be exceeded in any analyzed event.

When a PORV is opened in an increasing pressure transient, the release of coolant will cause the pressure increase to slow and reverse. As the PORV releases coolant, the RCS pressure decreases until a reset pressure is reached and the valve is signaled to close. The pressure continues to decrease below the reset pressure as the valve closes.

Wolf Creek - Unit 1 B 3.4.12-2 Revision 56

LTOP System B 3.4.12 BASES BACKGROUND RHR Suction Relief Valve Reauirements (continued)

  • During LTOP MODES, the RHR System is operated for decay heat removal and low pressure letdown control. Therefore, the RHR suction isolation valves are open in the piping from the RCS hot legs to the inlets of the RHR pumps. While these valves are open the RHR suction relief valves are exposed to the RCS and are able to relieve pressure transients in the RCS.

The RHR suction isolation valves must be open to make the RHR suction relief valves OPERABLE for RCS overpressure mitigation. The RHR suction relief valves are spring loaded, bellows type water relief valves with pressure tolerances and accumulation limits established by Section III of the American Society of Mechanical Engineers (ASME)

Code (Ref. 3) for Class 2 relief valves.

RCS Vent Requirements Once the RCS is depressurized, a vent exposed to the containment atmosphere will maintain the RCS at containment ambient pressure in an RCS overpressure transient, ifthe relieving requirements of the transient do not exceed the capabilities of the vent. Thus, the vent path must be capable of relieving the flow resulting from the limiting LTOP mass or heat input transient, and maintaining pressure below the P/T limits. The required vent capacity may be provided by one or more vent paths.

APPLICABLE Safety analyses (Ref. 4) demonstrate that the reactor vessel is adequately SAFETY ANALYSES protected against exceeding the Reference 1 P/T limits. In MODES 1, 2, and 3, the pressurizer safety valves will prevent RCS pressure from exceeding the Reference 1 limits. In MODE 3 (with any RCS cold leg temperature < 3681F) and below, overpressure prevention falls to two OPERABLE RCS relief valves or to a depressurized RCS and a sufficient sized RCS vent. Each of these means has a limited overpressure relief capability.

The actual temperature at which the pressure in the P/T limit curve falls below the pressurizer safety valve setpoint increases as the reactor vessel material toughness decreases due to neutron embrittlement. Each time the PTLR curves are revised, the LTOP System must be re-evaluated to ensure its functional requirements can still be met using the RCS relief valve method or the depressurized and vented RCS condition.

Wolf Creek - Unit 1 B 3.4.12-3 Revision 0

LTOP System B 3.4.12 BASES APPLICABLE The PTLR contains the acceptance limits that define the LTOP SAFETY ANALYSES requirements. Any change to the RCS must be evaluated against the (continued) Reference 9 analyses to determine the impact of the change on the LTOP acceptance limits.

Transients that are capable of overpressurizing the RCS are categorized as either mass or heat input transients, examples of which follow:

Mass Input Type Transients

a. Inadvertent safety injection; or
b. Charging/letdown flow mismatch.

Heat Input Type Transients

a. Inadvertent actuation of pressurizer heaters;
b. Loss of RHR cooling; or
c. Reactor coolant pump (RCP) startup with temperature asymmetry within the RCS or between the RCS and steam generators.

The following are required with exception described below during the LTOP MODES to ensure that mass and heat input transients do not occur, which either of the LTOP overpressure protection means cannot handle:

a. Rendering both safety injection pumps and one ECCS centrifugal charging pump incapable of injection (the NCP shall not be capable of injecting into the RCS);
b. Deactivating the accumulator discharge isolation valves in their closed positions or by venting the affected accumulator; and
c. Precluding start of an RCP if secondary temperature is more than 50°F above primary temperature in any one loop. LCO 3.4.5, "RCS Loops - MODE 3," LCO 3.4.6, "RCS Loops - MODE 4," and LCO 3.4.7, "RCS Loops - MODE 5, Loops Filled," provide this protection.

Operation below 350°F but greater than 325 0 F with all ECCS centrifugal charging and safety injection pumps OPERABLE is allowed for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. During low pressure, low temperature operation all automatic safety injection actuation signals except Containment Pressure - High are Wolf Creek - Unit 1 B 3.4.12-4 Revision 56

LTOP System B 3.4.12 BASES APPLICABLE blocked. In normal conditions a single failure of the ESF actuation SAFETY ANALYSES. circuitry will result in the starting of at most one train of safety injection (continued) (one centrifugal charging pump, and one safety injection pump). For temperatures above 325 0 F, an overpressure event occurring as a result of starting two pumps can be successfully mitigated by operation of both PORV's without exceeding Appendix G limit. Given the short time duration that this condition is allowed and the low probability of a single failure causing an overpressure event during this time, the single failure of a PORV is not assumed. Initiation of both trains of safety injection during this 4-hour time frame due to operator error or a single failure occurring during testing of a redundant channel are not considered to be credible accidents.

Although LTOP is required to be OPERABLE when RCS temperature is less than 368 0 F, operation with all ECCS centrifugal charging pumps and both safety injection pumps OPERABLE is acceptable when RCS temperature is greater than 350 0 F. Should an inadvertent safety injection occur above 350 0 F, a single PORV has sufficient capacity to relieve the combined flow rate of all ECCS pumps and the NCP. Above 350 0 F, two RCPs and all pressurizer safety valves are required to be OPERABLE.

Operation of an RCP eliminates the possibility of a 50°F difference existing between indicated and actual RCS temperature as a result of heat transport effects. Considering instrument uncertainties only, an indicated RCS temperature of 350°F is sufficiently high to allow full RCS pressurization in accordance with Appendix G limitations. Should an overpressure event occur in these conditions, the pressurizer safety valves provide acceptable. and redundant overpressure protection.

The Reference 9 analyses demonstrate that either one RCS relief valve or the depressurized RCS and RCS vent can maintain RCS pressure below limits when only one ECCS centrifugal charging pump (in addition to the NCP) is actuated. However, the LCO allows only one ECCS centrifugal charging pump OPERABLE during the LTOP MODES. The NCP shall not be capable of injecting into the RCS. Since neither one RCS relief valve nor the RCS vent can handle the pressure transient caused by accumulator injection, when RCS temperature is low, the LCO also requires accumulator isolation when accumulator pressure is greater than or equal to the maximum RCS pressure for the existing RCS cold leg temperature allowed in the PTLR.

The isolated accumulators must have their discharge valves closed and the valve power supply breakers fixed in their open positions.

Fracture mechanics analyses established the temperature of LTOP Applicability at 3680 F.

Wolf Creek - Unit 1 B 3.4.12-5 Revision 56

LTOP System B 3.4.12 BASES APPLICABLE PORV Performance SAFETY ANALYSES (continued) The fracture mechanics analyses show that the vessel is protected when the PORVs are set to open at or below the limit shown in the PTLR. The setpoints are derived by analyses that model the performance of the LTOP System, assuming the mass injection transient of one ECCS centrifugal charging pump and the NCP injecting into the RCS and the heat injection transient of starting an RCP with the RCS 50°F colder than the secondary coolant. These analyses consider pressure overshoot and undershoot beyond the PORV opening and closing, resulting from signal processing and valve stroke times. The PORV setpoints at or below the derived limit ensures the Reference 1 P/T limits will be met.

The PORV setpoints in the PTLR will be updated when the revised P/T limits conflict with the LTOP analysis limits. The P/T limits are periodically modified as the reactor vessel material toughness decreases due to neutron embrittlement caused by neutron irradiation. Revised limits are determined using neutron fluence projections and the results of examinations of the reactor vessel material irradiation surveillance specimens. The Bases for LCO 3.4.3, "RCS Pressure and Temperature (P/T) Limits," discuss these examinations.

The PORVs are considered active components. Thus, the failure of one PORV is assumed to represent the worst case, single active failure.

RHR Suction Relief Valve Performance The RHR suction relief valves do not have variable pressure and temperature lift setpoints like the PORVs. Analyses show that one RHR suction relief valve with a setpoint at or between 436.5 psig and 463.5 psig will pass flow greater than that required for the limiting LTOP transient while maintaining RCS pressure less than the P/T limit curve.

As the RCS P/T limits are decreased to reflect the loss of toughness in the reactor vessel materials due to neutron embrittlement, the RHR suction relief valves must be analyzed to still accommodate the design basis transients for LTOP.

The RHR suction relief valves are considered active components. Thus, the failure of one valve is assumed to represent the worst case single active failure.

Wolf Creek - Unit 1 B 3.4.12-6 Revision 56

LTOP System B 3.4.12 BASES APPLICABLE RCS Vent Performance SAFETY ANALYSIS (continued) -: .With the RCS depressurized, analyses show a vent size of 2.0 square inches is capable of mitigating the limiting LTOP transient. The capacity of a vent this size is greater than the flow of the limiting transient for the LTOP configuration, one ECCS centrifugal charging pump OPERABLE, maintaining RCS pressure less than the maximum pressure on the P/T limit curve.

The RCS vent size will be re-evaluated for compliance each time the P/T limit curves are revised based on the results of the vessel material surveillance.

The RCS vent is passive and is not subject to active failure.

The LTOP System satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii).

LCO This LCO requires that the LTOP System is OPERABLE. The LTOP System is OPERABLE when the maximum coolant input or heat input bounded by that assumed in the analyses and required pressure relief capabilities are OPERABLE. Violation of this LCO could lead to the loss of low temperature overpressure mitigation and violation of the Reference 1 limits as a result of an operational transient.

To limit the coolant input capability, the LCO requires that a maximum of zero safety injection pumps and one ECCS centrifugal charging pump be capable of injecting into the RCS, and all accumulator discharge isolation valves be closed and immobilized (when accumulator pressure is greater than or equal to the maximum RCS pressure for the existing RCS cold leg temperature allowed in the PTLR). The NCP shall not be capable of injecting into the RCS when this specification is applicable.

The LCO is modified by four Notes. Note 1 allows two ECCS centrifugal charging pumps to be made capable of injecting into the RCS for < 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> for pump swap operations. One hour provides sufficient time to safely complete the actual transfer and to complete the administrative controls and surveillance requirements associated with the swap. The intent is to minimize the actual time that more than one ECCS centrifugal charging pump is physically capable of injection. This is accomplished by racking out the breaker for one pump or employing two independent means to prevent a pump start in accordance with SR 3.4.12.2.

Note 2 recognizes the Applicability overlap between LCO's 3.4.12 and 3.5.2 and states that two safety injection pumps and two ECCS centrifugal charging pumps may be made capable of injecting into the RCS:

Wolf Creek - Unit 1 B 3.4.12-7 Revision 56

LTOP System B 3.4.12 BASES LCO (a) In MODE 3 with any RCS cold leg temperature < 368 0 F and ECCS (continued) pumps OPERABLE pursuant to LCO 3.5.2, "ECCS-Operating", and (b) For up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> after entering MODE 4 from MODE 3 or the temperature of one or more RCS cold legs decreases below 325°F, whichever comes first.

Note 3 states that one or more safety injection pumps may be made capable of injecting into the RCS in MODES 5 and 6 when the RCS water level is below the top of the reactor vessel flange for the purpose of protecting the decay heat removal function.

Note 4 states that the accumulator may be unisolated when the accumulator pressure is less than the maximum RCS pressure for the existing RCS cold leg temperature as allowed by the P/T limit curves provided in the PTLR. The accumulator discharge isolation valve Surveillance is not required under these pressure and temperature conditions.

The elements of the LCO that provide low temperature overpressure mitigation through pressure relief are:

a. Two OPERABLE PORVs; or A PORV is OPERABLE for LTOP when its block valve is open, its lift setpoint is set to the limit required by the PTLR and testing proves its ability to open at this setpoint, and motive power is available to the two valves and their control circuits.
b. Two OPERABLE RHR suction relief valves; or An RHR suction relief valve is OPERABLE for LTOP when its RHR suction isolation valves are open, its setpoint is at or between 436.5 psig and 463.5 psig, and testing has proven its ability to open at this setpoint.
c. One OPERABLE PORV and one OPERABLE RHR suction relief valve; or
d. A depressurized RCS and an RCS vent.

An RCS vent is OPERABLE when open with an area of >_

2.0 square inches.

Wolf Creek - Unit 1 B 3.4.12-8 Revision 1

LTOP System B 3.4.12 BASES LCO Each of these. methods of overpressure prevention is capable of (continued). .. ,mitigating the limiting LTOP transient.

APPLICABILITY This LCO is applicable in MODE 3 when any RCS cold leg temperature is 368 0 F, in MODE 4, in MODE 5 and in MODE 6 when the reactor vessel head is on. The pressurizer safety valves provide overpressure protection that meets the Reference 1 P/T limits in MODES 1, 2, and 3.

When the reactor vessel head is off, overpressurization cannot occur.

LCO 3.4.3 provides the operational P/T limits for all MODES. LCO 3.4.10, "Pressurizer Safety Valves," requires the OPERABILITY of the pressurizer safety valves that provide overpressure protection during MODES 1, 2, and 3.

Low temperature overpressure prevention is most critical during shutdown when the RCS is water solid, and a mass or heat input transient can cause a very rapid increase in RCS pressure when little or no time allows operator action to mitigate the event.

ACTIONS A Note prohibits the application of LCO 3.0.4b. to an inoperable LTOP System. There is an increased risk associated with entering MODE 3 from MODE 4 and MODE 4 from MODE 5 with LTOP inoperable and the provisions of LCO 3.0.4b., which allow entry into a MODE or other specified condition in the Applicability with the LCO not met after performance of a risk assessment addressing inoperable systems and components, should not be applied in this circumstance.

A.1 and B.1 With one or more safety injection pumps or two ECCS centrifugal charging pumps capable of injecting into the RCS, RCS overpressurization is possible.

To immediately initiate action to restore restricted coolant input capability to the RCS reflects the urgency of removing the RCS from this condition.

C.1, D.1, and D.2 An unisolated accumulator requires isolation within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This is only required when the accumulator pressure is at or more than the maximum RCS pressure for the existing temperature allowed by the P/T limit curves.

Wolf Creek - Unit 1 B 3.4.12-9 Revision 56

LTOP System B 3.4.12 BASES ACTIONS C.1, D.1, and D.2 (continued)

If isolation is needed and cannot be accomplished in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, Required Action D.1 and Required Action D.2 provide two options, either of which must be performed in the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. By increasing the RCS temperature to > 368 0 F, an accumulator pressure of 648 psig cannot exceed the LTOP limits if the accumulators are fully injected.

Depressurizing the accumulators below the LTOP limit from the PTLR also gives this protection.

The Completion Times are based on operating experience that these activities can be accomplished in these time periods and on engineering evaluations indicating that an event requiring LTOP is not likely in the allowed times.

E. 1I In MODE 3 with any RCS cold leg temperature < 368 0 F or MODE 4, with one required RCS relief valve inoperable, the RCS relief valve must be restored to OPERABLE status within a Completion Time of 7 days. Two RCS relief valves in any combination of the PORVS and the RHR suction relief valves are required to provide low temperature overpressure mitigation while withstanding a single failure of an active component.

The Completion Time considers the facts that only one of the RCS relief valves is required to mitigate an overpressure transient and that the likelihood of an active failure of the remaining valve path during this time period is very low.

F. 1 The consequences of operational events that will overpressurize the RCS are more severe at lower temperature (Ref. 7). Thus, with one of the two RCS relief valves inoperable in MODE 5 or in MODE 6 with the head on, the Completion Time to restore two valves to OPERABLE status is 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The Completion Time represents a reasonable time to investigate and repair several types of relief valve failures without exposure to a lengthy period with only one OPERABLE RCS relief valve to protect against overpressure events.

Wolf Creek - Unit 1 B 3.4.12-10 Revision 0

LTOP System B 3.4.12 BASES ACTIONS G.1 (continued)

The RCS must be depressurized and a vent must be established within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> when:

a. Both required RCS relief valves are inoperable; or
b. A Required Action and associated Completion Time of Condition A, B, D, E, or F is not met; or
c. The LTOP System is inoperable for any reason other than Condition A, B, C, D, E, or F.

The vent must be sized >_2.0 square inches to ensure that the flow capacity is greater than that required for the worst case mass input transient reasonable during the applicable MODES. This action is needed to protect the RCPB from a low temperature overpressure event and a possible brittle failure of the reactor vessel.

The Completion Time considers the time required to place the plant in this Condition and the relatively low probability of an overpressure event during this time period due to increased operator awareness of administrative control requirements.

SURVEILLANCE SR 3.4.12.1, SR 3.4.12.2, and SR 3.4.12.3 REQUIREMENTS To minimize the potential for a low temperature overpressure event by limiting the mass input capability, a maximum of zero safety injection pumps and a maximum of one ECCS centrifugal charging pump are verified to be capable of injecting into the RCS and the accumulator discharge isolation valves are verified closed and with power removed from the valve operator.

Verification that each accumulator is isolated is only required when accumulator pressure is greater than or equal to the maximum RCS pressure for the existing. RCS cold leg temperature allowed by the P/T limit curves provided in the PTLR.

The safety injection pumps and one ECCS centrifugal charging pump are rendered incapable of injecting into the RCS through removing the power from the pumps by racking the breakers out under administrative control.

An alternate method of cold overpressure protection may be employed using at least two independent means to render a pump incapable of injecting into the RCS such that a single failure or single action will not Wolf Creek - Unit 1 B 3.4.12-11 Revision 56

LTOP System B 3.4.12 BASES SURVEILLANCE SR 3.4.12.1, SR 3.4.12.2, and SR 3.4.12.3 (continued)

REQUIREMENTS result in an injection into the RCS. This may be accomplished by placing the pump control switch in pull to lock and closing at least one valve in the discharge flow path, or by closing at least one valve in the discharge flow path and removing power from the valve operator, or by closing at least one manual valve in the discharge flow path under administrative control.

Providing pumps are rendered incapable of injecting into the RCS, they may be energized for purposes such as testing or for filling accumulators.

The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is sufficient, considering other indications and alarms available to the operator in the control room, to verify the required status of the equipment.

SR 3.4.12.4 Each required RHR suction relief valve shall be demonstrated OPERABLE by verifying its RHR suction isolation valves are open and by testing it in accordance with the Inservice Testing Program. This Surveillance is only required to be performed if the RHR suction relief valve is being used to meet this LCO.

The RHR suction isolation valves are verified to be opened every 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The Frequency is considered adequate in view of other administrative controls such as valve status indications available to the operator in the control room that verify the RHR suction isolation valves remain open.

The ASME Code (Ref. 8), test per Inservice Testing Program verifies OPERABILITY by proving proper relief valve mechanical motion and by measuring and, if required, adjusting the lift setpoint.

SR 3.4.12.5 The RCS vent of >_2.0 square inches is proven OPERABLE by verifying its open condition either:

a. Once every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for a valve that is not locked, sealed, or otherwise secured in the open position.

Wolf Creek - Unit 1 B 3.4.12-12 Revision 32

ECCS - Shutdown B 3.5.3 B 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS)

B 3.5.3 ECCS - Shutdown BASES BACKGROUND The Background section for Bases 3.5.2, "ECCS - Operating," is applicable to these Bases, with the following modifications.

In MODE 4, the required ECCS train consists of two separate subsystems: centrifugal charging (high head) and residual heat removal (RHR) (low head).

The ECCS flow paths consist of piping, valves, heat exchangers, and pumps such that water from the refueling water storage tank (RWST) can be injected into the Reactor Coolant System (RCS) following the accidents described in Bases 3.5.2.

APPLICABLE The Applicable Safety Analyses section of Bases 3.5.2 also applies SAFETY ANALYSES to this Bases section.

Due to the stable conditions associated with operation in MODE 4 and the reduced probability of occurrence of a Design Basis Accident (DBA), the ECCS operational requirements are reduced. It is understood in these reductions that certain automatic safety injection (SI) actuation is not available. In this MODE, sufficient time exists for manual actuation of the required ECCS to mitigate the consequences of a DBA.

For MODE 3, with the accumulators blocked, and MODE 4, the parameters assumed in the generic bounding thermal hydraulic analysis for the limiting DBA (Reference 1) are based on a combination of limiting parameters for MODE 3, with the accumulators blocked, and parameters for MODE 4. However, assumed ECCS availability is based on MODE 4 conditions; the minimum available ECCS flow is calculated assuming only one OPERABLE ECCS train.

Only one train of ECCS is required for MODE 4. This requirement dictates that single failures are not considered during this MODE of operation. The ECCS trains satisfy Criterion 3 of 10 CFR 50.36(c)(2)(ii).

LCO In MODE 4, one of the two independent (and redundant) ECCS trains is required to be OPERABLE to ensure that sufficient ECCS flow is available to the core following a DBA.

Wolf Creek - Unit I B 3.5.3-1 Revision 56

ECCS - Shutdown B 3.5.3 BASES LCO In MODE 4, an ECCS train consists of a centrifugal charging subsystem (continued) and an RHR subsystem. Each train includes the piping, instruments, and controls to ensure an OPERABLE flow path capable of taking suction from the RWST and transferring suction to the containment sump.

During an event requiring ECCS actuation, a flow path is required to provide an abundant supply of water from the RWST to the RCS via the ECCS pumps and their respective supply headers to two cold leg injection nozzles. In the long term, this flow path may be switched to take its supply from the containment sump and to deliver its flow to the RCS hot and cold legs.

This LCO is modified by a Note that allows an RHR train to be considered OPERABLE during alignment and operation for decay heat removal, if capable of being manually realigned (remote or local) to the ECCS mode of operation and not otherwise inoperable. This allows operation in the RHR mode during MODE 4. Only one RHR train is placed into operation to reduce RCS temperature. For an RHR train to be considered OPERABLE during shutdown, the train cannot be placed in service until RCS temperature is less than 225 OF (plant computer)/215 OF (main control board). For an RHR train to be considered OPERABLE during startup, the train must be isolated from the RCS prior to RCS temperature exceeding 225 OF (plant computer)/215 OF (main control board).

APPLICABILITY In MODES 1, 2, and 3, the OPERABILITY requirements for ECCS are covered by LCO 3.5.2.

In MODE 4 with RCS temperature below 350°F, one OPERABLE ECCS train is acceptable without single failure consideration, on the basis of the stable reactivity of the reactor and the limited core cooling requirements.

In MODES 5 and 6, plant conditions are such that the probability of an event requiring ECCS injection is extremely low. Core cooling requirements in MODE 5 are addressed by LCO 3.4.7, "RCS Loops -

MODE 5, Loops Filled," and LCO 3.4.8, "RCS Loops - MODE 5, Loops Not Filled." MODE 6 core cooling requirements are addressed by LCO 3.9.5, "Residual Heat Removal (RHR) and Coolant Circulation - High Water Level," and LCO 3.9.6, "Residual Heat Removal (RHR) and Coolant Circulation - Low Water Level."

ACTIONS A Note prohibits the application of LCO 3.0.4b. to an inoperable ECCS centrifugal charging pump subsystem when entering MODE 4. There is an increased risk associated with entering MODE 4 from MODE 5 with an Wolf Creek - Unit 1 B 3.5.3-2 Revision 56

ECCS - Shutdown B 3.5.3 BASES ACTIONS A.1 (continued) inoperable ECCS centrifugal charging pump subsystem and the provisions of LCO 3.0.4b. which allow entry into a MODE or other specified condition in the Applicability with the LCO not met after performance of a risk assessment addressing inoperable systems and components, should not be applied in this circumstance.

With no ECCS RHR subsystem OPERABLE, the plant is not prepared to respond to a loss of coolant accident or to continue a cooldown using the RHR pumps and heat exchangers. The Completion Time of immediately to initiate actions that would restore at least one ECCS RHR subsystem to OPERABLE status ensures that prompt action is taken to restore the required cooling capacity. Normally, in MODE 4, reactor decay heat is removed from the RCS by an RHR loop. If no RHR loop is OPERABLE for this function, reactor decay heat must be removed by some alternate method, such as use of the steam generators. The alternate means of heat removal must continue until the inoperable RHR loop components can be restored to operation so that decay heat removal is continuous.

With both RHR pumps and heat exchangers inoperable, it would be unwise to require the plant to go to MODE 5, where the only available heat removal system is the RHR. Therefore, the appropriate action is to initiate measures to restore one ECCS RHR subsystem and to continue the actions until the subsystem is restored to OPERABLE status.

B.1 With no ECCS high head subsystem OPERABLE, due to the inoperability of the centrifugal charging pump or flow path from the RWST, the plant is not prepared to provide high pressure response to Design Basis Events requiring SI. The 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Completion Time to restore at least one ECCS high head subsystem to OPERABLE status ensures that prompt action is taken to provide the required cooling capacity or to initiate actions to place the plant in MODE 5, where an ECCS train is not required.

C.1 When the Required Actions of Condition B cannot be completed within the required Completion Time, a controlled shutdown should be initiated.

Twenty-four hours is a reasonable time, based on operating experience, to reach MODE 5 in an orderly manner and without challenging plant systems or operators.

Wolf Creek - Unit 1 B 3.5.3-3 Revision 56

ECCS - Shutdown B 3.5.3 BASES SURVEILLANCE SR 3.5.3.1 REQUIREMENTS The applicable Surveillance descriptions from Bases 3.5.2 apply.

REFERENCES The applicable references from Bases 3.5.2 apply.

1. WCAP-12476, Revision 1, "Evaluation of LOCA During Mode 3 and Mode 4 Operation for Westinghouse NSSS," November 2000.

Wolf Creek - Unit 1 B 3.5.3-4 Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - Title Page Technical Specification Cover Page Title Page TAB - Table of Contents i 34 DRR 07-1057 7/10/07 ii 29 DRR 06-1984 10/17/06 iii 44 DRR 09-1744 10/28/09 TAB - B 2.0 SAFETY LIMITS (SLs)

B 2.1.1-1 0 Amend. No. 123 12/18/99 B 2.1.1-2 14 DRR 03-0102 2/12/03 B 2.1.1-3 14 DRR 03-0102 2/12/03 B 2.1.1-4 0 Amend. No. 123 2/12/03 B 2.1.2-1 0 Amend. No. 123 12/18/99 B 2.1.2-2 12 DRR 02-1062 9/26/02 B 2.1.2-3 0 Amend. No. 123 12/18/99 TAB - B 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILTY B 3.0-1 34 DRR 07-1057 7/10/07 B 3.0-2 0 Amend. No. 123 12/18/99 B 3.0-3 0 Amend. No. 123 12/18/99 B 3.0-4 19 DRR 04-1414 10/12/04 B 3.0-5 19 DRR 04-1414 10/12/04 B 3.0-6 19 DRR 04-1414 10/12/04 B 3.0-7 19 DRR 04-1414 10/12/04 B 3.0-8 19 DRR 04-1414 10/12/04 B 3.0-9 42 DRR 09-1009 7/16/09 B 3.0-10 42 DRR 09-1009 7/16/09 B 3.0-11 34 DRR 07-1057 7/10/07 B 3.0-12 34 DRR 07-1057 7/10/07 B 3.0-13 34 DRR 07-1057 7/10/07 B 3.0-14 34 DRR 07-1057 7/10/07 B 3.0-15 34 DRR 07-1057 7/10/07 B 3.0-16 34 DRR 07-1057 7/10/07 TAB - B 3.1 REACTIVITY CONTROL SYSTEMS B 3.1.1-1 0 Amend. No. 123 12/18/99 B 3.1.1-2 0 Amend. No. 123 12/18/99 B 3.1.1-3 0 Amend. No. 123 12/18/99 B 3.1.1-4 19 DRR 04-1414 10/12/04 B 3.1.1-5 0 Amend. No. 123 12/18/99 B 3.1.2-1 0 Amend. No. 123 12/18/99 B 3.1.2-2 0 Amend. No. 123 12/18/99 B 3.1.2-3 0 Amend. No. 123 12/18/99 B 3.1.2-4 0 Amend. No. 123 12/18/99 B 3.1.2-5 0 Amend. No. 123 12/18/99 B 3.1.3-1 0 Amend. No. 123 12/18/99 B 3.1.3-2 0 Amend. No. 123 12/18/99 B 3.1.3-3 0 Amend. No. 123 12/18/99 B 3.1.3-4 0 Amend. No. 123 12/18/99 Wolf Creek - Unit 1 Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.1 REACTIVITY CONTROL SYSTEMS (continued)

B 3.1.3-5 0 Amend. No. 123 12/18/99 B 3.1.3-6 0 Amend. No. 123 12/18/99 B 3.1.4-1 0 Amend. No. 123 12/18/99 B 3.1.4-2 0 Amend. No. 123 12/18/99 B 3.1.4-3 48 DRR 10-3740 12/28/10 B 3.1.4-4 0 Amend. No. 123 12/18/99 B 3.1.4-5 0 Amend. No. 123 12/18/99 B 3.1.4-6 48 DRR 10-3740 12/28/10 B 3.1.4-7 0 Amend. No. 123 12/18/99 B 3.1.4-8 0 Amend. No. 123 12/18/99 B 3.1.4-9 0 Amend. No. 123 12/18/99 B 3.1.5-1 0 Amend. No. 123 12/18/99 B 3.1.5-2 0 Amend. No. 123 12/18/99 B 3.1.5-3 0 Amend. No. 123 12/18/99 B 3.1.5-4 0 Amend. No. 123 12/18/99 B 3.1.6-1 0 Amend. No. 123 12/18/99 B 3.1.6-2 0 Amend. No. 123 12/18/99 B 3.1.6-3 0 Amend. No. 123 12/18/99 B 3.1.6-4 0 Amend. No. 123 12/18/99 B 3.1.6-5 0 Amend. No. 123 12/18/99 B 3.1.6-6 0 Amend. No. 123 12/18/99 B 3.1.7-1 0 Amend. No. 123 12/18/99 B 3.1.7-2 0 Amend. No. 123 12/18/99 B 3.1.7-3 48 DRR 10-3740 12/28/10 B 3.1.7-4 48 DRR 10-3740 12/28/10 B 3.1.7-5 48 DRR 10-3740 12/28/10 B 3.1.7-6 0 Amend. No. 123 12/18/99 B 3.1.8-1 0 Amend. No. 123 12/18/99 B 3.1.8-2 0 Amend. No. 123 12/18/99 B 3.1.8-3 15 DRR 03-0860 7/10/03 B 3.1.8-4 15 DRR 03-0860 7/10/03 B 3.1.8-5 0 Amend. No. 123 12/18/99 B 3.1.8-6 5 DRR 00-1427 10/12/00 TAB - B 3.2 POWER DISTRIBUTION LIMITS B 3.2.1-1 48 DRR 10-3740 12/28/10 B 3.2.1-2 0 Amend. No. 123 12/18/99 B 3.2.1-3 48 DRR 10-3740 12/28/10 B 3.2.1-4 48 DRR 10-3740 12/28/10 B 3.2.1-5 48 DRR 10-3740 12/28/10 B 3.2.1-6 48 DRR 10-3740 12/28/10 B 3.2.1-7 48 DRR 10-3740 12/28/10 B 3.2.1-8 48 DRR 10-3740 12/28/10 B 3.2.1-9 29 DRR 06-1984 10/17/06 B 3.2.1-10 48 DRR 10-3740 12/28/10 B 3.2.2-1 48 DRR 10-3740 12/28/10 B 3.2.2-2 0 Amend. No. 123 12/18/99 B 3.2.2-3 48 DRR 10-3740 12/28/10 B 3.2.2-4 48 DRR 10-3740 12/28/10 B 3.2.2-5 48 DRR 10-3740 12/28/10 B 3.2.2-6 48 DRR 10-3740 12/28/10 Wolf Creek - Unit 1 ii Revtision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES

-PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.2 POWER DISTRIBUTION LIMITS (continued)

B 3.2.3-1 0 Amend. No. 123 12/18/99 B 3.2.3-2 0 Amend. No. 123 12/18/99 B 3.2.3-3 0 Amend. No. 123 12/18/99 B 3.2.4-1 0 Amend. No. 123 12/18/99 B 3.2.4-2 0 Amend. No. 123 12/18/99 B 3.2.4-3 48 DRR 10-3740 12/28/10 B 3.2.4-4 0 Amend. No. 123 12/18/99 B 3.2.4-5 48 DRR 10-3740 12/28/10 B 3.2.4-6 0 Amend. No. 123 12/18/99 B 3.2.4-7 48 DRR 10-3740 12/28/10 TAB - B 3.3 INSTRUMENTATION B 3.3.1-1 0 Amend. No. 123 12/18/99 B 3.3.1-2 0 Amend. No. 123 12/18/99 B 3.3.1-3 0 Amend. No. 123 12/18/99 B 3.3.1-4 0 Amend. No. 123 12/18/99 B 3.3.1-5 0 Amend. No. 123 12/18/99 B 3.3.1-6 0 Amend. No. 123 12/18/99 B 3.3.1-7 5 DRR 00-1427 10/12/00 B 3.3.1-8 0 Amend. No. 123 12/18/99 B 3.3.1-9 0 Amend. No. 123 12/18/99 B 3.3.1-10 29 DRR 06-1984 10/17/06 B 3.3.1-11 0 Amend. No. 123 12/18/99 B 3.3.1-12 0 Amend. No. 123 12/18/99 B 3.3.1-13 0 Amend. No. 123 12/18/99 B 3.3.1-14 0 Amend. No. 123 12/18/99 B 3.3.1-15 0 Amend. No. 123 12/18/99 B 3.3.1-16 0 Amend. No. 123 12/18/99 B 3.3.1-17 0 Amend. No. 123 12/18/99 B 3.3.1-18 0 Amend. No. 123 12/18/99 B 3.3.1-19 0 Amend. No. 123 12/18/99 B 3.3.1-20 0 Amend. No. 123 12/18/99 B 3.3.1-21 0 Amend. No. 123 12/18/99 B 3.3.1-22 0 Amend. No. 123 12/18/99 B 3.3.1-23 9 DRR 02-0123 2/28/02 B 3.3.1-24 0 Amend. No. 123 12/18/99 B 3.3.1-25 0 Amend. No. 123 12/18/99 B 3.3.1-26 0 Amend. No. 123 12/18/99 B 3.3.1-27 0 Amend. No. 123 12/18/99 B 3.3.1-28 2 DRR 00-0147 4/24/00 B 3.3.1-29 1 DRR 99-1624 12/18/99 B 3.3.1-30 1 DRR 99-1624 12/18/99 B 3.3.1-31 0 Amend. No. 123 12/18/99 B 3.3.1-32 20 DRR 04-1533 2/16/05 B 3.3.1-33 48 DRR 10-3740 12/28/10 B 3.3.1-34 20 DRR 04-1533 2/16/05 B 3.3.1-35 19 DRR 04-1414 10/13/04 B 3.3.1-36 20 DRR 04-1533 2/16/05 B 3.3.1-37 20 DRR 04-1533 2/16/05 B 3.3.1-38 20 DRR 04-1533 2/16/05 B 3.3.1-39 25 DRR 06-0800 5/18/06 Wolf Creek - Unit 1 iii Revi4sion 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.3 INSTRUMENTATION (continued)

B 3.3.1-40 20 DRR 04-1533 2/16/05 B 3.3.1-41 20 DRR 04-1533 2/16/05 B 3.3.1-42 20 DRR 04-1533 2/16/05 B 3.3.1-43 20 DRR 04-1533 2/16/05 B 3.3.1-44 20 DRR 04-1533 2/16/05 B 3.3.1-45 20 DRR 04-1533 2/16/05 B 3.3.1-46 48 DRR 10-3740 12/28/10 B 3.3.1-47 20 DRR 04-1533 2/16/05 B 3.3.1-48 48 DRR 10-3740 12/28/10 B 3.3.1-49 20 DRR 04-1533 2/16/05 B 3.3.1-50 20 DRR 04-1533 2/16/05 B 3.3.1-51 21 DRR 05-0707 4/20/05 B 3.3.1-52 20 DRR 04-1533 2/16/05 B 3.3.1-53 20 DRR 04-1533 2/16/05 B 3.3.1-54 20 DRR 04-1533 2/16/05 B 3.3.1-55 25 DRR 06-0800 5/18/06 B 3.3.1-56 20 DRR 04-1533 2/16/05 B 3.3.1-57 20 DRR 04-1533 2/16/05 B 3.3.1-58 29 DRR 06-1984 10/17/06 B 3.3.1-59 20 DRR 04-1533 2/16/05 B 3.3.2-1 0 Amend. No. 123 12/18/99 B 3.3.2-2 0 Amend. No. 123 12/18/99 B 3.3.2-3 0 Amend. No. 123 12/18/99 B 3.3.2-4 0 Amend. No. 123 12/18/99 B 3.3.2-5 0 Amend. No. 123 12/18/99 B 3.3.2-6 7 DRR 01-0474 5/1/01 B 3.3.2-7 0 Amend. No. 123 12/18/99 B 3.3.2-8 0 Amend. No. 123 12/18/99 B 3.3.2-9 0 Amend. No. 123 12/18/99 B 3.3.2-10 0 Amend. No. 123 12/18/99 B 3.3.2-11 0 Amend. No. 123 12/18/99 B 3.3.2-12 0 Amend. No. 123 12/18/99 B 3.3.2-13 0 Amend. No. 123 12/18/99 B 3.3.2-14 2 DRR 00-0147 4/24/00 B 3.3.2-15 0 Amend. No. 123 12/18/99 B 3.3.2-16 0 Amend. No. 123 12/18/99 B 3.3.2-17 0 Amend. No. 123 12/18/99 B 3.3.2-18 0 Amend. No. 123 12/18/99 B 3.3.2-19 37 DRR 08-0503 4/8/08 B 3.3.2-20 37 DRR 08-0503 4/8/08 B 3.3.2-21 37 DRR 08-0503 4/8/08 B 3.3.2-22 37 DRR 08-0503 4/8/08 B 3.3.2-23 37 DRR 08-0503 4/8/08 B 3.3.2-24 39 DRR 08-1096 8/28/08 B 3.3.2-25 39 DRR 08-1096 8/28/08 B 3.3.2-26 39 DRR 08-1096 8/28/08 B 3.3.2-27 37 DRR 08-0503 4/8/08 B 3.3.2-28 37 DRR 08-0503 4/8/08 B 3.3.2-29 0 Amend. No. 123 12/18/99 B 3.3.2-30 0 Amend. No. 123 12/18/99 B 3.3.2-31 52 DRR 11-0724 4/11/11 Wolf Creek - Unit 1 iv Re~vision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.3 INSTRUMENTATION (continued)

B 3.3.2-32 .52 DRR 11-0724 4/11/11 B 3.3.2-33 0 Amend. No. 123 12/18/99 B 3.3.2-34 0 Amend. No. 123 12/18/99 B 3.3.2-35 20 DRR 04-1533 2/16/05 B 3.3.2-36 20 DRR 04-1533 2/16/05 B 3.3.2-37 20 DRR 04-1533 2/16/05 B 3.3.2-38 20 DRR 04-1533 2/16/05 B 3.3.2-39 25 DRR 06-0800 5/18/06 B 3.3.2-40 20 DRR 04-1533 2/16/05 B 3.3.2-41 45 Amend. No. 187 (ETS) 3/5/10 B 3.3.2-42 45 Amend. No. 187 (ETS) 3/5/10 B 3.3.2-43 20 DRR 04-1533 2/16/05 B 3.3.2-44 20 DRR 04-1533 2/16/05 B 3.3.2-45 20 DRR 04-1533 2/16/05 B 3.3.2-46 54 DRR 11-2394 11/16/11 B 3.3.2-47 43 DRR 09-1416 9/2/09 B 3.3.2-48 37 DRR 08-0503 4/8/08 B 3.3.2-49 20 DRR 04-1533 2/16/05 B 3.3.2-50 20 DRR 04-1533 2/16/05 B 3.3.2-51 43 DRR 09-1416 9/2/09 B 3.3.2-52 43 DRR 09-1416 9/2/09 B 3.3.2-53 43 DRR 09-1416 9/2/09 B 3.3.2-54 43 DRR 09-1416 9/2/09 B 3.3.2-55 43 DRR 09-1416 9/2/09 B 3.3.2-56 43 DRR 09-1416 9/2/09 B 3.3.2-57 43 DRR 09-1416 9/2/09 B 3.3.3-1 0 Amend. No. 123 12/18/99 B 3.3.3-2 5 DRR 00-1427 10/12/00 B 3.3.3-3 0 Amend. No. 123 12/18/99 B 3.3.3-4 0 Amend. No. 123 12/18/99 B 3.3.3-5 0 Amend. No. 123 12/18/99 B 3.3.3-6 8 DRR 01-1235 9/19/01 B 3.3.3-7 21 DRR 05-0707 4/20/05 B 3.3.3-8 8 DRR 01-1235 9/19/01 B 3.3.3-9 8 DRR 01-1235 9/19/01 B 3.3.3-10 19 DRR 04-1414 10/12/04 B 3.3.3-11 19 DRR 04-1414 10/12/04 B 3.3.3-12 21 DRR 05-0707 4/20/05 B 3.3.3-13 21 DRR 05-0707 4/20/05 B 3.3.3-14 8 DRR 01-1235 9/19/01 B 3.3.3-15 8 DRR 01-1235 9/19/01 B 3.3.4-1 0 Amend. No. 123 12/18/99 B 3.3.4-2 9 DRR 02-1023 2/28/02 B 3.3.4-3 15 DRR 03-0860 7/10/03 B 3.3.4-4 19 DRR 04-1414 10/12/04 B 3.3.4-5 1 DRR 99-1624 12/18/99 B 3.3.4-6 .9 DRR 02-0123 2/28/02 B 3.3.5-1 0 Amend. No. 123 12/18/99 B 3.3.5-2 1 DRR 99-1624 12/18/99 B 3.3.5-3 1 DRR 99-1624 12/18/99 Wolf Creek - Unit 1 V Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.3 INSTRUMENTATION (continued)

B 3.3.5-4 1 DRR 99-1624 12/18/99 B 3.3.5-5 0 Amend. No. 123 12/18/99 B 3.3.5-6 22 DRR 05-1375 6/28/05 B 3.3.5-7 22 DRR 05-1375 6/28/05 B 3.3.6-1 0 Amend. No. 123 12/18/99 B 3.3.6-2 0 Amend. No. 123 12/18/99 B 3.3.6-3 0 Amend. No. 123 12/18/99 B 3.3.6-4 0 Amend. No. 123 12/18/99 B 3.3.6-5 0 Amend. No. 123 12/18/99 B 3.3.6-6 0 Amend. No. 123 12/18/99 B 3.3.6-7 0 Amend. No. 123 12/18/99 B 3.3.7-1 0 Amend. No. 123 12/18/99 B 3.3.7-2 0 Amend. No. 123 12/18/99 B 3.3.7-3 0 Amend. No. 123 12/18/99 B 3.3.7-4 0 Amend. No. 123 12/18/99 B 3.3.7-5 0 Amend. No. 123 12/18/99 B 3.3.7-6 0 Amend. No. 123 12/18/99 B 3.3.7-7 0 Amend. No. 123 12/18/99 B 3.3.7-8 0 Amend. No. 123 12/18/99 B 3.3.8-1 0 Amend. No. 123 12/18/99 B 3.3.8-2 0 Amend. No. 123 12/18/99 B 3.3.8-3 0 Amend. No. 123 12/18/99 B 3.3.8-4 0 Amend. No. 123 12/18/99 B 3.3.8-5 0 Amend. No. 123 12/18/99 B 3.3.8-6 24 DRR 06-0051 2/28/06 B 3.3.8-7 0 Amend. No. 123 12/18/99 TAB - B 3.4 REACTOR COOLANT SYSTEM (RCS)

B 3.4.1-1 0 Amend. No. 123 12/18/99 B 3.4.1-2 10 DRR 02-0411 4/5/02 B 3.4.1-3 10 DRR 02-0411 4/5/02 B 3.4.1-4 0 Amend. No. 123 12/18/99 B 3.4.1-5 0 Amend. No. 123 12/18/99 B 3.4.1-6 0 Amend. No. 123 12/18/99 B 3.4.2-1 0 Amend. No. 123 12/18/99 B 3.4.2-2 0 Amend. No. 123 12/18/99 B 3.4.2-3 0 Amend. No. 123 12/18/99 B 3.4.3-1 0 Amend. No. 123 12/18/99 B 3.4.3-2 0 Amend. No. 123 12/18/99 B 3.4.3-3 0 Amend. No. 123 12/18/99 B 3.4.3-4 0 Amend. No. 123 12/18/99 B 3.4.3-5 0 Amend. No. 123 12/18/99 B 3.4.3-6 0 Amend. No. 123 12/18/99 B 3.4.3-7. 0 Amend. No. 123 12/18/99 B 3.4.4-1 0 Amend. No. 123 12/18/99 B 3.4.4-2 29 DRR 06-1984 10/17/06 B 3.4.4-3 0 Amend. No. 123 12/18/99 B 3.4.5-1 0 Amend. No. 123 12/18/99 B 3.4.5-2 53 DRR 11-1513 7/18/11 B 3.4.5-3 29 DRR 06-1984 10/17/06 B 3.4.5-4 0 Amend. No. 123 12/18/99 Wolf Creek - Unit 1 vi Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.4 REACTOR COOLANT SYSTEM (RCS) (continued)

