ML101970547

From kanterella
Jump to navigation Jump to search
IR 05000285-10-007; on 01/01/2010 - 06/21/2010; Omaha Public Power District Fort Calhoun Station, Inspection Procedure 92701, Followup
ML101970547
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 07/15/2010
From: Caniano R
Division of Reactor Safety IV
To: Bannister D
Omaha Public Power District
References
EA-10-084, FOIA/PA-2014-0210 IR-10-007
Download: ML101970547 (32)


See also: IR 05000285/2010007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

July 15, 2010

EA-10-084

David J. Bannister, Vice President

and Chief Nuclear Officer

Omaha Public Power District

9610 Power Lane

Blair, NE 68008

SUBJECT: FORT CALHOUN STATION - NRC FOLLOWUP INSPECTION - INSPECTION

REPORT 05000285/2010007; PRELIMINARY SUBSTANTIAL FINDING

Dear Mr. Bannister:

The U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Fort Calhoun

Station. The enclosed inspection report documents the inspection findings, which were

discussed, with Mr. J. Reinhart Site Vice President, and other members of your staff on

June 21,2010.

The attached report documents the results of the inspection, which reviewed an unresolved item

from the 2009 Component Design Basis Inspection at the Fort Calhoun Station (URI

05000285/2009006-03). The inspection examined activities conducted under your license as

they relate to safety and compliance with the NRC's rules and regulations with respect to

external flooding.

This report discusses preliminary results of the inspection including a finding, which involves a

failure to establish and maintain procedures to protect the intake structure and auxiliary building

during external flooding events. The inspectors determined that the protection strategy

discussed in station operating procedures, if implemented, would be insufficient to protect vital

station facilities to an external flood level of 1014 feet mean sea level, as described in the Fort

Calhoun Station Updated Safety Analysis Report and station procedures. This finding was

assessed based on the best available information, including influential assumptions, using the

applicable significance determination process. The preliminary significance (Yellow) was based

on the extrapolated external flood frequencies established by the Fort Calhoun Station

Individual Plant Examination for External Events and credit given for use of a portable gas

powered pump system. Additional details of the primary assumptions associated with the

preliminary significance determination process are documented in Attachment 2 of the

enclosure.

The finding is also an apparent violation of NRC requirements and is being considered for

escalated enforcement action in accordance with the NRC Enforcement Policy. The current

Enforcement Policy is included on the NRC's Web site at

Omaha Public Power District -2-

Before we make a final decision on this matter, we are providing you an opportunity (1) to

present to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive

at the finding and its significance, at a Regulatory Conference or (2) submit your position on the

finding to the NRC in writing. If you request a Regulatory Conference, it should be held within

30 days of the receipt of this letter and we encourage you to submit supporting documentation

at least one week prior to the conference in an effort to make the conference more efficient and

effective. If a Regulatory Conference is held, it will be open for public observation. If you

decide to submit only a written response, such submittal should be sent to the NRC within 30

days of the receipt of this letter.

In accordance with NRC Inspection Manual Chapter 0609, we intend to complete our evaluation

using the best available information and issue our final determination of safety significance

within 90 calendar days of the date of this letter. The significance determination process

encourages an open dialogue between the NRC staff and the licensee. However, the dialogue

should not impact the timeliness of the staff's final determination.

Since the NRC has not made a final determination in this matter, a Notice of Violation is not

being issued for these inspection findings at this time. In addition, please be advised that the

number and characterization of apparent violations described in the enclosed inspection report

may change as a result of further NRC review.

If you have additional questions about NRC rules and processes, please contact Mr. Thomas

Farnholtz at (817) 860-8243.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosures will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at ~:...:.::..c:..:.:..;::=:...:.::..c=~",

~.::::::;:::.=..:..:=.:..:= (the Public Electronic Reading Room).

Sincerely,

Docket: 50-285

License: DPR-40

Enclosure:

NRC Inspection Report 05000285/20010007

w/Attachments: Attachment 1: Supplemental Information

Attachment 2: Phase 3 Analysis

Attachment 3: SPAR-H Worksheets

Attachment 4: Flooding Frequency Sensitivity

Attachment 5: Significance Determination Processes Combinations

Attachment 6: Additional Fault Trees

Omaha Public Power District - 3-

cc wiEnciosure:

Jeffrey A. Reinhart

Site Vice President

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

William Hansher

Manager - Nuclear Licensing

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

David A. Repka

Winston & Strawn

1700 K Street, NW

Washington, DC 20006-3817

Chairman

Washington County Board of Supervisors

P.O. Box 466

Blair, NE 68008

Ms. Julia Schmitt, Manager

Radiation Control Program

Nebraska Health & Human Services

Division of Public Health

P.O. Box 95026

Lincoln, NE 68509-5026

Ms. Melanie Rasmussen

Radiation Control Program Officer

Bureau of Radiological Health

Iowa Department of Public Health

Lucas State Office Building, 5th Floor

321 East 12th Street

Des Moines, IA 50319

Chief, Technological Hazards Branch

FEMA, Region VII

9221 Ward Parkway

Suite 300

Kansas City, MO 64114-3372

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 50-285

License: DPR-40

Report Nos.: 05000285/2010007

Licensee: Omaha Public Power District

Facility: Fort Calhoun Station

Location: 9610 Power Lane

Blair, NE 68008

Dates: February 9,2010 (Onsite)

April 13, 2010 (Onsite)

January 1, 2010 - June 14, 201 0 (In-Office)

Lead Inspector: G. George, Reactor Inspector, Engineering Branch 1

Inspectors: J. Kirkland, Senior Resident Inspector, Fort Calhoun Station

M. Williams, Reactor Inspector, Plant Support Branch 2

Others: G. Replogle, Senior Reactor Analyst, Division of Reactor Safety

D. Loveless, Senior Reactor Analyst, Division of Reactor Safety

Approved By: Thomas Farnholtz, Branch Chief, Engineering Branch 1

- 1- Enclosure

SUMMARY OF FINDINGS

IR 05000285/2010007; 01101/2010 - 06/21/2010; Fort Calhoun Station: Inspection Procedure 92701, Followup.

The report covers a 6-month period of followup inspection by regional based inspectors from the

NRC Region IV office. One apparent violation of NRC requirements with potential substantial

(Yellow) safety significance was identified. The significance of most findings is indicated by their

color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." Findings for which the significance determination process does not

apply may be Green or be assigned a severity level after NRC management review. The NRC's

program for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006.

A. NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Mitigating Systems

  • Yellow. The inspectors identified an apparent violation of Technical

Specification 5.8.1.a, "Procedures," for failure to establish and maintain

procedures that protect the intake structure and auxiliary building during external

flooding events. The inspectors determined that the procedural guidance of GM-

RR-AE-1002, "Flood Control Preparedness for Sandbagging," was inadequate

because stacking and draping sandbags at a height of four feet over the top of

floodgates would be insufficient to protect the vital facilities to 1014 feet mean

sea level, as described in the Updated Safety Analysis Report and station

procedures. The licensee has entered this condition into their corrective action

program as Condition Report 2010-2387. As result of this violation, the licensee

has implemented a corrective action plan to correct identified deficiencies and

ensure site readiness.

This performance deficiency is more than minor because it adversely affected the

Mitigating Systems Cornerstone attribute of external events and affected the

cornerstone objective of ensuring the availability and reliability of systems that

respond to initiating events to prevent undesirable consequences. The

inspectors determined the finding resulted in the degradation of equipment and

functions specifically designed to mitigate a flooding initiating event. In addition,

an external flood event would degrade two or more trains of a multi-train safety

system. Therefore, the finding was potentially risk significant to flood initiators

and a Phase 3 analysis was required. The preliminary change in core damage

frequency was calculated to be 3.1 E-5/year indicating that the finding was of

substantial safety significance (Yellow). The finding was determined to have a

crosscutting aspect in the area of problem identification and resolution, corrective

action program, for failure to take appropriate corrective actions to address safety

issues and adverse trends in a timely manner, commensurate with their safety

significance and complexity. Specifically, from 2003 to 2008, the licensee failed

to initiate appropriate corrective actions to ensure reguiatory compiiance of the

external flooding design basis was maintained. [P.i (d)] (Section 40A5.i)

-2- Enclosure

REPORT DETAILS

40A5 Other Activities

.1 IP 92701, "Followup": URI 05000285/2009006-03, "Failure to Update Flood Protection

for Safety Related Buildings"

a. Inspection Scope

As documented in NRC Inspection Report 2009006, the NRC inspectors identified an

unresolved item concerning external flood protection for plant areas considered vital to

allow the reactor to achieve cold shutdown. The unresolved item concerned: (1) the

ability of the licensee to protect the Fort Calhoun Station auxiliary building, intake

structure, and turbine building basement from external floods up to flood elevation 1013

feet mean sea level* (MSL) as stated in the Updated Safety Analysis Report (USAR) and

station procedures; and, (2) upon receiving new flooding information in November 2003,

if the licensee was required to update the USAR.

Because further inspection was necessary, the issue was considered an unresolved item

pending further NRC Region IV review. The NRC Region IV review was to determine:

1. If the failure to meet the self-imposed standard of flood protection up to 1013 feet

MSL * is a performance deficiency in accordance with NRC Manual Chapter 0612.

2. If a violation of NRC requirements is associated with the performance deficiency

because the licensee did not update the external flood design basis when new

information was received in November 2003.

  • Note: During this inspection, the inspectors determined that the Fort Calhoun

Station original USAR described protection of the facility up to 1014 feet MSL.

This unresolved item was identified as URI 05000285/2009006-03, "Failure to Update

Flood Protection for Safety Related Buildings." Based on followup inspections

conducted at the Fort Calhoun Station and the NRC Region IV office, the inspectors

determined that no further inspection is necessary. Therefore, URI

05000285/2009006-03 will be closed. Findings are documented in the following section.

b. Findings

Failure to Maintain External Flood Procedures

Introduction. The inspectors identified a Yellow, apparent violation of Technical

Specification 5.8.1.a, "Procedures," for failure to establish and maintain procedures that

protect the intake structure and auxiliary building during external flood events.

Specifically, stacking and draping sandbags on floodgates IS not a suffiCient

configuration to protect the auxiliary building and intake structure to an external flood

height of 1014 feet MSL as stated in station operating procedures and the USAR.

-3- Enclosure

Description. The inspectors determined design basis flood elevations at the Fort

Calhoun Station by reviewing USAR Chapter 2.7, "Hydrology," USAR Chapter 9.8, "Raw

Water System," and Technical Specification 2.16, "River LeveL"

USAR Section 2.7.1.2 states, in part:

"The design flood elevation of 1,006 feet based on a 0.1 percent probability

flood is considered conservative. Without special provisions, the plant can

accommodate flood levels of up to 1,007 [feet mean sea level]. Steel flood

gates are permanently mounted above and adjacent to openings in structures

containing equipment required for a safe and orderly plant shutdown. In the

event of high water levels, these flood gates can be installed to provide

protection to a level of 1,009.5 [feet mean sea level]. In the Intake Structure,

protection to 1009.5 [feet] MSL is accomplished with flood gates and

sandbagging. The plant can be protected by sandbags, temporary earth

levees and other methods to allow a safe shutdown with a flood elevation of

1,013 [feet mean sea level]."

USAR Section 9.8.6 states, in part:

"Protection for the raw water pumps and their drives against floods is

provided at three elevations as indicated on Figure 9.8-1. The pumps are

permanently protected against any water level up to elevation 1007.5 feet

MSL by the Class I concrete substructure of the intake building. Protection is

provided to elevation 1009.5 [feet MSL] by sandbags around the traveling

screen areas and by gasketed steel closures at exterior doorway openings in

the intake structure reinforced concrete perimeter walls. Protection to

elevation 1014.5 feet [MSL] is provided by additional sandbags around the

traveling screen areas, and by supplementing the intake structure perimeter

walls with sandbags. The water level inside the intake cells can be controlled

by positioning the exterior sluice gates to restrict the inflow into the cells."

Technical Specification 2.16, "Basis," dated November 1, 2007, states:

"The maximum Missouri River level of 1009 feet MSL is the level at which the

installed flood gates will protect the plant. Any increase in river level will

require sand bagging to repel the water to a maximum flood level of 1014 feet

[MSL] or greater."

When the licensee determines it is necessary to protect the plant at elevated flood

levels, the licensee implementsSection I of procedure AOP-1, "Acts of Nature." AOP-1

is a procedure required by Technical Specification 5.8.1.a and NRC Regulatory Guide 1.33, Appendix A, Section 6.w. AOP-1 directs the licensee to implement applicable

sections of procedures PE-RR-AE-1 001, "F!oodgate !nstallation and Removal," and GM-

RR-AE-1002, "Flood Control Preparedness for Sandbagging," when river levels reach

specified heights of 1002, 1004, 1007, and 1009 feet MSL.

- 4- Enclosure

GM-RR-AE-1002, step 7.4 states:

"The primary focus for flood protection should be directed to those facilities

which are considered vital with respect to nuclear safety and credited with

flood protection in the Individual Plant Examination of External Events

Flooding evaluation, Reference 2.3. These facilities shall be protected at the

sacrifice of the other facilities if site conditions warrant. The vital facilities are:

Auxiliary Building, Intake Structure, and Turbine Building Basement."

Reference 2.3 of procedure GM-RR-AE-1002 is the Individual Plant Examination of

External Events for Fort Calhoun Station, Section 5.2, "External Flooding," Table 5.2.3.

This table credited flood protection by sandbagging up to 1010.8 ft MSL for the turbine

building and up to 1013.5 feet MSL for the auxiliary building and intake structure. Table

5.2.3, "Impact of Periodic Flood due to Rain and Snow," comments that "severe core

damage results if either intake or auxiliary building sandbagging fails." The turbine

building, which does not contain safety related equipment necessary for safe shutdown,

was assumed lost at floods greater than 1010.8 feet MSL.

Attachment 9.5 of procedure GM-RR-AE-1002 contains specific instructions that plant

operators would use to protect from flood crest above 1009 feet mean sea levei. The

attachment notes that sandbags would be tied and draped over the top of floodgates to

supplement the protection capability to the projected flood crest. Specifically, the

attachment stated, "Place additional sandbags on top of the floodgates to raise the

protection against the expected crest of the flood." Additionally, Attachment 9.8 of

GM-RR-AE-1002 stated the intake structure and auxiliary building could be protected to

1014.5 feet MSL with floodgates and sandbags.

The inspectors requested a demonstration of flood protection for vital facilities against

flood levels above the probable maximum flood level of 1009 feet MSL. As a result of

this demonstration, the inspectors determined that the procedural guidance of GM-RR-

AE-1 002 was inadequate because stacking and draping sandbags at a height of five feet

over the top of floodgates would be insufficient to protect the vital facilities to 1014 feet

MSL, as described in the USAR and station procedures. The sandbagging activity

would be insufficient because the %-inch cross section on the top of the floodgates was

too small to support a stacked sandbag configuration that would retain five feet of

moving water. Therefore, the inspectors determined that a failure of the sandbags would

cause potential damage to the auxiliary building, intake structure, and turbine building

and their equipment at external flood levels above 1009.5 feet MSL.

The inspectors also identified plant personnel would need to take additional action to

prevent flooding through the traveling screen discharge trench in the intake structure or

the intake structure would be potentially lost at a flood level of 1008 feet MSL.

Furthermore, the inspectors determined that any actions taken per AOP-1 could be

difficult because of the risk to personnel safety when flood waters are within the

protected area.

While reviewing the Fort Calhoun Station design basis, the inspectors discovered the

licensee missed several opportunities to implement appropriate corrective actions when

new external flood information was available. The failure to implement appropriate

corrective actions directly contributed to the licensee's failure to identify inadequacies in

their external flood procedures and strategy.

-5- Enclosure

As documented in Condition Report 2002-1296, the licensee obtained external flood

information from the Federal Emergency Management Administration and an Army

Corps of Engineers letter to Omaha Public Power District (OPPD), dated January 14,

1993. The information estimated projected flood elevations to be three feet greater than

the flood elevations described in the original USAR. The corrective actions were to

evaluate the information to determine if the design basis and procedures would need to

be updated. The licensee determined that the design basis would remain the same;

however, a USAR change would reflect that an evaluation of the new information's

impact on the design basis was completed. A USAR change was submitted to the NRC

in January 2008, but no change to operating procedures was initiated.

During the evaluation associated with Condition Report 2002-1296, the licensee

identified that more recent external flood information was available from the Army Corps

of Engineers. In July 2003, the licensee identified that external flood frequencies and

associated Missouri River levels evaluated in the 2003 draft version of Army Corps of

Engineers report, "Upper Mississippi River System Flow Frequency Study (final version

January 2004)," had increased since last evaluated the Army Corps of Engineers letter

to OPPD, dated January 14, 1993. This condition was entered into the corrective action

program as Condition Report 2003-2664.

The licensee's corrective action tasked the licensee's probabilistic risk assessment

group to evaluate the new 2003 external flood data, update the existing external flood

analysis, and develop a set of recommended strategies to mitigate high risk external

flood scenarios. This external flood analysis was completed in August 2005. The

licensee realized the new flood elevations were approximately three feet higher for each

flooding frequency. Additionally, when the 2003 data was extrapolated to a 1000-year

flood frequency, the licensee found the 1OOO-year flood elevation to be 1010.5 feet MSL.

Following this discovery, the licensee updated the external flood analysis in 2005;

however, no corrective action was written to evaluate the potential change to the plants

design basis or operating procedures. Consequently, the 2005 external flood analysis

was not mentioned in the USAR change initiated in January 2008. Furthermore, the

licensee did not develop a corrective action plan to ensure the design basis and

regulatory compliance was maintained, as required by corrective action program.

Analysis. The inspectors determined the failure to establish and maintain adequate

procedures to protect the auxiliary building and intake structure to external flood heights

between 1008 and 1014 feet MSL is a performance deficiency. Specifically, the licensee

failed to maintain procedures for combating a significant flood as recommended by NRC

Regulatory Guide 1.33, Appendix A, Section 6.w, "Acts of Nature." This performance

deficiency is more than minor because it adversely affected the Mitigating Systems

Cornerstone attribute of external events and affected the cornerstone objective of

ensuring the availability and reliability of systems that respond to initiating events to

prevent undesirable consequences. The inspectors determined the finding resulted in

the degradation of equipment and functions specifically designed to mitigate a flooding

i_i-f*i,.,,+i __ _ ,It'... _... 1_ _ ,..Irli+i __ ",, _ _ V'+_ ... __ I +1 __ ......1 _~, _ _ ... ,.,_III,J -I __ ... _,.l_ oh .. , _ _ ... --.. ___ ... __ :_ ..... _.t:

IIlI1.Io.llIl~ CiVCilll. III aUUILIVII, CUI v A l v f l t O I ItVVU eVC;lll VVVUfU Uv~lauv l,VVV VI IIIUIIf;;J lIeUlf.::;) VI

a multi-train safety system. Therefore, the finding was potentially risk significant to flood

initiators and a Phase 3 analysis of the significance determination process was required.

-6- Enciosure

A Region IV senior reactor analyst performed the Phase 3 significance determination.

The preliminary change in core damage frequency was calculated to be 3.1 E-5/year

indicating that the finding was of substantial safety significance (Yellow). The risk

important sequence included a station blackout, loss of all dc power, failure of the

turbine-driven auxiliary feedwater pump, and failure of the diesel-driven auxiliary

feedwater pump. Remaining mitigation equipment that helped to limit the significance

included the licensee's temporary gasoline powered pump system that can provide

makeup water to the steam generators.

The inspectors determined the finding has a crosscutting aspect in the area of problem

identification and resolution, corrective action program, for failure to take appropriate

corrective actions to address safety issues and adverse trends in a timely manner,

commensurate with their safety significance and complexity. Specifically, from 2003 to

2008, the licensee failed to initiate appropriate corrective actions to ensure regulatory

compliance of the external flood design basis was maintained. [P.1 (d)]

Enforcement. Technical Specification 5.8.1.a, "Procedures," states, "Written procedures

and administrative policies shall be established, implemented, and maintained covering

the following activities: (a) The applicable procedures recommended in Regulatory

Guide 1.33, Revision 2, Appendix A, 1978." From 1976 to 1978, Fort Calhoun Station

established written procedures recommended by NRC Regulatory Guide 1.33, Appendix

A, Revision 1. NRC Regulatory Guide 1.33, Appendix A, Section 6 recommends

procedures for combating emergencies and other significant events. Section 6.w, "Acts

of Nature" recommends procedures for combating tornado, dam failure, flood, and

earthquakes. Contrary to Technical Specification 5.8.1.a and NRC Regulatory Guide

1.33, since 1976, the licensee failed to maintain written procedures for combating a

significant flood as recommended by NRC Regulatory Guide 1.33, Appendix A, Section

6.w, "Acts of Nature." Specifically, the licensee failed to establish and maintain station

procedures that adequately prescribe steps to mitigate external flooding conditions in the

auxiliary building and intake structure between 1008 and 1014 feet mean sea level. The

licensee has entered this condition into their corrective action program as Condition

Report 2010-2387. Pending completion of a final significance determination, the

performance deficiency will be considered an apparent violation, AV 05000285/2010007-

01, "Failure to Maintain External Flood Procedures."

40A6 Meetings

Exit Meeting Summary

On June 21, 2010, the inspectors presented the inspection results to Mr. J. Reinhart, and

other members of the licensee staff. The licensee acknowledged the issues presented.

The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was identified.

-7- Enclosure

SUPPLEMENTAL !NFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

H. Faulhaber, Manager, Nuclear Engineering

M. Frans, Manager, System Engineering

J. Gasper, Manager, Design Engineering

D. Guinn, Supervisor, Regulatory Compliance

A. Hackerott, Supervisor, Risk Engineering

J. Herman, Manager, Engineering Programs

K. Hyde, Supervisor, Design Engineering

T. Mathews, Manager, Nuclear Licensing

E. Matzke, Regulatory Compliance

T. Nellenbach, Plant Manager

J. Reinhart, Site Vice President

D. Trausch, Assistant Plant Manager

NRC Personnel

R. Azua, Senior Project Engineer, Projects Branch E

M. Markley, Chief, Plant Licensing Branch IV-1

J. Wingebach, Resident Inspector, Fort Calhoun Station

L. Wilkins, Project Manager, Plant Licensing Branch IV-1

W. Schaup, Project Engineer, Projects Branch E

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000285/2010007 -01 AV Failure to Maintain External Flood Procedures (40A5.1)

Closed

05000285/2009006-03 URI Failure to Update Flood Protection of Safety Related Buildings

