Letter Sequence Approval |
---|
TAC:MD0031, Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors (Approved, Closed) |
|
MONTHYEARML0603103722006-01-18018 January 2006 Application for Technical Specification Improvement to Eliminate Requirements for the Hydrogen Monitors Using the Consolidated Line Item Improvement Process Project stage: Request ML0627605162006-10-0202 October 2006 Tech Spec Pages for Amendment 191 Application for Technical Specification Improvement to Eliminate Requirements for the Hydrogen Monitors Using the Consolidated Line Item Improvement Process Project stage: Other ML0616400452006-10-0202 October 2006 Issuance of License Amendment 191 Application for Technical Specification Improvement to Eliminate Requirements for the Hydrogen Monitors Using the Consolidated Line Item Improvement Process Project stage: Approval 2006-01-18
[Table View] |
|
---|
Category:Letter
MONTHYEARNMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 NMP1L3564, Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b NMP1L3563, Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208)2023-12-0404 December 2023 Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) IR 05000220/20234022023-11-28028 November 2023 Security Baseline Inspection Report 05000220/2023402 and 05000410/2023402 NMP1L3557, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000220/20234202023-11-0101 November 2023 Security Baseline Inspection Report 05000220/2023420 and 05000410/2023420 ML23305A0052023-11-0101 November 2023 Operator Licensing Examination Approval IR 05000220/20230032023-10-25025 October 2023 Integrated Inspection Report 05000220/2023003 and 05000410/2023003 IR 05000220/20235012023-10-17017 October 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000220/2023501 and 05000410/2023501 IR 05000220/20230112023-10-16016 October 2023 Comprehensive Engineering Team Inspection Report 05000220/2023011 and 05000410/2023011 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans NMP1L3554, Submittal of Revision 28 to the Final Safety Analysis Report (Updated), Fire Protection Design Criteria Document, 10CFR50.59 Evaluation Summary Report, 10CFR54.37(b) Aging Management Review, and Technical Specifications with Revised Bases2023-10-0606 October 2023 Submittal of Revision 28 to the Final Safety Analysis Report (Updated), Fire Protection Design Criteria Document, 10CFR50.59 Evaluation Summary Report, 10CFR54.37(b) Aging Management Review, and Technical Specifications with Revised Bases C IR 05000220/20233032023-09-20020 September 2023 Retake Operator Licensing Examination Report 05000220/2023303 ML23250A0822023-09-19019 September 2023 Regulatory Audit Summary Regarding LARs to Adopt TSTF-505, Rev. 2, and 10 CFR 50.69 ML23257A1732023-09-14014 September 2023 Requalification Program Inspection IR 05000220/20230052023-08-31031 August 2023 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2023005 and 05000410/2023005) RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs NMP2L2851, Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations2023-08-25025 August 2023 Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration NMP1L3534, License Amendment Request - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2023-08-18018 August 2023 License Amendment Request - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation ML23220A0262023-08-0808 August 2023 Licensed Operator Positive Fitness-for-Duty Test IR 05000220/20234012023-08-0808 August 2023 Cyber Security Inspection Report 05000220/2023401 and 05000410/2023401 (Cover Letter Only) NMP1L3545, Supplemental Information Letter to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems .2023-08-0404 August 2023 Supplemental Information Letter to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems . RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor IR 05000220/20230022023-08-0101 August 2023 Integrated Inspection Report 05000220/2023002 and 05000410/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 NMP1L3544, Fifth Inservice Inspection Interval, First Inservice Inspection Period 2023 Owner'S Activity Report for RFO-27 Inservice Examinations2023-07-14014 July 2023 Fifth Inservice