B 3.4.5-5 12 DRR 02-1062 9/26/02 B 3.4.5-6 12 DRR 02-1062 9/26/02 B 3.4.6-1 53 DRR 11-1513 7/18/11 B 3.4.6-2 29 DRR 06-1984 10/17/06 B 3.4.6-3 12 DRR 02-1062 9/26/02 B 3.4.6-4 12 DRR 02-1062 9/26/02 B 3.4.6-5 12 DRR 02-1062 9/26/02 B 3.4.7-1 12 DRR 02-1062 9/26/02 B 3.4.7-2 17 DRR 04-0453 5/26/04 B 3.4.7-3 42 DRR 09-1009 7/16/09 B 3.4.7-4 42 DRR 09-1009 7/16/09 B 3.4.7-5 12 DRR 02-1062 9/26/02 B 3.4.8-1 53 DRR 11-1513 7/18/11 B 3.4.8-2 42 DRR 09-1009 7/16/09 B 3.4.8-3 42 DRR 09-1009 7/16/09 B 3.4.8-4 42 DRR 09-1009 7/16/09 B 3.4.9-1 0 Amend. No. 123 12/18/99 B 3.4.9-2 0 Amend. No. 123 12/18/99 B 3.4.9-3 0 Amend. No. 123 12/18/99 B 3.4.9-4 0 Amend. No. 123 12/18/99 B 3.4.10-1 5 DRR 00-1427 10/12/00 B 3.4.10-2 5 DRR 00-1427 10/12/00 B 3.4.10-3 0 Amend. No. 123 12/18/99 B 3.4.10-4 32 DRR 07-0139 2/7/07 B 3.4.11-1 0 Amend. No. 123 12/18/99 B 3.4.11-2 1 DRR 99-1624 12/18/99 B 3.4.11-3 19 DRR 04-1414 10/12/04 B 3.4.11-4 0 Amend. No. 123 12/18/99 B 3.4.11-5 1 DRR 99-1624 12/18/99 B 3.4.11-6 0 Amend. No. 123 12/18/99 B 3.4.11-7 32 DRR 07-0139 2/7/07 B 3.4.12-1 56 DRR 12-1792 11/7/12 B 3.4.12-2 56 DRR 12-1792 11/7/12 B 3.4.12-3 0 Amend. No. 123 12/18/99 B 3.4.12-4 56 DRR 12-1792 11/7/12 B 3.4.12-5 56 DRR 12-1.792 11/7/12 B 3.4.12-6 56 DRR 12-1792 11/7/12.

B 3.4.12-7 56 DRR 12-1792 11/7/12 B 3.4.12-8 1 DRR 99-1624 12/18/99 B 3.4.12-9 56 DRR 12-1792 11/7/12 B 3.4.12-10 0 Amend. No. 123 12/1.8/99 B 3.4.12-11 56 DRR 12-1792 11/7/12 B 3.4.12-12 32 DRR 07-0139 2/7/07 B 3.4.12-13 0 Amend. No. 123 12/18/99 B 3.4.12-14 32 DRR 07-0139 2/7/07 B 3.4.13-1 0 Amend. No. 123 12/18/99 B 3.4.13-2 29 DRR 06-1984 10/17/06 B 3.4.13-3 29 DRR 06-1984 10/17/06 B 3.4.13-4 35 DRR 07-1553 9/28/07 B 3.4.13-5 35 DRR 07-1553 9/28/07 B 3.4.13-6 29 DRR 06-1984 10/17/06 Wolf Creek - Unit 1 vii Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.4 REACTOR COOLANT SYSTEM (RCS) (continued)

B 3.4.14-1 0 Amend. No. 123 12/18/99 B 3.4.14-2 0 Amend. No. 123 12/18/99 B 3.4.14-3 0 Amend. No. 123 12/18/99 B 3.4.14-4 0 Amend. No. 123 12/18/99 B 3.4.14-5 32 DRR 07-0139 2/7/07 B 3.4.14-6 32 DRR 07-0139 2/7/07 B 3.4.15-1 31 DRR 06-2494 12/13/06 B 3.4.15-2 31 DRR 06-2494 12/13/06 B 3.4.15-3 33 DRR 07-0656 5/1/07 B 3.4.15-4 33 DRR 07-0656 5/1/07 B 3.4.15-5 31 DRR 06-2494 12/13/06 B 3.4.15-6 31 DRR 06-2494 12/13/06 B 3.4.15-7 31 DRR 06-2494 12/13/06 B 3.4.15-8 31 DRR 06-2494 12/13/06 B 3.4.16-1 31 DRR 06-2494 12/13/06 B 3.4.16-2 31 DRR 06-2494 12/13/06 B 3.4.16-3 31 DRR 06-2494 12/13/06 B 3.4.16-4 31 DRR 06-2494 12/13/06 B 3.4.16-5 31 DRR 06-2494 12/13/06 B 3.4.17-1 29 DRR 06-1984 10/17/06 B 3.4.17-2 44 DRR 09-1744 10/28/09 B 3.4.17-3 52 DRR 11-0724 4/11/11 B 3.4.17-4 29 DRR 06-1984 10/17/06 B 3.4.17-5 29 DRR 06-1984 10/17/06 B 3.4.17-6 29 DRR 06-1984 10/17/06 B 3.4.17-7 44 DRR 09-1744 10/28/09 TAB - B 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS)

B 3.5.1-1 0 Amend. No. 123 12/18/99 B 3.5.1-2 0 Amend. No. 123 12/18/99 B 3.5.1-3 0 Amend. No. 123 12/18/99 B 3.5.1-4 0 Amend. No. 123 12/18/99 B 3.5.1-5 1 DRR 99-1624 12/18/99 B 3.5.1-6 1 DRR 99-1624 12/18/99 B 3.5.1-7 16 DRR 03-1497 11/4/03 B 3.5.1-8 1 DRR 99-1624 12/18/99 B 3.5.2-1 0 Amend. No. 123 12/18/99 B 3.5.2-2 0 Amend. No. 123 12/18/99 B 3.5.2-3 0 Amend. No. 123 12/18/99 B 3.5.2-4 0 Amend. No. 123 12/18/99 B 3.5.2-5 41 DRR 09-0288 3/20/09 B 3.5.2-6 42 DRR 09-1009 7/16/09 B 3.5.2-7 42 DRR 09-1009 7/16/09 B 3.5.2-8 38 DRR 08-0624 5/1/08 B 3.5.2-9 38 DRR 08-0624 5/1/08 B 3.5.2-10 41 DRR 09-0288 3/20/09 B 3.5.2-11 41 DRR 09-0288 3/20/09 B 3.5.3-1 56 DRR 12-1792 11/7/12 B 3.5.3-2 56 DRR 12-1792 11/7/12 B 3.5.3-3 56 DRR 12-1792 11/7/12 B 3.5.3-4 56 DRR 12-1792 11/7/12 Wolf Creek - Unit 1 viii Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) (continued)

B 3.5.4-1 0 Amend. No. 123 12/18/99 B 3.5.4-2 0 Amend. No. 123 12/18/99 B 3.5.4-3 0 Amend. No. 123 12/18/99 B 3.5.4-4 0 Amend. No. 123 12/18/99 B 3.5.4-5 0 Amend. No. 123 12/18/99 B 3.5.4-6 26 DRR 06-1350 7/24/06 B 3.5.5-1' 21 DRR 05-0707 4/20/05 B 3.5.5-2 21 DRR 05-0707 4/20/05 B 3.5.5-3 2 Amend. No. 132 4/24/00 B 3.5.5-4 21 DRR 05-0707 4/20/05 TAB - B 3.6 CONTAINMENT SYSTEMS B 3.6.1-1 0 Amend. No. 123 12/18/99 B 3.6.1-2 0 Amend. No. 123 12/18/99 B 3.6.1-3 0 Amend. No. 123 12/18/99 B 3.6.1-4 17 DRR 04-0453 5/26/04 B 3.6.2-1 0 Amend. No. 123 12/18/99 B 3.6.2-2 0 Amend. No. 123 12/18/99 B 3.6.2-3 0 Amend. No. 123 12/18/99 B 3.6.2-4 0 Amend. No. 123 12/18/99 B 3.6.2-5 0 Amend. No. 123 12/18/99 B 3.6.2-6 0 Amend. No. 123 12/18/99 B 3.6.2-7 0 Amend. No. 123 12/18/99 B 3.6.3-1 0 Amend. No. 123 12/18/99 B 3.6.3-2 0 Amend. No. 123 12/18/99 B 3.6.3-3 0 Amend. No. 123 12/18/99 B 3.6.3-4 49 DRR 11-0014 1/31/11 B 3.6.3-5 49 DRR 11-0014 1/31/11 B 3.6.3-6 49 DRR 11-0014 1/31/11 B 3.6.3-7 41 DRR 09-0288 3/20/09 B 3.6.3-8 36 DRR 08-0255 3/11/08 B 3.6.3-9 36 DRR 08-0255 3/11/08 B 3.6.3-10 8 DRR 01-1235 9/19/01 B 3.6.3-11 36 DRR 08-0255 3/11/08 B 3.6.3-12 36 DRR 08-0255 3/11/08 B 3.6.3-13 50 DRR 11-0449 3/9/11 B 3.6.3-14 36 DRR 08-0255 3/11/08 B 3.6.3-15 39 DRR 08-1096 8/28/08.

