Inspection/Activity Plan, 03/01/2010-06/30/2010, Enclosure - Report 22
ML100620978
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 03/03/2010
From: Wert L
Division Reactor Projects I
To:
Tennessee Valley Authority
Shared Package
ML100620957 List:
References
IR-10-001
Download: ML100620978 (2)


Text

Page 1 of 2 Browns Ferry 03/03/2010 07:05:57 Inspection / Activity Plan Report 22 03/01/2010 - 06/30/2011 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EB3ISI - UNIT 3 INSERVICE INSPECTION 1 3 03/08/2010 03/12/2010 IP 7111108G Inservice Inspection Activities - BWR PSB1-RP - RP ACCESS CONTROLS 1 1, 2, 3 03/22/2010 03/26/2010 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 03/22/2010 03/26/2010 IP 71151 Performance Indicator Verification PSB1EP - EMERGENCY PREPAREDNESS INSPECTION 1 1, 2, 3 05/03/2010 05/07/2010 IP 7111402 Alert and Notification System Evaluation 1, 2, 3 05/03/2010 05/07/2010 IP 7111403 Emergency Response Organization Augmentation Testing 1, 2, 3 05/03/2010 05/07/2010 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 05/03/2010 05/07/2010 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2, 3 05/03/2010 05/07/2010 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM PREP 7 1 05/17/2010 05/21/2010 V23304 BROWNS FERRY/JULY 2009 EXAM AT POWER FACILITIES PSB1-RP - RP GROUNDWATER PROTECTION 1 1, 2, 3 05/31/2010 06/04/2010 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative OL EXAM - INITIAL EXAM - WEEK 1 7 1 06/07/2010 06/11/2010 V23304 BROWNS FERRY/JULY 2009 EXAM AT POWER FACILITIES PSB1-RP - RP PUBLIC RADIATION PROTECTION 4 1, 2, 3 06/14/2010 06/18/2010 IP 71124.05 Radiation Monitoring Instrumentation 1, 2, 3 06/14/2010 06/18/2010 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2, 3 06/14/2010 06/18/2010 IP 71124.07 Public Radiation Safety 1, 2, 3 06/14/2010 06/18/2010 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2, 3 06/14/2010 06/18/2010 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM - WEEK 2 7 1 06/14/2010 06/25/2010 V23304 BROWNS FERRY/JULY 2009 EXAM AT POWER FACILITIES ORD INSP - ORDER ISSUE FOLLOW UP ITEMS 1,5,8,9 2 1, 2, 3 06/28/2010 06/30/2010 IP 92702 Followup On Corrective Actions For Violations And Deviations TI-177 - GAS INTRUSION 2 1, 2, 3 08/09/2010 08/13/2010 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System PI&R - PROBLEM IDENTIFICATION AND RESOLUTION IN 5 1, 2, 3 08/30/2010 09/03/2010 IP 71152B Identification and Resolution of Problems 1, 2, 3 09/20/2010 09/24/2010 IP 71152B Identification and Resolution of Problems OL RQ - REQUAL INSPECTION 3 1, 2 10/11/2010 10/15/2010 IP 7111111B Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Browns Ferry 03/03/2010 07:05:57 Inspection / Activity Plan Report 22 03/01/2010 - 06/30/2011 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EB3ISI - UNIT 1 INSERVICE INSPECTION 1 1 11/01/2010 11/05/2010 IP 7111108G Inservice Inspection Activities - BWR ORD INSP - ORDER INSPECTION FOLLOW UP ITEMS 6,7,10 2 1, 2, 3 12/06/2010 12/08/2010 IP 92702 Followup On Corrective Actions For Violations And Deviations OL EXAM - INITIAL PREP WEEK 2 1 01/24/2011 01/28/2011 V23344 BROWNS FERRY/FEBRUARY 2011 EXAM AT POWER FACILITIES EB3HS - HEAT SINK 1 1, 2, 3 02/07/2011 02/11/2011 IP 7111107T Heat Sink Performance OL EXAM - INITIAL EXAM - WEEK 1 2 1 02/07/2011 02/11/2011 V23344 BROWNS FERRY/FEBRUARY 2011 EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 2 2 1 02/14/2011 02/25/2011 V23344 BROWNS FERRY/FEBRUARY 2011 EXAM AT POWER FACILITIES PSB1 RP - RP OCCUPATIONAL WEEK1 3 1, 2, 3 02/28/2011 03/04/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 02/28/2011 03/04/2011 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 02/28/2011 03/04/2011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 02/28/2011 03/04/2011 IP 71124.04 Occupational Dose Assessment 1, 2, 3 02/28/2011 03/04/2011 IP 71151 Performance Indicator Verification EB3ISI - UNIT 2 INSERVICE INSPECTION 1 2 03/14/2011 03/18/2011 IP 7111108G Inservice Inspection Activities - BWR PSB1-RP - RP OCCUPATIONAL WEEK 2 2 1, 2, 3 03/15/2011 03/19/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 03/15/2011 03/19/2011 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 03/15/2011 03/19/2011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 03/15/2011 03/19/2011 IP 71124.04 Occupational Dose Assessment 1, 2, 3 03/15/2011 03/19/2011 IP 71151 Performance Indicator Verification MODS - MODIFICATION/50.59 INSPECTION 3 1, 2, 3 04/11/2011 04/15/2011 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 1, 2, 3 04/25/2011 04/29/2011 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 4 1, 2, 3 06/13/2011 06/17/2011 IP 7111401 Exercise Evaluation 1, 2, 3 06/13/2011 06/17/2011 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 06/13/2011 06/17/2011 IP 71151-EP01 Drill/Exercise Performance 1, 2, 3 06/13/2011 06/17/2011 IP 71151-EP02 ERO Drill Participation 1, 2, 3 06/13/2011 06/17/2011 IP 71151-EP03 Alert & Notification System This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure