Letter Sequence RAI |
---|
|
|
MONTHYEARML0925906132009-09-30030 September 2009 Plan for the Scoping and Screening Methodology Regulatory Audit Regarding the Palo Verde Nuclear Generating Station, Units 1, 2, and 3 License Renewal Application Review (TAC Nos. ME0254 - ME0256) Project stage: Other ML0927405912009-09-30030 September 2009 E-mail Nrr/De/Eeeb Concerning Review of Palo Verde License Renewal - No RAI Project stage: Approval ML0927502372009-11-0303 November 2009 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML0928900112009-11-12012 November 2009 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML0930902462009-11-18018 November 2009 Plan for the Aging Management Program Audit Regarding the Palo Verde Nuclear Generating Station, Units 1, 2, & 3 License Renewal Application Review (TAC Nos. ME0254, ME0255, ME0256) Project stage: Other ML0932004132009-12-0404 December 2009 Correction to Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1015302192009-12-16016 December 2009 APS 2004 Pump Installation Completion Report for PVNGS Firing Range Well. Filed with Adwr on Aug. 3, 2004 (PV-406) PVNGS Project stage: Request ML0933800512009-12-23023 December 2009 Request for Additional Information, License Renewal Application Project stage: RAI ML0934908302009-12-29029 December 2009 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application) Project stage: RAI ML1002702902010-01-13013 January 2010 Follow-up Clarification to the Response to September 30, 2009, RAI Regarding Severe Accident Mitigation Alternatives for the Review of the PVNGS License Renewal Application, Amendment No. 7 Project stage: Supplement ML0932902982010-01-14014 January 2010 RAI for the Review of the PVNGS Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1001503782010-01-28028 January 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application (TAC Nos. ME0254, ME0255, ME0256) Project stage: RAI ML1002700692010-02-19019 February 2010 RAI for the Review of the Palo Verde Nuclear Generating Station Units 1, 2, 3, LRA (Tac Nos. ME0254, ME0255, & ME0256) Project stage: RAI ML1006106042010-02-19019 February 2010 Response to December 29, 2009, Request for Additional Information Regarding Aging Management Program Audit for Review of License Renewal Application Amendment No. 9 Project stage: Request ML1003602962010-03-0202 March 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application (TAC Nos. ME0254, ME0255, and ME0256) Project stage: RAI ML1001506182010-03-12012 March 2010 Summary of Telephone Conference Call Held Between NRC and Arizona Public Service Company, Concerning Containment Coatings Pertaining to the Palo Verde, Units 1, 2, and 3, LRA Project stage: Other ML1013802152010-04-0101 April 2010 License Renewal - April 1 Webinar on Metal Fatigue Arizona Public Service Company Presentation Slides Project stage: Other ML1002212962010-04-0707 April 2010 Audit Report Regarding the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application (TAC Nos. ME0254, ME0255, ME0256) Project stage: Other ML1009603672010-04-0808 April 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application (TAC Nos. ME0254, ME0255, and ME0256) Project stage: RAI ML1009804822010-04-20020 April 2010 05/06/10 Notice of Public Working Meeting with Arizona Public Service to Discuss Issues Related to the Palo Verde Nuclear Generating Station License Renewal Application Project stage: Meeting ML1011603572010-04-28028 April 2010 Request for Additional Information - Palo Verde License Renewal Review Project stage: RAI ML1013102272010-04-29029 April 2010 Response to April 8, 2010, Request for Additional Information Regarding Security Assessments, for the Review of the PVNGS License Renewal Application Project stage: Request ML1013401002010-06-0202 June 2010 License Renewal - Request for Additional Information Concerning Metal Fatigue Project stage: RAI ML1012703882010-06-25025 June 2010 License Renewal - May 6, 2010 Public Meeting - Arizona Public Service Handout Project stage: Meeting ML1013408012010-06-25025 June 2010 License Renewal - May 6, 2010 Public Meeting Summary Project stage: Meeting ML1013702892010-07-0606 July 2010 Summary of Tele Conf Call Held on 4/23/10, Between the USNRC and Arizona Public Service, Concerning the Palo Verde Generating Nuclear Station, Units 1, 2, and 3, License Renewal Application Project stage: Other ML1017402172010-07-13013 July 2010 Scoping and Screening Audit Report for the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application (TACs ME0254, ME0255, and ME0256) Project stage: Other ML1013408292010-07-14014 July 2010 License Renewal - Summary of Conference