Inspection Interval, First Inservice Inspection Period 2023 Owner'S Activity Report for RFO-27 Inservice Examinations ML23186A1642023-07-0606 July 2023 Operator Licensing Retake Examination Approval NMP2L2846, Nine Mire Point Nuclear Station, Units 1 and 2, General License 30-day Cask Registration Notifications2023-07-0505 July 2023 Nine Mire Point Nuclear Station, Units 1 and 2, General License 30-day Cask Registration Notifications ML23192A0622023-06-30030 June 2023 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance, Report No. 10CFR21-0136, Rev. 0 IR 05000220/20230102023-06-29029 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000220/2023010 and 05000410/2023010 ML23131A4242023-06-23023 June 2023 Issuance of Amendment No. 249 Regarding the Revision to Technical Specification 3.3.1 to Adopt Technical Specifications Task Force Traveler TSTF-568 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3539, Day Commitment Response - Relief Request I5R-11 Concerning the Installation of a Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208)2023-06-0909 June 2023 Day Commitment Response - Relief Request I5R-11 Concerning the Installation of a Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling IR 05000410/20233022023-05-15015 May 2023 Initial Operator Licensing Examination Report 05000410/2023302 2024-02-01
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23131A4242023-06-23023 June 2023 Issuance of Amendment No. 249 Regarding the Revision to Technical Specification 3.3.1 to Adopt Technical Specifications Task Force Traveler TSTF-568 ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23082A3502023-04-17017 April 2023 Issuance of Amendment No. 192, Revision of Surveillance Requirements Associated with Emergency Diesel Generator Testing ML23025A4122023-02-28028 February 2023 Issuance of Amendment No. 248 to Revise Alternative Source Term Calculation for Main Steam Isolation Valve Leakage and Non-MSIV Leakage ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position ML22033A3102022-03-0404 March 2022 Issuance of Amendment No. 190, Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML22021B6602022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000)-Enclosure 1 ML22021B6592022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000) (Letter) ML22031A2762022-02-0101 February 2022 Issuance of Indemnity Agreement Amendments-Enclosure 2 ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements ML21295A7342021-11-15015 November 2021 Issuance of Amendment No. 187 Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21082A2212021-04-29029 April 2021 Issuance of Amendment No. 186, Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML21033A5302021-04-0101 April 2021 Issuance of Amendments to Adopt Technical Specifications Task Force TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML21083A1752021-03-24024 March 2021 Correction to License Page for Amendment No. 245 Related to Relaxation of Surveillance Frequency for Instrument Line Flow Check Valve ML21049A0062021-03-16016 March 2021 Issuance of Amendment No. 245 for Relaxation of Surveillance Frequency for Instrument-Line Flow Check Valve ML21013A0052021-02-0404 February 2021 Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML21033A9432021-02-0202 February 2021 Correction to Acceptance of Requested License Amendment to Adopt Technical Specification Task Force Traveler 582 ML20332A1152021-01-29029 January 2021 Issuance of Amendment No. 183 Regarding Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML20241A1902020-10-20020 October 2020 Issuance of Amendment No. 182 to Change Allowable Main Steam Isolation Valve Leak Rates ML20141L6362020-07-10010 July 2020 Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 ML20134H9402020-07-0808 July 2020 Issuance of Amendments Revising the High Radiation Area Administrative Controls ML20021A0702020-04-0606 April 2020 Issuance of Amendments to Delete License Conditions for Decommissioning Trusts ML20034G5462020-03-12012 March 2020 Issuance of Amendments Revising Instrument Testing and Calibration Definitions ML19301B0052019-11-25025 November 2019 Issuance of Amendment No. 239 Administrative