IR 05000259/2020004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000259/2020004, 05000260/2020004, 05000296/2020004, 07200052/2020002 and Exercise of Enforcement Discretion
ML21028A218
Person / Time
Site: Browns Ferry  
Issue date: 01/28/2021
From: Tom Stephen
NRC/RGN-II/DRP/RPB5
To: Jim Barstow
Tennessee Valley Authority
References
EA-20-135 IR 2020002, IR 2020004
Download: ML21028A218 (20)


Text

January 28, 2021

SUBJECT:

BROWNS FERRY NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000259/2020004, 05000260/2020004, 05000296/2020004, 07200052/2020002 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Mr. Barstow:

On December 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Browns Ferry Nuclear Plant. On January 26, 2021, the NRC inspectors discussed the results of this inspection with Mr. Matthew Rasmussen, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Thomas A. Stephen, Chief Reactor Projects Branch #5 Division of Reactor Projects

Docket Nos. 05000259, 05000260, 05000296 and 07200052 License Nos. DPR-33, DPR-52 and DPR-68

Enclosure:

As stated.

Inspection Report

Docket Numbers:

05000259, 05000260, 05000296, and 07200052

License Numbers:

DPR-33, DPR-52 and DPR-68

Report Numbers:

05000259/2020004, 05000260/2020004, 05000296/2020004 and

07200052/2020002

Enterprise Identifier: I-2020-004-0052 and I-2020-002-0084

Licensee:

Tennessee Valley Authority

Facility:

Browns Ferry Nuclear Plant

Location:

Athens, Alabama

Inspection Dates:

October 01, 2020 to December 31, 2020

Inspectors:

S. Downey, Senior Reactor Inspector

M. Kirk, Resident Inspector

D. Lanyi, Senior Operations Engineer

H. Lynn, Senior Health Physicist

M. Magyar, Reactor Inspector

A. Nielsen, Senior Health Physicist

C. Rapp, Senior Project Engineer

M. Riley, Reactor Inspector

J. Seat, Project Engineer (Lead)

C. Stott, Resident Inspector

Approved By:

Thomas A. Stephen, Chief

Reactor Projects Branch #5

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Browns Ferry Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000260/2020010-01 Water Hammer Analysis for Unit 2 HPCI Turbine Exhaust Piping 71111.17T Closed EDG EA-20-135 Failure to Comply with 10 CFR 37 for the Protection of Disused Steam Dryer Pieces Stored in a Concrete Module 71124.08 Closed LER 05000259,05000260/20 20-001-01 LER 2020-001-01 for Browns Ferry Nuclear Plant,

Units 1 and 2, Manual Reactor Shutdown of Two Units on Decreasing Condenser Vacuum due to Eel Grass Intrusion 71153 Closed LER 05000259,05000260/20 20-001-00 LER 2020-001-00 for Browns Ferry Nuclear Plant,

Unit 1 re Manual Reactor Shutdown of Two Units on Decreasing Condenser Vacuum due to Eel Grass Intrusion 71153 Closed

PLANT STATUS

Unit 1 began the inspection period in the end of cycle coast down at approximately 85 percent rated thermal power (RTP). On October 2, 2020, the unit was shut down for a planned refueling outage. Unit 1 entered Mode 1 on November 4, 2020, and was shut down on November 5, 2020, to address an Electrohydraulic Control (EHC) leak and elevated Main Turbine vibrations.

The Unit entered Mode 1 again on November 7, 2020 and achieved 85 percent RTP on November 9, 2020. The Unit remained at 85 percent RTP until December 6, 2020, when power was reduced to 60 percent RTP for implementation of a temporary modification to a recirculation flow sensing element. Unit 1 achieved RTP on December 10, 2020, where it remained through the end of the inspection period.

Unit 2 operated at or near RTP for the entire inspection period.

Unit 3 began the inspection period at 100 percent RTP. On December 10, 2020, Unit 3 power was reduced to 50 percent RTP for planned condenser tube maintenance. Unit 3 returned to RTP on December 13, 2020, where it remained through the end of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease 2019 (COVID-19),resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week; conducted plant status activities as described in IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather associated with Hurricane Zeta on October 28, 2020.

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated that flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on November 18, 2020.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1, Reactor water level instrumentation during 1R13 (refueling outage) on October 4, 2020
(2) Unit 3, Train B control bay chiller with Train A out of service for maintenance on October 21, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1, Fire Area 16-K, Auxiliary instrument room #1 on October 5, 2020.
(2) Unit 3, Fire Area 16-A, Control bay chiller room, on October 5, 2020.
(3) Unit 3, Fire Area 21, Diesel generator building on October 9, 2020.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (2 Samples)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Units 1 and 2, 4kV Shutdown board room C on October 6, 2020
(2) Unit 2 Reactor building elevation 565' on November 19, 2020

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors evaluated boiling water reactor non-destructive testing by reviewing the following examinations from October 12 - 16, 2020:

1. Ultrasonic Testing (UT)

a. DRHR-1-2, Pipe to Valve, ASME Class 2 (reviewed) b. N10-1, Safe End to Pipe, ASME Class 1, Manual UT (reviewed)

2. Magnetic Particle Testing (MT)

a. 1-47B455-2268-IA, High Pressure Coolant Injection (HPCI) Welded, ASME Class 2 (reviewed)

3. Penetrant Testing (PT)

a. MS-1-021-181-C0R0, Replacement of 1-FCV-1-169 and associated piping, ASME Class 3 (reviewed)

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The licensee completed the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), "Requalification Requirements," of the NRC's "Operator's Licenses." During the week of November 30, 2020, the inspector performed an in-office review of the overall pass/fail results of the individual operating examinations and the crew simulator operating examinations in accordance with Inspection Procedure (IP) 71111.11, "Licensed Operator Requalification Program." These results were compared to the thresholds established in Section 3.02, "Requalification Examination Results of IP 71111.11.

The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam completed on September 25, 2020.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during the following activities:
  • Unit 1 shutdown and cooldown activities to support refueling outage 1R13 on October 3, 2020, and October 4, 2020
  • Unit 1 startup on November 4, 2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification training in the Unit 2 simulator on November 19, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 2, Function 047-C, Heat removal function of the Turbine Generator Controls EHC system following maintenance to disable main steam bypass valve 1 in the closed position on September 27, 2020.
(2) Units 1, 2 and 3, Function 055-B, Annunciator system associated with the diesel generators on December 16, 2020.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1, High risk evolution (HRE) during lowered inventory until the completion of cavity flood-up and fuel pool gates removed from October 4, 2020 to October 6, 2020.
(2) Unit 1, Yellow shutdown risk due to high decay heat on October 3, 2020.
(3) Unit 1, Heavy lift of the reactor pressure vessel head lift on October 6, 2020.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Operability determination of offsite power via Unit Station Service Transformer (USST) 2B after receipt of USST 2B Load Tap Changer Abnormal alarm on October 2, 2020.
(2) Unit 1 and 2, Shutdown board A battery following discovery of a degraded cell on August 27, 2020.
(3) Unit 1, Operability evaluation associated with a degraded flow indication for 1B reactor recirculation pump on October 30, 2020.
(4) Unit 1, Main steam line B relief valve following leakage found at the bolted connection between the pilot base to main body of the valve during reactor coolant system pressure test performed on October 29, 2020.