Calls on Metal Fatigue Project stage: Other ML1018908912010-07-21021 July 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1021504162010-08-0606 August 2010 Letter - Palo Verde License Renewal - Transmittal Letter with Safety Evaluation Report with Open Items to Arizona Public Service Company Project stage: Approval ML1023102542010-08-24024 August 2010 Forthcoming Meeting to Discuss the Draft Supplemental Environmental Impact Statement (Dseis) for Palo Verde Nuclear Generating Station ML1021801672010-08-31031 August 2010 NUREG-1437 Supplement 43, Dfc Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Palo Verde Nuclear Generating Station (Draft for Comment) Project stage: Draft Other ML1025600222010-09-27027 September 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application (TAC Nos. ME0254, ME0255, and ME0256) Project stage: RAI ML1020305002010-10-15015 October 2010 Summary of Tele Conf Call Held on 7/21/10, Btw the USNRC and Arizona Public Service Company, Concerning Draft Request for Additional Information Pertaining to the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal App Project stage: Draft RAI ML1034909162011-01-11011 January 2011 Safety Evaluation Report Related to the License Renewal of Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Tac Nos. ME0254, ME0255, ME0256) Project stage: Approval ML1104905402011-03-0303 March 2011 Correction of Typographical Error in Safety Evaluation Report Related to License Renewal (TAC Nos. ME0254, ME0255, and ME0256) Project stage: Approval ML1108719552011-04-21021 April 2011 License Renewal - Appendices a, B, C, and D to the Renewed Operating License for Unit 1 (NPF-41) Project stage: Acceptance Review ML1108004782011-04-21021 April 2011 Notice of Issuance of Renewed Facility Operating License Nos. NPF-41, NPF-51, NPF-74 for Additional 20-Year Period - FRN Project stage: Request ML1108004552011-04-21021 April 2011 Issuance of Renewed Facility Operating Licenses for Palo Verde Nuclear Generating Station (TAC Numbers ME0254, ME0255, and ME0256) Project stage: Approval 2010-04-20
[Table View] |
|
---|
Category:Letter
MONTHYEARML24295A0362024-10-23023 October 2024 Regulatory Audit Plan in Support of Relief Request No. 71; Resubmittal of Relief Request-30 IR 05000528/20244022024-10-22022 October 2024 Security Baseline Inspection Report 05000528/2024402 and 05000529/2024402 and 05000530/2024402 ML24296B2142024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 02: Alternative Request Allowing Normally Closed Valves with a Safety Function to Close to Be Exercise Tested Once Per Refueling Cycle ML24296B2152024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 03: Alternative Request Allowing Removal of the Lower Acceptance Criteria Threshold from Solenoid-Operated Valves ML24296B2172024-10-18018 October 2024 Submittal of Unit 1 Core Operating Limits Report, Revision 34, Unit 2 Core Operating Limits Report, Revision 26, and Unit 3 Core Operating Limits Report, Revision 3 ML24292A2192024-10-18018 October 2024 Core Operating Limits Report Revision 34, 26 and 33 ML24292A0322024-10-17017 October 2024 Th Refueling Outage Steam Generator Tube Inspection Report ML24285A2562024-10-11011 October 2024 License Renewal - Alloy 600 Management Program Plan Response to Request for Additional Information IR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-08-21021 August 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) 05000530/LER-2024-002, Invalid Specified System Actuation of Train B Emergency Diesel Generator2024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A 05000530/LER-2024-001, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium 05000529/LER-2024-001, Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater2024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24129A1482024-05-0707 May 2024 And Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 ML24032A1542024-04-0303 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) 2024-09-27
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24297A6212024-10-22022 October 2024 Request for Additional Information Relief Request (RR) No. 72: Re-Submittal of RR-39/ASME Code X1 IWC-3420, IWA-3300 ML24257A1012024-09-11011 September 2024 Request for Additional Information License Renewal Commitment for AMP of Alloy 600 Components ML24143A1112024-05-20020 May 2024 Draft 2nd Round Request for RAIs Concerning LAR to Modify LCO for TS 3.5.2, LCO for TS 3.6.5, and Surveillance Requirements 3.5.1.2 and 3.5.2.2 for TS 3.5.1 and TS 3.5.2 ML24123A2002024-05-0101 May 2024 (E-Mail) Draft 2nd Round Request for Additional Information Concerning License Amendment Request to Modify Limiting Condition for Operation (LCO) for Technical Specification (TS) 3.5.2, LCO for TS 3.6.5, 3.5.1.2 and 3.5.2.2 for TS 3.5.1, a ML24114A2812024-04-19019 April 2024 Request for Additional Information (RAI-10150-R1) ML24011A1002024-01-10010 January 2024 March 2024 Emergency Preparedness Program Inspection - Request for Information ML23334A1612023-11-30030 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - RAIs Associated with License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23334A0072023-11-29029 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR That Revises TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23298A1232023-10-25025 October 2023 NRR E-mail Capture - Palo Verde, Unit 1 - RAIs for Relief Request 70, Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle ML23031A3392023-01-31031 January 2023 In-service Inspection Request for Information ML23013A0632023-01-13013 January 2023 NRR E-mail Capture - Palo Verde Unit 1 -Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22348A1672022-12-14014 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22339A2372022-12-0505 December 2022 NRR E-mail Capture - Palo Verde Unit 1 – Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22272A3252022-09-29029 September 2022 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML22209A1752022-07-28028 July 2022 Inservice Inspection Request for Information ML22187A2632022-07-0606 July 2022 Notification of Inspection (NRC IR 05000528/2022004, 05000529/2022004 and 05000530/2022004) and Request for Information ML22067A2292022-03-0202 March 2022 Inservice Inspection Inspection PWR Request for Information ML22055A5842022-02-24024 February 2022 NRR E-mail Capture - Palo Verde, Unit 3 - Final RAIs for 22nd Refueling Outage (Spring 2021) Steam Generator Tube Inservice Inspection Report ML22035A3302022-02-10010 February 2022 Requests for Confirmation of Information for Exemption to Delete Diverse Auxiliary Feedwater Actuation System Based on Risk-Informed Process for Evaluations ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information ML21245A2222021-09-0101 September 2021 Request for Information ML21200A2392021-07-20020 July 2021 Docs Request AC - AA August 2021 ML21154A0082021-05-26026 May 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Official RAIs for LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21042B9692021-02-18018 February 2021 Notification of NRC Design Bases Assurance Inspection and Initial Request for Information ML21043A1462021-02-11011 February 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAI for an Order Associated with Indirect License Transfer from Public Service Company of New Mexico to Avangrid, Inc ML21023A0212021-01-13013 January 2021 PVNGS PI&R Request for Information RA ML21011A1972021-01-12012 January 2021 Unit 2, and Unit 3 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012) and Request for Information ML20227A0992020-08-14014 August 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20118D1362020-04-28028 April 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20049A0992020-02-14014 February 2020 Notification of Cyber Security Inspection (NRC Inspection Report 05000528/2020401; 05000529/2020401; and 05000530/2020401) and Request for Information ML20049A0252020-02-12012 February 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for License Amendment Request Associated with Changes to Emergency Plan Staffing Requirements ML20021A3172020-01-21021 January 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for Relief Request 64, Impractical Examinations for the Third 10-Year ISI Interval ML19317D0782019-11-13013 November 2019 NRR E-mail Capture - Palo Verde 1 - Requests for Additional Information on Unit 1 21st Refueling Outage Steam Generator Tube Inspection Report ML19234A3202019-08-29029 August 2019 Redacted - Request for Additional Information for Amendment and Exemption Request to Support the Implementation of Framatome High Thermal Performance Fuel (EPID L-2018-LLA-0194; EPID L-2018-LLE-0010) ML19155A1842019-05-30030 May 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mvib Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19095A6552019-04-0404 April 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mphb Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19044A7342019-02-13013 February 2019 NRR E-mail Capture - Palo Verde1, 2, and 3 - Official Requests for Additional Information for RR 62, Third and Fourth 10-Year ISI Intervals, Proposed Alternative - Pressurizer Heat Sleeve Repairs ML19008A3612019-01-0808 January 2019 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR Associated with Response Time Testing of Pressure Transmitters ML18341A0252018-12-0303 December 2018 Notification of NRC Design Bases Assurance Inspection (Teams)(05000528/2019011, 05000529/2019011, and 05000530/2019011) and Initial Request for Information ML18271A0392018-10-0202 October 2018 Non Proprietary - Supplemental Information Needed for Acceptance of Requested License Amendments and Exemptions Implementation of Framatome High Thermal Performance Fuel (Epids L-2018-LLA-0194 and L-2018-LLE-0010) ML18221A5102018-08-23023 August 2018 Request for Additional Information License Amendment Request to Adopt Risk-Informed Completion Times (CAC Nos. MF6576, MF6577, and MF6578; EPID: L-2015-LLA-0001) ML18229A3132018-08-17017 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 - Second Se ML18227A8672018-08-15015 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 ML18124A0112018-05-0303 May 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official Eeob RAIs for TSTF-505 (4b) LAR (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001) ML18099A0072018-04-0606 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for 10 CFR 50.69 LAR (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276) ML18094B1122018-04-0404 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAIs for TSTF-505 (Initiative 4b) LAR (CAC Nos. MF6576, MF6577, and MF6578: EPID L-2015-LLA-0001) ML18066A7032018-03-0707 March 2018 Notification of Nrc Design Bases Assurance Inspection (Programs) 05000528/2018011, 05000529/2018011, and 05000530/2018011 Initial Request for Information ML17248A0162017-08-31031 August 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAI for RRs PRR-03, PRR-04 and PRR-05, Pump Testing ML17107A0052017-04-14014 April 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Ngf LAR and Exemption RAIs (CAC Nos. MF8076 to MF8081) 2024-09-11
[Table view] |
Text
June 2, 2010 Mr. Randall K. Edington Executive Vice President, Nuclear Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION (TAC NOS. ME0254, ME0255, AND ME0256)
Dear Mr. Edington:
By letter dated December 11, 2008, as supplemented by letter dated April 14, 2009, Arizona Public Service Company (APS) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 to renew Operating License Nos. NPF-41, NPF-51, and NPF-74 for the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, respectively. The staff is reviewing the information contained in the license renewal application and has identified in the enclosure area where additional information is needed to complete the review. Further requests for additional information may be issued in the future.
A mutually agreeable date for your response, as discussed with Angela Krainik of APS staff, was determined to be 30 calendar days from the date of this letter. If you have any questions, please contact me at 301-415-1906 or by e-mail at Lisa.Regner@nrc.gov.
Sincerely,
/RA/
Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-528, 50-529, and 50-530
Enclosure:
As stated cc w/encl: See next page
ML101340100 OFFICE LA:DLR PM:RPB2:DLR (A)BC:RARB:DLR BC:RPB2:DLR PM:RPB2:DLR NAME SFigueroa LRegner GShukla DWrona LRegner DATE 05/18/10 05/24/10 05/26/10 06/02/10 06/02/10
Letter to R. Edington from L. Regner dated June 2, 2010
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION (TAC NOS. ME0254, ME0255, AND ME0256)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail Resource
L. Regner D. Drucker R. Hall B. Mizuno, OGC R. Treadway, RIV G. Pick, RIV
PALO VERDE NUCLEAR GENERATING STATION (PVNGS)
LICENSE RENEWAL APPLICATION (LRA)
REQUEST FOR ADDITIONAL INFORMATION (RAI)
RAI 4.3-1 Issue In the public meeting between Arizona Public Service Company (APS) and the U.S. Nuclear Regulatory Commission (NRC) held on Thursday, May 6, 2010, APS indicated that it had updated the design basis transients for the metal fatigue time-limited aging analysis (TLAA) to be consistent with those listed in the updated final safety analysis report (UFSAR) for the facility.
Further, APS stated that the updated transient projection basis is based on the applicants updated transient recount activities for the TLAA. The applicant clarified that the 25 percent assumed transient occurrence basis used in the original TLAA was only applied to five or six transients for which recount data could not be found.
Request Clarify which of the transients in Tables 4.3-2 and 4.3-3 of the LRA (as modified by Amendment 14) the 25 percent assumed transient occurrence basis remains applicable to and justify why the application of this assumption is considered to yield a conservative 60-year cycle occurrence basis for these transients.
