Letter Sequence Request |
---|
TAC:MD9491, ECCS Conditions and Required Actions with < 100 Percent Equivalent ECCS Flow (Approved, Closed) |
|
MONTHYEARWO 08-0019, Application to Revise Technical Specification 3.5.2, ECCS-Operating, in Accordance with TSTF-325-A2008-08-18018 August 2008 Application to Revise Technical Specification 3.5.2, ECCS-Operating, in Accordance with TSTF-325-A Project stage: Request ML0826101852008-09-17017 September 2008 Acceptance Review Email, License Amendment Request to Revise Technical Specification 3.5.2, ECCS - Operating, in Accordance with TSTF-325A Project stage: Acceptance Review ML0909607342009-05-15015 May 2009 Issuance of Amendment No. 182, Revise Technical Specification 3.5.2, ECCS - Operating, in Accordance with TSTF-325A, ECCS Conditions and Required Actions with <100% Equivalent ECCS Flow Project stage: Approval 2008-09-17
[Table View] |
|
---|
Category:Letter type:WO
MONTHYEARWO 23-0002, Operating Corp., Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-0082023-12-26026 December 2023 Operating Corp., Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 WO 23-0014, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations WO 23-0009, Financial Protection Levels2023-03-31031 March 2023 Financial Protection Levels WO 22-0056, Operating Corporations Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-0082022-12-19019 December 2022 Operating Corporations Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 WO 22-0021, Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report2022-08-29029 August 2022 Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report WO 22-0015, Generation Station - Guarantee of Payment of Deferred Premiums2022-05-0606 May 2022 Generation Station - Guarantee of Payment of Deferred Premiums WO 22-0011, Operating Corp., Financial Protection Levels2022-03-29029 March 2022 Operating Corp., Financial Protection Levels WO 22-0007, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-0909 March 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations WO 21-0064, Operating Corporation, Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-0082021-12-29029 December 2021 Operating Corporation, Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 WO 21-0031, (Wcgs), Supplement to One-Time Request for Exemption from the Biennial Emergency Preparedness2021-08-12012 August 2021 (Wcgs), Supplement to One-Time Request for Exemption from the Biennial Emergency Preparedness WO 21-0027, One-Time Request for Exemption from the Biennial Emergency Preparedness2021-07-29029 July 2021 One-Time Request for Exemption from the Biennial Emergency Preparedness WO 21-0015, License Amendment Request (LAR) for Revision to the Emergency Plan2021-05-25025 May 2021 License Amendment Request (LAR) for Revision to the Emergency Plan WO 21-0020, Operating Corp - Guarantee of Payment of Deferred Premiums2021-05-0707 May 2021 Operating Corp - Guarantee of Payment of Deferred Premiums WO 21-0019, Operating Corp Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations2021-04-14014 April 2021 Operating Corp Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations WO 21-0014, Financial Protection Levels2021-03-30030 March 2021 Financial Protection Levels WO 21-0010, Submittal of Revision 34 to Updated Safety Analysis Report2021-03-11011 March 2021 Submittal of Revision 34 to Updated Safety Analysis Report WO 21-0002, Notification of Readiness for Supplemental Inspection 927232021-01-28028 January 2021 Notification of Readiness for Supplemental Inspection 92723 WO 20-0058, Operating Corporation'S Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-0082020-12-23023 December 2020 Operating Corporation'S Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 WO 20-0050, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange2020-11-10010 November 2020 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange WO 20-0040, Corrected Revision 33 of the Wolf Creek Generating Station Updated Safety Analysis Report2020-07-23023 July 2020 Corrected Revision 33 of the Wolf Creek Generating Station Updated Safety Analysis Report WO 20-0048, Request for Notice of Enforcement Discretion for Technical Specifications 3.8.1, AC Sources - Operating2020-06-30030 June 2020 Request for Notice of Enforcement Discretion for Technical Specifications 3.8.1, AC Sources - Operating WO 20-0047, Guarantee of Payment of Deferred Premiums2020-05-0707 May 2020 Guarantee of Payment of Deferred Premiums WO 20-0029, License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2020-04-20020 April 2020 License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies WO 20-0024, Financial Protection Levels2020-03-31031 March 2020 Financial Protection Levels WO 19-0059, Docket No. 50-482: Wolf Creek Nuclear Operating Corporation'S Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-0082019-12-23023 December 2019 Docket No. 50-482: Wolf Creek Nuclear Operating Corporation'S Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 WO 19-0033, License Amendment Request for Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System2019-08-29029 August 2019 License Amendment Request for Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System WO 19-0031, Supplement 1 to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-08-0808 August 2019 Supplement 1 to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 WO 19-0011, Financial Protection Levels2019-03-27027 March 2019 Financial Protection Levels WO 19-0013, Supplement to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-03-11011 March 2019 Supplement to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 WO 18-0045, Submittal of Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Revision to the Emergency Plan2018-11-19019 November 2018 Submittal of Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Revision to the Emergency Plan WO 18-0047, Timeline for Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-11-15015 November 2018 Timeline for Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term WO 18-0044, Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-11-15015 November 2018 Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term WO 18-0036, Operating Corporation (WCNOC) - Notification of Readiness for Supplemental Inspection2018-08-15015 August 2018 Operating Corporation (WCNOC) - Notification of Readiness for Supplemental Inspection WO 18-0034, Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-08-0909 August 2018 Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term WO 18-0031, Inservice Inspection (ISI) Program Relief Request from the Requirements of American Society of Mechanical Engineers (ASME) Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 12018-07-23023 July 2018 Inservice Inspection (ISI) Program Relief Request from the Requirements of American Society of Mechanical Engineers (ASME) Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 1 WO 18-0016, License Amendment Request for Revision to the Emergency Plan2018-05-0909 May 2018 License Amendment Request for Revision to the Emergency Plan WO 18-0014, Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-16016 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations WO 18-0015, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2018-04-0505 April 2018 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) WO 18-0004, Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of ...2018-01-15015 January 2018 Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of ... WO 17-0093, License Amendment Request (LAR) for Revision to the