B 3.6.3-16 39 DRR 08-1096 8/28/08 B 3.6.3-17 36 DRR 08-0255 3/11/08 B 3.6.3-18 36 DRR 08-0255 3/11/08 B 3.6.3-19 36 DRR 08-0255 3/11/08 B 3.6.4-1 39 DRR 08-1096 8/28/08 B 3.6.4-2 0 Amend. No. 123 12/18/99 B 3.6.4-3 0 Amend. No. 123 12/18/99 B 3.6.5-1 0 Amend. No. 123 12/18/99 B 3.6.5-2 .37 DRR 08-0503 4/8/08 B 3.6.5-3 .13 DRR 02-1458 12/03/02 B 3.6.5-4 0 Amend. No. 123 12/18/99 B 3.6.6-1 42 DRR 09-1009 7/16/09 B 3.6.6-2 0 Amend. No. 123 12/18/99 Wolf Creek - Unit 1 ix Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.6 CONTAINMENT SYSTEMS (continued)

B 3.6.6-3 37 DRR 08-0503 4/8/08 B 3.6.6-4 42 DRR 09-1009 7/16/09 B 3.6.6-5 0 Amend. No. 123 12/18/99 B 3.6.6-6 18 DRR 04-1018 9/1/04 B 3.6.6-7 0 Amend. No. 123 12/18/99 B 3.6.6-8 32 DRR 07-0139 2/7/07 B 3.6.6-9 32 DRR 07-0139 2/7/07 B 3.6.7-1 0 Amend. No. 123 12/18/99 B 3.6.7-2 42 DRR 09-1009 7/16/09 B 3.6.7-3 0 Amend. No. 123 12/18/99 B 3.6.7-4 29 DRR 06-1984 10/17/06 B 3.6.7-5 42 DRR 09-1009 7/16/09 TAB - B 3.7 PLANT SYSTEMS B 3.7.1-1 0 Amend. No. 123 12/18/99 B 3.7.1-2 0 Amend. No. 123 12/18/99 B 3.7.1-3 0 Amend. No. 123 12/18/99 B 3.7.1-4 0 Amend. No. 123 12/18/99 B 3.7.1-5 32 DRR 07-0139 2/7107 B 3.7.1-6 32 DRR 07-0139 2/7/07 B 3.7.2-1 44 DRR 09-1744 10/28/09 B 3.7.2-2 44 DRR 09-1744 10/28/09 B 3.7.2-3 44 DRR 09-1744 10/28/09 B 3.7.2-4 44 DRR 09-1744 10/28/09 B 3.7.2-5 44 DRR 09-1744 10/28/09 B 3.7.2-6 44 DRR 09-1744 10/28/09 B 3.7.2-7 44 DRR 09-1744 10/28/09 B 3.7.2-8 44 DRR 09-1744 10/28/09 B 3.7.2-9 44 DRR 09-1744 10/28/09 B 3.7.2-10 44 DRR 09-1744 10/28/09 B 3.7.2-11 44 DRR 09-1744 10/28/09 B 3.7.3-1 37 DRR 08-0503 4/8/08 B 3.7.3-2 50 DRR 11-0449 3/9/11 B 3.7.3-3 37 DRR 08-0503 4/8/08 B 3.7.3-4 37 DRR 08-0503 4/8/08 B 3.7.3-5 37 DRR 08-0503 4/8/08 B 3.7.3-6 37 DRR 08-0503 4/8/08 B 3.7.3-7 37 DRR 08-0503 4/8/08 B 3.7.3-8 37 DRR 08-0503 4/8/08 B 3.7.3-9 37 DRR 08-0503 4/8/08 B 3.7.3-10 38 DRR 08-0624 5/1/08 B 3.7.3-11 37 DRR 08-0503 4/8/08 B 3.7.4-1 1 DRR 99-1624 12/18/99 B 3.7.4-2 1 DRR 99-1624 12/18/99 B 3.7.4-3 19 DRR 04-1414 10/12/04 B 3.7.4-4 19 DRR 04-1414 10/12/04 B 3.7.4-5 DRR 99-1624 12/18/99 B 3.7.5-1 54 DRR 11-2394 11/16/11 Wolf Creek - Unit 1 X Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

(4)

IMPLEMENTED TAB - B 3.7 PLANT SYSTEMS (continued)

B 3.7.5-2 54 DRR 11-2394 11/16/11 B 3.7.5-3 0 Amend. No. 123 12/18/99 B 3.7.5-4 44 DRR 09-1744 10/28/09 B 3.7.5-5 44 DRR 09-1744 10/28/09 B 3.7.5-6 44 DRR 09-1744 10/28/09 B 3.7.5-7 32 DRR 07-0139 2/7/07 B 3.7.5-8 14 DRR 03-0102 2/12/03 B 3.7.5-9 32 DRR 07-0139 2/7/07 B 3.7.6-1 0 Amend. No. 123 12/18/99 B 3.7.6-2 0 Amend. No. 123 12/18/99 B 3.7.6-3 0 Amend. No. 123 12/18/99 B 3.7.7-1 0 Amend. No. 123 12/18/99 B 3.7.7-2 0 Amend. No. 123 12/18/99 B 3.7.7-3 0 Amend. No. 123 12/18/99 B 3.7.7-4 1 DRR 99-1624 12/18/99 B 3.7.8-1 0 Amend. No. 123 12/18/99 B 3.7.8-2 0 Amend. No. 123 12/18/99 B 3.7.8-3 0 Amend. No. 123 12/18/99 B 3.7.8-4 0 Amend. No. 123 12/18/99 B 3.7.8-5 0 Amend. No. 123 12/18/99 B 3.7.9-1 3 Amend. No. 134 7/14/00 B 3.7.9-2 3 Amend. No. 134 7/14/00 B 3.7.9-3 3 Amend. No. 134 7/14/00 B 3.7.9-4 3 Amend. No. 134 7/14/00 B 3.7.10-1 41 DRR 09-0288 3/20/09 B 3.7.10-2 41 DRR 09-0288 3/20/09 B 3.7.10-3 41 DRR 09-0288 3/20/09 B 3.7.10-4 41 DRR 09-0288 3/20/09 B 3.7.10-5 41 DRR 09-0288 3/20/09 B 3.7.10-6 41 DRR 09-0288 3/20/09 B 3.7.10-7 41 DRR 09-0288 3/20/09 B 3.7.10-8 41 DRR 09-0288 3/20/09 B 3.7.10-9 41 DRR 09-0288 3/20/09 B 3.7.11-1 0 Amend. No. 123 12/18/99 B 3.7.11-2 0 Amend. No. 123 12/18/99 B 3.7.11-3 0 Amend. No. 123 12/18/99 B 3.7.11-4 0 Amend. No. 123 12/18/99 B 3.7.12-1 0 Amend. No. 123 12/18/99 B 3.7.13-1 24 DRR 06-0051 2/28/06 B 3.7.13-2 1 DRR 99-1624 12/18/99 B 3.7.13-3 42 DRR 09-1009 7/16/09 B 3.7.13-4 1 DRR 99-1624 12/18/99 B 3.7.13-5 1 DRR 99-1624 12/18/99 B 3.7.13-6 12 DRR 02-1062 9/26/02 B 3.7.13-7 1 DRR 99-1624 12/18/99 B 3.7.13-8 1 DRR 99-1624 12/18/99 B 3.7.14-1 0 Amend. No. 123 12/18/99 B 3.7.15-1 0 Amend. No. 123 12/18/99 B 3.7.15-2 0 Amend. No. 123 12/18/99 B 3.7.15-3 0 Amend. No. 123 12/18/99 B 3.7.16-1 5 DRR 00-1427 10/12/00 Wolf Creek - Unit 1 xi Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.7 PLANT SYSTEMS (continued)