===71111.17T - Evaluations of Changes, Tests, and Experiments

Sample Selection (IP Section 02.01)

The inspectors evaluated unresolved item (URI)05000260/2020010-01, "Water Hammer Analysis for Unit 2 HPCI Turbine Exhaust Piping," related to engineering change 71988, for closure.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01)===

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Units 1 and 2, Control bay chiller B after replacement of condenser fan motor on October 5, 2020
(2) Units 1 and 2, C 4kV shutdown board testing following preventative maintenance and a design change on October 17, 2020
(3) Unit 3, Electric board room air conditioning unit (ACU) 3B post maintenance testing following planned maintenance activities on November 22, 2020
(4) Unit 2, Reactor core isolation cooling (RCIC) steam line inboard isolation valve breaker following thermal overload heater replacement on December 12, 2020
(5) Unit 1, 1B recirculation pump flow temporary modification on December 9, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 1 refueling outage activities from October 2, 2020 to November 7, 2020.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 1, 1-SR-3.1.7.7, Standby Liquid Control (SLC) System Functional Test on October 20, 2020
(2) Unit 3, 3-SR-3.5.1.6(CS II), Core Spray Flow Rate Loop II on October 23, 2020
(3) Unit 1, 1-SR-3.5.1.9(RHR II), LOOP II RHR Simulated Automatic Actuation Test on October 4, 2020
(4) Unit 1, 0-SR-3.8.1.9(A), Diesel Generator A Emergency Unit 1 Load Acceptance Test on October 8, 2020
(5) Units 1, 2, and 3, 0-SI-4.5.C.1(C2), C2 Residual Heat Removal Service Water (RHRSW) Quarterly Flowrate Test on November 23, 2020
(6) Unit 1, 1-SR-3.1.4.1, SCRAM Insertion Times Test on October 3, 2020
(7) Unit 3, 3-SR-3.5.1.7, HPCI Main and Booster Pump Set Developed Head and Flow Rate Test at Rated Reactor Pressure on December 9, 2020.

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Unit 1, Pressure isolation valve leak test of residual heat removal (RHR) low pressure core injection valves, 1-FCV-74-67 and 1-CKV-74-68, on October 16, 2020

FLEX Testing (IP Section 03.02) (1 Sample)

(1) Testing of Triton FLEX Floating Booster Pump on November 9, 2020

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Classification and notification during licensed operator requalification simulator training in the Unit 3 Simulator on November 19,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Contamination and Radioactive Material Control (IP Section 03.03) (1 Sample)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) Observed controls for highly radioactive materials stored in the spent fuel pool.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (2 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) Unit 3 Transversing Incore Probe room entry.
(2) Unit 3 under-vessel maintenance activities.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (1 Sample)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) Refuel floor area.

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

(1) Inspectors evaluated the licensees performance in controlling, labelling and securing radioactive materials.

Radioactive Waste System Walkdown (IP Section 03.02 (1 Sample)

(1) Inspectors walked down accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality.

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the licensees characterization and classification of radioactive waste.

(1)2020 Reactor Water Cleanup Waste (2)2020 Dry Active Waste (DAW)

Shipment Preparation (IP Section 03.04) (1 Sample)

(1) The inspectors observed that a shipment containing radioactive material was prepared according to requirements.

Shipping Records (IP Section 03.05) (4 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) RW 19-211, Type B, Filters
(2) RW 20-096, Type B, Resin
(3) RW 19-158, Type B, Irradiated Equipment
(4) RW 20-097, SCO, Contaminated Pump

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (October 1, 2019 - September 30, 2020)
(2) Unit 2 (October 1, 2019 - September 30, 2020)
(3) Unit 3 (October 1, 2019 - September 30, 2020)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (3 Samples)

(1) Unit 1 (October 1, 2019 - September 30, 2020)
(2) Unit 2 (October 1, 2019 - September 30, 2020)
(3) Unit 3 (October 1, 2019 - September 30, 2020)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (3 Samples)

(1) Unit 1 (October 1, 2019 - September 30, 2020)
(2) Unit 2 (October 1, 2019 - September 30, 2020)
(3) Unit 3 (October 1, 2019 - September 30, 2020)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) March 22, 2019 - October 1, 2020

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in biofouling mitigation and operator performance that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors conducted safety culture interviews with individuals from operations, training, radiation protection, and engineering during and prior to the most recent refueling outage on Unit 1. The inspectors concluded that employees interviewed were willing to raise nuclear safety concerns through at least one of the several means available without fear of retaliation.
(2) Condition Report (CR) 1624488, Marine biofouling that resulted in damage to the plant's traveling water screens, Unit 1 and 2 Shutdown, and Unit 3 reduction in power

71153 - Followup of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000259/2020-001-00, Manual Reactor Shutdown of Two Units on Decreasing Condenser Vacuum due to Eel Grass Intrusion (ADAMS Accession No.

ML20260H103), The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements.

(2) LER 05000259/2020-001-01, Manual Reactor Shutdown of Two Units on Decreasing Condenser Vacuum due to Eel Grass Intrusion (ADAMS Accession No.

ML20322A440), The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements. The inspectors reviewed the updated LER submittal.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855.1 - Operation of an Independent Spent Fuel Storage Installation at Operating Plants Operation of an Independent Spent Fuel Storage Installation at Operating Plants

(1) The inspectors evaluated the licensees activities related to long-term operation and monitoring of their independent spent fuel storage installation.

INSPECTION RESULTS

URI Water Hammer Analysis for Unit 2 HPCI Turbine Exhaust Piping URI 05000260/2020010-01 71111.17T

Description:

The NRC opened an unresolved item in inspection report 05000259/2020010, 05000260/2020010 and 05000296/2020010 (ADAMS Accession Number ML20174A300) in order to determine if a violation of 10 CFR 50.59 existed pertaining to the effects of water hammer on the Unit 2 high pressure coolant injection (HPCI) turbine exhaust piping. Engineering Change (EC) 71988 implemented a modification to the Unit 2 HPCI turbine exhaust line and HPCI vacuum breaker subsystem to minimize backflow from the suppression pool into the HPCI exhaust line following a HPCI turbine trip. The Browns Ferry Updated Final Safety Analysis Report (UFSAR) Section 6.4.1 stated that the function of the vacuum breakers was to prevent intermittent negative pressure in the exhaust piping from pulling water out of the torus and causing a water hammer problem. The UFSAR also stated that the HPCI system piping material is composed of carbon steel and is designed to USA Standard (USAS) B31.1.0-1967, Power Piping, which required in section 101.5, Dynamic Effects, that impact forces caused by all external and internal conditions (e.g., water hammer)be considered in the piping design.

Calculation MDQ0020732016000535, "Analysis of Browns Ferry Nuclear Unit 2 HPCI Turbine Exhaust Steam Line Transient Loads Following HPCI Turbine Exhaust System Plant Modifications," Revision 1, analyzed the effects of water hammer induced piping loads in the exhaust lines following the plant modifications to ensure the exhaust lines could handle the stresses upon restarting. The inspectors identified that MPR Report 0048-0052-RPT-001, "Independent Technical Review on Browns Ferry Unit 2 HPCI Turbine Exhaust Piping Proposed Modification," Revision 1, stated that the calculation used a non-conservative assumption of 2% water volume as an input into the water hammer analysis in calculation CDQ0020732016000533, "Browns Ferry Nuclear Plant Summary of Piping Analysis N1-273-01R," Revision 4. The inspectors questioned if the stresses in the HPCI turbine exhaust piping remained within the limits set forth in USAS B31.1.0-1967 upon restarting of the HPCI pump.

To address the issue, the licensee developed a new model of the HPCI turbine exhaust line in calculation MDQ0000732020001009, "Analysis of HPCI Turbine Exhaust Steam Line Transient Loads," Revision 0, to reflect the appropriate water volume in the exhaust line and revised calculation CDQ0020732016000533 to evaluate the impact of the stresses caused on the piping upon HPCI restarting. The licensee concluded that, based on the evaluations performed, the stresses caused by a HPCI restart on the turbine exhaust piping would not result in exceeding the allowable stress limits set forth in USAS B31.1.0-1967. The inspectors reviewed the licensee's evaluation and did not identify a violation of 10 CFR 50.59 requirements.