RAI 4.3-2 Issue Table 4.3-3 in Amendment 14 of the LRA provides an adequate technical basis that PVNGS operates as a base load plant and that Transient No. 3, 5 percent per minute power ramp increase, from 15 percent to 100 percent power, and Transient No. 4, 5 percent per minute power ramp decrease, from 15 percent to 100 percent power, do not need to be counted relative to the 15,000 cycle limits for these transients. However, it appears that technical specification (TS) 5.5.5 and UFSAR Section 3.9.1.1 may still require these transients to be counted, specifically because these transients are currently listed as transients in Section I and II of UFSAR Table 3.9-1.
Section 4.3.2.1 of the LRA states that for the Unit 1 instrument nozzles, the calculated cumulative usage factor (CUF) of 0.68 is based on this 15,000 load following cycle limit.
However, there is a factor of five difference in the CUF that is reported for these components for Unit 1 and those that are reported for the instrument nozzles at Units 2 and 3.
Request
- 1. Clarify, with justification, whether these transients are required to be counted per TS 5.5.5 and UFSAR Section 3.9.1.1. If these transients are required to be counted per TS 5.5.5 and UFSAR Section 3.9.1.1, clarify the actions that will be taken to resolve the inconsistency if it is determined there is a valid technical basis for not counting these transients.
ENCLOSURE
2
- 2. Clarify whether either Transient No. 3 or Transient No. 4 has occurred at the PVNGS site to date. If either transient has occurred, clarify how this is consistent with the plant being operated as a base load plant and justify not counting these transients.
- 3. Clarify why there is a factor of five difference between the CUFs reported for the instrument nozzles at Unit 1 from those that are reported for the corresponding nozzles at Units 2 and 3.
RAI 4.3-3 Issue Section 4.3.5 of the LRA states that the calculated stresses in limiting locations were less than allowable in the revised design analyses for the reactor coolant hot leg sample lines piping and the steam generator (SG) downcomer and feedwater recirculation lines piping. However, LRA Section 4.3.5 does not provide sufficient information for the staff to confirm these assertions.
Request Provide the code allowable stress limits and the stress ranges obtained in the revised design analyses for the reactor coolant hot leg sample line piping and the SG downcomer and feedwater recirculation line piping. Also, provide the American Society of Mechanical Engineer Code edition and specific subsection used for the revised design analyses for these piping components.
RAI 4.3-4 Issue Section 4.3.4 of the LRA states that for reactor pressure vessel (RPV) shell and lower head, RPV inlet and outlet nozzles, and safety injection nozzle (forging knuckle), the maximum applicable environmental factors (Fen) for low alloy steel was used and was determined following NUREG/CR-6583, Effects of LWR Coolant Environments on Fatigue Design Curves of Carbon and Low-Alloy Steels. However, LRA Section 4.3.4 does not provide sufficient information to confirm this statement.
Request Demonstrate that the Fen factor used for assessment of the reactor coolant environment impact on the RPV shell and lower head, RPV inlet and outlet nozzles, and safety injection nozzle (forging knuckle) are the maximum applicable for a given material. Provide a basis and justification for any assumptions that were made for the parameters in the assessment, such as strain rate, dissolved oxygen, temperature and sulfur content.
RAI 4.3-5 Issue Note 7 and 9 of Table 4.3-11 of the LRA provides the reanalysis computed Fen values for load set pairs with a significant fatigue contribution for the charging system nozzle (safe end) and the safety injection nozzle (safe end), respectively. Section 4.3.4 of the LRA does not contain sufficient information on the assumptions that have been used for the environmental Fen factor calculations.
3 Request
- 1. Describe in detail the methodology that has been used for the environmental Fen factor calculation of the charging system nozzle and the safety injection nozzle.
- 2. Provide a basis for any assumptions that were made for the parameters, such as strain rate, dissolved oxygen, and temperature, in the assessment of a computed Fen value for the load set pairs with a significant fatigue contribution.
- 3. Confirm the value of the maximum Fen factor used for all remaining load set pairs.
RAI 4.3-6
Background
LRA Section 4.3.4 states that a bounding Fen factor of 1.49 was used for the Alloy 600 component, pressurizer heater penetrations. NUREG/CR-6335, Fatigue Strain-Life Behavior of Carbon and Low-Alloy Steels, Austenitic Stainless Steels, and Alloy 600 in LWR Environments, provides the statistical characterizations used to derive this Fen factor of 1.49 for Alloy 600, and states the fatigue S-N database (fatigue per load cycle curves) for Alloy 600 is extremely limited and does not cover an adequate range of material and loading variables that might influence fatigue life. It further states that the data was obtained from relatively few heats of material and are inadequate to establish the effect of strain rate on fatigue life in air or of temperature in a water environment. NUREG/CR-6909, Effect of LWR Coolant Environments on the Fatigue Life of Reactor Materials, incorporates more recent fatigue data using a larger database for determining the Fen factor of nickel alloys.
Issue The Fen factor of 1.49 for nickel alloys may be non-conservative. The Fen for nickel alloys based on NUREG/CR-6909 varies based on temperature, strain rate and dissolved oxygen. Based on actual plant operating conditions the Fen factor can vary from a value of 1.0 to 4.52 based on this methodology. Therefore, the CUF value for the pressurizer heater penetrations may be as high as 2.86 using the CUF presented in the LRA and the maximum Fen derived from NUREG/CR-6909 which would exceed the design limit of 1.0 when considering environmental effects of reactor coolant during the period of extended operation.
Request
- 1. Since the Fen for nickel alloys can vary from 1.0 to 4.52 based on NUREG/CR-6909 and the CUF value may exceed the design limit of 1.0 for the pressurizer heater penetrations when considering environmental effects, justify using a value of 1.49 for the Fen factor for this nickel alloy component.
- 2. Describe the current or future planned actions to update the CUF calculation with Fen factor for the Alloy 600 component only, consistent with the methodology in NUREG/CR-6909. If there are no current or future planned actions to update the CUF calculation with Fen factor for the Alloy 600 component consistent with the methodology in NUREG/CR-6909, provide a justification for not performing the update.
Palo Verde Nuclear Generating Station, Units 1, 2, and 3 cc:
Steve Olea Mr. John C. Taylor, Director, Nuclear Arizona Corporation Commission Generation 1200 W. Washington Street El Paso Electric Company Phoenix, AZ 85007 340 E. Palm Lane, Suite 310 Phoenix, AZ 85004 Mr. Douglas Kent Porter, Senior Counsel Southern California Edison Company Mr. James Ray Law Department, Generation Resources Public Service Company of New Mexico P.O. Box 800 2401 Aztec NE, MS Z110 Rosemead, CA 91770 Albuquerque, NM 87107-4224 Senior Resident Inspector Mr. Geoffrey M. Cook U.S. Nuclear Regulatory Commission Southern California Edison Company P.O. Box 40 5000 Pacific Coast Highway, Bldg. D21 Buckeye, AZ 85326 San Clemente, CA 92672 Regional Administrator, Region IV Mr. Robert Henry U.S. Nuclear Regulatory Commission Salt River Project 612 E. Lamar Blvd., Suite 400 6504 E. Thomas Road Arlington, TX 76011-4125 Scottsdale, AZ 85251 Chairman Mr. Jeffrey T. Weikert Maricopa County Board of Supervisors Assistant General Counsel 301 W. Jefferson, 10th Floor El Paso Electric Company Phoenix, AZ 85003 Mail Location 167 123 W. Mills Mr. Aubrey V. Godwin, Director El Paso, TX 79901 Arizona Radiation Regulatory Agency 4814 S. 40th Street Mr. Eric Tharp Phoenix, AZ 85040 Los Angeles Department of Water & Power Southern California Public Power Authority Mr. Ron Barnes, Director P.O. Box 51111, Room 1255-C Regulatory Affairs Los Angeles, CA 90051-0100 Palo Verde Nuclear Generating Station Mail Station 7636 Mr. Brian Almon P.O. Box 52034 Public Utility Commission Phoenix, AZ 85072-2034 William B. Travis Building P.O. Box 13326 Mr. Dwight C. Mims, Vice President 1701 N. Congress Avenue Regulatory Affairs and Plant Improvement Austin, TX 78701-3326 Palo Verde Nuclear Generating Station Mail Station 7605 P.O. Box 52034 Phoenix, AZ 85072-2034