DOCUMENTS REVIEWED

Section 40A5: Other Activities

PROCEDURES

NUMBER REVISION

AOP-1 Acts of Nature 23

AOP-30 Emergency Fill of Emergency Feedwater Storage Tank 9

EPIP-TSC-2 Emergency Plan Implementing Procedure: Catastrophic 7

Flooding Preparations

A1-1 Attachment 1

PROCEDURES

NUMBER TITLE REVISION

FCSG-24 Corrective Action Program Guideline 22

GM-RR-AE-1002 Repair-Rework: Flood Control Preparedness for Sandbagging 8

OCAG-1 Operation Contingency Action Guideline 12

PE-RR-AE-1001 Floodgate Installation and Removal 3

TBD-AOP-18 Loss of Raw Water 7

TBD-AOP-19 Loss of Shutdown Cooling 14

TBD-AOP-38 Blair Water Main Trouble 3

CALCULATIONS

NUMBER TITLE

CCF-103-048-RPT External Flooding Analysis August 12,2005

CORRECTIVE ACTION DOCUMENT NAME

200201296 200302664 200904166 201000225 201002101

201002387

MISCELLANEOUS DOCUMENTS

TITLE DATE

Fort Calhoun External Action Plan April 8, 2010

A1-2 Attachment 1

PHASE 3 ANALYSIS

FAILURE TO PROTECT SAFE SHUTDOWN EQUIPMENT FROM EXTERNAL FLOODING

A senior reactor analyst conducted a Phase 3 significance determination process (SOP)

analysis in accordance with Manual Chapter 0609, Appendix A, "Determining the Significance of

Reactor Inspection Findings for At-Power Situations." This Phase 3 SOP represents a best-

estimate risk evaluation of the performance deficiency.

1. SOP Assumptions

a. NRC Manual Chapter 0609, Appendix G, "Shutdown Operations Significance

Determination Process," was not used for this SOP. The appendix stated, in part:

"Appendix G is applicable during refueling outages, forced outages, and

maintenance outages starting when the licensee has met the entry

conditions for RHR [residual heat removal] and RHR cooling has been

initiated, and ending when the licensee is heating up and RHR has been

secured." [Emphasis added]

Since the initiating event would occur after RHR was secured by procedure (to prevent

a containment bypass pathway) and the reactor coolant system heated up to Mode 3

conditions, the at-power SOP was used for this case. Further, the finding would have

required a quantitative assessment (Phase 3) irrespective of which significance

determination procedure was used.

b. The analyst considered the increase in risk from flooding for the:

  • Intake structure: 1008 to 1014 feet mean sea level (MSL). The intake structure

housed raw water pumps (service water pumps).

  • Auxiliary building: 1010 to 1014 feet MSL. The auxiliary building was the

primary risk driver. Most of the equipment that was negatively impacted by the

performance deficiency was located in the auxiliary building - emergency diesel

generators, safety related switchgear, auxiliary feedwater pumps (basement),

safety injection pumps, etc.

c. The performance deficiency did not impact flooding of the turbine building. The licensee

did not protect the turbine building above 1009.5 feet MSL by procedure. The non-

safety related diesel-driven auxiliary feedwater pump was located in the basement.

d. Dam failures were not a factor in the performance deficiency, but could flood the site to

well above 1014 feet MSL. Flooding frequencies above 1014 feet MSL (Technical

Specification Bases 2.16 specified elevation) were not considered.

e. The performance deficiency existed for many years. Therefore, in accordance with

Manuai Chapter 0609, Appendix A, Attachment oj, Usage Ruie i:i, "Exposure Time," the

analyst determined that the exposure period was one year.

f. When the auxiliary building, turbine building and intake structure were assumed lost, the

conditional core damage probability (CCDP) was 1.0. This was expected because all

A2-1 Attachment 2

normal plant equipment was assumed failed by the floodwaters. This did not include

credit for the portable gasoline powered pumps to refill the steam generators. A

correction to account for gasoline-powered pump failure was addressed separately.

Consequently, the SOP reduced to: (1) the flooding frequencies; (2) the gasoline

powered pump system failure probability; and (3) comparison to the baseline risk

assuming a 10 percent probability that the sandbagging protection failed.

g. A fault tree to estimate the failure probability for the gasoline-powered pumps was

constructed and solved using the simplified plant analysis risk (SPAR) model. After

flooding greater than 1010 feet MSL, the gasoline powered pumps would be the only

equipment available to provide makeup water to the steam generators. The fault tree

assumed:

III Both pumps must function for the action to be successful.

III Human error probabilities associated with installing the gasoline powered pump

system were evaluated using NUREG/CR 6883, "The SPAR-H Human Reliability

Analysis Method," August 2005 (Attachment 3). From this evaluation, the analyst

inserted a human error probability basic event into the system fault tree. The

SPAR-H worksheets were broken up into two sections, a "diagnosis" section and

an "action" section. The diagnosis section evaluated the probability that

operators would fail to diagnose the problem, such that mitigating actions would

not be taken. The action section estimated the probability that operators (or

craftsmen) would fail to successfully install and operate the system.

II The analyst assumed that operators would properly diagnose the flood.

  • The "action" portion of the SPAR-H worksheet was much more difficult to

perform and the probability of failure was over-riding (when compared to

the diagnosis portion).

III The analyst used the licensee's estimates for gasoline pump failure probability.

  • Other basic components that would have very low failure probabilities, such as

manual isolation valves, were not included in the fault tree.

III The action to obtain sufficient fuel for long-term pump operation was not

modeled. While the licensee had a procedural step that instructed personnel to

obtain gasoline, no other specifics were provided. The pumps' gasoline

consumption was not readily known and the exact methods that might be used to

obtain gasoline were unclear. Gasoline was on-site, located in an above ground

tank at the 1004-foot elevation; however, flooding may make the tank

inaccessible (it could float away). Nonetheless, the analyst assumed that plant

personnel could obtain sufficient gasoline without undue difficulty.

A2-2 Attachment 2

h. The licensee's Individual Plant Examination of External Events (page 5-23) contained

the following assumptions. The second, third and fourth table columns specified the

assumed failure probabilities for equipment located in the buildings:

Elevation Intake Turbine bldg Aux bldg

(ft MSL)

1007.5-1009.5 0 0 0

1009.5-1010.8 .01 .05 0

1010.8-1012.3 .1 Lost .1

1012.3-1013.5 .9 Lost f"\

.::3

Notes:

i. The licensee had assumed a sandbagging failure probability of 0.9 for flood

elevations between 1012.3 and 1013.5 feet MSL. The analyst considered this

assumption unreasonable for use in a base case evaluation. A base case

evaluation is an assessment of the baseline risk, assuming that no performance

deficiency occurred. If the performance deficiency did not exist, the licensee

should have had a high level of assurance that mitigating actions (sandbagging)

would be successful. For the purpose of this analysis, the sandbagging base

case failure probability was assumed to be 0.1 when flood waters were above

1010.8 feet MSL.

ii. A current case evaluation is a risk estimate that includes the performance

deficiency. The current case evaluation assumed that the sandbagging failed at

1008 feet MSL at the intake structure and at 1010 feet MSL at the auxiliary

building. The delta-core damage frequency (CD F) was the difference between the

base case and current case risk evaluations.

2. Calculation of Increase in CDF

a. Equipment lost because of the performance deficiency: The analyst identified the risk

important pieces of equipment and when they would fail. This was accomplished by

reviewing site procedures and interviewing licensee personnel.

Elevation {feet MSL} Performance Deficienc~ ImQact

1007.5 - Intake Structure Floor Some water leaks into intake

structure. Sandbag berms within the

building should limit the affect of

short duration crests. The analyst

assumed that significant flooding

would occur at 1008 feet MSL.

1008 - Loss of offsite power (LOOP) and Loss of all four raw water pumps.

loss of intake structure due to flooding (The LOOP was unrelated to the

I performance deficiency).

