Letter Sequence RAI |
---|
|
Results
Other: ML071900365, ML11109A067, ML13043A527, ML13067A315, ML13077A284, ML14217A206, ML15007A430, ML15055A004, ML15055A014, ML15268A128, NL-07-078, Station Blackout (SBO) / Appendix R Diesel Generator Commitment, Response to NRC Review Status of License Renewal Application, NL-10-054, Correction to License Renewal Application, NL-12-037, License Renewal Application - Revised Reactor Vessel Internals Program and Inspection Plan Compliant with MRP-227-A, NL-14-013, Additional Information Regarding the License Renewal Application - Action Item 7 from MRP-227-A
|
MONTHYEARNL-07-056, Supplement to License Renewal Application2007-05-0303 May 2007 Supplement to License Renewal Application Project stage: Supplement NL-07-078, Station Blackout (SBO) / Appendix R Diesel Generator Commitment, Response to NRC Review Status of License Renewal Application2007-06-21021 June 2007 Station Blackout (SBO) / Appendix R Diesel Generator Commitment, Response to NRC Review Status of License Renewal Application Project stage: Other ML0719003652007-07-25025 July 2007 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from ENO, Inc. for Renewal of the Operating License for the Indian Point Nuclear Generating Unit Project stage: Other ML0727804392007-10-16016 October 2007 Summary of Telephone Conference Call with Entergy Nuclear Operations, Inc., Requests for Additional Information Project stage: RAI NL-10-054, Correction to License Renewal Application2010-05-27027 May 2010 Correction to License Renewal Application Project stage: Other ML11109A0672011-04-19019 April 2011 2011/04/19 Indian Point Lr Hearing - FW: OAR - Safety PM Change for the License Renewal Project for Indian Point...(Tac Nos. MD5407 & MD5408) Project stage: Other NL-12-037, License Renewal Application - Revised Reactor Vessel Internals Program and Inspection Plan Compliant with MRP-227-A2012-02-17017 February 2012 License Renewal Application - Revised Reactor Vessel Internals Program and Inspection Plan Compliant with MRP-227-A Project stage: Other ML12223A3882012-09-10010 September 2012 RAI for the Review of the Indian Pont Nuclear Generating Unit Nos. 2 and 3, LRA Set 2012-02 Project stage: RAI ML12223A3672012-09-12012 September 2012 08/08/2012 Summary of Telephone Conference Call Held Between NRC and Entergy Nuclear Operations, Inc., Concerning RAI Set 2012-02, Reactor Vessel Internals Program Pertaining to the Indian Point, Units 2 & 3, License Renewal Application Project stage: RAI ML12278A0772012-10-16016 October 2012 Request for Additional Information for the Review of the Indian Point Nuclear Generating Units 2 and 3, License Renewal Application, Set 2012-03 (TAC Nos. MD5407 and MD5408) Project stage: RAI NL-12-140, Reply to Request for Additional Information Regarding the License Renewal Application2012-10-17017 October 2012 Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI NL-12-166, Reply to Request for Additional Information Regarding the License Renewal Application2012-11-20020 November 2012 Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI ML15334A2562013-02-0606 February 2013 Official Exhibit - ENT000660-00-BD01 - Letter from J. Daly, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3 LRA, Set 2013-01 (TAC Nos. MD5407 and Project stage: Request ML15335A2722013-02-0606 February 2013 Official Exhibit - NRC000187-00-BD01 - Letter from John Daily, NRC, to Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-01 (TAC Nos. MD5407 and Project stage: RAI ML13015A1752013-02-0606 February 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, LRA, Set 2013-01 Project stage: RAI ML15222A8962013-02-0606 February 2013 ENT000660 - Letter from J. Daly, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application, Set 2013-01 (TAC Nos. MD54 Project stage: Request ML15223A2632013-02-0606 February 2013 NRC000187 - Letter from John Daily, NRC, to Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-01 (TAC Nos. MD5407 and MD5408) Feb. 6, Project stage: RAI ML13043A5272013-02-26026 February 2013 PM Change Letter - February 2013 Project stage: Other ML13067A3152013-03-0808 March 2013 Correction to Project Manager Change for the License Renewal of Indian Point, Units 2 and 3 (TAC Nos. MD5407 & MD5408) Project stage: Other ML13077A2842013-03-0808 March 2013 Correction PM Letter Indian Point Project stage: Other NL-13-052, Reply to Request for Additional Information Regarding the License Renewal Application2013-05-0707 May 2013 Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI ML13162A6062013-06-12012 June 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-02 (TAC Nos. MD5407 and MD5408) Project stage: RAI ML13186A1692013-07-17017 July 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013 03 (TAC Nos. MD5407 and MD5408) Project stage: RAI ML15222A8982013-07-26026 July 2013 ENT000661 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application, Set 2013-04 (TAC Nos. MD5 Project stage: Request ML15334A2572013-07-26026 July 2013 Official Exhibit - ENT000661-00-BD01 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3 Lr Application, Set 2013-04 (TAC Nos Project stage: Request ML13204A1992013-07-26026 July 2013 RAI for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-04 (TAC Nos. MD5407 and MD5408) Project stage: RAI ML13240A0762013-09-0303 September 2013 RAI Set 2013-5 follow-up RAI on CP Project stage: RAI ML13318A4502013-11-19019 November 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating, Units 2 and 3, License Renewal Application, Set 2013-06 (TAC Nos. MD5407 and MD5408) Project stage: RAI ML14027A4152014-01-16016 January 2014 Enclosure 2 to NL-14-010, Attachment 2, Final Response to U.S. NRC RAI 6-A Items 1 and 2 on the Rvi Program and Rvi Inspection Plan Project stage: Request NL-14-010, Units, 2 & 3 - Reply to Request for Additional Information Regarding the License Renewal Application2014-01-16016 January 2014 Units, 2 & 3 - Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI NL-14-013, Additional Information Regarding the License Renewal Application - Action Item 7 from MRP-227-A2014-01-28028 January 2014 Additional Information Regarding the License Renewal Application - Action Item 7 from MRP-227-A Project stage: Other ML14084A3872014-04-0101 April 2014 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2014-01 (TAC Nos. MD5407 and MD5408) Project stage: RAI ML15334A2582014-04-0909 April 2014 Official Exhibit - ENT000662-00-BD01 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3 LRA, Set 2014-02 (TAC Nos. MD5407 and Project stage: Request ML15222A9012014-04-0909 April 2014 ENT000662 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application, Set 2014-02 (TAC Nos. MD5 Project stage: Request ML14094A1732014-04-0909 April 2014 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2014-02 Project stage: RAI NL-14-093, Reply to Request for Additional Information Regarding License Renewal Application2014-08-0505 August 2014 Reply to Request for Additional Information Regarding License Renewal Application Project stage: Response to RAI ML14217A2062014-08-14014 August 2014 Respect for Withholding Information from Public Disclosure Project stage: Other ML14206B1742014-08-14014 August 2014 Review of Draft Audit Report Regarding Indian Point Nuclear Generating Unit Nos 2 and 3, License Renewal Application Project stage: Draft Approval ML14259A1152014-09-0909 September 2014 Submittal of Westinghouse Review of Draft NRC Audit Report Regarding Indian Point Nuclear Generating Units Nos. 2 and 3 Project stage: Request ML14265A2262014-09-25025 September 2014 Request for Withholding Information from Public Disclosure Regarding the Aging Management Audit Report Associated with Indian Point, Units 2 and 3 License Renewal Application (TACs MD5407 and MD5408) Project stage: Withholding Request Acceptance ML15007A4302015-01-0909 January 2015 Project Manager Change for the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (TAC Nos. MD5407 and MD5408) Project stage: Other ML15055A0042015-02-17017 February 2015 Lr Hearing - Indian Point: Reissue of RAI 3.0.3-2 from Set 2014-01 for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, LRA Project stage: Other ML15055A0142015-02-18018 February 2015 Lr Hearing - Reissue of RAI 3.0.3-2 from Set 2014-01 for Review of Indian Point, Units 2 and 3, LRA Project stage: Other ML15055A0082015-02-18018 February 2015 Lr Hearing - Indian Point: Reissue of RAI 3.0.3-2 from Set 2014-01 for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, LRA Project stage: RAI ML15055A0122015-02-18018 February 2015 Lr Hearing - Indian Point: Reissue of RAI 3.0.3-2 from Set 2014-01 for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, LRA (Tac Nos. MD5407 and MD5408) Project stage: RAI NL-15-019, Reply to Request for Additional Information 3.0.3-2 from Set 2014-01 for the Review of the License Renewal Application2015-03-10010 March 2015 Reply to Request for Additional Information 3.0.3-2 from Set 2014-01 for the Review of the License Renewal Application Project stage: Response to RAI ML15071A1012015-05-0404 May 2015 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-01 (TAC Nos. MD5407 and MD5408) Project stage: RAI ML15170A4562015-07-0707 July 2015 RAI for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-02 Project stage: RAI ML15190A2912015-07-22022 July 2015 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review Project stage: RAI NL-15-092, Reply to Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-01 (TAC Nos. MD5407 and MD5408)2015-08-18018 August 2015 Reply to Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-01 (TAC Nos. MD5407 and MD5408) Project stage: Response to RAI 2013-07-17
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML22309A0062022-12-12012 December 2022 Public Non-Sensitive Meeting Summary on Clarification Call with Holtec Regarding Request for Additional Information for Indian Point Unit 2 Master Decommissioning Trust Agreement as Per Indian Point Nuclear Generating Facility Unit 1 and 2 ML21342A1402021-12-0909 December 2021 Summary of Public Meeting in Tarrytown, Ny, to Discuss Indian Point Units 1, 2, and 3 (IPEC) Post-shutdown Decommissioning Activities Report ML21055A9122021-02-24024 February 2021 (E-mail Dated 2/24/2021) Summary of Feb 8, 2021, Pre-submittal Meeting for Relief Request No. IP3-ISI-RR-16, Code Case N-513-4 Periodic Inspection Frequency Extension ML20321A0002020-11-17017 November 2020 Summary of 9/30/20 Pre-Submittal Meeting with Entergy to Discuss Proposed One-Time Exemption Request - Biennial Emergency Preparedness Onsite Evaluated Exercise Requirements ML20289A7322020-10-15015 October 2020 2020 Annual Assessment Meeting for Indian Point - Meeting Summary ML20083F5962020-03-23023 March 2020 Summary of Teleconference with the National Marine Fisheries Service for Indian Point Biological Opinion ML20059P1292020-03-0303 March 2020 Summary of Partially Closed Pre-submittal Public Meeting with Entergy Nuclear Operations, Inc. to Discuss the Proposed License Amendment Request to Replace the Indian Point Unit No. 3 Crane with a New Holtec High-Lift Crane (EPID L:2019-LRM ML19330F5182019-11-29029 November 2019 Summary of Public Meeting Between the NRC and Entergy Regarding Pre-Submittal of a License Transfer Application to Holtec International for Indian Point Energy Center ML19319A0242019-10-0202 October 2019 NEIMA Meeting - Courtney Williams Comments ML19319A0282019-10-0202 October 2019 NEIMA Meeting - Marilyn Elie Comments ML19319A0272019-10-0202 October 2019 NEIMA Meeting - Linda Puglisi Comments ML19319A0252019-10-0202 October 2019 NEIMA Meeting - Jenean Eichenholtz Comments ML19198A2392019-07-17017 July 2019 Annual Assessment Meeting for Indian Point Energy Center - Meeting Summary ML18200A2722018-07-19019 July 2018 Summary of Annual Assessment Meeting for Indian Point Energy Center ML18131A0572018-05-11011 May 2018 Summary of 04/12/2018 Meeting with the State of New York Regarding the Indian Point Generating Unit No. 2 