Edits to the Technical Specifications ML19204A0632019-09-13013 September 2019 Independent Spent Fuel Storage Installation, James A. FitzPatrick, and Nine Mile Point - Issuance of Amendments to Revise the Emergency Response Organization Staff ML19176A0332019-08-28028 August 2019 Issuance of Amendments to Adopt TSTF-564, Safety Limit MCPR ML19176A0862019-07-30030 July 2019 Issuance of Amendment No. 237 Changes to Containment Oxygen Concentration Requirements RS-19-017, Application to Remove the Table of Contents from Technical Specifications and Place It Under Licensee Control2019-06-14014 June 2019 Application to Remove the Table of Contents from Technical Specifications and Place It Under Licensee Control ML19008A4542019-01-22022 January 2019 Issuance of Amendment No. 236 Revising Technical Specifications to Adopt TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control ML18304A3652019-01-16016 January 2019 2. Issuance of Amendments to Revise the Average Power Range Monitor Requirements ML18344A4522019-01-11011 January 2019 Issuance of Amendment No. 234 Change to Remove Boraflex Credit from Spent Fuel Racks ML18324A7232018-12-13013 December 2018 Issuance of Amendment No. 233 Relocation of Surveillance Requirement Frequencies to Inservice Testing Program ML18342A0152018-12-0909 December 2018 Issuance of Amendment No. 174 to Revise TS 3.5.1, ECCS-Operating, for One-Time Extension of High Pressure Core Spray Completion Time & Associated Surveillance Requirement (Emergency Circumstances) ML18309A3012018-11-15015 November 2018 R. E. Ginna - Issuance of Amendment Nos. 327, 305, 232, 173, and 133, Respectively, Eliminating the Nuclear Advisory Committee Requirements ML18206A2822018-08-0202 August 2018 Issuance of Amendments to Relocate the Staff Qualification Requirements ML18137A6142018-06-26026 June 2018 Calvert Cliffs Independent Spent Fuel Storage Installation; Nine Mile Point Nuclear Station; and R. E. Ginna Nuclear Power Plant - Issuance of Amendments Revising Emergency Action Level Schemes ML18131A2912018-06-0808 June 2018 Issuance of Amendment No. 170 Removal of Note Associated with Surveillance Requirement 3.5.1.2 (CAC No. MGO148; EPID L-2017-LLA-0294) ML18113A0452018-05-29029 May 2018 Issuance of Amendments to Revise Technical Specification Requirements for Secondary Containment ML18073A3642018-03-28028 March 2018 Issuance of Amendment No. 168 to Revise Technical Specifications to Adopt TS Traveler Force 542, Revision 2, Reactor Pressure Vessel Water Inventory Control (CAC No. MF9357; EPID L-2017-LLA-0178) ML18060A0162018-03-16016 March 2018 Issuance of Amendment No. 167 to Revise Technical Specifications 2.1.1.2 Safety Limit Minimum Critical Power Ratio ML18032A1772018-03-0606 March 2018 Issuance of Amendment No. 166 to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-522 (CAC No. MF9804; EPID L-2017-LLA-0232) ML17324B1782017-12-21021 December 2017 Issuance of Amendment to Allow Greater Flexibility in Performing Surveillance Testing in Modes 1, 2, or 3 of Emergency Diesel Generators(Cac No. MF9579; EPID L-2017-LLA-0203) ML17268A2632017-10-31031 October 2017 Issuance of Amendment to Reduce Steam Dome Pressure in Reactor Core Safety Limits (CAC No. MF8942; EPID L-2016-LLA-0038) ML17163A3552017-08-31031 August 2017 Calvert Cliff, Clinton, Dresden, LaSalle, Limerick, Nine Mile Point, Peach Bottom, Quad Cities, R. E. Ginna, and Three Miles Island - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules(Cac Nos. MF9470-MF9490) ML17152A3202017-06-30030 June 2017 Issuance of Amendments Emergency Plans Emergency Action Level HU1.5 ML17073A0672017-05-26026 May 2017 Issuance of Amendments Revising the Technical Specification Requirements for the Inservice Testing Program (CAC Nos. MF8238 - MF8256) 2023-06-23
[Table view] Category:Safety Evaluation