A2-3 Attachment 2

Elevation ,feet MSL} Performance Deficienc~ Im12act

1009.5 - Top of auxiliary building floodgates Flooding starts in auxiliary building,

and turbine building sandbags. The diesel- turbine building and technical support

driven auxiliary feedwater pump was located center above 1009.5 feet MSL. The

in turbine building basement. All other analyst assumed that small crests

remaining equipment (other than the above 1009.5 feet MSL would not

gasoline-powered pumps) was located in the result in substantial flooding in the

auxiliary building (pumps in the basement). buildings.

1010 - 0.5 feet above floodgate All remaining normal plant equipment

lost because of the performance

deficiency.

1011 - Level when procedures estimate that

floodwaters spill into emergency diesel

generator rooms (assuming drains are

appropriately plugged). The building

structure prevents water from entering at

lower elevations. However, switchgear is

already lost.

b. Base case and current case CCOPs: The analyst calculated the base and current case

CCOPs using the Fort Calhoun SPAR model, Revision 3.45, assuming a truncation limit

of 1E-13. This portion of the analysis did not credit the gasoline-powered pumps, as the

SPAR model did not include the pumps. The gasoline-powered pumps were factored

into the final SOP by use of a separate fault tree (Attachment 6).

  • Base case CCOP for each flood elevation: Assuming no performance deficiency and

no credit for gasoline-powered pumps. Credit for the gasoline powered system was

provided later in this SOP:

Elevation{ft MSL} CCDP Egui(;!ment Lost l Increased Probabilit~

1008-1009.5 1.017E-3 Non-recoverable LOOP initiating event

1009.5-1010.8 1.046E-3 Non-recoverable LOOP initiating event

Probability of raw water pump failure (.01),

Probability of diesel driven auxiliary

feedwater pump failure (.05)

1010.8-1014 1.1 E-1 Non-recoverable LOOP initiating event;

Probability of raw pump failure (0.1),

Probability of diesel driven auxiliary

feedwater pump failure (1.0), Probability of

emeraencv diesel aenerator failure (0 1)

_ J _ '- "

Probability of auxiliary feedwater pump

failure (0.1)

A2-4 Attachment 2

3 Current case CCOP for performance deficiency elevations: No gasoline pumps were

provided in this step. Increased failure rates because of the performance deficiency

are in bold:

Elevation{ft MSL} CCDP Egui~ment Lostz Increased Probabilit1!

1008 -1010 1.25E-3 Non-recoverable LOOP, Probability of

diesel driven auxiliary feedwater pump

failure (.05). Probability of raw water

pump failure (1.0)

1010 -1014 1.0 Non-recoverable LOOP; Probability of

diesel driven auxiliary feedwater pump

failure (1.0), Probability of 4kV

switchgear failure (1.0), Probability of

all auxiliary feedwater pumps failing

(1.0)

c. Calculation of Increase in COF: To obtain consistent elevation bins for analysis, the

above bins must be broken up further. The frequency for a given elevation bin (A) was

the difference in the frequency of exceedance between the upper and lower bin

elevation limits.

Delta CDF = 2:: Abin * (CCDP current - CCDP base) * Pgas pump fail

Elevation {ft A CCDP CCDP base Pgas HumH fail Delta Time After

MSL) current CDF/bin 1004 ft

MSL*

1008-1009.5 3.2E-3/yr 1.25E-3 1.017E-3 2.56E-2 1.9E-8/yr 30 hrs

1009.5-1010 4E-4/yr 1.25E-3 1.046E-3 2.56E-2 2.1 E-9/yr 41.25 hrs

1010-1010.8 8E-4/yr 1.0 1.04E-3 2.56E-2 2E-5/yr 45 hrs

1010.8-1014 5E-4/yr 1.0 1.1 E-1 2.56E-2 1.1 E-5/yr 51 hrs to

75 hrs

Total 3.1E-5/yr

  • Based on licensee's flood level increase rate of 4ft/30 hours

3. Sensitivit1! Cases

a. Operator can prevent intake structure flooding until 1010 feet MSL. This would assume

that an operator could successfully maintain intake structure level, using raw water

pumps and sluice gates, to prevent water from flooding through the traveling screen

discharge trench. This had little impact on the SOP results. The first two delta-COF

A2-5 Attachment 2

elevation bins capture this aspect of the assumed event. Setting both to zero would

reduce the de!ta-CDF by about 2E-B/yr.

b. Flooding freguencies differ by significant amounts. The uncertainty with the flooding

frequencies was high. The licensee used the shape of the flooding frequency curve at

another station (Cooper Nuclear Station) and applied it to the Fort Calhoun Station

flooding frequencies that were provided by the United States Army Corps of Engineers.

The Army Corps of Engineers only provided information out to the 500-year flood

(2E-3/year). The licensee extrapolated the remainder of the information. Almost all of

the calculated risk was in the extrapolated region. To address this uncertainty, the

analyst assumed that the Army Corps of Engineers data was correct but the

extrapolated information could vary significantly, either higher or lower.

For the sensitivity cases, the analyst targeted the flooding elevation at the 1E-5/year

point for comparison. At the 1E-5/year point on the Fort Calhoun flood hazard curve, the

flood level was 1013.5 feet MSL. The analyst then constructed alternate curves, two

above and two below this base curve. The curves are shown in Attachment 4. The

curves were numbered Case 1 through Case 5. Case 3 was the licensee's estimate and

was considered the best available information for this assessment.

Using data from the 5 curves, the analyst generated a delta-CDF for each case. The

analyst summarized the results below:

Delta-CDF by Sensitivity Case

Case 2 Case 5

2.5E-5/year 3.5E-5/year

  • Licensee assumptions

It's important to note that Case 1 may be unrealistically low. After almost 100,000 years

of additional exposure, the flood elevation at the1 E-5/year point was a little over 1 foot

above that predicted by the Army Corps of Engineers at the 1/500 year point. Likewise,

Case 5 may be unrealistically high. The plotted line deviates from the Army Corps of

Engineers' estimates at a sharper angle.

c. Alternate Method of Refilling Essential Feedwater Tank (SPAR-H 2, Attachment 3): The

licensee proposed an alternate method for refilling the essential feedwater tank. The

offsite fire water tank (at a higher elevation across the highway) could be used to refill

the essential feedwater tank. The advantage of using this tank was that the reliance on

the gasoline-powered pumps would be reduced. Instead of requiring that both gasoline

powered pumps remain functional (one to fill the steam generators and one to refill the

essential feedwater storage tank), the licensee could have one pump fail and still satisfy

the steam generator makeup function.

The alternate fill method required operators to attach a fire hose between fittings that

could be used to connect the two tanks. It also required that the licensee have water

trucks periodically refill the firewater tank. The procedure that drove these actions was

normally performed following a loss of the Blair water supply. The procedural steps to

use the firewater tank to refill the essential feedwater storage tank would be

implemented after other sources of water became unavailable (it was the last option on

the list). The floodwater was expected to eliminate the following water sources, as

A2-6 Attachment 2

specified: (1) demineralized water system (1008 feet MSL); (2) condensate storage tank

(1008 feet MSL); (3) Blair water (1007 feet MSL); (4) the diesel-driven auxiliary

feedwater pump (1009.5 MSL); and (5) the on-site plant fire water system (1008 feet

MSL). Therefore, operators would not likely initiate these actions until the 1009.5-foot

elevation. At this flood level, two of the components that would require connection (with

a fire hose) would be under water.

To evaluate the scenario, the analyst adjusted the gasoline power pumps system fault

tree so that a failure of both fire pumps would be needed to fail the system (not just one

pump). The analyst added a new basic event to account for the human error probability

for the new manual actions. The analyst also made other adjustments to model use of

the firewater tank. The adjusted fault tree is shown in Attachment 6, second fault tree.