Reactor Pressure Vessel Head Penetration Alternative Weld Repair ML18117A3162018-04-30030 April 2018 Summary of 04/03/2018 Meeting with Entergy on Planned Submittal of Propose Alternative for Reactor Pressure Vessel Head Nozzle Weld Repair ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18002A2562018-01-30030 January 2018 11/30/2017 and 12/19/2017 Summary Telephone Conference Calls with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point License Renewal Application ML17256A2862017-09-25025 September 2017 Summary of Telephone Call on 09/06/17, Between NRC and Entergy Concerning Next Steps from the Site Audit on 08/1-3/17 ML17180A5032017-09-21021 September 2017 04/19/2017 Summary of Teleconference with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point Unit Nos. 2 and 3 License Renewal Application ML17237A2132017-08-25025 August 2017 Memo E-mail to File -Summary of July 26, 2017, Meeting with Entergy to Discuss Proposed License Amendment Request, New Criticality Safety Analysis ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17160A1652017-06-27027 June 2017 Summary of Telephone Conference Call Held on May 31,2017, Between the NRC and Entergy Nuclear Operations Inc. Concerning Requests for Additional Information Pertaining to the Indian Point, License Renewal Application (TAC Nos. MD5407/MD5408 ML17172A1972017-06-20020 June 2017 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 ML17157B5422017-06-20020 June 2017 Conference Call on 2nd Round RAIs - Final ML17082A3112017-04-11011 April 2017 Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 ML16281A2162016-10-25025 October 2016 10/04/2016,Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Proposed Changes to the Service Water Integrity Program for the Indian Point Nuclear Generating, Units 2 and 3 (IP2 and IP3) License Renewal Application (LRA) ML16209A3712016-08-17017 August 2016 July 21, 2016, Summary of Conference Call Held Between NRC and Entergy Nuclear Operations, Inc. Concerning the Draft RAI for the Review of the Indian Point, Units 2 & 3, License Renewal Application, Set 2016-01 (TAC Nos. MD5407 & MD5408) ML16188A0202016-07-0505 July 2016 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 ML16133A4992016-06-21021 June 2016 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Safety Review ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML15351A2032015-12-30030 December 2015 Summary of Conference Call Held on December 9, 2015, Between the NRC and Entergy Nuclear Operations, Inc. Concerning the Draft Audit Plan for the Service Water Integrity and Fire Water System Aging Management Programs ML15190A2912015-07-22022 July 2015 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review ML15152A0762015-05-29029 May 2015 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 on 5/20/2015 ML15120A6442015-05-0606 May 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review ML15107A1752015-04-28028 April 2015 041615, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML15093A5052015-04-14014 April 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Environmental Review ML15051A5022015-03-10010 March 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML15022A1602015-02-11011 February 2015 and 01/13/15, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML14197A5832014-09-18018 September 2014 Summary of the June 19, 2014, Category 1 Public Meeting with Entergy to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Tear Task Force Recommendation 2.1 ML14260A4312014-09-17017 September 2014 Revised Summary of Annual Assessment Meeting for Indian Point Energy Center on 6/4/2014 ML14238A7262014-09-10010 September 2014 Summary of Conference Call Held on July 30, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations Inc., Regarding a Draft Request for Additional Information on Removal of Certain Aging Management Review Items ML14219A6742014-08-14014 August 2014 July 15, 2014 Summary of Telephone Conference Call Held Between