Emergency Plan2017-12-19019 December 2017 License Amendment Request (LAR) for Revision to the Emergency Plan WO 17-0092, Request for Regulatory Conference (EA-17-149)2017-11-0808 November 2017 Request for Regulatory Conference (EA-17-149) WO 17-0065, Submittal of LER 17-S01-00 for Wolf Creek Nuclear Operating Corp., Regarding Contraband Introduced Into the Protected Area Boundary2017-10-10010 October 2017 Submittal of LER 17-S01-00 for Wolf Creek Nuclear Operating Corp., Regarding Contraband Introduced Into the Protected Area Boundary WO 17-0042, Operating Corporation Supplement to RAI Response Regarding Adopting New EAL Scheme2017-04-26026 April 2017 Operating Corporation Supplement to RAI Response Regarding Adopting New EAL Scheme WO 17-0041, Supplement to Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report2017-04-20020 April 2017 Supplement to Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report WO 17-0033, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations.2017-04-17017 April 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations. WO 17-0023, Submittal of Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report2017-03-27027 March 2017 Submittal of Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report WO 17-0026, Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses2017-03-22022 March 2017 Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses WO 17-0013, Response to Request for Additional Information Regarding License Amendment Request for Adopting Revised Emergency Action Level Scheme2017-03-16016 March 2017 Response to Request for Additional Information Regarding License Amendment Request for Adopting Revised Emergency Action Level Scheme WO 17-0009, Revision 30 to Updated Safety Analysis Report2017-03-0909 March 2017 Revision 30 to Updated Safety Analysis Report WO 16-0068, Docket No. 50-482: Request for Regulatory Conference2016-12-21021 December 2016 Docket No. 50-482: Request for Regulatory Conference 2023-05-17
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML24018A2482024-01-18018 January 2024 License Amendment Request to Modify the Implementation Date of License Amendment No. 238 ML23331A4972023-11-27027 November 2023 Supplement to License Amendment Request to Modify the 90-Day Implementation of License Amendment No. 237 ML23320A2772023-11-16016 November 2023 License Amendment Request to Revise Ventilation Filter Testing Program Criteria in Technical Specification 5.5.11.b and Administrative Correction of Absorber in Technical Specification 5.5.11 ML23171B1312023-06-20020 June 2023 Additional Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 23-0003, License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications2023-03-0101 March 2023 License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML23045A1952023-02-14014 February 2023 Transmittal of the National Pollution Discharge Elimination System Permit Renewal Application for Wolf Creek Generating Station I-NE07-PO02 ET 23-0002, Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2023-02-0707 February 2023 Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22353A5552022-12-15015 December 2022 Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements ET 22-0006, Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2022-12-0101 December 2022 Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 22-0010, License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2022-08-0202 August 2022 License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0001, Removal of the Table of Contents from the Technical Specifications2022-01-12012 January 2022 Removal of the Table of Contents from the Technical Specifications ET 21-0004, License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2021-09-29029 September 2021 License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 21-0005, Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-1912021-08-12012 August 2021 Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-191 WO 21-0015, License Amendment Request (LAR) for Revision to the Emergency Plan2021-05-25025 May 2021 License Amendment Request (LAR) for Revision to the Emergency Plan WM 21-0005, Supplement to License Amendment Request for Change to Owner Licensee Names2021-05-24024 May 2021 Supplement to License Amendment Request for Change to Owner Licensee Names ML21070A0582021-03-11011 March 2021 Changes to Technical Specification Bases - Revisions 82, 83, 84, and 85 WO 20-0050, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange2020-11-10010 November 2020 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange WM 20-0006, (WCGS) - License Amendment Request for Change to Owner Licensee Names2020-11-0404 November 2020 (WCGS) - License Amendment Request for Change to Owner Licensee Names ET 20-0007, License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers2020-06-0808 June 2020 License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers ET 20-0004, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2020-04-27027 April 2020 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) WO 20-0029, License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2020-04-20020 April 2020 License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies WO 19-0033, License Amendment Request for Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System2019-08-29029 August 2019 License Amendment Request for Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System WO 19-0031, Supplement 1 to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-08-0808 August 2019 Supplement 1 to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 ML19052A5462019-04-0101 April 2019 Issuance of Amendment No. 220 Revision to the Emergency Plan ET 19-0002, License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-03-18018 March 2019 License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0003, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange2019-02-25025 February 2019 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange ET 19-0001, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-01-23023 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 WO 18-0044, Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-11-15015 November 2018 Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term WO 18-0034, Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-08-0909 August 2018 Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ML18135A1462018-05-0909 May 2018 Attachments I to V: Evaluation of Proposed Changes, Emergency Plan Change Summary, ERO Position Matrix, Summary of Shift Staffing and Letter of Consultation and Concurrence from Off-Site Response Organizations Ack of Opportunity WO 18-0016, License Amendment Request for Revision to the Emergency Plan2018-05-0909 May 2018 License Amendment Request for Revision to the Emergency Plan ET 18-0007, Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System.2018-02-15015 February 2018 Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. ML17363A1422017-12-19019 December 2017 License Amendment Request (LAR) for Revision to the Emergency Plan (Attachments and Enclosures) WM 17-0021, Updated Request for Consent to Indirect Transfer of Control2017-09-0505 September 2017 Updated Request for Consent to Indirect Transfer of Control WO 17-0026, Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses2017-03-22022 March 2017 Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses ML17054C2232017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed COLR Changes ET 17-0001, License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses, Enclosure 10 - CAW-16-45002017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses, Enclosure 10 - CAW-16-4500 ML17054C2272017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Alternative Source Term, Rev 1 ML17054C2362017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses, Enclosure 9 - CAW-16-4499 ML17054C2192017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Evaluation ML17054C2352017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - WOG-93-066 ML17054C2302017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - A-3788, Technical Report, Appendix a, Fission Product Removal Effectiveness of Chemical Additives in PWR Containment Sprays ML17054C2332017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - CAW-92-287 ML17054C2202017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed Technical Specification Changes ML17054C2262017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - WCAP-18083-NP, Rev 0, Westinghouse Revised Thermal Design Procedure Uncertainty Calculations. ML17054C2222017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed Technical Specification Bases Changes ML17054C2322017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - OG-92-25, Steam Generator Tube Uncovery Issue ML17054C2212017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Revised Technical Specification Pages ML17054C2292017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Responses to NRC RAIs on August 2013 Methodology Transition LAR Submittal NEI 99-01, Wolf Creek Nuclear Operating Corporation Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors2016-09-30030 September 2016 Wolf Creek Nuclear Operating Corporation Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors 2024-01-18
[Table view] Category:Technical Specification
MONTHYEARML23320A2772023-11-16016 November 2023 License Amendment Request to Revise Ventilation Filter Testing Program Criteria in Technical Specification 5.5.11.b and Administrative Correction of Absorber in Technical Specification 5.5.11 ML23068A1232023-03-0909 March 2023 Changes to Technical Specification Bases Revisions 91 and 92 ET 23-0002, Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2023-02-0707 February 2023 Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22353A5552022-12-15015 December 2022 Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements ET 22-0006, Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2022-12-0101 December 2022 Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 22-0012, Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-07-12012 July 2022 Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ML22067A0302022-03-0808 March 2022 Changes to Technical Specification Bases - Revisions 86, 87, 88, 89, and 90 ML21070A0582021-03-11011 March 2021 Changes to Technical Specification Bases - Revisions 82, 83, 84, and 85 WO 20-0050, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange2020-11-10010 November 2020 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange ET 20-0004, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2020-04-27027 April 2020 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) WO 20-0029, License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2020-04-20020 April 2020 License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML20070L9822020-03-0202 March 2020 Changes to Technical Specification Bases - Revisions 80 and 81 ET 19-0002, License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-03-18018 March 2019 License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ML19078A1302019-03-11011 March 2019 Changes to Technical Specification Bases - Revisions 78 and 79 WO 19-0013, Supplement to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-03-11011 March 2019 Supplement to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 WO 18-0044, Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-11-15015 November 2018 Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ML18075A0242018-03-0808 March 2018 Changes to Technical Specification Bases - Revisions 76 and 77 WO 18-0004, Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of ...2018-01-15015 January 2018 Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of ... ML17073A0932017-03-0909 March 2017 Changes to Technical Specification Bases - Revisions 74 and 75 ML17054C2212017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Revised Technical Specification Pages ML17054C2222017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed Technical Specification Bases Changes ML17054C2202017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed Technical Specification Changes ML16076A3572016-03-10010 March 2016 Changes to Technical Specification Bases - Revisions 67 Through 73 WO 15-0051, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10 and 3.8.1.142015-09-23023 September 2015 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10 and 3.8.1.14 ML15077A0662015-03-11011 March 2015 Changes to Technical Specification Bases, Revisions 61 Through 66 WO 14-0092, Submittal of Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report2014-12-15015 December 2014 Submittal of Technical Specification 5.6.8 - Post Accident Monitoring (PAM) Report ET 13-0028, Application to Revise Technical Specifications to Replace a Methodology to TS 5.6.5, Core Operating Limits Report.2013-09-23023 September 2013 Application to Revise Technical Specifications to Replace a Methodology to TS 5.6.5, Core Operating Limits Report. ET 13-0023, License Amendment Request for the Transition to Westinghouse Core Design and Safety Analysis2013-08-13013 August 2013 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analysis ML13079A0602013-03-0808 March 2013 Changes to Technical Specification Bases - Revisions 55 and 56 ML12080A2162012-03-12012 March 2012 Changes to Technical Specification Bases - Revisions 50 Through 54 WO 11-0086, Application to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating2011-11-30030 November 2011 Application to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating ML1107500362011-03-10010 March 2011 Changes to Technical Specification Bases - Revisions 45 Through 49 ML1007801282010-03-11011 March 2010 Changes to Technical Specification Bases - Revisions 41 Through 44 ML1006401412010-03-0404 March 2010 Supplemental Information for Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation, Auxiliary Feedwater - Trip of All Main Feedwater Pumps ET 10-0011, Supplemental Information for Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation, Auxiliary Feedwater - Trip of All Main Feedwater Pumps2010-03-0404 March 2010 Supplemental Information for Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation, Auxiliary Feedwater - Trip of All Main Feedwater Pumps ML1006400442010-03-0303 March 2010 Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation, Auxiliary Feedwater - Trip of All Main Feedwater Pumps ET 09-0025, Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Program, and TS 5.6.10, Steam Generator Tube Inspection Report2009-09-15015 September 2009 Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Program, and TS 5.6.10, Steam Generator Tube Inspection Report WO 09-0022, Request for Approval of Changes to the Technical Specification 3.8.1, AC Sources - Operating, Bases2009-09-0303 September 2009 Request for Approval of Changes to the Technical Specification 3.8.1, AC Sources - Operating, Bases ML0907506242009-03-11011 March 2009 Submittal of Changes to Technical Specification Bases - Revisions 36 Through 40 WO 