As shown in the SPAR-H worksheet (Attachment 3, SPAR-H-2) the assumptions for the

new human error probability included nominal available time, high stress (fittings hard to

find and work under water), moderate complexity, low experience (connecting fittings

under water), nominal procedures, missing/misleading ergonomics (location of fittings

under water), nominal fitness for duty, and nominal work processes. Instead of a failure

probability of 2.56E-2 for the failure of the gas pump system, a failure probability of

1.3E-2 was generated. This would reduce the overall delta-COF by a factor of two. The

resultant delta-COF was 1.5E-5/year. However, since the challenge of locating and

manipulating components under water invoked large uncertainties, this action was not

credited in the SOP.

d. Use of Tabletop Generated, Non-Procedural Actions: The licensee asked the NRC to

credit non-proceduralized actions that were identified during a tabletop exercise

(installing metal plates over auxiliary building doorways). The licensee's probabilistic

risk assessment team had not credited this action in an analysis themselves.

In response to the finding, the licensee conducted a tabletop exercise to determine what

actions might be specified by the technical support center during a simulated flood. The

tabletop team determined that metal plates could be installed over auxiliary building

doors (on the water side). They specified that thick metal plates would be needed (3/4"

to 1" thick), that craftsmen would weld supporting structures to the plates and that the

plates would be secured, but not welded, to the outside of the doorways. The analyst

noted that it was unclear if the actions would work, and they could cause failure of

existing flood barriers before 1009.5 feet MSL (the leak tight floodgates and sandbag

berms would have to be removed). The NRC's "Risk Assessment of Operational Events

Handbook," Revision 1.03, Section 6.3.2 stated, in part:

In general, no recovery or repair actions should be credited where ... there is no

procedure or training. It may be possible to justify exceptions in unique

situations, such as a procedure is not needed because the recovery is skill of the

craft. ..

Still, the analyst used the SPAR-H method to evaluate the action. The SPAR-H

worksheet (see Attachment 3, SPAR-H-3) documented that the failure probability was

very close to 1.0. To implement the proposed actions, craftsmen would need to

construct and erect about 10 covers for doors, including some double doors and at least

one rollup door. The licensee did not have an adequate supply of the thick plates on site

to cover all of the doors. However, an abundant supply of thinner plates, some 3/8-inch

A2-7 Attachment 2

thick and other rough deck plate material, were available. The yard that housed the

plates was outdoors and the ground was covered with gravel, not asphalt

(1005 feet MSL). The technical support center was not manned until floodwaters were

near the yard elevation (1004 feet MSL); therefore, floodwaters may already be in the

yard before meaningful recommendations could be made. If floodwaters entered the

yard, getting the plates to a location to support cutting and welding may be difficult.

There were experienced welders onsite, but only three welding machines were available

that could be operated on the three available portable electric generators. A loss of

offsite power was expected at 1008 feet MSL. Cutting the plates to size would require a

cutting machine that may not be available after a loss of offsite power.

No method was specified for installing the plates, but the team determined it was

necessary to install them on the water side of the doors (to let the water pressure help

keep them in place). To do this, at least some floodgates would likely need to be

removed. The tabletop team specified that they would not weld the plates to the

doorways. The current floodgates had rubber seals (some inflatable) to help prevent in-

leakage, while the new plates would not have this feature. This would introduce a new

failure mechanism not previously considered (substantial leakage past a plate at an

elevation below 1009.5 feet MSL).

Flood projections often change and are rarely accurate. If the flood projections started

out below 1009.5 feet MSL and then increased, floodwaters may be upon the floodgates

(and sandbag berms) already, making removing them unmanageable. The bottoms of

some auxiliary building floodgates sat at approximately 1007 feet MSL. Large sandbag

berms would need to be removed from several doors.

Alternate Evaluation: The analyst also performed an alternate evaluation (Attachment 3,

SPAR-H-3, Method 2), assuming that the licensee could be successful installing plates

over auxiliary building doors 50 percent of the time. Assuming this chance of success,

however, the delta-COF would be reduced by a factor of two. No formal credit was

provided in the SOP.

4. Large Early Release Frequency (LERF):

Nominally, for large dry containments, the delta-LERF was less than 0.1 times the delta-

COF. However, the loss of all control room indications would make it more difficult to

obtain the information needed to insure a timely public evacuation. The NRC processes

to evaluate delta-LERF were not well suited for this finding. The analyst consulted with a

LERF expert in the Office of Nuclear Reactor Regulation. The expert indicated that

because of the large dry containment, and the relatively large pressure failure rating of

containment, that a large amount of time would be available to evacuate the public. The

analyst then spoke with regional emergency preparedness experts and found that the

licensee had alternate means to identify core damage (radiation levels outside of

containment). Further, the analyst reviewed Fort Calhoun Emergency Classification

levels and noted that a general area emergency would be declared if - "conditions exist

which in the judgment of the command and control position warrant declaration of a

General Emergency." In conclusion, the analyst qualitatively determined that the color of

the delta-LERF would not exceed that associated with the estimated delta-COF.

A2-8 Attachment 2

SPAR-H WORKSHEETS

1. SPAR-H-1

Refill Steam Generators Using Gasoline Puml2s {Onl~}

Performance Shal2ing Diagnosis Action

Factor

PSF Level Multil2lier PSF Level Multil2lier

Time Expansive 0.01 >5 times required 0.1

Stress Nominal 1.0 High 2.0

Complexity Nominal 1.0 Moderate 2.0

Experience Nominal 1.0 Nominal 1.0

Procedures Nominal 1.0 Nominal 1.0

Ergonomics Nominal 1.0 Poor 10.0

Fitness for Duty Nominal 1.0 Nominal 1.0

1W0rk Processes Nominal 1.0 Nominal 1.0

Nominal Base 1.0E-2

PSFs 1.0E-2 4.0

frotal 1.0E-4 4E-3

Failure Probability 4E-3

Justifications for Action (over-riding), only items that del2arted from nominal:

Time: Greater than 5 times necessary. The river was expected to rise at a rate of four

feet in 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. The licensee would expect an approximate two-day notice of a river

crest at 1009 feet MSL or higher, assuming that the licensee started taking actions at

1000 feet MSL and received early warning of the coming flood. The analyst assumed

that the turbine building would be flooded at approximately 1009.5 feet MSL. Plant

personnel should start installing the gasoline powered pump system when the Army

Corps of Engineers projects flooding at or above 1009 feet MSL. The procedure for

installing the system was detailed, all of the equipment was staged, and plant personnel

should be able to assemble the equipment in less than one shift without much difficulty.

Testing of one pump could only be accomplished after the floodwaters enter the turbine

building. While this would occur after the loss of offsite power, the operators should

have substantial time before the essential feedwater storage tank emptied.

Stress: High. Once installed, operation of the gasoline pump system would rely on

alternate methods of measuring steam generator water level. Operators could either

use a portable instrument to determine steam generator water level or overfill the steam

generators and wait a given amount of time before the next filling evolution. The turbine

building would be dark and uncomfortable.

Tho

      • -

occonti~1 fot=>';IAI~tt=>r ct{"\r~nt=> t~nk \hI{"\1

- - - - ..... - * * __ ......... _ .. _ * ............ -::::1 ...... _ .....

II'; .*

~,,--.-

nt=>t=>,; t() ht=> rt=>fillt=>,;

_ - - "'- - - . - *..* _ -

Ie: \J\It=>1I Thp nllmn

- - --_ * * . * * . - r--****I

t()

~-

refill this tank must be located close to the floodwaters. When floodwaters increase, the

pump would need to be moved to a higher elevation. Failure to do so could cause the

gasoline engine to fail. The reliance on this temporary system to prevent core damage,

A3-1 Attachment 3

with minimal indications of reactor coolant system or containment conditions, would

contribute to the stress level.