U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Environmental Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License R ML14206B1282014-08-0101 August 2014 June 19, 2014 & July 16, 2014 Summary of Conference Calls Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Regarding Entergy Response to a Request for Additional Information ML14178A8682014-06-25025 June 2014 Summary of Annual Assessment Meeting for Indian Point Energy Center on 6/4/2014 ML14136A0052014-05-27027 May 2014 Summary of Phone Call Between New York State Department of State and U.S. Nuclear Regulatory Commission on May 7, 2014, Regarding the Coastal Zone Management Act Consistency Review ML14105A3542014-04-24024 April 2014 Summary of Conference Call Held on March 26, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning a Draft Request for Additional Information on the Reactor Vessel Internals Program ML14078A3992014-03-21021 March 2014 Summary of Conference Call Held on February 20, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning a Draft Request for Additional Information on LR-ISG-2012-02 and Draft LR-ISG-2013-01 ML13256A0862013-09-24024 September 2013 Summary of Meeting with Entergy Nuclear Operations, Inc. and Netco on Indian Point Unit 2 Spent Fuel Pool Management 2022-12-12
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23171B0442023-06-23023 June 2023 Enclosure - Indian Point Energy Center - Request for Additional Information for Independent Spent Fuel Storage Installation Facility-Only Emergency Plan License Amendment ML22292A2402022-10-21021 October 2022 RAIs for Master Dtf Agreement on IP1 IP2 10 18 2022 ML22103A2442022-04-13013 April 2022 Attachment - Request for Additional Information - License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled Condition for Indian Point Energy Center ML22104A0352022-04-13013 April 2022 Request for Additional Information Related to Exemption Request from Emergency Planning Holtec Decommissioning International, LLC Indian Point Energy Center ML22006A0452022-01-0505 January 2022 PSDAR RAIs Final ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) ML21183A1602021-06-30030 June 2021 Update Request for Additional Information - Indian Point Energy Center Quality Assurance Program Manual (06/30/2021 E-mail) ML21138A9412021-05-18018 May 2021 Request for Additional Information - Indian Point Energy Center Quality Assurance Program Manual (05/18/2021 E-mail) ML21112A2672021-04-22022 April 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (Public Redacted Version) ML21019A5672021-01-19019 January 2021 Second Round Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML21013A0152021-01-12012 January 2021 Draft Request for Additional Information (E-mail Dated 1/12/2021) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML20268C2352020-09-24024 September 2020 Request for Additional Information (E-mail Dated 9/24/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML20233B0152020-08-20020 August 2020 Request for Additional Information (E-mail Dated 8/20/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML20190A2342020-07-0808 July 2020 Request for Additional Information - Application for Order Consenting to Transfers of Control of Licenses (07/08/2020 E-mail) ML20190A1502020-06-25025 June 2020 (06/25/2020 E-mail) Draft Request for Additional Information Application for Order Consenting to Transfers of Control of Licenses ML20106F2492020-04-15015 April 2020 E-mail (04/15/2020) Request for Additional Information Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic ML20070J7902020-03-10010 March 2020 Request for Information to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000286/2020012 ML19045A6252019-02-14014 February 2019 Request for Additional Information - Proposed License Amendment Request Regarding Storage of Fresh and Spent Nuclear Fuel in the Spent Fuel Pool - 2/14/19 E-mail from R.Guzman to M.Mirzai NL-18-053, Response to Request for Additional Information Regarding Relief Request IP3-ISI-RR-11 for Reactor Vessel Weld Inservice Inspection Frequency Extension2018-07-18018 July 2018 Response to Request for Additional Information Regarding Relief Request IP3-ISI-RR-11 for Reactor Vessel Weld Inservice Inspection Frequency Extension ML18155A4842018-06-0404 June 2018 Request for Additional Information Regarding Relief Request IP3-ISI-RR-11, E-mail from R.Guzman to C.Mackaman ML18143B6792018-05-23023 May 2018 Request for Additional Information Regarding LAR for One-Time Extension of the Containment Leakage Rate Test - Email from R.Guzman to M.Mirzai ML18094B0922018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to B. S. Ford RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for ISFSI Docket Nos.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72-59) ML17296A2352017-10-23023 October 2017 Request for Additional Information -10/23/17 E-mail from R.Guzman to R.Louie Cyber Security Plan Milestone 8 Implementation Schedule (CAC Nos. MF9656, MF9657, MF9658; EPID: L-2017-LLA-0217) ML17277B5482017-10-0303 October 2017 Request for Additional Information - Relief Request IP2-ISI-RR-20 Regarding Weld Examination ML17219A1062017-08-10010 August 2017 Request for Additional Information Regarding Inter-Unit Transfer of Spent Fuel - Shielded Transfer Canister Requests for Additional Information ML17200A0852017-07-19019 July 2017 Request for Additional Information Regarding the Connection of Non-Seismic Boric Acid Recovery System to RWST Seismic Piping ML17197A0002017-07-17017 July 2017 Request for Additional Information Regarding Inter-Unit Transfer of Spent Fuel ML17170A2862017-06-27027 June 2017 RAI Set 2017-06 ML17103A4182017-04-25025 April 2017 Baffle Bolt Rais. Requests for Additional Information for the Review of the Indian Point License Renewal Application (TAC Nos. MD5407 and MD5408) ML17088A4052017-04-20020 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-3 (CAC Nos. MD5407 and MD5408) ML17088A3272017-04-19019 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408) ML17100A1282017-04-11011 April 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment of Inter Unit Transfer of Spent Fuel ML17046A2312017-03-0808 March 2017 Request for Additional Information for the Review of the Indian Point License Renewal - Set 2017-01 ML16232A1192016-09-12012 September 2016 Request for Additional Information for the Review of the Indian Point Nuclear Generating Units Nos. 2 and 3, License Renewal Application Environmental Review - Severe Accident Mitigation Alternatives (CAC Nos. MD5411 and MD5412) ML16138A1942016-07-25025 July 2016 Request for Additional Information for the Review of License Renewal Application, Set 2016-01 ML16139A0302016-06-10010 June 2016 Request for Additional Information Regarding Conditional Exemption from End-of-Line Moderator Temperature Coefficient Measurement ML16112A2262016-04-26026 April 2016 Request for Additional Information Regarding Relief Request IP2-ISI-RR-02 Alternative Examination Volume Required by Code Case N-729-1 ML16041A5782016-02-18018 February 2016 Request for Additional Information Related to License Amendment Request Regarding Moderator Temperature Coefficient Measurement Change ML16005A6292016-01-14014 January 2016 Request for Additional Information Regarding Relief Request IP2-RR-19 ML16013A0642016-01-13013 January 2016 NRR E-mail Capture - Request for Additional Information Entergy CNRO-2015-00023 - Revision to Entergy Quality Assurance Program Manual (Fleet Submittal CAC Nos. MF7086-MF7097) ML15341A1662015-12-0707 December 2015 NRR E-mail Capture - Entergy Fleet RR-EN-15-1, Request for Additional Information (CACs MF6341-MF6349) ML15148A4032015-06-29029 June 2015 Request for Additional Information Regarding the Spent Fuel Pool Criticality Analysis ML15156B2742015-06-16016 June 2015 Request for Additional Information Regarding Request to Permanently Extend the Frequency of the Containment Integrated Leak Rate Test ML15125A0972015-05-0606 May 2015 Request for Additional Information Regarding License Amendment to