MONTHYEARML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23131A4242023-06-23023 June 2023 Issuance of Amendment No. 249 Regarding the Revision to Technical Specification 3.3.1 to Adopt Technical Specifications Task Force Traveler TSTF-568 ML23156A6832023-06-22022 June 2023 Authorization and Safety Evaluation of Alternative Relief Request I5R-14 ML23156A6822023-06-22022 June 2023 Authorization and Safety Evaluation of Alternative Relief Request I5R-11 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23103A1912023-04-20020 April 2023 Request for Threshold Determination Under 10 CFR 50.80 ML23082A3502023-04-17017 April 2023 Issuance of Amendment No. 192, Revision of Surveillance Requirements Associated with Emergency Diesel Generator Testing ML23094A1422023-04-0505 April 2023 Approval of Alternative Request I5R-13 to Utilize Specific Provisions of Code Case N-716-3 ML23025A4122023-02-28028 February 2023 Issuance of Amendment No. 248 to Revise Alternative Source Term Calculation for Main Steam Isolation Valve Leakage and Non-MSIV Leakage ML22339A0582022-12-21021 December 2022 Relief Request Associated with Pump Periodic Verification Tests of Core Spray System Pumps ML22293B8052022-11-30030 November 2022 Constellation Energy Generation, Llc_Fleet - Request to Authorize Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position ML22094A0012022-04-15015 April 2022 Constellation Energy Generation, LLC - Proposed Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles (Epids L-2021-LLR-0057 and L-2021-LLR-0058) ML22061A0402022-03-11011 March 2022 Relief Request Associated with Excess Flow Check Valves ML22033A3102022-03-0404 March 2022 Issuance of Amendment No. 190, Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements ML21277A2482021-11-16016 November 2021 Letter with Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (Public Version) ML21295A7342021-11-15015 November 2021 Issuance of Amendment No. 187 Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21256A1792021-11-0202 November 2021 Issuance of Amendment No. 246 Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML21280A0782021-10-27027 October 2021 Proposed Alternative to Use of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-893 (Epids L-2020-LLR-0147 and L-2020-LLR-0148) ML21230A2062021-09-0303 September 2021 Proposed Alternative to Use ASME OM Code Case OMN-28 ML21216A2202021-08-0505 August 2021 Proposed Alternative to Eliminate Certain Documentation Requirements for Pressure Retaining Bolting ML21166A1682021-06-25025 June 2021 ML21140A1532021-06-0303 June 2021 Correction to April 22, 2021 Safety Evaluation for Requests for Alternative to the Inservice Testing Requirements of the ASME OM Code for the Fifth 10-Year Program Interval ML21082A2212021-04-29029 April 2021 Issuance of Amendment No. 186, Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML21109A2162021-04-22022 April 2021 Proposed Alternative to Inservice Testing Requirements of the ASME OM Code for the Fifth 10-Year Interval ML21105A3382021-04-22022 April 2021 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Concerning Examination Coverage of Certain Class 1 and 2 Component Welds ML21033A5302021-04-0101 April 2021 Issuance of Amendments to Adopt Technical Specifications Task Force TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML21049A0062021-03-16016 March 2021 Issuance of Amendment No. 245 for Relaxation of Surveillance Frequency for Instrument-Line Flow Check Valve ML21049A0242021-02-23023 February 2021 Alternative Request to the Requirements of the ASME OM Code for the Testing Intervals for the Instrument-Line Flow Check Valves ML21013A0052021-02-0404 February 2021 Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML21028A6732021-02-0303 February 2021 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L-2020-LLR-011 ML20332A1152021-01-29029 January 2021 Issuance of Amendment No. 183 Regarding Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML21005A0612021-01-14014 January 2021 Proposed Alternatives to Extend the Safety Relief Valve Testing Interval (EPID L-2020-LLR-0014 Through L-2020-LLR-0018) ML20287A1302020-11-0505 November 2020 Review of Quality Assurance Program Changes ML20241A1902020-10-20020 October 2020 Issuance of Amendment No. 182 to Change Allowable Main Steam Isolation Valve Leak Rates ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20232A1712020-09-0101 September 2020 Request to Use Alternative Code Case OMN-26 ML20141L6362020-07-10010 July 2020 Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 ML20134H9402020-07-0808 July 2020 Issuance of Amendments Revising the High Radiation Area Administrative Controls ML20141L0532020-06-0202 June 2020 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML20113F0412020-04-30030 April 2020 Proposed Alternative to the Submittal Schedule for Certain Reports (COVID-19) ML20021A0702020-04-0606 April 2020 Issuance of Amendments to Delete License Conditions for Decommissioning Trusts ML20028E3992020-02-0404 February 2020 Proposed Alternative to Use ASME Code Case N-879 ML19301B0052019-11-25025 November 2019 Issuance of Amendment No. 239 Administrative Edits to the Technical Specifications ML19269C5342019-09-27027 September 2019 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques 2023-08-21
[Table view] |
Text
October 2, 2006 Mr. Timothy J. OConnor Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P. O. Box 63 Lycoming, NY 13093
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT NO. 1 - ISSUANCE OF AMENDMENT RE: APPLICATION FOR TECHNICAL SPECIFICATION IMPROVEMENT TO ELIMINATE REQUIREMENTS FOR THE HYDROGEN MONITORS USING THE CONSOLIDATED LINE ITEM IMPROVEMENT PROCESS (TAC NO. MD0031)
Dear Mr. OConnor:
The Commission has issued the enclosed Amendment No. 191 to Facility Operating License No. DPR-63 for the Nine Mile Point Nuclear Station, Unit No. 1 (NMP-1). The amendment consists of changes to the Technical Specifications (TSs) in response to your application transmitted by letter dated January 18, 2006.
The amendment deletes the reference to the hydrogen monitors in TS 3.6.11, Accident Monitoring Instrumentation.
A copy of the related Safety Evaluation is enclosed. A Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice.
Sincerely,
/RA/
Timothy G. Colburn, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-220
Enclosures:
- 1. Amendment No. 191 to DPR-63
- 2. Safety Evaluation cc w/encls: See next page
ML061640045 *SE input provided by memo. No substantial changes made.
OFFICE LPL-1\PE LPLI-1\PM LPLI-1\LA ITSB\BC LPLI-1\BC NAME NMorgan TColburn SLittle TKobetz* RLaufer DATE 7/03/06 7/03/06 7/05/06 05/24/2006 10/02/06 Nine Mile Point Nuclear Station, Unit No. 1 cc:
Mr. Michael J. Wallace Mark J. Wetterhahn, Esquire President Winston & Strawn Nine Mile Point Nuclear Station, LLC 1700 K Street, NW c/o Constellation Energy Group Washington, DC 20006 750 East Pratt Street Baltimore, MD 21202 Supervisor Town of Scriba Mr. Mike Heffley Route 8, Box 382 Senior Vice President and Chief Oswego, NY 13126 Nuclear Officer Constellation Generation Group Carey W. Fleming, Esquire 1997 Annapolis Exchange Parkway Senior Counsel Suite 500 Constellation Generation Group, LLC Annapolis, MD 21401 750 East Pratt Street, 17th Floor Baltimore, MD 21202 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 126 Lycoming, NY 13093 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mr. Paul D. Eddy Electric Division NYS Department of Public Service Agency Building 3 Empire State Plaza Albany, NY 12223 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399
NINE MILE POINT NUCLEAR STATION, LLC (NMPNS)
DOCKET NO. 50-220 NINE MILE POINT NUCLEAR STATION, UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 191 License No. DPR-63
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Nine Mile Point Nuclear Station, LLC (the licensee) dated January 18, 2006, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-63 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A, which is attached hereto, as revised through Amendment No. 191, are hereby incorporated into the license. Nine Mile Point Nuclear Station, LLC shall operate the facility in accordance with the Technical Specifications.
- 3. This license amendment is effective as of the date of its issuance and shall be implemented within 60 days.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Richard J. Laufer, Chief Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the License and Technical Specifications Date of Issuance: October 2, 2006
ATTACHMENT TO LICENSE AMENDMENT NO. 191 TO FACILITY OPERATING LICENSE NO. DPR-63 DOCKET NO. 50-220 Replace the following page of the Facility Operating License with the attached revised page.