Corrective Action Reference(s): Condition Report 1606616

Enforcement Discretion Enforcement Action EA-20-135: Failure to Comply with 10 CFR 37 for the Protection of Disused Steam Dryer Pieces Stored in a Concrete Module 71124.08

Description:

From April 29, 2018 - April 20, 2019 the licensee moved pieces of activated/contaminated steam dryers into a large concrete storage module outside the Protected Area. Although this waste material exceeded the threshold for a Category 2 quantity of radioactivity, it did not contain discrete radioactive sources, ion-exchange resins, or activated material that weighs less than 2,000 kg. Therefore, the steam dryer waste is exempt from 10 CFR 37 Subparts B, C, and D, but must comply with the requirements of 10 CFR 37.11(c)(1) - 10 CFR 37.11(c)(4) instead. The inspectors noted that there was no monitored alarm system at the access points to the concrete module.

Corrective Actions: The licensee entered the issue into their corrective action program.

Corrective Action References: CR 1646655

Enforcement:

Violation: 10 CFR 37.11(c)(2) requires that a Category 2 quantity of radioactive waste, that is exempt from Subparts B, C, and D, must be secured with a monitored alarm at the access control point. Contrary to this, from April 29, 2018 to the present, the licensee has stored a Category 2 quantity of exempt waste in a concrete storage module with no monitored alarm system at the access control point.

Basis for Discretion: This violation met the criteria for Enforcement Discretion as described in Enforcement Guidance Memorandum (EGM) 14-001, "Interim Guidance for Dispositioning 10 CFR Part 37 Violations with Respect to Large Components or Robust Structures Containing Category 1 or Category 2 Quantities of Material at Power Reactor Facilities Licensed Under 10 CFR Parts 50 and 52." For tracking purposes, this Enforcement Discretion is being documented as a Minor violation with associated Enforcement Action number EA-20-135.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 26, 2021, the inspectors presented the integrated inspection results to Mr.

Matthew Rasmussen, Site Vice President and other members of the licensee staff.

  • On October 16, 2020, the inspectors presented the ISI Exit Meeting inspection results to S.M. Bono, Site Vice President and other members of the licensee staff.
  • On October 23, 2020, the inspectors presented the RP Inspection Exit Meeting inspection results to Barry Tidwell, Technical Assistant to the Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60855.1

Procedures

0-SR-DCS3.1.2.1

Spent Fuel Storage Inspection

Revision

25

71111.01

Procedures

0-AOI-100-3

Flood Above Elevation 558'