Complexity: Moderately complex. Craftsmen would need to remove piping flanges and

install new components that were manufactured to fit into the piping locations, which

may be difficult. Some of the pieces were heavy. At approximately 1008 feet MSL, the

plant would experience a loss of offsite power and the turbine building would lose

artificial lighting and normal electrical power. While the system could be installed into

position earlier, the system would need to be filled and tested to ensure that the pumps

were not vapor-locked. The pump that was to refill the essential feedwater storage tank

would take suction from the floodwaters, which would not enter the turbine building prior

to the loss of offsite power. Operators would need to ensure that the pump was

sufficiently close to the water level to allow for proper suction and filling.

Ergonomics: Poor. The analyst determined that the ergonomics for implementing

Procedure PE-RR-AE-1002, "Installation of Portable Steam Generator Makeup Pumps,"

Revision 2, were "Poor." For system startup and subsequent operation, operators and

maintenance personnel would be working under emergency lighting conditions or

possibly in the dark. Workers would complete their tasks around and in flood waters.

Operations would involve routine handling of gasoline. No procedural steps were

provided to instruct the operators how to obtain or where to store the gasoline, so these

actions would need to be developed. Operators would periodically need to tend the

system to start and stop it, depending on the level in the steam generators. No steam

generator indication was available at the location. Steam generator level indication was

available at another location using a portable instrument.

2. SPAR-H-2

Connecting Fire Hose Between Firewater Tank and Essential Feedwater

Tank

Performance Diagnosis Action

Shaeing Factor

PSF Level Multielier PSF Level Multielier

rnme Nominal 1.0 Nominal 1.0

Stress Nominal 1.0 High 2.0

Complexity Nominal 1.0 Moderate 2.0

Experience Nominal 1.0 Low 3.0

Procedures Nominal 1.0 Nominal 1.0

Ergonomics Nominal 1.0 Missing/Misleading 50.0

Fitness for Duty Nominal 1.0 Nominal 1.0

~ork. Processes Nominal 1.0 Nominal 1.0

Nominal Base 1.0E-2 1.0E-3

[i-'::it-s [ 1.0[ 600

~otal 1.0E-2 3.7E-1

Failure Probability 3.7E-1

A3-2 Attachment 3

Justifications for Action (over-riding), only items that departed from nominal:

Stress: High. This action was expected to occur after floodwaters had entered portions

of the site. The procedure that drove the action was used after other water sources

were depleted, after floodwaters reached 1009.5 feet MSL. The floodwater was

expected to fail the demineralized water system at 1008 feet MSL, condensate storage

tank at 1008 feet MSL, the Blair water system at 1007 feet MSL, the diesel-driven

auxiliary feedwater pump at 1009.5 feet MSL, and the plant fire water system at

1008 feet MSL. The action would align an outbuilding fire water tank up to the essential

feedwater storage tank via a fire hose and a connection point on each system. Both

connection points would likely be submerged and could be difficult to locate. Concerns

about personal safety would also contribute to the stress level.

Complexity: Moderately complex. Under normal plant conditions, the action would not

be complex. Having floodwaters cover needed connection points makes the task much

more difficult.

Experience: Low. This action was not normally performed by plant personnel on a

routine basis. The action of finding connection points below the water level and then

connecting the fire hoses was not practiced. Even very experienced craftsmen may

have difficulty accomplishing this task.

Ergonomics: Missing/Misleading. Needed information, labeling and location of the

valves and connections, would be difficult to obtain for components under water.

3. SPAR-H-3

Construct and Install Steel Plates to Cover Auxilia!y Building Doors

Performance Diagnosis Action

Sha!;!ing Factor

PSF Level Multil2lier PSF Level Multi!;!lier

Time Not evaluated If= time required 10

(actually may not have

sufficient time)

Stress Not evaluated High 2.0

Complexity Not evaluated High 2.0

Experience Not evaluated Low 3.0

Procedures Not evaluated Not Available 50.0

Ergonomics Not evaluated Missing/Misleading 50.0

Fitness for Duty Not evaluated Nominal 1.0

lWork Processes Not evaluated Nominal 1.0

INominal Base 1.0E-~ 1.0E-3 1

PSFs I I 300,000'

I ~otal .991

9.9E-1

A3-3 Attachment 3

Justifications for Action (over-riding), only items that departed from nominal:

Time: Equals time required. This action was determined by a tabletop exercise after the

issue was identified. The licensee wanted to demonstrate that the emergency response

organization could develop an acceptable method to protect safe shutdown equipment

under extreme flooding conditions. The analyst interviewed the tabletop team members.

The members had varying levels of knowledge regarding NRC identified flooding

concerns; most knew about a flooding seal issue (not part of this performance

deficiency). A few were aware that the NRC had concerns with the plant's ability to cope

with more significant floods. The exercise lasted about 90 minutes,

During the initial portions of the exercise, flooding projections were within those

addressed by plant procedures. No additional actions were developed by the team

during this phase. Then the scenario changed such that the projected flooding level was

1017 feet MSL. This was outside of the existing procedural guidance for a flood (other

than the action to stack sandbags on top of the floodgates). The team determined that

stacking sandbags on top of the floodgates would not work because the narrow ledge of

the floodgates did not allow construction of a leak tight barrier to 1017 feet MSL. The

team identified the following additional mitigation strategy:

Fabricate and install steel plates in front of all of the auxiliary building doors.

The team specified that they would not weld the plates over the door openings but would

fasten the plates in place. They were not confident that the doorframes would support

welding. The team would have plant personnel weld supporting structures to the plates

themselves for stability. The plates would be cut to size for all of the auxiliary building

doorways and some plates would be welded together to cover rollup doors. They

believed that they needed %-inch to 1-inch thick steel plate for the task. They did not

take the simulation further.

Analyst Assessment: These actions were modeled using SPAR-H and the calculated

failure probability was close to 1.0. However, no credit was provided in the SOP

because it was not clear that the actions would work and the NRC's "Risk Assessment of

Operational Events Handbook," Revision 1.03, Section 6.3.2 stated, in part:

In general, no recovery or repair actions should be credited where ... there is no

procedure or training. It may be possible to justify exceptions in unique

situations, such as a procedure is not needed because the recovery is skill of the

craft. ..

In addition, a different group of individuals in the technical support center at the time of

an actual flood might specify different recommendations.

Craftsmen 'Nould need to construct and erect about 10 covers for doors, including some

double doors and at least one rollup door. The licensee did not have an adequate

supply of the thick plates on site to cover all of the doors. However, an abundant supply

of thinner piates, some 3i8 inch thick and other rough deck piate materiai, were

available. The yard that housed the plates was outdoors and the ground was covered

with gravel, not asphalt (1005 feet MSL). The technical support center was not manned

until floodwaters were near the yard elevation (1004 feet MSL); therefore, floodwaters

could be in the yard before meaningful recommendations could be made. If floodwaters

A3-4 Attachment 3

entered the yard, getting the plates to a location to support cutting and welding may be

difficult.

Experienced welders were onsite, but only three welding machines were available that

could be operated on the three available portable electric generators. A loss of offsite

power was expected at 1008 feet MSL; cutting the plates to size would require a cutting

machine that would not likely be available after a loss of offsite power.

No method was specified for installing the plates, but the tabletop team determined it

was necessary to install them on the water side of the doors, to utilize the water

pressure to keep them in place. To do this, some floodgates would likely need to be

removed. The floodgates had rubber seals, some inflatable, to help prevent in-leakage.

The new plates would not have this feature. This could introduce a new failure

mechanism not previously considered (substantial leakage past a plate at an elevation

below 1009.5 feet MSL).

Flood projections often change and are rarely accurate. If the flood projections started

out below 1009.5 feet MSL and then increased, floodwaters may be upon the floodgates

and sandbag berms, making removal of floodgates and berms unmanageable. The

bottoms of some auxiliary building floodgates sat at approximately 1007 feet MSL.

