Acceptance Review Email, License Amendment Request to Adopt TSTF-490, Revision 0, Deletion of E-Bar Definition and Revision to RCS Specific Activity Technical Specifications
ML13025A248
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/25/2013
From: Lauren Gibson
Plant Licensing Branch IV
To: Roehler R
Arizona Public Service Co
Gibson L
References
TAC MF0397, TAC MF0398, TAC MF0399
Download: ML13025A248 (1)


Text

Lent, Susan From: Gibson, Lauren Sent: Friday, January 25, 201311:54 AM To: 'Robert. Roehler@aps.com'

Subject:

Acceptance Review Results for TSTF-490 License Amendment Request (TAC Nos. MF0397, MF0398, and IVlF0399)

By letter dated December 12, 2012 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML12353A158), Arizona Public Service (APS, the licensee) submitted a license amendment for Palo Verde Nuclear Generating Station. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (f\IRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me.

Lauren K. Gibson Project Manager Columbia Generating Station Palo Verde Nuclear Generating Station Division of Operating Reactor Licensing U.S. Nuclear Regulatory Commission (301) 415-1056 1