Revision

0048

0-AOI-100-7

Severe Weather

Revision 46

0-TI-599

External Flood Protection Program

Revision

0002

0-TI-600

External Flood Protection Program Bases Document

Revision

0003

NPG-SPP-07.1.8

Severe Weather and Natural Disasters

Revision 1

NPG-SPP-09.22

External Flood Protection Program

Revision

0003

71111.04

Drawings

3-47E866-7

Flow Diagram Air Conditioning Chilled Water

Procedures

0-OI-31

Control Bay and Off-Gas Treatment Building Air

Conditioning System

163

0-OI-31-ATT-1

Valve Lineup Checklist

137

71111.05

Drawings

0-47E864-4

Flow Diagram Ventilation & Air Conditioning Air Flow

Revision 67

Fire Plans

FPR-Volume 2

Fire Protection Report Volume 2

Revision 67

71111.06

Calculations

NDN-000-999-2007-

0031

BFN Probabilistic Risk Assessment - Internal Flooding

Analysis

Revision

2

NDN00099920070031

BFN Probabilistic Risk Assessment - Internal Flooding

Analysis

Revision 2

71111.12

Corrective Action

Documents

CR 1478387, 1440533,

1446447, 1444522,

13390711, 1346921,

1575085, 1471958,

1617180, 1625454,

25455, 1650049

CRs 1640334, 1640153,

26190, 1626176,

1610483, 1647115,

1455874

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

System 055 Health Report

U1/2 Function/System 055-B (a)(1) Plan

Revision 1

20-EEB-047-238

Lift Servo Wires to Disable U2 BPV #1 in the Closed

Position

09/27/2020

Procedures

0-TI-346

Maintenance Rule Performance Indicator Monitoring,

Trending, and Reporting - 10CFR50.65

0-TI-346

Maintenance Rule Performance Indicator Monitoring,

Trending, and Reporting - 10CFR50.65

Revision 53

Work Orders

WO 120053142,

119871580, 119871577,

119871578, 119871579,

21726332, 121142067,

21643646, 121276680,

119822353

WOs 119946024,

21618778, 121619276

71111.13

Engineering

Evaluations

EWR20MEB072099

BFN Unit 1 Core Decay Heat Load Analysis

07/17/20

Miscellaneous

Unit 1 Cycle R13 - Outage Safety Plan

Procedures

0-TPP-FPP-011

BFN NFPA 805 Non-Power Operations Fire Risk

Management

Revision 4

MSI-0-000-LFT001

Lifting Instructions for the Control of Heavy Loads

Revision 77

NPG-SPP-10.6

Infrequently Performed Test or Evolution

Revision 2

71111.15

Calculations

EDQ02482003002

4160V Shutdown Boards A, B, C, D, and 3EB 250V

DC Battery Load Study, Voltage Drop, and Short

Circuit Calculation

Revision 19

Corrective Action

Documents

CR 1632677

CR 1641624

CRs 1648565, 1648452,

1648258

Drawings

1-47E610-68-1

Mechanical Control Diagram Reactor Recirculation

System

Revision 23

7567F-000

Model 7567F 6x10 Relief Valve

Miscellaneous

Adverse Condition Monitoring and Contingency Plan

11/02/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

for 1-FE-68-81

Operational Decision-Making Issue Evaluation

Document for CR 1649288

11/02/2020

Operability

Evaluations

Prompt Determination of Operability Documentation

for CR 1649288

Procedures

OPDP-11

Operational Decision-Making Issue Evaluation

Process

Revision 9

OPDP-8

Operability Determinations Process and Limiting

Conditions for Operation Tracking

Revision 26

Work Orders

WO 121634962

WO 121548591

WOs 121703225,

21702130, 121690633,

20590185

71111.17T Calculations

CDQ0020732016000533

Browns Ferry Nuclear Plant Summary of Piping

Analysis N1-273-01R

Revision 5

MDQ0000732020001009 Analysis of HPCI Turbine Exhaust Steam Line

Transient Loads

Revision 0

MDQ0020732016000535 Analysis of Browns Ferry Nuclear Unit 2 HPCI Turbine

Exhaust Steam Line Transient Loads Following HPCI

Turbine Exhaust System Plant Modifications

Revision 1

Miscellaneous

BFN-50-C-7103

Structural Analysis and Qualification of Mechanical

and Electrical Systems (Piping and Instrument Tubing)

