ML102710252

From kanterella
Jump to navigation Jump to search

Acceptance Review E-mail, License Amendment Request to Revise Updated Final Safety Analysis Report, Feedwater Line Break Analysis with LOOP and Single Failure Analysis
ML102710252
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 09/28/2010
From: Lauren Gibson
Plant Licensing Branch IV
To: Stroud R
Arizona Public Service Co
Gibson, Lauren, NRR/DORL/LPL4, 415-1056
References
TAC ME4596, TAC ME4597, TAC ME4598
Download: ML102710252 (2)


Text

From:

Gibson, Lauren Sent:

Tuesday, September 28, 2010 10:25 AM To:

Russell.Stroud@aps.com Cc:

Hall, Randy; Lent, Susan; Burkhardt, Janet

Subject:

Acceptance Review Results for LAR to Revise Feedwater Line Break with LOOP and Single Failure Analysis September 28, 2010

SUBJECT:

Acceptance Review Results for LAR to Revise Feedwater Line Break with LOOP and Single Failure Analysis By letter dated August 27, 2010, Arizona Public Service (APS, the licensee) submitted a license amendment for Palo Verde Nuclear Generating Station, Units 1, 2, and 3. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in a sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me.

Lauren Gibson, Project Manager Plant Licensing Branch 4 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation E-mail Properties Mail Envelope Properties (6F9E3C9DCAB9E448AAA49B8772A448C52625F593B4)

Subject:

Acceptance Review Results for LAR to Revise Feedwater Line Break with LOOP and Single Failure Analysis Sent Date: 9/28/2010 10:24:53 AM Received Date: 9/28/2010 10:24:53 AM From: Gibson, Lauren Created By: Lauren.Gibson@nrc.gov

Recipients:

Russell.Stroud@aps.com (Russell.Stroud@aps.com)

Tracking Status: None Randy.Hall@nrc.gov (Hall, Randy)

Tracking Status: None Susan.Lent@nrc.gov (Lent, Susan)

Tracking Status: None Janet.Burkhardt@nrc.gov (Burkhardt, Janet)

Tracking Status: None Post Office:

HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 9088 9/28/2010 Options Expiration Date:

Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: