License Renewal - May 6, 2010 Public Meeting Summary
ML101340801
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/25/2010
From: Lisa Regner
License Renewal Projects Branch 2
To:
Arizona Public Service Co
Regner L M, NRR/DLR, 415-1906
Shared Package
ML101340802 List:
References
TAC ME0254, TAC ME0255, TAC ME0256
Download: ML101340801 (6)


Text

June 25, 2010 LICENSEE: Arizona Public Service Company FACILITY: Palo Verde Nuclear Generating Station, Units 1, 2, and 3

SUBJECT:

SUMMARY

OF PUBLIC MEETING HELD ON MAY 6, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING THE METAL FATIGUE REVIEW PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION (ME0254, ME0255, AND ME0256)

On May 6, 2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC or the staff), and representatives of Arizona Public Service Company (APS),

at NRC headquarters in Rockville, Maryland. The purpose of the meeting was to discuss metal fatigue related topics identified during the NRC staff review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, license renewal application. The meeting provided APS representatives the opportunity to present plans to resolve remaining metal fatigue review issues. The meeting was open to the public as stated in the meeting notice dated April 20, 2010. provides a listing of the participants and Enclosures 2 provides the slides used by APS at the meeting. The draft request for additional information (RAI) questions presented in the slides can be found in the conference call summary document available in the NRCs Agencywide Documents Access and Management System under Accession Number ML101340829.

By letter dated April 28, 2010, APS submitted Amendment No.14 to the license renewal application (LRA) which included a revision to Section 4.3 Metal Fatigue. Many of the staffs concerns were addressed in this submittal as discussed in the slides in Enclosure 2 and in the May conference call summary. By letter dated May 27, 2010, APS submitted Amendment No. 16 to the LRA which provided conforming changes to the remainder of Section 4.3. The

staff may issue RAI questions to address any remaining metal fatigue concerns. Any metal fatigue issues not resolved will be reflected as an Open or Confirmatory Item in the staffs Safety Evaluation Report with Open Items schedule for issuance on July 30, 2010.

Public feedback forms were provided, however no members of the public attended.

/RA/

Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-528, 50-529, and 50-530

Enclosures:

As stated cc w/encls: See next page

(Pkg) ML101340802, (Ltr) ML101340801, (Encl) ML101270388 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME YEdmonds LRegner DWrona LRegner DATE 05/26/10 06/02/10 06/03/10 06/25/10

Memorandum to Arizona Public Service Company from L. Regner dated June 25, 2010

SUBJECT:

SUMMARY

OF PUBLIC MEETING HELD ON MAY 6, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING THE METAL FATIGUE REVIEW PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION (ME0254, ME0255, AND ME0256)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail Resource


L. Regner D. Drucker R. Hall B. Mizuno, OGC R. Treadway, RIV G. Pick, RIV

PUBLIC MEETING

SUMMARY

PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS May 6, 2010 PARTICIPANTS AFFILIATIONS David Wrona U.S. Nuclear Regulatory Commission (NRC)

Lisa Regner NRC Allen Hiser NRC James Medoff NRC On Yee NRC Angela Krainik Arizona Public Service Company (APS)

Glenn Michael APS Eugene Montgomery APS Mark Radspinner APS Alfred Meeden APS Douglas Berg APS Winston Borrero APS Thomas Weber APS Richard Schaller Utilities Service Alliance Eric Blocher Strategic Teaming and Resource Sharing Alliance Donald Stevens Worley Parsons Curt Carney Structural Integrity Associates David Gerber Structural Integrity Associates ENCLOSURE 1

Palo Verde Nuclear Generating Station, Units 1, 2, and 3 cc:

Mr. Steve Olea Mr. John C. Taylor, Director, Nuclear Arizona Corporation Commission Generation 1200 W. Washington Street El Paso Electric Company Phoenix, AZ 85007 340 E. Palm Lane, Suite 310 Phoenix, AZ 85004 Mr. Douglas Kent Porter, Senior Counsel Southern California Edison Company Mr. James Ray Law Department, Generation Resources Public Service Company of New Mexico P.O. Box 800 2401 Aztec NE, MS Z110 Rosemead, CA 91770 Albuquerque, NM 87107-4224 Senior Resident Inspector Mr. Geoffrey M. Cook U.S. Nuclear Regulatory Commission Southern California Edison Company P.O. Box 40 5000 Pacific Coast Highway, Bldg. D21 Buckeye, AZ 85326 San Clemente, CA 92672 Regional Administrator, Region IV Mr. Robert Henry U.S. Nuclear Regulatory Commission Salt River Project 612 E. Lamar Blvd., Suite 400 6504 E. Thomas Road Arlington, TX 76011-4125 Scottsdale, AZ 85251 Chairman Mr. Jeffrey T. Weikert Maricopa County Board of Supervisors Assistant General Counsel 301 W. Jefferson, 10th Floor El Paso Electric Company Phoenix, AZ 85003 Mail Location 167 123 W. Mills Mr. Aubrey V. Godwin, Director El Paso, TX 79901 Arizona Radiation Regulatory Agency 4814 S. 40th Street Mr. Eric Tharp Phoenix, AZ 85040 Los Angeles Department of Water & Power Southern California Public Power Authority Mr. Ron Barnes, Director P.O. Box 51111, Room 1255-C Regulatory Affairs Los Angeles, CA 90051-0100 Palo Verde Nuclear Generating Station Mail Station 7636 Mr. Brian Almon P.O. Box 52034 Public Utility Commission Phoenix, AZ 85072-2034 William B. Travis Building P.O. Box 13326 Mr. Dwight C. Mims, Vice President 1701 N. Congress Avenue Regulatory Affairs and Plant Improvement Austin, TX 78701-3326 Palo Verde Nuclear Generating Station Mail Station 7605 Mr. Randall K. Edington P.O. Box 52034 Executive Vice President Phoenix, AZ 85072-2034 Nuclear/CNO Arizona Public Service Company P.O. Box 52034, Mail Station 7602 Phoenix, AZ 85072-2034

Arizona Public Service Companys Metal Fatigue Webinar Presentation conducted on April 1, 2010 can be found in the Agencywide Documents Access and Maintenance System at accession number ML101270388.