Letter Sequence Meeting |
|---|
|
Results
Other: ML091130221, ML092590613, ML092750130, ML093090246, ML093500101, ML100150618, ML100221296, ML101340829, ML101370289, ML101380215, ML101740217, ML110871955
|
MONTHYEARML0911302212009-04-14014 April 2009 To License Renewal Application Project stage: Other ML0925906132009-09-30030 September 2009 Plan for the Scoping and Screening Methodology Regulatory Audit Regarding the Palo Verde Nuclear Generating Station, Units 1, 2, and 3 License Renewal Application Review (TAC Nos. ME0254 - ME0256) Project stage: Other ML0927405912009-09-30030 September 2009 E-mail Nrr/De/Eeeb Concerning Review of Palo Verde License Renewal - No RAI Project stage: Approval ML0927501302009-11-0303 November 2009 Summary of Telephone Conference Call Held on September 16, 2009 Between the U.S. NRC and Arizona Public Service Company, Pertaining to the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: Other ML0927502372009-11-0303 November 2009 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML0928900112009-11-12012 November 2009 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML0930902462009-11-18018 November 2009 Plan for the Aging Management Program Audit Regarding the Palo Verde Nuclear Generating Station, Units 1, 2, & 3 License Renewal Application Review Project stage: Other ML0932004132009-12-0404 December 2009 Correction to Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML0935001012009-12-0707 December 2009 Submittal of Annual Update to the License Renewal Application, and License Renewal Application Amendment No. 3 Project stage: Other ML1015302192009-12-16016 December 2009 APS 2004 Pump Installation Completion Report for PVNGS Firing Range Well. Filed with Adwr on Aug. 3, 2004 (PV-406) PVNGS Project stage: Request ML1011101292009-12-23023 December 2009 PVNGS, Units 1, 2, and 3, Environmental Documents for NRC Review of the PVNGS LRA Project stage: Request ML0933800512009-12-23023 December 2009 Request for Additional Information, License Renewal Application Project stage: RAI ML0934908302009-12-29029 December 2009 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application) Project stage: RAI ML1002702902010-01-13013 January 2010 Follow-up Clarification to the Response to September 30, 2009, RAI Regarding Severe Accident Mitigation Alternatives for the Review of the PVNGS License Renewal Application, Amendment No. 7 Project stage: Supplement ML0932902982010-01-14014 January 2010 RAI for the Review of the PVNGS Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1001503782010-01-28028 January 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1006106042010-02-19019 February 2010 Response to December 29, 2009, Request for Additional Information Regarding Aging Management Program Audit for Review of License Renewal Application Amendment No. 9 Project stage: Request ML1002700692010-02-19019 February 2010 RAI for the Review of the Palo Verde Nuclear Generating Station Units 1, 2, 3, LRA (Tac Nos. ME0254, ME0255, & ME0256) Project stage: RAI ML1003602962010-03-0202 March 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1001506182010-03-12012 March 2010 Summary of Telephone Conference Call Held Between NRC and Arizona Public Service Company, Concerning Containment Coatings Pertaining to the Palo Verde, Units 1, 2, and 3, LRA Project stage: Other ML1013802152010-04-0101 April 2010 License Renewal - April 1 Webinar on Metal Fatigue Arizona Public Service Company Presentation Slides Project stage: Other ML1002212962010-04-0707 April 2010 Audit Report Regarding the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: Other ML1009603672010-04-0808 April 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1009804822010-04-20020 April 2010 Notice of Public Working Meeting with Arizona Public Service to Discuss Issues Related to the Palo Verde Nuclear Generating Station License Renewal Application Project stage: Meeting ML1011603572010-04-28028 April 2010 Request for Additional Information - Palo Verde License Renewal Review Project stage: RAI ML1013102272010-04-29029 April 2010 Response to April 8, 2010, Request for Additional Information Regarding Security Assessments, for the Review of the PVNGS License Renewal Application Project stage: Request ML1013401002010-06-0202 June 2010 License Renewal - Request for Additional Information Concerning Metal Fatigue Project stage: RAI ML1012703882010-06-25025 June 2010 License Renewal - May 6, 2010 Public Meeting - Arizona Public Service Handout Project stage: Meeting ML1013408012010-06-25025 June 2010 License Renewal - May 6, 2010 Public Meeting Summary Project stage: Meeting ML1013702892010-07-0606 July 2010 Summary of Tele Conf Call Held on 4/23/10, Between the USNRC and Arizona Public Service, Concerning the Palo Verde Generating Nuclear Station, Units 1, 2, and 3, License Renewal Application Project stage: Other ML1017402172010-07-13013 July 2010 Scoping and Screening Audit Report for the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application (TACs ME0254, ME0255, and ME0256) Project stage: Other ML1013408292010-07-14014 July 2010 License Renewal - Summary of Conference Calls on Metal Fatigue Project stage: Other ML1018908912010-07-21021 July 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1021504162010-08-0606 August 2010 Letter - Palo Verde License Renewal - Transmittal Letter with Safety Evaluation Report with Open Items to Arizona Public Service Company Project stage: Approval ML1023102542010-08-24024 August 2010 Forthcoming Meeting to Discuss the Draft Supplemental Environmental Impact Statement (Dseis) for Palo Verde Nuclear Generating Station ML1021801672010-08-31031 August 2010 NUREG-1437 Supplement 43, Dfc Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Palo Verde Nuclear Generating Station (Draft for Comment) Project stage: Draft Other ML1025600222010-09-27027 September 2010 Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application Project stage: RAI ML1020305002010-10-15015 October 2010 Summary of Tele Conf Call Held on 7/21/10, Btw the USNRC and Arizona Public Service Company, Concerning Draft Request for Additional Information Pertaining to the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal App Project stage: Draft RAI ML1034909162011-01-11011 January 2011 Safety Evaluation Report Related to the License Renewal of Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Tac Nos. ME0254, ME0255, ME0256) Project stage: Approval ML1104905402011-03-0303 March 2011 Correction of Typographical Error in Safety Evaluation Report Related to License Renewal Project stage: Approval ML1108719552011-04-21021 April 2011 License Renewal - Appendices a, B, C, and D to the Renewed Operating License for Unit 1 (NPF-41) Project stage: Other ML1108004552011-04-21021 April 2011 Issuance of Renewed Facility Operating Licenses for Palo Verde Nuclear Generating Station (TAC Numbers ME0254, ME0255, and ME0256) Project stage: Approval ML1108004782011-04-21021 April 2011 Notice of Issuance of Renewed Facility Operating License Nos. NPF-41, NPF-51, NPF-74 for Additional 20-Year Period - FRN Project stage: Request 2010-04-01
[Table View] |
Text
June 25, 2010 LICENSEE:
Arizona Public Service Company FACILITY:
Palo Verde Nuclear Generating Station, Units 1, 2, and 3
SUBJECT:
SUMMARY
OF PUBLIC MEETING HELD ON MAY 6, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING THE METAL FATIGUE REVIEW PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION (ME0254, ME0255, AND ME0256)
On May 6, 2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC or the staff), and representatives of Arizona Public Service Company (APS),
at NRC headquarters in Rockville, Maryland. The purpose of the meeting was to discuss metal fatigue related topics identified during the NRC staff review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, license renewal application. The meeting provided APS representatives the opportunity to present plans to resolve remaining metal fatigue review issues. The meeting was open to the public as stated in the meeting notice dated April 20, 2010.
provides a listing of the participants and Enclosures 2 provides the slides used by APS at the meeting. The draft request for additional information (RAI) questions presented in the slides can be found in the conference call summary document available in the NRCs Agencywide Documents Access and Management System under Accession Number ML101340829.
By letter dated April 28, 2010, APS submitted Amendment No.14 to the license renewal application (LRA) which included a revision to Section 4.3 Metal Fatigue. Many of the staffs concerns were addressed in this submittal as discussed in the slides in Enclosure 2 and in the May conference call summary. By letter dated May 27, 2010, APS submitted Amendment No. 16 to the LRA which provided conforming changes to the remainder of Section 4.3. The staff may issue RAI questions to address any remaining metal fatigue concerns. Any metal fatigue issues not resolved will be reflected as an Open or Confirmatory Item in the staffs Safety Evaluation Report with Open Items schedule for issuance on July 30, 2010.
Public feedback forms were provided, however no members of the public attended.
/RA/
Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-528, 50-529, and 50-530
Enclosures:
As stated cc w/encls: See next page
(Pkg) ML101340802, (Ltr) ML101340801, (Encl) ML101270388 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME YEdmonds LRegner DWrona LRegner DATE 05/26/10 06/02/10 06/03/10 06/25/10
Memorandum to Arizona Public Service Company from L. Regner dated June 25, 2010
SUBJECT:
SUMMARY
OF PUBLIC MEETING HELD ON MAY 6, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING THE METAL FATIGUE REVIEW PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION (ME0254, ME0255, AND ME0256)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail Resource L. Regner D. Drucker R. Hall B. Mizuno, OGC R. Treadway, RIV G. Pick, RIV
ENCLOSURE 1 PUBLIC MEETING
SUMMARY
PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS May 6, 2010 PARTICIPANTS AFFILIATIONS David Wrona U.S. Nuclear Regulatory Commission (NRC)
Lisa Regner NRC Allen Hiser NRC James Medoff NRC On Yee NRC Angela Krainik Arizona Public Service Company (APS)
Glenn Michael APS Eugene Montgomery APS Mark Radspinner APS Alfred Meeden APS Douglas Berg APS Winston Borrero APS Thomas Weber APS Richard Schaller Utilities Service Alliance Eric Blocher Strategic Teaming and Resource Sharing Alliance Donald Stevens Worley Parsons Curt Carney Structural Integrity Associates David Gerber Structural Integrity Associates
Palo Verde Nuclear Generating Station, Units 1, 2, and 3 cc:
Mr. Steve Olea Arizona Corporation Commission 1200 W. Washington Street Phoenix, AZ 85007 Mr. Douglas Kent Porter, Senior Counsel Southern California Edison Company Law Department, Generation Resources P.O. Box 800 Rosemead, CA 91770 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 40 Buckeye, AZ 85326 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 612 E. Lamar Blvd., Suite 400 Arlington, TX 76011-4125 Chairman Maricopa County Board of Supervisors 301 W. Jefferson, 10th Floor Phoenix, AZ 85003 Mr. Aubrey V. Godwin, Director Arizona Radiation Regulatory Agency 4814 S. 40th Street Phoenix, AZ 85040 Mr. Ron Barnes, Director Regulatory Affairs Palo Verde Nuclear Generating Station Mail Station 7636 P.O. Box 52034 Phoenix, AZ 85072-2034 Mr. Dwight C. Mims, Vice President Regulatory Affairs and Plant Improvement Palo Verde Nuclear Generating Station Mail Station 7605 P.O. Box 52034 Phoenix, AZ 85072-2034 Mr. John C. Taylor, Director, Nuclear Generation El Paso Electric Company 340 E. Palm Lane, Suite 310 Phoenix, AZ 85004 Mr. James Ray Public Service Company of New Mexico 2401 Aztec NE, MS Z110 Albuquerque, NM 87107-4224 Mr. Geoffrey M. Cook Southern California Edison Company 5000 Pacific Coast Highway, Bldg. D21 San Clemente, CA 92672 Mr. Robert Henry Salt River Project 6504 E. Thomas Road Scottsdale, AZ 85251 Mr. Jeffrey T. Weikert Assistant General Counsel El Paso Electric Company Mail Location 167 123 W. Mills El Paso, TX 79901 Mr. Eric Tharp Los Angeles Department of Water & Power Southern California Public Power Authority P.O. Box 51111, Room 1255-C Los Angeles, CA 90051-0100 Mr. Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 N. Congress Avenue Austin, TX 78701-3326 Mr. Randall K. Edington Executive Vice President Nuclear/CNO Arizona Public Service Company P.O. Box 52034, Mail Station 7602 Phoenix, AZ 85072-2034
Arizona Public Service Companys Metal Fatigue Webinar Presentation conducted on April 1, 2010 can be found in the Agencywide Documents Access and Maintenance System at accession number ML101270388.