08-0019, Application to Revise Technical Specification 3.5.2, ECCS-Operating, in Accordance with TSTF-325-A2008-08-18018 August 2008 Application to Revise Technical Specification 3.5.2, ECCS-Operating, in Accordance with TSTF-325-A ET 08-0041, Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation.2008-08-14014 August 2008 Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation. ML0811201492008-04-29029 April 2008 Corrected Technical Specification Pages, Amendment No. 177 Revision to Technical Specification 3.7.3, Main Feedwater Isolation Valves, to Add Main Feedwater Regulating Valves and MFRV Bypass Valves ML0807805602008-03-0707 March 2008 Changes to Technical Specification Bases - Revisions 32 Through 35 ML0804501852008-02-28028 February 2008 Withdrawal of License Amendment Request on Steam Generator Tube Inspections WO 08-0001, Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process2008-01-15015 January 2008 Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process ML0707402282007-03-0909 March 2007 Changes to Technical Specification Bases - Revisions 24 Through 31 ML0631905352006-11-15015 November 2006 Tech Spec Pages for Issuance of License Amendment 172 Regarding Revision to Technical Specification 5.5.8 on the Inservice Testing Program ML0627804522006-10-0505 October 2006 Technical Specification Pages - Issuance of Amendment Revise Containment Sump Surveillance Requirement to Verify Strainer Integrity ML0624201502006-08-29029 August 2006 Techncial Specification, Addition of Surveillance Requirement 3.3.1.16 to TS Table 3.3.1.16 WM 06-0033, Revision to Technical Specification (TS) 3.7.2, Main Steam Isolation Valves (Msivs), and TS 3.7.3, Main Feedwater Isolation Valves (Mfivs).2006-08-25025 August 2006 Revision to Technical Specification (TS) 3.7.2, Main Steam Isolation Valves (Msivs), and TS 3.7.3, Main Feedwater Isolation Valves (Mfivs). 2023-03-09
[Table view] Category:Amendment
MONTHYEARML23320A2772023-11-16016 November 2023 License Amendment Request to Revise Ventilation Filter Testing Program Criteria in Technical Specification 5.5.11.b and Administrative Correction of Absorber in Technical Specification 5.5.11 ET 23-0002, Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2023-02-0707 February 2023 Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22353A5552022-12-15015 December 2022 Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements ET 22-0012, Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-07-12012 July 2022 Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating WO 18-0004, Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of ...2018-01-15015 January 2018 Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of ... ML16076A3572016-03-10010 March 2016 Changes to Technical Specification Bases - Revisions 67 Through 73 WO 11-0086, Application to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating2011-11-30030 November 2011 Application to Revise Technical Specification (TS) 3.8.1, AC Sources - Operating ET 09-0025, Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Program, and TS 5.6.10, Steam Generator Tube Inspection Report2009-09-15015 September 2009 Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Program, and TS 5.6.10, Steam Generator Tube Inspection Report WO 08-0019, Application to Revise Technical Specification 3.5.2, ECCS-Operating, in Accordance with TSTF-325-A2008-08-18018 August 2008 Application to Revise Technical Specification 3.5.2, ECCS-Operating, in Accordance with TSTF-325-A ML0811201492008-04-29029 April 2008 Corrected Technical Specification Pages, Amendment No. 177 Revision to Technical Specification 3.7.3, Main Feedwater Isolation Valves, to Add Main Feedwater Regulating Valves and MFRV Bypass Valves ML0804501852008-02-28028 February 2008 Withdrawal of License Amendment Request on Steam Generator Tube Inspections WO 08-0001, Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process2008-01-15015 January 2008 Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process ML0631905352006-11-15015 November 2006 Tech Spec Pages for Issuance of License Amendment 172 Regarding Revision to Technical Specification 5.5.8 on the Inservice Testing Program ML0627804522006-10-0505 October 2006 Technical Specification Pages - Issuance of Amendment Revise Containment Sump Surveillance Requirement to Verify Strainer Integrity ML0624201502006-08-29029 August 2006 Techncial Specification, Addition of Surveillance Requirement 3.3.1.16 to TS Table 3.3.1.16 WO 06-0023, Revision to Technical Specification 3.5.2, ECCS - Operating.2006-06-0202 June 2006 Revision to Technical Specification 3.5.2, ECCS - Operating. ET 05-0001, Exigent Request for Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Tube Surveillance Program2005-04-18018 April 2005 Exigent Request for Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Tube Surveillance Program ML0507702972005-03-16016 March 2005 Tech Spec Page for Amendment 160 Revised Seal Injection Flow Rates ML0503301602005-01-31031 January 2005 Technical Specifications, Amendment 156 Plant Protection Test Times, Completion Times and Surveillance Test Intervals ML0503502612005-01-31031 January 2005 Tech Spec Pages for Amendment 158, Elimination of Requirements to Provide Monthly Operating Reports and Annual Occupational Radiation Exposure Reports. WO 04-0050, Revision to Technical Specification (TS) 3.8.1, AC Sources-Operating, Diesel Generator Start Time Surveillance Requirements2004-12-13013 December 2004 Revision to Technical Specification (TS) 3.8.1, AC Sources-Operating, Diesel Generator Start Time Surveillance Requirements WO 04-0031, Revision to Technical Specification (TS) 5.3, Unit Staff Qualifications, and Corrections to Various TSs2004-10-0707 October 2004 Revision to Technical Specification (TS) 5.3, Unit Staff Qualifications, and Corrections to Various TSs WO 04-0027, Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Recombiners and Hydrogen Monitors Using the Consolidated Line Item Improvement Process2004-07-23023 July 2004 Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Recombiners and Hydrogen Monitors Using the Consolidated Line Item Improvement Process WO 04-0035, Application for Technical Specification Improvement to Eliminate Requirements to Provide Monthly Operating Reports and Occupational Radiation Exposure Reports Using the Consolidated Line Item Improvement Process2004-07-23023 July 2004 Application for Technical Specification Improvement to Eliminate Requirements to Provide Monthly Operating Reports and Occupational Radiation Exposure Reports Using the Consolidated Line Item Improvement Process WO 03-0057, Revision to Technical Specifications Regarding Extensions of AC Electrical Power Distribution Completion Time2003-10-30030 October 2003 Revision to Technical Specifications Regarding Extensions of AC Electrical Power Distribution Completion Time ML0221200382002-07-29029 July 2002 Technical Specifications for Amendment 123, Limited Removal of Suspension of Positive Reactivity Additions 2023-02-07
[Table view] |
Text
W6LF CREEK rNUCLEAR OPERATING CORPORATION Matthew W. Sunseri Vice President Operations and Plant Manager August 18, 2008 WO 08-0019 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Subject:
Docket No. 50-482: Application To Revise Technical Specification 3.5.2, " ECCS - Operating," In Accordance With TSTF-325-A Gentlemen:
Pursuant to 10 CFR 50.90, Wolf Creek Nuclear Operating Corporation (WCNOC) hereby requests an amendment to Facility Operating License No. NPF-42 for the Wolf Creek Generating Station (WCGS).
The proposed amendment would modify Technical Specification (TS) 3.5.2, "ECCS -
Operating," requirements in accordance with Technical Specification Task Force (TSTF) TSTF-325-A, Revision 0, "ECCS Conditions and Required Actions <100% Equivalent ECCS Flow."
This TS improvement was approved June 29, 1999 in a letter from William D. Beckner, Chief, Technical Specifications Branch, NRR, to James Davis, Director, Operations Department, NEI.
Attachment I provides a description of the proposed change and supporting technical evaluation. Attachment II provides the existing TS pages marked up to show the proposed changes. Attachment III provides revised (clean) TS pages. Attachment IV provides a summary of the regulatory commitments made in this submittal. Attachment V provides the existing TS Bases pages marked up to show proposed changes and is for information only.
Final TS Bases changes will be implemented pursuant to TS 5.5.14, "Technical Specification (TS) Bases Control Program," at the time the amendment is implemented.
It has been determined that this amendment application does not involve a significant hazard consideration as determined per 10 CFR 50.92. Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment needs to be prepared in connection with the issuance of this amendment.
This amendment application was reviewed by the Plant Safety Review Committee. In accordance with 10 CFR 50.91, a copy of this amendment application, with attachments, is being provided to the designated Kansas State official.
P.O. Box 411 / Burlington, KS 66839 / Phone: (620) 364-8831 An Equal Opportunity Employer M/F/HC/VET
WO 08-0019 Page 2 of 3 WCNOC requests approval of the proposed amendment by July 1, 2009. The changes proposed are not required to address an immediate safety concern. It is anticipated that the license amendment, as approved, will be effective upon issuance and will be implemented within 90 days from the date of issuance. Please contact me at (620) 364-4008 or Mr. Richard Flannigan at (620) 364-4117 for any questions you may have regarding this application.
Sincerely, Matthew W. Sunseri MWS/rlt Attachments: Evaluation IV Proposed Technical Specification Changes (Mark-up)
Il Revised Technical Specification Pages IV Regulatory Commitments V Proposed Technical Specification Bases Changes (For Information Only) cc: E. E. Collins (NRC), w/a T. A. Conley (KDHE), w/a V. G. Gaddy (NRC), w/a B. K. Singal (NRC), w/a Senior Resident Inspector (NRC), w/a
WO 08-0019 Page 3 of 3 STATE OF KANSAS )
SS COUNTY OF COFFEY )
Matthew W. Sunseri, of lawful age, being first duly sworn upon oath says that he is Vice President Operations and Plant Manager of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.
Matthew W. Sunseri Vice President Operations and Plant Manager SUBSCRIBED and sworn to before me this I 3'4b day of at*t
,2008.
SANDY M.GHOLSON hota4 Public Notary Public - State of Kansas My Appt. Expires *,5/9O01 Expiration Date 5/Ihbo II
Attachment I to WO 08-0019 Page 1 of 6 EVALUATION
- 1.
SUMMARY
DESCRIPTION
- 2. DETAILED DESCRIPTION
- 3. TECHNICAL EVALUATION
- 4. REGULATORY EVALUATION 4.1 Applicable Regulatory Requirements/Criteria 4.2 Precedent 4.3 Significant Hazards Consideration 4.4 Conclusion
- 5. ENVIRONMENTAL CONSIDERATION
- 6. REFERENCES
Attachment I to WO 08-0019 Page 2 of 6 EVALUATION
- 1.
SUMMARY
DESCRIPTION The proposed amendment would modify technical specification (TS) requirements related to Emergency Core Cooling Systems (ECCS) in TS 3.5.2, "ECOS - Operating."
The changes are consistent with Nuclear Regulatory Commission (NRC) Industry Technical Specification Task Force (TSTF) Standard Technical Specification change TSTF-325-A, Revision 0, "ECCS Conditions and Required Actions with <100% Equivalent ECCS Flow,"
(Reference 6.1). This TS improvement was approved in a June 29, 1999 (Reference 6.2) letter from William D. Beckner, Chief, Technical Specifications Branch, NRR, to James Davis, Director, Operations Department, NEI.
- 2. DETAILED DESCRIPTION Consistent with Revision 0 of TSTF-325-A, the proposed TS changes include:
- 1. "AND at least 100% of the ECCS flow equivalent to a single OPERABLE ECCS train available" has been deleted from Condition A.
- 2. Create a new condition, Condition C that states, "Less than 100% of the ECCS flow equivalent to a single OPERABLE train available." Required Action C.1, "Enter LCO 3.0.3" and its Completion Time of "Immediately."
The wording in the new Condition C is the same as that deleted from the existing Condition A.
- 3. TECHNICAL EVALUATION 3.1 System Description The primary function of the ECCS is to provide emergency core cooling in the event of a loss of coolant accident (LOCA) resulting from a break in the primary reactor coolant system (RCS) or to provide emergency boration in the event of a steam and/or feedwater break accident. The ECCS components are designed so that a minimum of three accumulators, one centrifugal charging pump, one safety injection pump, and one residual heat removal (RHR) pump, together with their associated valves and piping, ensure adequate core cooling and provide emergency boration. The onsite emergency diesels assure adequate emergency power to at least one train of electrically operated components in the event that a loss of offsite power occurs simultaneously with a LOCA.
There are three modes of ECCS operation: injection mode, cold leg recirculation mode, and hot leg recirculation mode. In the injection mode, water is taken from the refueling water storage tank (RWST) and injected into the RCS cold legs. When sufficient water is removed from the RWST to ensure that enough boron has been added to keep the reactor subcritical and the containment recirculation sump has enough water to supply the RHR pump with its required net positive suction head, the suctions of the RHR pumps are shifted to the containment recirculation sumps. The RHR pumps in turn supply the RCS and the other ECCS pumps.
Water is now being taken from the containment recirculation sumps, cooled by component
Attachment I to WO 08-0019 Page 3 of 6 cooling water in the RHR heat exchangers, and returned to the RCS cold legs. Approximately 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> after the initiation of safety injection, the ECCS is shifted to hot leg recirculation. This is done because the top of the core could potentially be in a boiling condition where boron could plate out on the core. Hot leg recirculation provides a backflush where water will enter the top of the core and reduce the boiling and the resulting boron precipitation. The flow path in hot leg recirculation is from the containment recirculation sump, through RHR heat exchangers, and into the RCS hot legs.
3.2 Justification for Change In January 2008, control room personnel declared both trains of ECCS inoperable and determined that LCO 3.5.2 was not met. LCO 3.5.2 requires two ECCS trains be OPERABLE.
LCO 3.0.3 was subsequently entered when it was determined that an associated ACTION in LCO 3.5.2 did not exist. Condition A of LCO 3.5.2 is applicable when one or more trains is inoperable AND at least 100% of the ECCS flow equivalent to a single OPERABLE ECCS train is available. Condition A was not entered since 100% ECCS flow equivalent was not available.
Therefore, LCO 3.0.3 was entered and the plant subsequently proceeded to MODE 3. When the "B" RHR train was restored to OPERABLE status, LCO 3.0.3 was exited and Condition A of LCO 3.5.2 was entered with 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore the opposite train to OPERABLE status. It was subsequently determined that the LCO 3.5.2 Condition A entry time should have commenced at the time that LCO 3.0.3 was entered. This determination is based on the wording in the LCO 3.0.3 TS Bases that specify that LCO 3.0.3 may be exited if ACTIONS exist that do not have expired Completion Times and these Completion Times are applicable from the point in time that the Condition is initially entered and not from the time LCO 3.0.3 is exited. During the investigation into this event, the existence of TSTF-325-A was identified and determined to be applicable to this event. If TSTF-325-A had been incorporated into the WCGS TSs, both Condition A and Condition C would have been entered and the confusion regarding the entry time into Condition A would not have existed.
Condition A of LCO 3.5.2 states, "One or more trains of ECCS inoperable AND at least 100% of the ECCS flow equivalent to a single OPERABLE ECCS train available." Per TSTF-325-A, this allows inoperabilities to be present in both trains, as long as 100% equivalent flow is available.
If a situation were to occur which resulted in less than 100% ECCS flow, then LCO 3.0.3 would be entered. However, the stated conditions for Condition A would no longer be applicable, as there was less than the 100% equivalent flow. It could be interpreted from the "AND" that Condition A is exited when LCO 3.0.3 is entered. This is in conflict with Section 1.3 on Completion Times, specifically Example 1.3-2. The intent is that even though LCO 3.0.3 is entered, the applicable Condition of the affected LCO (in this case, Condition A of LCO 3.5.2) should not be exited. Condition A should still be applicable, and the time tracked while in LCO 3.0.3. This will allow a smooth transition should a pump/train be restored and LCO 3.0.3 exited.
The transition can be accomplished by splitting Condition A into 2 separate Conditions, such that with any pump/train inoperable, Condition A will still be applicable.
Technical Specification 3.5.2 and associated Bases was written for the Improved Standard Technical Specifications and incorporated into the WCGS TSs with a flawed logic, making it difficult to determine the intent for entry/exit conditions in the LCO. The structure of LCO 3.5.2 has been rearranged to maintain Condition A in effect if failures should occur that reduce available flow to <100% of the required flow. In the case where inoperable ECCS train components reduce available flow below that required, and a subsequent partial restoration is made to provide 100% of the required flow, the proposed change makes the Completion Time
Attachment I to WO 08-0019 Page 4 of 6 for Condition A start when the initial inoperability occurred rather than (with literal interpretation of the existing arrangement) when Condition A was entered after the partial restoration.
Therefore, there is no change in the intent or application of the LCO.
- 4. REGULATORY EVALUATION 4.1 Applicable Regulatory Requirements/Criteria The regulatory basis for an LCO is to describe the lowest functional capability or performance level of equipment required for safe operation of the facility, to specify the minimum amount of equipment that must be OPERABLE to operate in a MODE, and to identify process parameters and specify Allowable Values to preserve Safety Analyses initial condition assumptions.
GDC 35, "Emergency core cooling," requires a system to provide abundant emergency core cooling. Suitable redundancy in components and features, and suitable interconnections, leak detection, isolation, and containment capabilities shall be provided.
GDC 36, "Inspection of emergency core cooling," requires the ECCS to be designed to permit appropriate periodic inspection of important components to assure the integrity and capability of the system.
GDC 37, "Testing of emergency core cooling system," requires the ECCS to be designed to permit appropriate periodic pressure and functional testing to assure the structural and leaktight integrity, the OPERABILITY and performance of the active components, and the OPERABILITY of the system as a whole.
The requirements of GDC 35, 36 and 37 continue to be met because the change being proposed will not affect the design capability, function, operation or methods of testing.
4.2 Precedent Amendment No. 198 (Reference 6.3), was issued on May 3, 2001 for the Palisades Plant. This amendment changes the structure of the ACTIONS table consistent with TSTF-325-A. The wording of the new Condition is different than the wording in TSTF-325-A. The WCNOC proposed amendment changes the structure of the ACTIONS table and uses the same words in the new Condition per TSTF-325-A. (ADAMS Accession Number ML011280347) 4.3 Significant Hazards Consideration WCNOC has evaluated whether or not a significant hazards consideration is involved with the proposed amendment by focusing on the three standards set forth in 10 CFR 50.92, Issuance of Amendment:
- 1. Does the proposed amendment involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No The proposed change corrects the structure of the ACTIONS table to assure its correct application. There is no change or intent in the way the Conditions are actually applied.
Attachment I to WO 08-0019 Page 5 of 6 The literal interpretation of the existing Conditions structure could, under some circumstances, provide longer than intended Completion Times for restoration of OPERABILITY. Since the proposed change affects neither the Conditions intent nor its application, the proposed change will not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Does the proposed amendment create the possibility of a new or different kind of accident from any previously evaluated?
Response: No The proposed change corrects the structure of the ACTIONS table to assure its correct application. The proposed change does not result in any physical alterations to the plant configuration, no new equipment additions, no equipment interface modifications, and no changes to any equipment function or the method of operating the equipment are being made. As the proposed change would not change the design, configuration or operation of the plant, no new or different kinds of accident modes are created. Therefore, the proposed change does not create the possibility of a new or different kind of accident from any previously evaluated.
- 3. Does the proposed amendment involve a significant reduction in a margin of safety?
Response: No The proposed change corrects the structure of the LCO to assure its correct application.
The proposed change is consistent with the requirements of the Technical Specifications. There is no change in intent or in the way the LCO is applied. Therefore, the proposed change does not involve a significant reduction in the margin of safety.
4.4 Conclusion The change to TS 3.5.2 is being made based on TSTF-325-A, "ECCS Conditions and Required Actions with <100% Equivalent ECCS Flow." The proposed change to the format of the existing Condition requirements is an administrative change because it does not alter the existing restriction on plant operation, but only clarifies the intent of the existing Condition requirements, making them consistent with the Completion Time rule of TS 1.3, "Completion Times." Based on the considerations discussed above, 1) there is a reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, 2) such activities will be conducted in compliance with the Commission's regulations, and 3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
- 5. ENVIRONMENTAL CONSIDERATION WCNOC has evaluated the proposed change and has determined that the change does not involve (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amount of effluent that my be released offsite, or (iii) a significant increase in the individual or cumulative occupational radiation exposure. Accordingly, the proposed changes meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Therefore, pursuant to 10 CFR 51.22(b), an environmental assessment of the proposed change is not required.
Attachment I to WO 08-0019 Page 6 of 6
- 6. REFERENCES 6.1 Technical Specification Task Force (TSTF) Improved Standard Technical Specifications Change Traveler, TSTF-325-A, Revision 0, "ECCS Conditions and Required Actions with <100% Equivalent ECCS Flow."
6.2 NRC Letter dated June 29, 1999, from William D. Beckner, Chief, Technical Specifications Branch, NRR, to James Davis, Director, Operations Department, NEI.
6.3 NRC Letter dated May 3, 2001, Amendment No. 198 to Facility Operational License No.
DPR-20 for the Palisades Plant.
Attachment II to WO 08-0019 Page 1 of 3 ATTACHMENT II PROPOSED TECHNICAL SPECIFICATION CHANGES (MARK-UP)
Attachment II to WO 08-0019 Page 2 of 3 ECCS - Operating 3.5.2 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) 3.5.2 ECCS - Operating LCO 3.5.2 Two ECCS trains shall be OPERABLE.
-NOTES-
- 1. In MODE 3, both safety injection (SI) pump flow paths may be isolated by closing the isolation valves for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to perform pressure isolation valve testing per SR 3.4.14.1.
- 2. Operation in MODE 3 with ECCS pumps made incapable of injecting pursuant to LCO 3.4.12, "Low Temperature Overpressure Protection (LTOP) System," is allowed for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> or until the temperature of all RCS cold legs exceeds 375 0 F, whichever comes first.
APPLICABILITY: MODES 1, 2, and 3.
Inosef r-Wolf(C*reek - Unit 1 3.5-3 Amendment No. 123
Attachment II to WO 08-0019 Page 3 of 3 Insert 3.5-3 C. Less than 100% of the C. 1 Enter LCO 3.0.3. Immediately ECCS flow equivalent to a single OPERABLE train available.
Attachment III to WO 08-0019 Page 1 of 2 ATTACHMENT III REVISED TECHNICAL SPECIFICATION PAGES
ECCS - Operating 3.5.2 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) 3.5.2 ECCS -Operating LCO 3.5.2 Two ECCS trains shall be OPERABLE.
NOT r- "*I--------- - - ---- - ------- - --------------
- 1. In MODE 3, both safety injection (SI) pump flow paths may be isolated by closing the isolation valves for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to perform pressure isolation valve testing per SR 3.4.14.1.
- 2. Operation in MODE 3 with ECCS pumps made incapable of injecting pursuant to LCO 3.4.12, "Low Temperature Overpressure Protection (LTOP) System," isallowed for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> or until the temperature of all RCS cold legs exceeds 3750F, whichever comes first.
APPLICABILITY: MODES 1, 2, and 3..
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One or more trains A.1 Restore train(s) to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> inoperable. OPERABLE status.
B. Required Action and B.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met. AND B.2 Be in MODE 4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> C. Less than 100% of the C. 1 Enter LCO 3.0.3. Immediately ECCS flow equivalent to a single OPERABLE ECCS train available.
Wolf Creek - Unit 1 3.5-3 Amendment No. +24
ECCS - Operating 3.5.2 SURVEILLANCE REQUIREMENTS SURVEILLANCE, , FREQUENCY SR 3.5.2.1 Verif y the following valves are in the listed position 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />s&,.)
with power to the valve operator removed.
Number Position Function BN HV-8813 Open Safety Injection to RWST Isolation Valve EM HV-8802A Closed SI Hot Legs 2 & 3 Isolation Valve EM HV-8802B Closed SI Hot Legs 1 & 4 Isolation Valve EM HV-8835 Open Safety Injection Cold Leg Isolation Valve EJ HV-8840 Closed RHR/SI Hot Leg Recirc -
Isolation Valve EJ HV-8809A Open RHR to Accum Inject Loops 1 & 2 Isolation Valve EJ HV-8809B Open RHR to Accum Inject Loops 3 & 4 Isolation Valve SR 3.5.2.2 Verify each ECCS manual, power operated, and 31 days automatic valve in the flow path, that is not locked, sealed, or otherwise secured in position, is in the correct position.
SR 3.5.2.3 Verify ECCS piping is full of water. 31 days SR 3.5.2.4 Verify each ECCS pump's developed head at the test In accordance with flow point is greater than or equal to the required the Inservice developed head. Testing Program (continued)
Wolf Creek - Unit 1 3.5-4 Amendment No. 123
Attachment IV to WO 08-0019 Page lofl ATTACHMENT IV REGULATORY COMMITMENTS The following table identifies those actions committed to by WCNOC in .this document. Any' other statements in this submittal are provided for informatibn purposes and are not considered to be regulatory commitments. Please direct questions regarding these commitments to Mr.
Richard Flannigan at (620) 364-4117.
Regulatory Commitments Due Date /Event*'
The proposed changes to the WCGS Technical Specifications will Within 90 days of NRC be implemented within 90 days of NRC approval, approval.
Attachment V to WO 08-0019 Page 1 of 4 ATTACHMENT V PROPOSED TECHNICAL SPECIFICATION BASES CHANGES (For Information Only)
Attachment V to WO 08-0019 ECCS - Operating Page 2 of 4 B 3.5.2 BASES APPLICABILITY In MODES 1, 2, and 3, the ECCS OPERABILITY requirements for the limiting Design Basis Accident, a large break LOCA, are based on full power operation. Although reduced power would not require the same level of performance, the accident analysis does not provide for reduced cooling requirements in the lower MODES. The centrifugal charging pump performance is based on a small break LOCA, which establishes the pump performance curve and has less dependence on power. The SI pump performance requirements are based on a small break LOCAK MODE 2 and MODE 3 requirements are bounded by the MODE 1 analysis.
This LCO is only applicable in MODE 3 and above. Below MODE 3, the system functional requirements are relaxed as described in LCO 3.5.3, "ECCS - Shutdown."
In MODES 5 and 6, plant conditions are such that the probability of an event requiring ECCS injection is extremely low. Core cooling requirements in MODE 5 are addressed by LCO 3.4.7, "RCS Loops -
MODE 5, Loops Filled," and LCO 3.4.8, "RCS Loops - MODE 5, Loops Not Filled." MODE 6 core cooling requirements are addressed by LCO 3.9.5, "Residual Heat Removal (RHR) and Coolant Circulation - High Water Level," and LCO 3.9.6, "Residual Heat Removal (RHR) and Coolant Circulation - Low Water Level."
ACTIONS A.1 With one or more trains inopera~ble. {dg,!/ea~s 02*ootelC *l t'6gvajgnto, " sir Ie,)PEG*BL-.C.C tr via*e VZn then~operal {3e-comc-pd nerhts must be returned to OPERABLE status wit in 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is based on an NRC reliability evaluation (Ref. 5) and is a reasonable time for repair of many ECCS components.
An ECCS train is inoperable if it is not capable of delivering design flow to the RCS. Individual components are inoperable if they are not capable of performing their design function or supporting systems are not available.
The LCO requires the OPERABILITY of a number of independent subsystems. Due to the redundancy of trains and the diversity of subsystems, the inoperability of one component in a train does not render the ECCS incapable of performing its function. Neither does the inoperability of two different components, each in a different train necessarily result in a loss of function for the ECCS.hh i e of hi/
n "i'* st in in co bin tion f e iph 10 Wolf Creek - Unit 1 B 3.5.2-6 Revision 0
Attachment V to WO 08-0019 Page 3 of 4 ECCS - Operating B 3.5.2 BASES ACTIONS A. 1 (continued) o euale to1 siyle P l _E CC-Ctrajvreiai
'a4.4a* l*.his allows increased flexib lity in plant operations under circums1ances when components in opposite trains are inoperable.
An event accompanied by a loss of offsite power and the failure of an EDG can disable one ECCS train until power is restored. A reliability analysis (Ref. 5) has shown that the impact of having one full ECCS train inoperable is sufficiently small to justify continued operation for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
Reference 6 describes situations in which one component, such as an RHR crossover valve, can disable both ECCS trains. With one or more component(s) inoperable such that 100% of the flow equivalent to a single OPERABLE ECCS train is not available, the facility is in a condition outside the accident analysis. Therefore, LCO 3.0.3 must be immediately entered.
B.1 and B.2 If the inoperable trains cannot be returned to OPERABLE status within the associated Completion Time, the plant must be brought to a MODE in which the LCO does not apply. To achieve this status, the plant must be brought to MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required plant conditions from full power
_", I conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.5.2.1 REQUIREMENTS Verification of proper valve position ensures that the flow path from the ECCS pumps to the RCS is maintained. Misalignment of these valves could render both ECCS trains inoperable. Securing these valves in position by removal of power or by key locking the control in the correct position ensures that they cannot change position as a result of an active failure or be inadvertently misaligned. These valves are of the type, described in References 6 and 7, that can disable the function of both ECCS trains and invalidate the accident analyses. A 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Frequency is considered reasonable in view of other administrative controls that will ensure a mispositioned valve is unlikely.
Wolf Creek - Unit 1 B 3.5.2-7 Revision 0
Attachment V of WO 08-0019 Page 4 of 4 Insert B 3.5.2-7 C.1 Condition A is applicable with one or more trains inoperable. The allowed Completion Time is based on the assumption that at least 100% of the ECCS flow equivalent to a single OPERABLE ECCS train is available. With less than 100% of the ECCS flow equivalent to a single OPERABLE ECCS train available, the facility is in a condition outside of the accident analyses. Therefore, LCO 3.0.3 must be entered immediately.