Revision 7

71111.19

Corrective Action

Documents

CR 1490500, 1652321,

1652433, 1653660

CR 1656181

Drawings

0-45E765-3

Wiring Diagram 4160V Shutdown Aux Power

Schematic Diagram

Revision 39

0-731E761-11

Elementary Diagram Emergency Equipment

Revision 25

0-76N4D-2

Wiring Diagram A/C Unit

Revision 7

2-45E2750-1

Wiring Diagram 480V Reactor MOV Board 2B

Connection Diagram

Revision 11

2-45E779-12

Wiring Diagram 480V Shutdown Aux Power Schematic

Diagram

Revision 21

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

3-45E3750-7

Wiring Diagram 480V Reactor MOV Board 3B

Connection Diagram

Revision 9

3-76N3S-1

Mechanical P.I.D. Piping Schematic EBR ACU 3A

Revision 1

Engineering

Changes

BFN-19-346-10

Rewire Breaker 1624 Critical STA Functions from the

STA Switch to the Breaker Auxiliary Contacts

Revision 2

Miscellaneous

BFN-VTD-E322-0220

Ellis and Watts - (C360 Air Conditioner) Installation,

Operation, Maintenance Manual

Revision 2

Procedures

1/2-ETU-SMI 3-C.4

Relay Calibration on 4kV Shutdown Board C

Revision 13

ECI-0-000-BKR008

Testing and Troubleshooting of Molded Case Circuit

Breakers and Motor Starter Overload Relays

Revision

109

EPI-0-000-BKR015

4kV Wyle/Siemens Horizontal Vacuum Circuit Breaker

(Type-3AF) and Compartment Maintenance

Revision 45

EPI-0-000-SWG001

Maintenance of 4160V GE Switchgear/Board Busses

and Compartments

Revision 27

EPI-3-031-CHR001

The Inspection and Maintenance of the Electric Board

Room 3A/3B Air Conditioning Unit

Revision 41

NPG-SPP-07.1.4

Work Management Prioritization-On Line

Revision 16

Work Orders

WO 11874452,

118744454, 120861091,

20160001,

21746995,120680730,

21738807, 121745488

WO 120593794,

20308063, 120593773,

20308064, 121297555,

21297562, 120593810,

20593799, 120251778

WO 121643263

WO 121784227,

21767501

71111.22

Corrective Action

Documents

CR 1648979

CR 1650962, 1651270

Drawings

1-47E811-1-APPJ

Appendix J Testing Boundary for Residual Heat

Removal System

Revision 8

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1-47E858-1

Flow Diagram RHR Service Water System

Revision 72

2-47E858-1

Flow Diagram RHR Service Water System

Revision 30

Procedures

0-SR-3.8.1.9(A)

Diesel Generator A Emergency Unit 1 Load

Acceptance Test

Revision

0013

0-SR-4.5.C.1(C2)

RHRSW Pump C2 IST Group A Quarterly Pump Test

Revision 12

0-TI-360

Containment Leak Rate Programs

Revision 48

1-SI-3.2.74(RHR II)

Pressure Isolation Valve Leakage Test RHR Loop II

Shutdown Cooling Return

Revision 11

1-SR-3.1.4.1

SCRAM Insertion Times

Revision

0018

1-SR-3.1.7.7

Standby Liquid Control System Functional Test

1-SR-3.5.1.9 (RHR II)

Loop II RHR Simulated Automatic Actuation Test

Revision

0017

3-SR-3.5.1.6(CS II)

Core Spray Flow Rate Loop II

FMS-FLEX Pump

Fleet Maintenance Strategy FLEX-Pump-T3 NET

Diesel Driven

Revision 1

PM Job Plan 79413

Triton Satellite Pump Maintenance and Diesel Engine

Run

Revision 1

Work Orders

WO 120251452

WO 120251579

1-SR-3.5.1.9(RHR II) - Loop II RHR Simulated

Automatic Actuation Test

10/04/2020

WO 120251773

0-SR-3.8.1.9(A) - Diesel Generator 'A' Emergency Unit

Load Acceptance Test

10/10/2020

WO 120896643

WO 120899415

3-SR-3.5.1.7 - HPCI Main and Booster PMP Set

Developed Head & Flow Rate Test at Rated Rx

Pressure

2/10/2020

WO 121002777

WO 121641763

1-SR-3.1.4.1 - SCRAM Insertion Times

10/05/2020

71124.08

Corrective Action

Documents

CR 1545278

Corrective Action

Documents

Resulting from

CR 1646655

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

Engineering

Evaluations

Low Level Waste Storage Module Number 1 -

Inventory

Procedures

Radioactive Material Shipping Manual, Volumes I - III

71152

Corrective Action

Documents

CRs 1543185, 1547045,

1560358, 1563233,

1569243, 1617191,

1617669, 1633311,

1650303, 1635949,

1635050, 1633311,

1639000, 1547045,

1560358

Self-

Assessments

Site Trimester Performance Assessment, BFN, June

20-September 2020