MONTHYEARML24151A3842024-10-31031 October 2024 – Issuance of Amendment Nos. 264 and 226 Support to Digital Modernization Project Installation (EPID L-2023-LLA-0025) and Exemption from the Requirements of 10 CFR 50.62 ML24303A0902024-10-29029 October 2024 Operator Licensing Examination Approval ML24303A2782024-10-29029 October 2024 10 CFR 50.46 Annual Report ML24299A2642024-10-25025 October 2024 Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Primary Containment Leakage Technical Specifications IR 05000352/20240122024-10-17017 October 2024 Commercial Grade Dedication Inspection Report 05000352/2024012 and 05000353/2024012 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24274A2372024-10-0707 October 2024 – Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Primary Containment Leakage Technical Specifications ML24278A3022024-10-0404 October 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10 CFR 50.62 ATWS Rule to Support the Digital Modernization Project Installation - Rev Unit 2 Technical Spec ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A0032024-09-27027 September 2024 Generation Station, Units 1 and 2 – Regulatory Audit Plan Supporting Review of the Component Interface Module System of the Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) (Redacted) ML24243A0482024-09-19019 September 2024 Generation Station, Unit Nos. 1 and 2 - Schedule Update for License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24215A4042024-09-18018 September 2024 Request for Withholding Information from Public Disclosure IR 05000352/20244202024-09-16016 September 2024 – Security Baseline Inspection Report 05000352/2024420 and 05000353/2024420 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds IR 05000352/20250102024-09-10010 September 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000352/2025010 and 05000353/2025010 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000352/20240052024-08-29029 August 2024 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2024005 and 05000353/2024005) ML24241A1952024-08-28028 August 2024 License Amendment Request for Modification to Technical Specification 3.6.1.2 and Main Steam Isolation Valve Leakage Rate Requirements ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24163A3902024-08-14014 August 2024 Request for Withholding Information from Public Disclosure ML24220A2392024-08-12012 August 2024 Correction to Technical Specification Page 3/4 3-11 in Amendment No. 225 IR 05000352/20240022024-08-12012 August 2024 Integrated Inspection Report 05000352/2024002 and 05000353/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24204A0712024-07-29029 July 2024 Issuance of Amendment Nos. 263 and 225 Technical Specifications for Main Steam Line Tunnel Temperature ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24208A1592024-07-25025 July 2024 Regulatory Audit Plan Supporting Review of the System Development Portion of Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) - Non-Proprietary ML24201A1662024-07-19019 July 2024 Response to Request for Additional Information for License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam L ML24199A1842024-07-15015 July 2024 RAI-LAR for Limerick EPID: L-2024-LLA-0079- Use This Version RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24180A1572024-06-28028 June 2024 Request to Return and Replace WEC Documents (EQ-EV-386-GLIM, EQ-QR- 433-GLIM, and APP-GW-GLR-611), to Meet 10CFR2.390 Request to Withdraw from Public Disclosure Requirements ML24170A7702024-06-20020 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, Opportunity for Hearing(Epid L-2024-LLA-0079) LTR 05000352/LER-2024-003, Core Operating Limits Report Thermal Limit Exceeded for Unit 1 Fuel Bundle GGK1232024-06-18018 June 2024 Core Operating Limits Report Thermal Limit Exceeded for Unit 1 Fuel Bundle GGK123 ML24166A1142024-06-14014 June 2024 Response to Requests for Additional Information (RAIs 15 Through 23) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24165A2642024-06-13013 June 2024 License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam Line Tunnel Temperature TS 3/4.7.9 05000352/LER-2024-002, Invalid Actuation Due to a Trip of 1B Reactor Protection System Circuit Breaker2024-06-10010 June 2024 Invalid Actuation Due to a Trip of 1B Reactor Protection System Circuit Breaker ML24151A2882024-06-10010 June 2024 Request for Withholding Information from Public Disclosure ML24151A2012024-06-10010 June 2024 Request for Withholding Information from Public Disclosure 05000352/LER-2024-001, Leakage for the Unit 1 `B Outboard Main Steam Isolation Valve Exceeded Technical Specification Limit2024-06-10010 June 2024 Leakage for the Unit 1 `B Outboard Main Steam Isolation Valve Exceeded Technical Specification Limit ML24150A0242024-05-29029 May 2024 Notification of Commercial Grade Dedication Inspection (05000352/2024012 and 05000353/2024012) and Request for Information ML24149A2112024-05-28028 May 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 IR 05000352/20243022024-05-20020 May 2024 Revised Initial Operator Licensing Examination Report 05000352/2024302 and 05000353/2024302 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000352/20240012024-05-0707 May 2024 Integrated Inspection Report 05000352/2024001 and 05000353/2024001 ML24124A0432024-05-0303 May 2024 Response to Requests for Additional Information (RAIs 9 Through 14) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24114A3222024-04-23023 April 2024 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) - Pivot to Unit ML24109A0702024-04-18018 April 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFRC50.52 ATWS Rule to Support the Digital Modernization Project Installation . 2024-09-06
[Table view] Category:Schedule and Calendars
MONTHYEARML24243A0482024-09-19019 September 2024 Generation Station, Unit Nos. 1 and 2 - Schedule Update for License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML14007A6202014-01-23023 January 2014 Revision of Schedule for the Conduct of Environmental Review of the Limerick Generating Station, License Renewal Application (TAC Nos. ME7346 and ME7347) ML13050A0202013-03-0404 March 2013 Revision of Schedule for the Conduct of Environmental Review for Limerick Generating Station Units 1 and 2 License Change ML12220A5932012-08-20020 August 2012 Revision of Schedule for the Conduct of Environmental Review of the Limerick Generating Stations Units, 1 and 2, LRA ML1105407242011-02-23023 February 2011 2/23/11 Ltr to F. Schiffley Re Participation in Commission Meeting on 50.46a Risk-informed Emergency Core Cooling System Rule on 3/24/11 RS-07-017, Amergen Energy Company, LLC, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations.2007-08-13013 August 2007 Amergen Energy Company, LLC, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations. RS-06-134, Response to NRC Regulatory Issue Summary 2006-15 Preparation and Scheduling of Operator License Examinations.2006-09-20020 September 2006 Response to NRC Regulatory Issue Summary 2006-15 Preparation and Scheduling of Operator License Examinations. 2024-09-19
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 March 4, 2013 Mr. Michael P. Gallagher Vice President License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION
Dear Mr. Gallagher:
By letter dated June 22, 2011, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR Part 54), to renew operating licenses NPF-39 and NPF-85 for Limerick Generating Station, Units 1 and 2 (LGS), for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). This letter is to inform you about a schedule change in the LGS license renewal review.
