MONTHYEARML24243A0482024-09-19019 September 2024 Generation Station, Unit Nos. 1 and 2 - Schedule Update for License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24215A4042024-09-18018 September 2024 Request for Withholding Information from Public Disclosure IR 05000352/20244202024-09-16016 September 2024 – Security Baseline Inspection Report 05000352/2024420 and 05000353/2024420 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds IR 05000352/20250102024-09-10010 September 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000352/2025010 and 05000353/2025010 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000352/20230022024-09-0404 September 2024 Reissued Integrated Inspection Report 05000352/2023002 and 05000353/2023002 IR 05000352/20240052024-08-29029 August 2024 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2024005 and 05000353/2024005) ML24241A1952024-08-28028 August 2024 License Amendment Request for Modification to Technical Specification 3.6.1.2 and Main Steam Isolation Valve Leakage Rate Requirements ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24163A3902024-08-14014 August 2024 Request for Withholding Information from Public Disclosure IR 05000352/20240022024-08-12012 August 2024 Integrated Inspection Report 05000352/2024002 and 05000353/2024002 ML24220A2392024-08-12012 August 2024 Correction to Technical Specification Page 3/4 3-11 in Amendment No. 225 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24204A0712024-07-29029 July 2024 Issuance of Amendment Nos. 263 and 225 Technical Specifications for Main Steam Line Tunnel Temperature ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24208A1592024-07-25025 July 2024 Regulatory Audit Plan Supporting Review of the System Development Portion of Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) - Non-Proprietary ML24201A1662024-07-19019 July 2024 Response to Request for Additional Information for License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam L ML24199A1842024-07-15015 July 2024 RAI-LAR for Limerick EPID: L-2024-LLA-0079- Use This Version RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24180A1572024-06-28028 June 2024 Request to Return and Replace WEC Documents (EQ-EV-386-GLIM, EQ-QR- 433-GLIM, and APP-GW-GLR-611), to Meet 10CFR2.390 Request to Withdraw from Public Disclosure Requirements ML24170A7702024-06-20020 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, Opportunity for Hearing(Epid L-2024-LLA-0079) LTR ML24166A1142024-06-14014 June 2024 Response to Requests for Additional Information (RAIs 15 Through 23) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24165A2642024-06-13013 June 2024 License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam Line Tunnel Temperature TS 3/4.7.9 ML24151A2882024-06-10010 June 2024 Request for Withholding Information from Public Disclosure ML24151A2012024-06-10010 June 2024 Request for Withholding Information from Public Disclosure ML24150A0242024-05-29029 May 2024 Notification of Commercial Grade Dedication Inspection (05000352/2024012 and 05000353/2024012) and Request for Information ML24149A2112024-05-28028 May 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 IR 05000352/20243022024-05-20020 May 2024 Revised Initial Operator Licensing Examination Report 05000352/2024302 and 05000353/2024302 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000352/20240012024-05-0707 May 2024 Integrated Inspection Report 05000352/2024001 and 05000353/2024001 ML24124A0432024-05-0303 May 2024 Response to Requests for Additional Information (RAIs 9 Through 14) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24114A3222024-04-23023 April 2024 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) - Pivot to Unit ML24109A0702024-04-18018 April 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFRC50.52 ATWS Rule to Support the Digital Modernization Project Installation . ML24093A0912024-04-17017 April 2024 Revised Estimated Review Completion Date Concerning License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24106A1832024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24096A1372024-04-0505 April 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Limerick Generating Station – Holtec MPC-89CBS RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report IR 05000352/20244012024-03-19019 March 2024 Security Baseline Inspection Report 05000352/2024401 and 05000353/2024401 ML24078A2752024-03-18018 March 2024 Response to Requests for Additional Information (RAIs 5, 6, 7, and 8) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog IR 05000352/20240102024-03-18018 March 2024 Biennial Problem Identification and Resolution Inspection Report 05000352/2024010 and 05000353/2024010 ML24067A2942024-03-0707 March 2024 Response to Requests for Additional Information (RAI 4, RAI 1.c Revision) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related. IR 05000352/20230062024-02-28028 February 2024 Annual Assessment Letter for Limerick Generating Station, Units 1 and 2 (Reports 05000352/2023006 and 05000353/2023006) ML24057A4272024-02-26026 February 2024 Response to Requests for Additional Information (RAIs 1, 2, and 3) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control ML24088A1102024-02-25025 February 2024 Fairbanks Morse (Fm) Part 21 Notification Report Number 23-01 Re Asco Stainless Steel Solenoid Valves 2024-09-06
[Table view] Category:Schedule and Calendars
MONTHYEARML24243A0482024-09-19019 September 2024 Generation Station, Unit Nos. 1 and 2 - Schedule Update for License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML14007A6202014-01-23023 January 2014 Revision of Schedule for the Conduct of Environmental Review of the Limerick Generating Station, License Renewal Application (TAC Nos. ME7346 and ME7347) ML13050A0202013-03-0404 March 2013 Revision of Schedule for the Conduct of Environmental Review for Limerick Generating Station Units 1 and 2 License Change ML12220A5932012-08-20020 August 2012 Revision of Schedule for the Conduct of Environmental Review of the Limerick Generating Stations Units, 1 and 2, LRA ML1105407242011-02-23023 February 2011 2/23/11 Ltr to F. Schiffley Re Participation in Commission Meeting on 50.46a Risk-informed Emergency Core Cooling System Rule on 3/24/11 RS-07-017, Amergen Energy Company, LLC, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations.2007-08-13013 August 2007 Amergen Energy Company, LLC, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations. RS-06-134, Response to NRC Regulatory Issue Summary 2006-15 Preparation and Scheduling of Operator License Examinations.2006-09-20020 September 2006 Response to NRC Regulatory Issue Summary 2006-15 Preparation and Scheduling of Operator License Examinations. 2024-09-19
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 20, 2012 Mr. Michael P. Gallagher Vice President License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION
Dear Mr. Gallagher:
By letter dated June 22,2011, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations, Part 54 (10 CFR Part 54), to renew Operating License NPF-39 and NPF-85 for Limerick Generating Station, Units 1 and 2 (LGS) for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). This letter is to inform you about a schedule change in the LGS license renewal review.