The revised page is identified by amendment number and contains marginal lines indicating the areas of change.
Remove Insert 3 3 Replace the following pages of Appendix A, Technical Specifications, with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert 269 269 272 272
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 191 TO FACILITY OPERATING LICENSE NO. DPR-63 NINE MILE POINT NUCLEAR STATION, LLC (NMPNS)
NINE MILE POINT NUCLEAR STATION UNIT NO. 1 (NMP-1)
DOCKET NO. 50-220
1.0 INTRODUCTION
By letter dated January 18, 2006 (Agencywide Documents Access and Management System Accession No. ML060310372), NMPNS (the licensee) submitted a request for changes to the NMP-1 Technical Specifications (TSs). The requested changes would delete the reference to the hydrogen monitors in TS 3.6.11, Accident Monitoring Instrumentation.
The Nuclear Regulatory Commission (NRC) has revised Section 50.44 to Part 50 of Title 10 of the Code of Federal Regulations (10 CFR), Standards for combustible gas control system in light-water-cooled power reactors. The amended standards eliminated the requirements for hydrogen recombiners and relaxed the requirements for hydrogen and oxygen monitoring. In letters dated December 17, 2002, and May 12, 2003, the Nuclear Energy Institute (NEI)
Technical Specification Task Force (TSTF) proposed to remove requirements for hydrogen recombiners and hydrogen and oxygen monitors from the standard technical specifications (STS), NUREGs 1430 - 1434, on behalf of the industry. This proposed change is designated TSTF-447.
The NRC staff prepared this model safety evaluation (SE) for the elimination of requirements regarding containment hydrogen recombiners and the removal of requirements from TS for containment hydrogen and oxygen monitors and solicited public comment (67 FR 50374, published August 2, 2002) in accordance with the Consolidated Line Item Improvement Process (CLIIP). The use of the CLIIP in this matter is intended to help the NRC to efficiently process amendments that propose to remove the hydrogen recombiner and hydrogen and oxygen monitor requirements from TSs. Licensees of nuclear power reactors to which this model applies were informed (68 FR 55416; September 25, 2003) that they could request amendments conforming to the model, and, in such requests, should confirm the applicability of this SE to their reactors and provide the requested plant-specific verifications and commitments.
[Note: Post-accident hydrogen recombiners are not installed at NMP-1, and there are no oxygen monitoring instrumentation requirements in the NMP-1 TSs. Therefore, the portions of the CLIIP model SE that discuss hydrogen recombiners and oxygen monitoring instrumentation are not applicable to NMP-1.]
2.0 REGULATORY EVALUATION
Regulatory Issue Summary 2000-06, Consolidated Line Item Improvement Process (CLIIP) for Adopting Standard Technical Specification Changes for Power Reactors, was issued on March 20, 2000. The CLIIP is intended to improve the efficiency of NRC licensing processes.
This is accomplished by processing proposed changes to the STS in a manner that supports subsequent license amendment applications. The CLIIP includes an opportunity for the public to comment on proposed changes to the STS following a preliminary assessment by the NRC staff and finding that the change will likely be offered for adoption by licensees. The NRC staff evaluates any comments received for a proposed change to the STS and either reconsiders the change or proceeds with announcing the availability of the change for proposed adoption by licensees. Those licensees opting to apply for the subject change to TSs are responsible for reviewing the NRC staff's evaluation, referencing the applicable technical justifications, and providing any necessary plant-specific information. Each amendment application made in response to the notice of availability would be processed and noticed in accordance with applicable rules and NRC procedures.
The Commissions regulatory requirements related to the content of TSs are set forth in 10 CFR 50.36. This regulation requires that the TSs include items in five specific categories.
These categories include 1) safety limits, limiting safety system settings and limiting control settings, 2) limiting conditions for operation (LCOs), 3) surveillance requirements (SRs), 4) design features, and 5) administrative controls. However, the regulation does not specify the particular TSs to be included in a plants license.