Large sandbag berms would need to be removed from several doors.

The analyst had asked the licensee to demonstrate the site's capability to erect and

install a steel panel over a representative door, preferably the rollup door. However, at

the time the significance determination was issued, the licensee had not performed a

demonstration. Based on the above, the analyst determined that the time required for

the action was the same as that available.

Stress: High. The stress encountered by the workforce would be high. The welders

and other craftsmen would not likely know that core damage could be imminent if they

did not succeed. Nonetheless, the time pressure on the staff would be significant. In

addition, struggling to complete the task with floodwaters already on site and with limited

resources would add to the pressure.

Complexity: High. With no procedural guidance, the craftsmen would have to devise

strategies on their own to fabricate and install the plates. Interference with floodgates

and sandbag berms would also create obstacles.

Experience: Low. No personnel on site would have sufficient experience with this task.

Welders would be experienced at welding, but the overall task was much more complex.

Procedures: Not available. No procedures were available.

Ergonomics: Missing/Misleading. Craftsmen would likely have to install the new plates

over the doorways while the site was at least partially flooded. At night, it would be dark,

if offsite power was lost, and floodwaters would present a hazardous condition.

Obtaining the construction materials under flooded conditions couid be difficuii. and iarge

heavy machinery may not work in the steel plate storage area.

A3-5 Attachment 3

4. Method 2

Alternate Evaluation: This method was not part of the NRC's normal processes for

evaluating the success of operator actions. The analyst assumed that the licensee could

protect the auxiliary building from floods between 1009.5 and 1014 feet MSL by the

alternate means described above 50 percent of the time. This assumption would reduce

the delta-COF associated with the performance deficiency by a factor of 2.0. Since this

method was outside the NRC processes, no formal credit was provided in the SOP.

A3-6 Attachment 3

FLOODING FREQUENCY SENSITIVITY

1. Flooding frequencies differ by significant amounts.

The uncertainty with the flooding frequencies was high. The licensee used the shape of

the flooding frequency curve at another station (Cooper Nuclear Station) and applied it to

the Fort Calhoun Station flooding frequencies that were provided by the United States

Army Corps of Engineers. The Army Corps of Engineers only provided information out

to the 500-year flood (2E-3/year). The licensee extrapolated the remainder of the

information. A!most a!! of the ca!culated risk was in the extrapolated region. To address

this uncertainty. the analyst assumed that the Army Corps of Engineers data was correct

but the extrapolated information could vary significantly. either higher or lower.

For the sensitivity cases, the analyst targeted the flooding elevation at the 1E-5/year

point for comparison. At the 1E-5/year point on the Fort Calhoun flood hazard curve, the

flood level was 1013.5 feet MSL. The analyst then constructed alternate curves, two

above and two below this base curve. The Curves are shown on the following page.

The curves were numbered Case 1 through Case 5. Case 3 was the licensee's estimate

and was considered the best available information for this assessment.

Using data from the 5 curves, the analyst generated a delta-CDF for each case. The

analyst summarized the results below:

Delta-CDF by Sensitivity Case

Case 2 Case 3*

2.5E-5/year 3.1 E-5/year

  • Licensee assumptions

It's important to note that Case 1 may be unrealistically low. After almost 100,000 years

of additional exposure, the flood elevation at the1 E-5/year point was a little over 1 foot

above that predicted by the Army Corps of Engineers at the 1/500 year point. Likewise,

Case 5 may be unrealistically high. The plotted line deviated from the Army Corps of

Engineers' estimates at a sharper angle.

A4-1 Attachment 4

Frequency Extrapolations - Height versus Logarithm of Flood Frequency

Excedance

1019

1018

1017

1016

1015

1014

1013

1012

1011

1010

1009

............ Corp Data

1008

lie Extrap

1007

2

1006~C;)sc3

1005~Casc4

C;)SC S

1004

1003

1002

1001

1000

999

7

996

995

1.00E-06 1.00E-OS LOOE-04 LOOE-03 1.00E-02 LOOE-Ol LOOE+OO

Case 3 was the best estimate case specified by the licensee.

Cases 1 and 2 were sensitivity cases that assumed that the licensee's best estimate was overly

conservative.

Cases 4 and 5 were sensitivity cases that assumed that the licensee's best estimate was non-

_ _ "_ _ _ _ "_J..! ** _

IjUII:::.tl VCllIVt.

A4-2 Attachment 4

SIGNIFICANCE DETERMINATION PROCESS COMBINATIONS

Target Case (Best Estimate)

Licensee's extrapolated flood frequencies

No credit for alternate essential feedwater tank filling method (components under water)

No credit for placing panels over doors (in accordance with SPAR-H)

Credit for gasoline powered pump system (without alternate filling method)

De!ta-CDF = 3.1 E-5 - Yellow

Best Case Assumptions

Best Case: flood frequency

Best Case: alternate essential feedwater tank fill (Attachment 3, SPAR H)

Best Case: alternate actions to place panels over doors (Failure probability = 50 percent, Not

Using SPAR-H)

I Delta-CDF =4E-6 * 0.5 * 0.5 = 1E-6 - White

Worst Case Assumptions

Worst Case Flood Frequency

No Credit for alternate essential feedwater tank filling method

No Credit for placing alternate panels over doors

Credit for gasoline powered pump system (without alternate filling method)

Delta-CDF = 3.5E-5 - Yellow

Target Case + 50 percent Credit for Placing Panels on Doors

Delta-CDF = 1.5E-5 - Yellow

Target Case + Credit for Alternate Essential Feedwater Tank Fill

Licensee's extrapolated flood frequency

Credit for alternate feedwater tank filling procedure

No credit for placing panels over doors

Delta-CDF = 1.5E-5 - Yellow

Target Case + Credit for Alternate Essential Feedwater Tank Fill + 50 percent Credit for

Placing Panels on Doors

A5-1 Attachment 5

Licensee's extrapolated flood frequency

Credit for alternate feedwater tank filling procedure

50 percent credit for placing panels over doors

Delta-CDF =7.5E-6 - White

AS-2 Attachment 5

ADDITIONAL FAULT TREES

Fault Tree 1

Gasoline Powered Pump System

o ~

PORTABLE

D D

o

EFW*XHE*PORTABLE

~

EFW *GDp*IylECH

[ ~J o

a ~

['~

~

EFW*CDp*CCF*RUN*1*4 EFW*GDp*CCF*START PUMp*1 A*FA1lS PL Mp*1 B*FA1LS

o-b o 0

D~ o o 0 t 0- --- 0

EFW*GDP*SSFS*BF EFW*GDp*FS*1A EFW*GDp*CCFR*BF EFW*GDp*FR*IA EFW*GDp*FR*1 A EFW*GDP*FS*1A EFW*GDp*FR*1B EFW*GDp*FS*JB

A6-1 Attachment 6

Fault Tree 2

Gasoline Powered Pump System

with Essential Feedwater Storage Tank Refill from Firewater Tank

9 POR1ABU,

I

[~ 9-9 9 9

g--9

H~-XHE*PORTAB!E EFW-GOP-MECH EIW-GOP-CtT-START

9~(ru'M¢

TANK-AND-PUNI'S-FAIL

g- 9

EFW-XIJE.FIREWfUER

I

GAS-PUMPS-FAIL EFW-GCP.sSFS-J3F EFW-GCP-FS-I A EFW-Gll'-CCTR-BF

I

EFW(;CP-FR-l A

--~

PUMP-IJ3..FAILS

I

D'~'9

9 9 9cw", ~rn~'" 9"w"np~"'lH

I'FWGCP-FR-l J3

Tr

I

HWGCP-FS-lB

EFW-GCP-FR-IA E1W-GDP-FS-1A

99

EFW-GCP-FR-IA EFW-GCP-IOS-IA

A6-2 Attachment 6