The staff recognizes that final issuance of the renewed Limerick operating license must await the agency's response to a recent remand from the United States Court of Appeals for the District of Columbia regarding the agency's waste confidence rule update (10 CFR Part 51.23).
Nonetheless, the Commission has authorized the staff to proceed with its environmental and safety reviews of license applications in the interim. Consequently, the staff will continue both its safety and environmental reviews of the Limerick license renewal application while the agency formulates its response to the waste confidence remand. Because the Draft Supplemental Environmental Impact Statement ("DSEIS") for Limerick discusses issues related to waste confidence, the staff will need additional time to ensure that the DSEIS is consistent with the Commission's directions on waste confidence. Hence, until the staff completes this process, the components of the schedule related to the environmental review are temporarily to be determined (TBD). As soon as possible, the Staff will issue a revised schedule that provides estimated completion dates for the environmental review. If the agency's ultimate resolution of the remanded waste confidence issues further impacts the analysis in the DSEIS or the Final Supplemental Environmental Impact Statement, the staff may issue a supplemental Environmental Impact Statement as appropriate. Such a supplement may further affect the staff's review schedule.
M. Gallagher -2 Enclosed is a revised schedule for the review of the LGS license renewal application. The schedule has been updated to reflect a change in the date (Le., TBD) for the issuance of the Draft Supplemental Environmental Impact Statement and the subsequent environmental review milestones.
If you have any questions on the revised schedule, please contact Leslie Perkins by telephone at 301-415-2375 or bye-mail at leslie.perkins@nrc.gov.
Sincerely, Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosure:
As stated cc w/encl: Listserv
LIMERICK GENERATING STATION LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE
- Publish Federal Register Notice (FJ~N) - LRA receipt and availabilit 7/2011 07/26/11 Publish FRN - LRA acceptability, environmental scoping period, 08/2011 08/24/11
, and opportunity for hearing Publish FRN -intent to conduct environmental scoping 08/2011 08/26/11
, Public Meeting - license renewal process and environmental 09/22/11 09/22/11 scoping
- Audit - scoping and screening methodology 09/19-23/11 09/19-23/11 I Deadline for filing hearing requests and petitions for intervention 10/24/11 10/24/11
- Environmental sco~ing ~erioq§i ends 10/28/11 10/28/11
.1'-udit - aging management ~rograms (AMp§)) 10103-14/11 [J::QlQ3-14/11
, Audit - environmental 11/07-10/11 11/07-10/11
- Inspection - scoping, screening, and AMPs 06/04-08/12 06/04-08/12 06/18-22/12 06/18-22/12 Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12 Issue draft supplemental environmel'1~al impact statement (SEIS) TBD*
Publish FRN- draft SEIS available for comments TBD*
ACRS subcommittee meeting on SER with open item(s) 09/2012 Public Meeting - draft SEIS meeting TBD*
= ~ of comment e<'rtod for the draft SEIS TBD*
ssue final SER 01/2013
.,CRS Full Committee meeting on SER 02/2013 Issue final SEIS TBD*
U.S. Environmental Protection Agency FRN - Availability of final TBD*
SEIS NRR decision TBD*
ENCLOSURE
Letter to M. Gallagher from M. Galloway dated August XX, 2012
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION Units, 1 AND 2 LICENSE RENEWAL APPLICATION DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource RidsNrrDraApla Resource RidsOgcMailCenter LPerkins DWrona RKuntz DMorey REnnis, DORL MSmith,OGC CKanatas, OGC EDiPaolo, SRI JAmbrosini, SRI (A)
NSieller, RI NMcNamara, RI DScrenci, RI NSheehan, RI
M. Gallagher - 2 Enclosed is a revised schedule for the review of the LGS license renewal application. The schedule has been updated to reflect a change in the date (i.e., TBD) for the issuance of the Draft Supplemental Environmental Impact Statement and the subsequent environmental review milestones.
If you have any questions on the revised schedule, please contact Leslie Perkins by telephone at 301-415-2375 or bye-mail at leslie.perkins@nrc.gov.
Sincerely, IRA!
Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION:
See next page ADAMS Accession No.: ML12220A593 *concurred via email OFFIC PM:DLR/RPB2 LA:DLR/RPB2* OGC (NLO) BC:DLR/RPB2 YEdmonds MSmith DWrona (MWentzel for) 8/15/12 8/16/12 8/16/12 OFFICIAL RECORD COpy
Letter to M. Gallagher from M. Galloway dated August 20, 2012
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION Units, 1 AND 2 LICENSE RENEWAL APPLICATION DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource RidsNrrDraApla Resource RidsOgcMailCenter LPerkins DWrona RKuntz DMorey REnnis, DORL MSmith,OGC CKanatas, OGC EDiPaolo, SRI JAmbrosini, SRI (A)
NSieller, RI NMcNamara, RI DScrenci, RI NSheehan, RI