Additionally, 10 CFR 50.36(c)(2)(ii) sets forth four criteria to be used in determining whether an LCO is required to be included in the TSs. These criteria are as follows:
- 1. Installed instrumentation that is used to detect, and indicate in the control room, a significant abnormal degradation of the reactor coolant pressure boundary.
- 2. A process variable, design feature, or operating restriction that is an initial condition of a design basis accident or transient analysis that assumes either the failure of or presents a challenge to the integrity of a fission product barrier.
- 3. A structure, system, or component that is part of the primary success path and which functions or actuates to mitigate a design basis accident or transient that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.
- 4. A structure, system, or component which operating experience or probabilistic risk assessment has shown to be significant to public health and safety.
Existing LCOs and related surveillances included as TS requirements which satisfy any of the criteria stated above must be retained in the TSs. Those TS requirements which do not satisfy these criteria may be relocated to other licensee-controlled documents.
As part of the rulemaking that revised 10 CFR 50.44, the Commission retained requirements for ensuring a mixed atmosphere, inerting Mark I and II containments, and providing hydrogen control systems capable of accommodating an amount of hydrogen generated from a metal-water reaction involving 75 percent of the fuel cladding surrounding the active fuel region in Mark III and ice condenser containments. The Commission eliminated the design-basis loss-of-coolant accident (LOCA) hydrogen release from 10 CFR 50.44 and consolidated the requirements for hydrogen and oxygen monitoring to 10 CFR 50.44 while relaxing safety classifications and licensee commitments to certain design and qualification criteria. The Commission also relocated without change, the hydrogen control requirements in 10 CFR 50.34(f) to 10 CFR 50.44, and the high point vent requirements from 10 CFR 50.44 to 10 CFR 50.46a.
3.0 TECHNICAL EVALUATION
The ways in which the requirements and recommendations for combustible gas control were incorporated into the licensing bases of commercial nuclear power plants varied as a function of when plants were licensed. Plants that were operating at the time of the Three Mile Island (TMI), Unit 2, accident are likely to have been the subject of confirmatory orders that imposed the combustible gas control functions described in NUREG-0737, Clarification of TMI Action Plan Requirements, as obligations. The issuance of plant-specific amendments adopting the changes of TSTF-447 to remove hydrogen recombiner and hydrogen and oxygen monitoring controls from TSs supersede the combustible gas control specific requirements imposed by post-TMI confirmatory orders.
3.1 Hydrogen Monitoring Equipment Section 50.44(b)(1), the STS, and plant-specific TSs currently contain requirements for monitoring hydrogen. Licensees have also made commitments to design and qualification criteria for hydrogen monitors in Item II.F.1, Attachment 6 of NUREG-0737 and Regulatory Guide (RG) 1.97, Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident. The hydrogen monitors are required to assess the degree of core damage during a beyond design-basis accident (DBA) and confirm that random or deliberate ignition has taken place. If an explosive mixture that could threaten containment integrity exists during a beyond DBA, then other severe accident management strategies, such as purging and/or venting, would need to be considered.
The hydrogen monitors are needed to implement these severe accident management strategies.
With the elimination of the design-basis LOCA hydrogen release, hydrogen monitors are no longer required to mitigate DBAs and, therefore, the hydrogen monitors no longer meet the definition of a safety-related component as defined in 10 CFR 50.2. RG 1.97 recommends classifying the hydrogen monitors as Category 1. RG 1.97 Category 1 is intended for key variables that most directly indicate the accomplishment of a safety function for DBA events and, therefore, are items usually addressed within TSs. As part of the rulemaking to revise 10 CFR 50.44, the Commission found that the hydrogen monitors no longer meet the definition of Category 1 in RG 1.97. The Commission concluded that Category 3, as defined in RG 1.97, is an appropriate categorization for the hydrogen monitors because the monitors are required to diagnose the course of beyond DBAs.
Hydrogen monitoring is not the primary means of indicating a significant abnormal degradation
of the reactor coolant pressure boundary. