MONTHYEARML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML22284A1442023-02-0303 February 2023 Issuance of Amendment No. 200 Regarding the Revision of Methodology Used for Flood Hazard Analysis ML22348A1372023-01-0505 January 2023 Issuance of Amendment No. 199 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML22252A2212022-09-30030 September 2022 Authorization and Safety Evaluation for Alternative Request IR-063 ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22187A2592022-07-12012 July 2022 Issuance of Relief Proposed Alternative Request Vr 12, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML22136A1132022-06-21021 June 2022 Issuance of Relief Proposed Alternative Requests VR-10, Revision 0, and VR-11, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval (EPIDs L-2021-LLR-0096; L-2021-LLR-0097) ML21322A2602022-01-10010 January 2022 Issuance of Amendment No. 197 Regarding the Adoption of TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystem, and TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Oper ML21270A1122021-11-16016 November 2021 Issuance of Amendment No. 196 Regarding Changes to the Emergency Plan ML21271A0782021-11-0505 November 2021 Issuance of Amendment No. 195 Regarding the Adoption of TSTF-230, Add New Condition B to LCO 3.6.2.3, 'Rhr Suppression Pool Cooling' ML21158A2122021-07-12012 July 2021 Issuance of Amendment No. 194 Regarding the Adoption of TSTF-002, Relocate the 10 Year Sediment Cleaning of the Fuel Oil Storage Tank to Licensee Control ML21123A2172021-05-0505 May 2021 Issuance of Relief Requests Vr 4, Revision 0, Vr 6, Revision 0, and Vr 8, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval (EPIDs L 2021 Llr 0010, L 2021 Llr 0011, L 2021 Llr 0012 COVID-19 ML21123A2892021-05-0404 May 2021 Issuance of Relief Request Vr 7, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML21081A0702021-04-27027 April 2021 Issuance of Amendment No. 193 Regarding the Adoption of TSTF-500, DC Electrical Rewrite - Update to TSTF-360 ML21063A2532021-03-0505 March 2021 Issuance of Relief Request SR-2, Revision 0, from Certain Requirements of the ASME OM Code (EPID L-2021-LLR-0005 (COVID-19)) ML21063A1572021-03-0404 March 2021 Safety Evaluation for Alternative Request SR-2, Revision 0 Related to one-time Extension Snubbers Testing to ASME OM Code for the Fourth 10-year Inservice Interval at Perry Nuclear Power Plant Unit 1, Docket Nos. 50-440 ML21035A1702021-03-0101 March 2021 Issuance of Amendment No. 192, Regarding Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20363A0062021-01-29029 January 2021 Issuance of Relief Proposed Alternative Request Associated with Fourth 10-Year Inservice Inspection Interval ML20311A6582020-11-10010 November 2020 Issuance of Relief Proposed Alternative Request Associated with Fourth Ten Year Interval Inservice Inspection Interval ML20279A4402020-10-0808 October 2020 Energy Harbor Fleet-Beaver Valley Power Station; Davis-Besse Nuclear Power Station, and Perry Nuclear Power Plant - Request to Use a Provision of a Later Edition of the ASME Engineers Boiler and Pressure Vessel Code, Section XI ML20266G2652020-09-24024 September 2020 Correction Letter for Relief Request IR-062 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML20252A0262020-09-18018 September 2020 Relief Request IR-062 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML20189A0032020-07-10010 July 2020 Relief Request PR-3 for Fourth 10-Year Pump and Valve Inservice Testing Program ML20154K7002020-07-0909 July 2020 Issuance of Amendment No. 190 Regarding Fire Protection Program Licensing Basis ML20118C1672020-05-22022 May 2020 Issuance of Amendment No. 189, Regarding Special Heavy Lifting Device Nondestructive Examination Frequency ML20099A1022020-05-22022 May 2020 Issuance of Amendment No. 188, Regarding Revision to Technical Specifications to Adopt TSTF-564, Safety Limit (Minimum Critical Power Ratio) MCPR ML19305B1312019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Enclosure 6, Non-Proprietary Safety Evaluation, Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19163A0232019-08-14014 August 2019 Issuance of Amendment No. 186 Concerning Changes to Emergency Response Organization ML19028A0302019-04-11011 April 2019 FENOC - Beaver Valley Power Station, Unit 1 & 2; Davis-Besse Nuclear Power Station Unit 1; and Perry Nuclear Power Plant Unit 1 - Approval of Certified Fuel Handler Training and Retraining Program ML19072A0122019-03-15015 March 2019 Correction to License Amendment No. 184 Related to Adoption of Technical Specification Task Force Traveler TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control ML19072A0852019-03-15015 March 2019 Correction to Request for Alternatives Related to Inservice Testing Program for the Fourth 10 Year Inservice Testing Interval ML19029A0902019-02-25025 February 2019 Request for Alternatives Related to Inservice Testing Program for the Fourth 10-Year Inservice Testing Interval (EPID Nos. L-2018-LLR-0092, 0093, 0094, 0095, and 0096) ML19022A3242019-02-25025 February 2019 Issuance of Amendment No. 185 Concerning Extension of Containment Leakage Test Frequency ML19037A0412019-02-25025 February 2019 Request for Alternative to Use ASME Code Case N-831 ML18292A8162018-12-12012 December 2018 Issuance of Amendment No. 184 Concerning Adoption of Technical Specification Task Force Traveler 542, Rev. 2, Reactor Pressure Vessel Water Inventory Control ML18199A2802018-08-23023 August 2018 Issuance of Amendment No. 183, Adopt Technical Specification Task Force Traveler TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18157A0842018-06-25025 June 2018 Issuance of Amendment No. 181 Concerning Adoption of TS Task Force Traveler TSTF-306-A, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration (CAC No. MG0150; EPID L-2017-LLA-0286) ML18110A1332018-05-16016 May 2018 Unit No. 1 - Issuance of Amendment No. 180 Concerning Changes to Technical Specifications Regarding Implementation of the Alternative Source Term (CAC No. MF9818; EPID L-2017-LLA-0241) ML18023A6252018-01-29029 January 2018 Approval of Alternative to Use BWRVIP Guidelines in Lieu of Certain ASME Code Requirements (CAC No. MG0149; EPID 2017-LLR-0112) (L-17-183) ML18004A1222018-01-22022 January 2018 FENOC-Beaver Valley, Davis-Besse, and Perry - Alternative for the Use of ASME Code Case N-513-4 (CAC Nos. MG0120, MG0121, MG0122, and MG0123; EPID L-2017-LLR-0088) ML17325B6902018-01-18018 January 2018 Issuance of Amendment Concerning Adoption of Technical Specification Task Force (TSTF) Traveler 400-A, Revision 1, Clarify SR on Bypass of DG Automatic Trips (CAC No. MF9855, EPID L-2017-LLA-0246) (L-17-089) ML17257A0982017-10-19019 October 2017 Issuance of Amendment Concerning Revisions to the Environmental Protection Plan (CAC No. MF9652; EPID L-7017-LLA-0226) (L-17-043) ML17270A0302017-10-16016 October 2017 Approval of Alternative to Use ASME Code Case N-513-4 for Repair of Emergency Service Water System Piping (CAC No. MG0130; EPID L-2017-LLR-0080)(L-17-278) ML17193A3822017-07-18018 July 2017 Correction to Safety Evaluation for License Amendment No. 177 ML17163A3542017-06-29029 June 2017 Issuance of Amendment Concerning Adoption of Tstf-501, Revision 1, Relocation of Diesel Fuel and Lube Oil Volume Values to Licensee Control (CAC No. MF8693) (L-16-236) ML17139C3722017-06-19019 June 2017 Issuance of Amendment Concerning Reduction of Steam Dome Pressure Value Specified in Technical Specification 2.1.1 (CAC No. MF8760) (L-16-179) 2023-09-28
[Table view] Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report 2024-01-30
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 February 22, 2012 Mr. Vito A. Kaminskas Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-PY -A290 P.O. Box 97, 10 Center Road Perry,OH 44081-0097
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT NO.1, RE: SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO REQUEST VR-1, REVISION 1, FOR THE THIRD 10-YEAR INTERVAL INSERVICE TESTING PROGRAM (TAC NO. ME7380)
Dear Mr. Kaminskas:
By letter to the U.S. Nuclear Regulatory Commission (NRC), dated October 16, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML112900204), FirstEnergy Nuclear Operating Company (FENOC, the licensee), submitted a request to the NRC for the use of an alternative to certain American Society of Mechanical Engineers (ASME) Code of Operation and Maintenance of Nuclear Power Plants (OM) Code requirements at Perry Nuclear Power Plant, Unit No.1 (PNPP).
Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section SO.SSa(a)(3)(i}, the licensee requested to use an alternative on the basis that it provides an acceptable level of quality and safety. The proposed alternative, contained in request VR-1, Revision 1, provides reasonable assurance that the hydraulic control unit valves, 1C 11-126, 1C11-127, 1C11-114, and 1C11-11S, are operationally ready. The alternative would authorize the licensee to have 177 Category B scram inlet and exhaust valves and 177 Category C scram discharge and charging water header check valves tested on the frequency identified in the Technical Specifications for the facility, in lieu of the ASME Code for Operation and OM Code requirements. All other ASME OM Code requirements for which relief was not specifically requested and approved in the subject request for relief remain applicable.
The NRC staff has reviewed the licensee's request and concludes, as set forth in the enclosed safety evaluation, that PNPP has adequately addressed all of the regulatory requirements set forth in 10 CFR, Section SO.SSa(a)(3)(i), and is in compliance with the requirements of the ASME OM Code. Therefore, the NRC staff authorizes the alternative in request, VR-1, Revision 1, for the remainder of the third 10-year inservice testing program interval for PNPP.
- v. Kaminskas - 2 If you have any questions, please contact the PNPP Project Manager, Michael Mahoney, at 301-415-3867 or via e-mail at MichaeI.Mahoney@nrc.gov.
The NRC staffs Safety Evaluation is enclosed.
Sincerely.
~~l::ef Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. STN 50-440
Enclosure:
Safety Evaluation cc w/encl: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO REQUESTVR-1, REVISION 1, FOR THE THIRD 10-YEAR INTERVAL INSERVICE TESTING PROGRAM FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT, UNIT NO.1 DOCKET NO: STN 50-440
1.0 INTRODUCTION
By letter to the U.S. Nuclear Regulatory Commission (NRC), dated October 16, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML112900204), FirstEnergy Nuclear Operating Company (FENOC, the licensee), submitted a request to the NRC for the use of an alternative to certain American Society of Mechanical Engineers (ASME) Code of Operation and Maintenance of Nuclear Power Plants (OM) Code requirements. The alternative, VR-1, Revision 1, would authorize the licensee to have 177 Category B scram inlet and exhaust valves and 177 Category C scram discharge and charging water header check valves tested on the frequency identified in the Technical Specifications (TSs) for the facility for the remainder of the third 1O-year inservice testing (1ST) program interval.
Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a(a)(3)(i), the licensee requested to use the proposed alternative in VR-1, Revision 1, on the basis that the alternative provides an acceptable level of quality and safety.
2.0 REGULATORY EVALUATION
Section 50.55a(f) of 10 CFR, "Inservice Testing Requirements," requires, in part, that 1ST of certain ASME Code Class 1, 2, and 3, components must meet the requirements of the ASME OM Code and applicable addenda, except where alternatives have been authorized or relief has been granted by the NRC pursuant to paragraphs (a)(3)(i), (a)(3)(ii), or (f)(6)(i) of 10 CFR 50.55a.
In proposing alternatives or requesting relief, a licensee must demonstrate that: (1) the proposed alternatives provide an acceptable level of quality and safety (10 CFR 50.55a(a)(3)(i>>;
(2) compliance would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety (10 CFR 50.55a(a)(3)(ii>>; or (3) conformance is impractical for the facility (10 CFR 50.55a(f)(6)(i>>. Section 50.55a allows the NRC to authorize alternatives and grant relief from ASME OM Code requirements upon making necessary findings.
PNPP's third 10-year 1ST program interval began on May 18, 2009, and is currently scheduled to end on May 17, 2019. The applicable ASME OM Code Edition and Addenda for PNPP is the 2001 Edition through the 2003 Addenda.
The NRC's findings with respect to authorizing VR-1, Revision 1, are given below:
3.0 TECHNICAL EVALUATION
ASME OM Code Requirements STC-3510, "Exercising Test Frequency", states that, "Active Category A, Category B, and Category C check valves shall be exercised nominally every three months, except as provided by ISTC-3520, ISTC-3540, ISTC-3550, ISTC-3560, ISTC-5221, and ISTC-5222.
Power-operated relief valves shall be exercise tested once per fuel cycle."
ISTC-5131 (a), "Valve Stroke Testing", states that, "Active valves shall have their stroke times measured when exercised in accordance with ISTC-3500."
ISTC-5221 (a), "Valve Obturator Movement" states that, "The necessary valve obturator movement during exercise testing shall be demonstrated by performing both an open and a close test."
Licensee's Proposed Alternative VR-1, Revision 1 Alternative testing was requested for the following hydraulic control unit (HCU) valves (typical of 177 HCUs):
1C11-126 - Scram Inlet Valve (Class 2, Category B) 1C11-127 - Scram Exhaust Valve (Class 2, Category B) 1C11-114 - Scram Discharge Header Check Valve (Class 2, Category C) 1C 11-115 - Charging Water Header Check Valve (Class 2, Category C)
The licensee states:
These valves operate as an integral part of their respective HCU (typical of 177) to rapidly insert the control rods into the core in support of the reactor scram function.
Specifically:
Scram Inlet Valve (1 C11-126) has a safety function to open and supply pressurized water to the bottom of the control rod drive piston to rapidly insert the control rod into the core.
Scram Exhaust Valve (1C11-127) has a safety function to open and vent water from above the control rod drive piston to the scram discharge header allowing control rod movement during the scram.
-3 Scram Discharge Header Check Valve (1 C 11-114) has a safety function to close and prevent reverse flow from the scram discharge header back to the top of the control rod drive piston; during the scram, this check valve has a safety function to open and allow water from above the control rod drive piston to flow into the scram discharge header (with 1C11-127 open) allowing control rod movement.
Charging Water Header Check Valve (1C11-115) has a safety function to close and prevent the loss of water pressure in the event supply pressure to the scram accumulator is lost; during the scram, this check valve opens to allow flow to the bottom of the control rod drive piston (with 1C11-126 open).
Reason for Request
The NRC granted relief from the requirements of the ASME OM Code, Paragraphs ISTC-5131 and ISTC-5221, at PNPP, based on Request VR-1, Revision 0, in an NRC safety evaluation (SE) dated October 22,2009 (ADAMS Accession No. ML092890032).
On May 19, 2011, the NRC issued Amendments 156 and 157, for the PNPP TSs that modified the scram time surveillance testing frequency requirements of TS 3.1.4, "Control Rod Scram Times" from 120 days cumulative operation in MODE 1 to 200 day's cumulative operation in MODE 1 (ADAMS Accession Nos. ML111060269 and ML11105A038, respectively). Approval of this proposed alternative to ISTC-3510, as described in VR-1, Revision 1, will align the testing frequencies of the specified ASME code components to the frequencies stated within TS 3.1.4 and TS Surveillance Requirements (SRs), SR 3.1.4.1, SR 3.1.4.2, SR 3.1.4.3 and SR 3.1.4.4.
The pneumatically operated scram inlet and exhaust valves full-stroke in milliseconds and are not provided with suitable position indication; therefore, to measure stroke times as required by ISTC-5131 (a), special test methods or test equipment would be required.
The check valves are not provided with position indication; therefore, to determine if the obturator has traveled to the proper position as required by ISTC-5221 (a), special test methods or test equipment would be required.
Approval of this proposed alternative would make the third 10-year 1ST program consistent with NUREG-1482, Revision 1, "Guidelines for Inservice Testing at water power plants," Section 4.4.6.
Proposed Alternative and Basis for Use:
As discussed in NUREG-1482, Revision 1, Section 4.4.6, the rod scram test frequency identified in the TSs for a facility may be used as the valve testing frequency to minimize rapid reactivity transients and wear of the control rod drive mechanisms. Verifying that the associated control rod meets the scram insertion time limits defined in the TSs can be an acceptable alternative method of detecting degradation of these valves.
The provisions of this request provide a reasonable alternative to the ISTC-3510, ISTC-5131(a) and ISTC-5221 (a) ASME OM Code requirements. The proposed method of detecting valve
- 4 degradation provides reasonable assurance of the operational readiness of each valve, provides an acceptable level of quality and safety for monitoring the valves, and ensures the valves are capable of performing their control rod drive safety functions.
The TS 3.1.4 SRs place conservative limits on the control rod insertion times, ensuring the necessary quality of the control rod drive system and its components are maintained.
Therefore, scram insertion timing per the requirements of SR 3.1.4.1, SR 3.1.4.2, SR 3.1.4.3 and SR 3.1.4.4, including test frequencies, shall be substituted for individual valve testing. For check valves 1C11-114 and 1C11-115, this includes only open direction testing.
NRC Staff Evaluation
By letter dated November 18, 2008 (ADAMS Accession No. ML083370198), FENOC submitted relief request VR-1, Revision O. Specifically, the licensee requested relief from the requirements of ASME OM Code 2001 Edition through OMb-2003 Addenda, Paragraphs ISTC-5131 (a) and ISTC-5221 (a) for the control rod drive (CRD) HCU scram valves, 1C11-126 and 1C11-127, and scram discharge header and charging water header check valves, 1C11 114 and 1C11-115 associated with the 177 HCUs. The basis for requesting VR-1, Revision 0 was:
- a. The scram inlet and exhaust valves were not provided with suitable position indication; therefore, measuring the full stroke time in accordance with ISTC-5131 (a) would require a special test method and/or test equipment
- b. The check valves were not provided with position indication; therefore, to determine if the obturator has traveled to the proper position as required by ISTC-5221 (a) would require a special test method and/or test equipment The licensee also requested that the scram inlet and exhaust valves and check valves were tested at the frequency designated in TS SR 3.1.4.1 and SR 3.1.4.2, in lieu of every three months, as required by Paragraph ISTC-3510 of the ASME OM Code.
Request VR-1, Revision 0, proposed an alternative to verify proper operation of HCU valves by completion of TS SR 3.1.4.1 which required the scram time for all control rods to be verified prior to thermal power exceeding 40 percent of rated thermal power after each reactor shutdown greater than or equal to 120 days. In addition, TS SR 3.1.4.2 required testing of a representative sample of the control rods at least once per 120 days of operation in MODE 1.
The TS SRs assured that the necessary quality of the system and components were maintained.
The Safety Evaluation (SE) (ADAMS Accession No. ML092890032) completed by the NRC staff for VR-1, Revision 0, granted the request from FENOC. The SE stated that the proposed alternative was consistent with the NRC staff position in NUREG-1482, Revision 1, Section 4.4.6, and would therefore provide reasonable assurance of the operational readiness of the CRD valves. After the relief requested by VR-1, Revision 0, was granted, FENOC requested and the NRC approved a change to TS SR 3.1.4.2 that extended the SR testing frequency from 120 to 200 days.
-5 Request VR-1, Revision 1, was initiated due to the fact that PNPP TS SR 3.1.4.2 changed and request VR-1, Revision 0, was granted based on TS SR 3.1.4.2 testing a representative sample of control rods at least once per 120 days of operation in MODE 1. None of the other conditions or attributes noted in Revision 0 of the VR-1 request changed. The change of test interval from 120 days to 200 days does not impact the basis that was used by the NRC in developing the SE for granting the relief requested in VR-1, Revision O. Requiring exercise testing of the scram inlet and exhaust valves and check valves every three months represents a hardship or unusual difficulty without an increase in the level of quality and safety since these valves can be adequately tested during the scram time testing per the SRs for TS 3.1.4. The proposed alternative in request VR-1, Revision 1, provides reasonable assurance that the valves are operationally ready and remains consistent with the staff position in NUREG-1482, Revision 1, and Section 4.4.6.
4.0 CONCLUSION
Based on the above evaluation, the NRC staff has determined that the proposed alternative in request VR-1, Revision 1, provides reasonable assurance that the HCU valves, 1C11-126, 1C11-127, 1C 11-114, and 1C11-115, are operationally ready. All other ASME OM Code requirements for which relief was not specifically requested and approved in the subject request for relief remain applicable. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(a)(3)(i), and is in compliance with the requirements of the ASME OM Code.
Therefore, the NRC staff authorizes the alternative in request, VR-1, Revision 1, for the remainder of the third 10-year 1ST program interval for PNPP, which began on May 18, 2009, and is currently scheduled to end on May 17, 2019.
Principle Contributor: Michael Farnan Date of issuance: February 22, 2012
V. Kaminskas - 2 If you have any questions, please contact the PNPP Project Manager, Michael Mahoney, at 301-415-3867 or via e-mail at MichaeI.Mahoney@nrc.gov.
The NRC staff's Safety Evaluation is enclosed.
Sincerely, IRA!
Jacob I. Zimmerman, Chief Plant Licensing Branch 111-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket No. STN 50-440
Enclosure:
Safety Evaluation cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL3-2 RlF RidsNrrDorlLpl3-2 Resource RidsNrrPMPerryResource RidsNrrLASRohrer Resource RidsOgcRp Resource RidsAcrsAcnw_MailCTR Resource RidsNrrDeEvib Resource RidsNrrDeEpnb Resource RidsRgn3MailCenter Resource ADAMS ACCESSION NO .. ML120370477 *Bsy memo d ate d NRR028 OFFICE LPL3-21PE LPL3-2/PM LPL3-2/LA DElEVIB/BC* DE/EPNM/BC* LPL3-2/BC NAME PHernandez MMahoney SRohrer HGonzalez TLupold JZimmerman TE 2/13/12 2113112 2/13/12 12/15/2011 112/15/2011 2/22/12 OFFICIAL RECORD COPY