Revision of Schedule for the Conduct of Environmental Review of the Limerick Generating Station, License Renewal Application (TAC Nos. ME7346 and ME7347)
ML14007A620
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 01/23/2014
From: John Lubinski
Division of License Renewal
To: Gallagher M
Exelon Generation Co
Perkins L, 415-2375
References
TAC MF7346, TAC MF7347
Download: ML14007A620 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 23, 2014 Mr. Michael P. Gallagher Vice President License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION, LICENSE RENEWAL APPLICATION (TAC NOS. ME7346 AND ME7347)

Dear Mr. Gallagher:

By letter dated June 22, 2011, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 (1 0 CFR Part 54), to renew Operating Licenses NPF-39 and NPF-85 for Limerick Generating Station, Units 1 and 2 (LGS), for review by the U.S. Nuclear Regulatory Commission (NRC or the Staff). This letter is to inform you about a schedule change in the LGS license renewal review.

On October 31, 2013, the Commission issued order CLI-13-07 directing the Staff to review the significance of any new severe accident mitigation alternatives-related information in its environmental review of Exelon's license renewal application, including the information presented in the Natural Resources Defense Council's waiver petition, and to discuss its review in the Final Supplemental Environmental Impact Statement (FSEIS). The Staff requires additional time to complete the Commission's directive in CLI-13-07.

Enclosed is the revised schedule for review of the LGS license renewal application. The schedule has been updated to reflect a change in the date for the issuance of the FSEIS.

If you have any questions on the revised schedule, please contact Leslie Perkins by telephone at 301-415-2375 or by e-mail at leslie.perkins@nrc.gov.

/Jd

~~;_/---:--i---_ __

Jo W. Lubins

  • irector Di sion of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353

Enclosure:

Revised Schedule cc w/encl: Listserv

..* ML14007A620 *concurred via email PM: BC: BC: D:DLR OFFICE LA:DLR PM: RPB2:DLR OGC NLO RPB1:DLR RPB1 :DLR RPB2:DLR YDiaz- BWittick Jlubinski NAME YEdmonds LPerkins CKanatas RPiasse Sanabria DATE 01/08/2014 01/9/2014 01/13/2014 01/3/2014 01/15/2014 01/23/2014 01/23/2014

Letter toM. Gallagher from J. Lubinski dated, January 23, 2014

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE LIMERICK GENERATING STATION, LICENSE RENEWAL APPLICATION (TAC NOS. ME7346, ME7347)

DISTRIBUTION:

HARD COPY:

DLRRF E-MAIL:

PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRerb Resource RidsNrrDirRsrg Resource RidsNrrDraApla Resource RidsOgcMaiiCenter LPerkins BWittick RPiasse YDiaz-Sanabria REnnis, DORL CKanatas, OGC EDiPaolo, SRI JAyala, Rl NMcNamara, Rl DScrenci, Rl NSheehan, Rl

LIMERICK GENERATING STATION LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 06/22/11 06/22/11 Publish Federal Register Notice (FRN) - LRA receipt and availability 07/2011 07/26/11 Publish FRN- LRA acceptability, environmental seeping period, 08/2011 08/24/11 and opportunity for hearing Publish FRN - intent to conduct environmental seeping 08/2011 08/26/11 Public Meeting - license renewal process and environmental 09/22/11 09/22/11 seeping Audit - seeping and screening methodology 09/19-23/11 09/19-23/11 Deadline for filing hearing requests and petitions for intervention 10/24/11 10/24/11 Environmental seeping period ends 10/28/11 10/28/11 Audit- ag_ing mana_gementprograms (AMPs) 10/03-14/11 10/03-14/11 Audit - environmental 11/07-10/11 11/07-10/11 Inspection - seeping, screening, and AMPs 06/04-08/12 06/04-08/12 06/18-22/12 06/18-22/12 Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12 Issue draft supplemental environmental impact statement (SEIS) 04/2013 04/30/2013 Publish FRN - draft SEIS available for comments 04/2013 05/10/2013 ACRS subcommittee meeting on SER with open item(s) 09/2012 09/05/2012 Public Meeting - draft SEIS meeting 05/2013 05/23/2013 End of comment period for the draft SEIS 06/2013 06/27/2013 Issue final SER 01/2013 01/10/2013 ACRS full committee meetin_g_ on SER 02/2013 02/07/2013 Issue final SEIS 08/2014 U.S. Environmental Protection Agency FRN-availability of final 09/2014 SEIS NRR decision TBD