UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555'()001 March 8,2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

CORRECTION TO PROJECT MANAGER CHANGE FOR THE LICENSE RENEWAL OF INDIAN POINT, UNITS 2 AND 3 (TAC NOS. MD5407 AND MD5408)

Dear Sir or Madam:

On February 26, 2013, the Nuclear Regulatory Commission (NRC) issued a Project Manager change letter Agency Documents and Management System (ADAMS) Accession No.

(ML13043A527) for License Renewal of Indian Point, Units 2 and 3.

Due to an inadvertent error, the effective date was stated as July 26, 2013. This date should be effectively immediately. No other changes were made.

We regret any inconvenience this may have caused.

Sincerely, IRA!

Dennis C. Morey, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286 Cc: Distribution via Listserv

March 8, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

CORRECTION TO PROJECT MANAGER CHANGE FOR THE LICENSE RENEWAL OF INDIAN POINT, UNITS 2 AND 3 (TAC NOS. MD5407 AND MD5408)

Dear Sir or Madam:

On February 26, 2013, the Nuclear Regulatory Commission (NRC) issued a Project Manager change letter Agency Documents and Management System (ADAMS) Accession No.

(ML13043A527) for License Renewal of Indian Point. Units 2 and 3.

Due to an inadvertent error, the effective date was stated as July 26,2013. This date should be effectively immediately. No other changes were made.

We regret any inconvenience this may have caused.

Sincerely, IRA!

Dennis C. Morey, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286 Cc: Distribution via Listserv ADAMS Accession Nos'.. ML13077A284 *concurred via email OFFICE LA:DLR:RPB1 PM:DLR:RPB1 BC:DLR:RPB1 NAME YEdmonds NFerrer DMorey DATE 3/7/2013 3/7/2013 3/8/2013 OFFICIAL RECORD COpy

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 20555-0001 February 26, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

PROJECT MANAGER CHANGE FOR THE LICENSE RENEWAL OF INDIAN POINT, UNITS 2 AND 3 (TAC NOS. MD5407 AND MD5408)

Dear Sir or Madam:

This letter provides notification of a change to the Safety Project Manager assigned to the Indian Point (IP) license renewa! review. Effective July 26, 2013, Mr. Nathaniel Ferrer will be the Safety Project Manager for the IP project.

All correspondence for the Project Manager associated with the safety review for IP license renewal should be sent to:

Mr. Nathaniel Ferrer, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-11 F1 Washington, DC 20555 Mr. Ferrer may be reached at 301-415-1045 or bye-mail at nathaniel.ferrer@nrc.gov Dennis C. Mo y, Chi Projects Branch 1 Division of License Ren wal . .

Office of Nuclear Reactor Regu'iation Docket Nos. 50-247and 50-286 cc: Distribution via Listserv

February 26, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

PROJECT MANAGER CHANGE FOR THE LICENSE RENEWAL OF INDIAN POINT, UNITS 2 AND 3 (TAC NOS. MD5407 AND MD5408)

Dear Sir or Madam:

This letter provides notification of a change to the Safety Project Manager assigned to the Indian Point (IP) license renewal review. Effective July 26,2013, Mr. Nathaniel Ferrer will be the Safety Project Manager for the IP project.

All correspondence for the Project Manager associated with the safety review for IP license renewal should be sent to:

Mr. Nathaniel Ferrer, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-11 F1 Washington, DC 20555 Mr. Ferrer may be reached at 301-415-1045 or bye-mail at nathaniel.ferrer@nrc.gov Sincerely, Ira!

Dennis C. Morey, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286 cc: Listserv ADAMS Accession No ML13043A527 OFFICE PM:RPB1:DLR LA:DLR BC:RPB1 :DLR NAME NFerrer YEdmonds DMorey DATE 2/25/13 2/21/13 2/26/13 OFFICIAL RECORD COpy