08/08/2012 Summary of Telephone Conference Call Held Between NRC and Entergy Nuclear Operations, Inc., Concerning RAI Set 2012-02, Reactor Vessel Internals Program Pertaining to the Indian Point, Units 2 & 3, License Renewal Application
ML12223A367
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 09/12/2012
From: Daily J
License Renewal Projects Branch 1
To:
Daily J
References
TAC MD5407, TAC MD5408
Download: ML12223A367 (6)


Text

~p.~ REG u{ UNITED STATES

,;z.~c,'" "'I"'q,. NUCLEAR REGULATORY COMMISSION

!<C ~ WASHINGTON, D.C. 20555"()001

~

~ ~

0

'<'/. ~ September 12, 2012

"'., ~o

        • ~

LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: Indian Point, Units 2 and 3 SUBJECT

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 8, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC.: CONCERNING RAI SET 2012-02, REACTOR VESSEL INTERNALS PROGRAM, PERTAINING TO THE INDIAN POINT ENERGY CENTER, UNITS 2 AND 3, LICENSE RENEWAL APPLICATION (TAC NOS. MD5407 AND MD5408)

The U.S Nuclear Regulatory CommiSSion (NRC or tne staff) and representatives of Entergy Nuclear Operations, Inc (Entergy or the applicant) held a telephone conference call on August 8, 2012, to discuss staff aging management questions related to the applicant's Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (lPEC), Units 2 and 3, license renewai application (LRA). The telephone conference call was useful in clarifying the requests for additional informalh:>n (RAis) on the issue.

Enclosure 1 provides a listing of the participants and Enclosure 2 contains a summary of the discussion.

The applicant had an opportunity t.o comment on this summary.

John Daily, Senior Proje t Manager Projects Branch 1 Division of License Renewal Office of Nuclear R.eactor Regulation Docket Nos. 50-247 and 50-286

Enclosures:

':. List of Participants 2 Discussion summary CC 'Nlencls: Listselv

TELEPHONE CONFERENCE CALL INDIAN POINT ENERGY CENTER LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS AugustS, 2012

.....

I PARTICIPANTS AFFILIATIONS

  • John Dailv U.S. Nuclear Reaulatorv Commission (NRC)

Jeff Poehler NRC Allen Hiser NRC OnYee NRC Alan Cox Entergy Nuclear Operations, Inc. (Entergy)

Ted Ivy Entergy Roger Waters Entergy Bob Dolansky Entergy Nelson Azevedo Entergy Mark Gray Westinghouse Cheryl Boggess Westinghouse Rick Basel Westinghouse Karli Szwed a Westinghouse Brad Grimmel Westinghouse ENCLOSURE 1

REQUEST FOR ADDITIONAL INFORMATION CONFERENCE CALL INDIAN POINT ENERGY CENTER, UNITS 2 AND 3 LICENSE RENEWAL APPLICATION REACTOR VESSEL INTERNALS PROGRAM AND MRP-227-A RAI SET 2012-02 August 8, 2012 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. (Entergy or the applicant) held a telephone conference call on August 8,2012, to discuss staff aging management questions related to the applicant's Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (lPEC), Units 2 and 3, license renewal application (LRA). The telephone conference call was useful in clarifying the requests for additional information (RAls) on the issue.

RAI Set 2012-02 Reactor Vessel Internals Program and MRP-227-A discussion RAI13 The applicant stated that there were no questions regarding Request for Additional Information (RAI) 13. RAI 13 will stand as-is.

RAI14 The applicant stated that for IPEC, Units 2 and 3, the updated final safety analysis report (UFSAR) treats split pins not as part of the core support structure, rather as part of the reactor vessel internals (RVI) package; therefore the applicant did not perform VT-3 inspections of them under the American Society of Mechanical Engineers (ASME) Code,Section XI, Table IW8 2500-1, Examination Category 8-N-3. The applicant also recounted its RAI response to RAI 8.

The staff stated that it understood the applicant's categorization of the split pins and Entergy's current management plans for them. The staff agreed that RAI 14 would be dropped. If the staff, during its review, has other questions regarding the split pins, then it will create a new RAI for those issues.

RAI15 The staff noted the applicant's response to RAI 12, which states that Entergy will use the Fatigue Monitoring Program to manage aging for RVI components that are associated with a fatigue time-limited aging analysis (TLAA) , and that it will review RVI fatigue calculations for the effects of a reactor coolant system water environment on cumulative usage factors (CUFs),

especially concerning effects on limiting locations, before the period of extended operation. The staff had questions regarding the following issues, and these were discussed with the applicant:

1. Whether Entergy's review described in the response to RAI 12 will include CUF calculations for the RVI that incorporate environmental factors (Fen) and, if CUF calculations are not performed, how the effects of the reactor water environment on the existing CUF analyses for RVI would be evaluated.

ENCLOSLIRE 2

-2

2. What action(s) Entergy would take if the consideration of environmental effects results in a CUF exceeding 1.0 for any RVI component (as opposed to just the most limiting one).
3. Whether evaluations being referenced by Entergy's term "ASME Code Class 1 fatigue evaluations for [RVls]," creates an inconsistency, since ASME Code Class 1 components are those designed to ASME Code Section III, Subsection NB (Le., reactor coolant pressure boundary components, not reactor vessel internals components).
4. Whether expanding Commitment No. 43 to include existing RVI fatigue calculations is appropriate to address Applicant/Licensee Action Item 8 of the Staffs Safety Evaluation of MRP-227 -A; the staff believes that a revision, or a separate commitment and UFSAR supplement to address review of RVls for environmentally-assisted fatigue, is more appropriate than a simple expansion of the existing commitment.

The applicant agreed that it would take the staff's questions into account as it prepares its responses to RAls 13 and 15. Both the staff and the applicant agreed that the discussion was useful in clarifying the RAls.

ENCLOSURE 2

SUBJECT:

Summary of Telephone Conference Call conducted on July 24, 2012 DISTRIBUTION:

HARD COPY:

DLRRF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource RidsOgcMailCenter JDaily TTran DMclntyre, OPA BSingal, DORL

'MNalker, RIV JDixon, RIV BTharakan, RIV WMaier, RIV VDricks, RIV NOKeefe , RIV AVegel, RIV GPick, RIV

LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: Indian Point, Units 2 and 3

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 8, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING RAI SET 2012-02, REACTOR VESSEL INTERNALS PROGRAM, PERTAINING TO THE INDIAN POINT ENERGY CENTER, UNITS 2 AND 3, LICENSE RENEWAL APPLICATION (TAC NOS. MD5407 AND MD5408)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. (Entergy or the applicant) held a telephone conference call on August 8, 2012, to discuss staff aging management questions related to the applicant's Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (lPEC), Units 2 and 3, license renewal application (LRA). The telephone conference call was useful in clarifying the requests for additional information (RAls) on the issue. provides a listing of the participants and Enclosure 2 contains a summary of the discussion.

The applicant had an opportunity to comment on this summary.

IRAJ John Daily, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286

Enclosures:

1. List of Participants
2. Discussion summary cc w/encls: Listserv DISTRIBUTION: See next page ADAMS Accession No ... ML12223A367 OFFICE LA:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1 :DLR NAME YEdmonds ..IDaily DMorey ..IDaily DATE 08/16/12 09/04/12 09/11/12 09/12/12 OFFICIAL RECORD COpy