B 3.7.16-2 23 DRR 05-1995 9/28/05 B 3.7.16-3 5 DRR 00-1427 10/12/00 B 3.7.17-1 7 DRR 01-0474 5/1/01 B 3.7.17-2 7 DRR 01-0474 5/1/01 B 3.7.17-3 5 DRR 00-1427 10/12/00 B 3.7.18-1 0 Amend. No. 123 12/18/99 B 3.7.18-2 0 Amend. No. 123 12/18/99 B 3.7.18-3 0 Amend. No. 123 12/18/99 B 3.7.19-1 44 DRR 09-1744 10/28/09 B 3.7.19-2 54 DRR 11-2394 11/16/11 B 3.7.19-3 54 DRR 11-2394 11/16/11 B 3.7.19-4 54 DRR 11-2394 11/16/11 B 3.7.19-5 54 DRR 11-2394 11/16/11 B 3.7.19-6 54 DRR 11-2394 11/16/11 B 3.7.19-7 54 DRR 11-2394 11/16/11 TAB - B 3.8 ELECTRICAL POWER SYSTEMS B 3.8.1-1 54 DRR 11-2394 11/16/11 B 3.8.1-2 0 Amend. No. 123 12/18/99 B 3.8.1-3 47 DRR 10-1089 6/16/10 B 3.8.1-4 54 DRR 11-2394 11/16/11 B 3.8.1-5 54 DRR 11-2394 11/16/11 B 3.8.1-6 25 DRR 06-0800 5/18/06 B 3.8.1-7 26 DRR 06-1350 7/24/06 B 3.8.1-8 35 DRR 07-1553 9/28/07 B 3.8.1-9 42 DRR 09-1009 7/16/09 B 3.8.1-10 39 DRR 08-1096 8/28/08 B 3.8.1-11 36 DRR 08-0255 3/11/08 B 3.8.1-12 47 DRR 10-1089 6/16/10 B 3.8.1-13 47 DRR 10-1089 6/16/10 B 3.8.1-14 47 DRR 10-1089 6/16/10 B 3.8.1-15 47 DRR 10-1089 6/16/10 B 3.8.1-16 26 DRR 06-1350 7/24/06 B 3.8.1-17 26 DRR 06-1350 7/24/06 B 3.8.1-18 26 DRR 06-1350 7/24/06 B 3.8.1-19 26 DRR 06-1350 7/24/06 B 3.8.1-20 26 DRR 06-1350 7/24/06 B 3.8.1-21 33 DRR 07-0656 5/1/07 B 3.8.1-22 33 DRR 07-0656 5/1/07 B 3.8.1-23 40 DRR 08-1846 12/9/08' B 3.8.1-24 33 DRR 07-0656 5/1/07 B 3.8.1-25 33 DRR 07-0656 5/1/07 B 3.8.1-26 33 DRR 07-0656 5/1/07 B 3.8.1-27 33 DRR 07-0656 5/1/07 B 3.8.1-28 33 DRR 07-0656 5/1/07 B 3.8.1-29 54 DRR 11-2394 11/16/11 B 3.8.1-30 33 DRR 07-0656 5/1/07 B 3.8.1-31 33 DRR 07-0656 5/1/07 B 3.8.1-32 33 DRR 07-0656 5/1/07 B 3.8.1-33 39 DRR 08-1096 8/28/08 B 3.8.1-34 47 DRR 10-1089 6/16/10 Wolf Creek - Unit 1 xii Revision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE-(1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.8 ELECTRICAL POWER SYSTEMS (continued)

B 3.8.2-1 .0 Amend. No. 123 12/18/99 B 3.8.2-2 Amend. No. 123 12/18/99 B 3.8.2-3 0 Amend. No. 123 12/18/99 B 3.8.2-4 0 Amend. No. 123 12/18/99 B 3.8.2-5 12 DRR 02-1062 9/26/02 B 3.8.2-6 12 DRR 02-1062 9/26/02 B 3.8.2-7 12 DRR 02-1062 9/26/02 B 3.8.3-1 1 DRR 99-1624 12/18/99 B 3.8.3-2 0 Amend. No. 123 12/18/99 B 3.8.3-3 0 Amend. No. 123 12/18/99 B 3.8.3-4 1 DRR 99-1624 12/18/99 B 3.8.3-5 0 Amend. No. 123 12/18/99 B 3.8.3-6 0 Amend. No. 123 12/18/99 B 3.8.3-7 12 DRR 02-1062 9/26/02 B 3.8.3-8 1 DRR 99-1624 12/18/99 B 3.8.3-9 0 Amend. No. 123 12/18/99 B 3.8.4-1 0 Amend. No. 123 12/18/99 B 3.8.4-2 0 Amend. No. 123 12/18/99 B 3.8.4-3 0 Amend. No. 123 12/18/99 B 3.8.4-4 0 Amend. No. 123 12/18/99 B 3.8.4-5 50 DRR 11-0449 3/9/11 B 3.8.4-6 50 DRR 11-0449 3/9/11 B 3.8.4-7 6 DRR 00-1541 3/13/01 B 3.8.4-8 0 Amend. No. 123 12/18/99 B 3.8.4-9 2 DRR 00-0147 4/24/00 B 3.8.5-1 0 Amend. No. 123 12/18/99 B 3.8.5-2 0 Amend. No. 123 12/18/99 B 3.8.5-3 0 Amend. No. 123 12/18/99 B 3.8.5-4 12 DRR 02-1062 9/26/02 B 3.8.5-5 12 DRR 02-1062 9/26/02 B 3.8.6-1 0 Amend. No. 123 12/18/99 B 3.8.6-2 0 Amend. No. 123 12/18/99 B 3.8.6-3 0 Amend. No. 123 12/18/99 B 3.8.6-4 0 Amend. No. 123 12/18/99 B 3.8.6-5 0 Amend. No. 123 12/18/99 B 3.8.6-6 0 Amend. No. 123 12/18/99 B 3.8.7-1 0 Amend. No. 123 12/18/99 B 3.8.7-2 5 DRR 00-1427 10/12/00 B 3.8.7-3 0 Amend. No. 123 12/18/99 B 3.8.7-4 0 Amend. No. 123 12/18/99 B 3.8.8-1 0 Amend. No. 123 12/18/99 B 3.8.8-2 0 Amend. No. 123 12/18/99 B 3.8.8-3 0 Amend. No. 123 12/18/99 B 3.8.8-4 12 DRR 02-1062 9/26/02 B 3.8.8-5 12 DRR 02-1062 9/26/02 B 3.8.9-1 54 DRR 11-2394 11/16/11 B 3.8.9-2 54 DRR 11-2394 11/16/11 B 3.8.9-3 54 DRR 11-2394 11/16/11 B 3.8.9-4 0 Amend. No. 123 12/18/99 B 3.8.9-5 0 Amend. No. 123 12/18/99 B 3.8.9-6 0 Amend. No. 123 12/18/99 Wolf Creek - Unit 1 xiii Re\4sbn56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (2) CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

TAB - B 3.8 ELECTRICAL POWER SYSTEMS (continued)

B 3.8.9-7 0 Amend. No. 123 12/18/99 B 3.8.9-8 1 DRR 99-1624 12/18/99 B 3.8.9-9 0 Amend. No. 123 12/18/99 B 3.8.10-1 0 Amend. No. 123 12/18/99 B 3.8.10-2 0 Amend. No. 123 12/18/99 B 3.8.10-3 0 Amend. No. 123 12/18/99 B 3.8.10-4 0 Amend. No. 123 12/18/99 B 3.8.10-5 12 DRR 02-1062 9/26/02 B 3.8.10-6 12 DRR 02-1062 9/26/02 TAB - B 3.9 REFUELING OPERATIONS B 3.9.1-1 0 Amend. No. 123 12/18/99 B 3.9.1-2 19 DRR 04-1414 10/12/04 B 3.9.1-3 19 DRR 04-1414 10/12/04 B 3.9.1-4 19 DRR 04-1414 10/12/04 B 3.9.2-1 0 Amend. No. 123 12/18/99 B 3.9.2-2 0 Amend. No. 123 12/18/99 B 3.9.2-3 0 Amend. No. 123 12/18/99 B 3.9.3-1 24 DRR 06-0051 2/28/06 B 3.9.3-2 51 DRR 11-0664 3/21/11 B 3.9.3-3 51 DRR 11-0664 3/21/11 B 3.9.3-4 53 DRR 11-1513 7/18/11 B 3.9.4-1 23 DRR 05-1995 9/28/05 B 3.9.4-2 13 DRR 02-1458 12/03/02 B 3.9.4-3 25 DRR 06-0800 5/18/06 B 3.9.4-4 23 DRR 05-1995 9/28/05 B 3.9.4-5 33 DRR 07-0656 5/1/07 B 3.9.4-6 23 DRR 05-1995 9/28/05 B 3.9.5-1 0 Amend. No. 123 12/18/99 B 3.9.5-2 32 DRR 07-0139 2/7/07 B 3.9.5-3 32 DRR 07-0139 2/7/07 B 3.9.5-4 32 DRR 07-0139 2/7/07 B 3.9.6-1 0 Amend. No. 123 12/18/99 B 3.9.6-2 42 DRR 09-1009 7/16/09 B 3.9.6-3 42 DRR 09-1009 7/16/09 B 3.9.6-4 42 DRR 09-1009 7/16/09 B 3.9.7-1 25 DRR 06-0800 5/18/06 B 3.9.7-2 0 Amend. No. 123 12/18/99 B 3.9.7-3 0 Amend. No. 123 12/18/99 Wolf Creek - Unit 1 xiv Relvision 56

LIST OF EFFECTIVE PAGES - TECHNICAL SPECIFICATION BASES PAGE (1) REVISION NO. (21 CHANGE DOCUMENT (3) DATE EFFECTIVE/

IMPLEMENTED (4)

Note 1 The page number is listed on the center of the bottom of each page.

Note 2 The revision number is listed in the lower right hand corner of each page. The Revision number will be page specific.

Note 3 The change document will be the document requesting the change. Amendment No.

123 issued the improved Technical Specifications and associated Bases which affected each page. The NRC has indicated that Bases changes will not be issued with License Amendments. Therefore, the change document should be a DRR number in accordance with AP 26A-002.

Note 4 The date effective or implemented is the date the Bases pages are issued by Document Control.

Wolf Creek - Unit 1 XV Revision 56