On August 20,2012, NRC sent a letter with a revised schedule for the LGS environmental schedule. The schedule was revised because of the United States Court of Appeals for the District of Columbia Circuit decision on the NRC waste confidence rule update (10 CFR Part 51.23). Because the Draft Supplemental Environmental Impact Statement (DSEIS) for LGS discusses issues related to waste confidence, the staff needed additional time to ensure that the DSEIS is consistent with the Commission's directions on waste confidence. That schedule indicated that future environmental milestones were to be determined after the staff completed this process. The NRC is now able to determine the schedule for completing the LGS environmental review.
Enclosed is a revised schedule for the review of the LGS license renewal application. The schedule has been updated to reflect a change in the date for the issuance of the DSEIS and the subsequent environmental review milestones.
If you have any questions on the revised schedule, please contact Leslie Perkins by telephone at 301-415-2375 or bye-mail atleslie.perkins@nrc.gov.//
Sincerely, //
//./
7"-'
. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosure:
As stated
March 4, 2013 Mr. Michael p, Gallagher Vice President License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION
Dear Mr,
Gallagher:
By letter dated June 22,2011, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR Part 54), to renew operating licenses NPF-39 and NPF-85 for Limerick Generating Station, Units 1 and 2 (LGS), for review by the U,S, Nuclear Regulatory Commission (NRC or the staff), This letter is to inform you about a schedule change in the LGS license renewal review, On August 20,2012, NRC sent a letter with a revised schedule for the LGS environmental schedule, The schedule was revised because of the United States Court of Appeals for the District of Columbia Circuit decision on the NRC waste confidence rule update (10 CFR Part 51,23), Because the Draft Supplemental Environmental Impact Statement (DSEIS) for LGS discusses issues related to waste confidence, the staff needed additional time to ensure that the DSEIS is consistent with the Commission's directions on waste confidence, That schedule indicated that future environmental milestones were to be determined after the staff completed this process, The NRC is now able to determine the schedule for completing the LGS environmental review, Enclosed is a revised schedule for the review of the LGS license renewal application, The schedule has been updated to reflect a change in the date for the issuance of the DSEIS and the subsequent environmental review milestones, If you have any questions on the revised schedule, please contact Leslie Perkins by telephone at 301 415-2375 or bye-mail at leslie, perkins@nrc,gov, Sincerely,
/ra/
John W, Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos, 50-352 and 50-353
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION:
See next page ADAMS Accession No,: ML13050A020 OFFICE PM:DLR/RPB LA:DLR/RPB2 C BC:DL DLR NAME LPerkins IKing mith DWrona
- JLubinski DATE 02/25/2013 02/22/2013 02/26/2013 212612013 3/4/2013 OFFICIAL RECORD COpy
Ltr to M. Gallagher from J. Lubinski, dated March 4,2013
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource RidsNrrDraApla Resource RidsOgcMailCenter LPerkins DWrona PMiliano DMorey REnnis, DORL MSmith,OGC CKanatas, OGC EDiPaolo, SRI JHawkins, RI NMcNamara, RI DScrenci, RI NSheehan, RI
LIMERICK GENERATING STATION LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 06/22/11 06/22/11 Publish Federal Register Notice (FRN) - LRA receipt and availability 07/2011 07/26/11 Publish FRN -LRA acceptability, environmental scoping period, and 08/2011 08/24/11 opportunity for hearing Publish FRN -intent to conduct environmental scoping 08/2011 08/26/11 Public Meeting -license renewal process and environmental scoping 09/22/11 09/22/11 Audit - scoping and screening methodology 09/19-23/11 09/19-23/11
- Deadline for filing hearing requests and petitions for intervention 10/24/11 10/24/11 Environmental scoping periods ends 10/28/11 10/28/11 Audit - aging management programs (AMPs) 10103-14/11 10103-14/11 Audit - environmental 11/07-10/11 11/07-10/11 I Inspection - scoping, screening, and AMPs 06/04-08/12 06/04-08/12 06/18-22/12 06/18-22/12 Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12 I Issue draft supplemental environmental impact statement (SEIS) 04/2013 Publish FRN- draft SEIS available for comments 04/2013
! ACRS subcommittee meeting on SER with open item(s) 09/2012 09/05/2012 Public Meeting- draft SEIS meeting 05/2013 End of comment period for the draft SEIS Issue final SER ACRS full committee meeting on SER 06/2013 01/2013 02/2013 01/10/2013 2107/2013
=
Issue final SEIS 11/2013 U.S. Environmental Protection Agency FRN-availability of final SEIS 11/2013 NRR decision *TBD
ENCLOSURE