Similar Documents at Fermi |
---|
Category:Letter
MONTHYEARIR 05000341/20240032024-11-0606 November 2024 Integrated Inspection Report 05000341/2024003 IR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000016/20240012024-11-0101 November 2024 Enrico Fermi Atomic Power Plant, Unit 1, NRC Inspection Report 05000016/2024001 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 February 6, 2013 Mr. Joseph H. Plona Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
NRC OFFICE OF INVESTIGATIONS REPORT NO. 3-2012-016
Dear Mr. Plona:
This refers to an investigation conducted by the U.S. Nuclear Regulatory Commission (NRC)
Office of Investigations (OI) to determine whether an electrical engineer at Engineering Management Specialists, Inc. (EMS) under contract with the Fermi Nuclear Power Plant was discriminated against for raising safety concerns. Based on the evidence developed during the investigation, we did not substantiate the allegation. The synopsis from the OI Report of Investigation is enclosed.
If you have any questions or comments regarding this matter, please contact an NRC Region III Office Allegation Coordinator by calling (800) 522-3025. The NRC Region III Office Allegation Coordinators are Jim Heller, Paul Pelke, Magdalena Gryglak, and Sarah Bakhsh.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's Rules of Practice, a copy of this letter, its enclosure, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). You should note that final NRC documents, including the final OI reports, may be made available to the public under the Freedom of Information Act (FOIA) subject to redaction of information pursuant to the FOIA. Requests under the FOIA should be made in accordance with 10 CFR 9.23, Request for Records. The instructions for making a request for information under the FOIA are accessible at http://www.nrc.gov/reading-rm/foia/foia-request.html.
Sincerely,
/RA/
Robert Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-341 License No. NPF-43
Enclosure:
OI Synopsis
Mr. Joseph H. Plona Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
NRC OFFICE OF INVESTIGATIONS REPORT NO. 3-2012-016
Dear Mr. Plona:
This refers to an investigation conducted by the U.S. Nuclear Regulatory Commission (NRC)
Office of Investigations (OI) to determine whether an electrical engineer at Engineering Management Specialists, Inc. (EMS) under contract with the Fermi Nuclear Power Plant was discriminated against for raising safety concerns. Based on the evidence developed during the investigation, we did not substantiate the allegation. The synopsis from the OI Report of Investigation is enclosed.
If you have any questions or comments regarding this matter, please contact an NRC Region III Office Allegation Coordinator by calling (800) 522-3025. The NRC Region III Office Allegation Coordinators are Jim Heller, Paul Pelke, Magdalena Gryglak, and Sarah Bakhsh.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's Rules of Practice, a copy of this letter, its enclosure, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). You should note that final NRC documents, including the final OI reports, may be made available to the public under the Freedom of Information Act (FOIA) subject to redaction of information pursuant to the FOIA. Requests under the FOIA should be made in accordance with 10 CFR 9.23, Request for Records. The instructions for making a request for information under the FOIA are accessible at http://www.nrc.gov/reading-rm/foia/foia-request.html.
Sincerely,
/RA/
Robert Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-341 License No. NPF-43
Enclosure:
OI Synopsis DOCUMENT NAME: G:\ORAIII\EICS\ALLEGATIONS\AMS-LTRS\11 AMS\110085 Fermi\110085 OI synopsis to lic.docx To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII RIII RIII RIII NAME Pelke Gilliam Goetz* Rubic Orth** Daley DATE 01/30/13 02/05/13 02/05/13 02/05/13 02/05/13 02/06/13 OFFICIAL RECORD COPY
- For permission to release the OI Synopsis
- The 3-week e-mail has expired
OI SYNOPSIS This investigation was initiated on March 28, 2012, by the U.S. Nuclear Regulatory Commission, Office of Investigations, Region III, to determine whether a contract electrical engineer at the Fermi Nuclear Plant was discriminated against for raising safety concerns.
Based upon the evidence, this investigation did not substantiate the allegation that a contract electrical engineer was discriminated against for raising safety concerns.
Case No. 3-2012-016 Enclosure