Permanently Extend the Frequency of the Containment Integrated Leak Rate Test ML15071A1012015-05-0404 May 2015 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-01 (TAC Nos. MD5407 and MD5408) ML15103A2592015-04-28028 April 2015 Request for Additional Information Regarding the Proposed License Amendment to Extend the Containment Type a Leak Rate Testing Frequency to 15 Years ML15104A5412015-04-22022 April 2015 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application Environmental Review (TAC Nos. MD5411 and MD5412) ML15072A4172015-03-17017 March 2015 Request for Additional Information Regarding Extension of the Containment Type a Leak Rate Testing Frequency to 15 Years ML14329B2452015-02-18018 February 2015 Request for Additional Information for the Review of the Indian Point Nuclear Generating Units 2 and 3, License Renewal Application Environmental Review (TAC Nos. MD5411 and MD5412) CNRO-2015-00008, Responses to NRC Request for Additional Information Regarding Change in Corporate Form of Entergy Nuclear Holding Company2015-02-18018 February 2015 Responses to NRC Request for Additional Information Regarding Change in Corporate Form of Entergy Nuclear Holding Company 2023-06-23
[Table view] |
Text
~p.~ REG u{ UNITED STATES
,;z.~c,'" "'I"'q,. NUCLEAR REGULATORY COMMISSION
!<C ~ WASHINGTON, D.C. 20555"()001
~
~ ~
- 0
'<'/. ~ September 12, 2012
"'., ~o
LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Indian Point, Units 2 and 3 SUBJECT
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 8, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC.: CONCERNING RAI SET 2012-02, REACTOR VESSEL INTERNALS PROGRAM, PERTAINING TO THE INDIAN POINT ENERGY CENTER, UNITS 2 AND 3, LICENSE RENEWAL APPLICATION (TAC NOS. MD5407 AND MD5408)
The U.S Nuclear Regulatory CommiSSion (NRC or tne staff) and representatives of Entergy Nuclear Operations, Inc (Entergy or the applicant) held a telephone conference call on August 8, 2012, to discuss staff aging management questions related to the applicant's Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (lPEC), Units 2 and 3, license renewai application (LRA). The telephone conference call was useful in clarifying the requests for additional informalh:>n (RAis) on the issue.
Enclosure 1 provides a listing of the participants and Enclosure 2 contains a summary of the discussion.
The applicant had an opportunity t.o comment on this summary.
John Daily, Senior Proje t Manager Projects Branch 1 Division of License Renewal Office of Nuclear R.eactor Regulation Docket Nos. 50-247 and 50-286
Enclosures:
':. List of Participants 2 Discussion summary CC 'Nlencls: Listselv
TELEPHONE CONFERENCE CALL INDIAN POINT ENERGY CENTER LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS AugustS, 2012
.....
I PARTICIPANTS AFFILIATIONS
- John Dailv U.S. Nuclear Reaulatorv Commission (NRC)
Jeff Poehler NRC Allen Hiser NRC OnYee NRC Alan Cox Entergy Nuclear Operations, Inc. (Entergy)
Ted Ivy Entergy Roger Waters Entergy Bob Dolansky Entergy Nelson Azevedo Entergy Mark Gray Westinghouse Cheryl Boggess Westinghouse Rick Basel Westinghouse Karli Szwed a Westinghouse Brad Grimmel Westinghouse ENCLOSURE 1
REQUEST FOR ADDITIONAL INFORMATION CONFERENCE CALL INDIAN POINT ENERGY CENTER, UNITS 2 AND 3 LICENSE RENEWAL APPLICATION REACTOR VESSEL INTERNALS PROGRAM AND MRP-227-A RAI SET 2012-02 August 8, 2012 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. (Entergy or the applicant) held a telephone conference call on August 8,2012, to discuss staff aging management questions related to the applicant's Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (lPEC), Units 2 and 3, license renewal application (LRA). The telephone conference call was useful in clarifying the requests for additional information (RAls) on the issue.
RAI Set 2012-02 Reactor Vessel Internals Program and MRP-227-A discussion RAI13 The applicant stated that there were no questions regarding Request for Additional Information (RAI) 13. RAI 13 will stand as-is.
RAI14 The applicant stated that for IPEC, Units 2 and 3, the updated final safety analysis report (UFSAR) treats split pins not as part of the core support structure, rather as part of the reactor vessel internals (RVI) package; therefore the applicant did not perform VT-3 inspections of them under the American Society of Mechanical Engineers (ASME) Code,Section XI, Table IW8 2500-1, Examination Category 8-N-3. The applicant also recounted its RAI response to RAI 8.
The staff stated that it understood the applicant's categorization of the split pins and Entergy's current management plans for them. The staff agreed that RAI 14 would be dropped. If the staff, during its review, has other questions regarding the split pins, then it will create a new RAI for those issues.
RAI15 The staff noted the applicant's response to RAI 12, which states that Entergy will use the Fatigue Monitoring Program to manage aging for RVI components that are associated with a fatigue time-limited aging analysis (TLAA) , and that it will review RVI fatigue calculations for the effects of a reactor coolant system water environment on cumulative usage factors (CUFs),
especially concerning effects on limiting locations, before the period of extended operation. The staff had questions regarding the following issues, and these were discussed with the applicant:
- 1. Whether Entergy's review described in the response to RAI 12 will include CUF calculations for the RVI that incorporate environmental factors (Fen) and, if CUF calculations are not performed, how the effects of the reactor water environment on the existing CUF analyses for RVI would be evaluated.
ENCLOSLIRE 2
-2
- 2. What action(s) Entergy would take if the consideration of environmental effects results in a CUF exceeding 1.0 for any RVI component (as opposed to just the most limiting one).
- 3. Whether evaluations being referenced by Entergy's term "ASME Code Class 1 fatigue evaluations for [RVls]," creates an inconsistency, since ASME Code Class 1 components are those designed to ASME Code Section III, Subsection NB (Le., reactor coolant pressure boundary components, not reactor vessel internals components).
- 4. Whether expanding Commitment No. 43 to include existing RVI fatigue calculations is appropriate to address Applicant/Licensee Action Item 8 of the Staffs Safety Evaluation of MRP-227 -A; the staff believes that a revision, or a separate commitment and UFSAR supplement to address review of RVls for environmentally-assisted fatigue, is more appropriate than a simple expansion of the existing commitment.
The applicant agreed that it would take the staff's questions into account as it prepares its responses to RAls 13 and 15. Both the staff and the applicant agreed that the discussion was useful in clarifying the RAls.
ENCLOSURE 2
SUBJECT:
Summary of Telephone Conference Call conducted on July 24, 2012 DISTRIBUTION:
HARD COPY:
DLRRF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource RidsOgcMailCenter JDaily TTran DMclntyre, OPA BSingal, DORL
'MNalker, RIV JDixon, RIV BTharakan, RIV WMaier, RIV VDricks, RIV NOKeefe , RIV AVegel, RIV GPick, RIV
LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Indian Point, Units 2 and 3
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 8, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING RAI SET 2012-02, REACTOR VESSEL INTERNALS PROGRAM, PERTAINING TO THE INDIAN POINT ENERGY CENTER, UNITS 2 AND 3, LICENSE RENEWAL APPLICATION (TAC NOS. MD5407 AND MD5408)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. (Entergy or the applicant) held a telephone conference call on August 8, 2012, to discuss staff aging management questions related to the applicant's Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (lPEC), Units 2 and 3, license renewal application (LRA). The telephone conference call was useful in clarifying the requests for additional information (RAls) on the issue. provides a listing of the participants and Enclosure 2 contains a summary of the discussion.
The applicant had an opportunity to comment on this summary.
IRAJ John Daily, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286
Enclosures:
- 1. List of Participants
- 2. Discussion summary cc w/encls: Listserv DISTRIBUTION: See next page ADAMS Accession No ... ML12223A367 OFFICE LA:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1 :DLR NAME YEdmonds ..IDaily DMorey ..IDaily DATE 08/16/12 09/04/12 09/11/12 09/12/12 OFFICIAL RECORD COpy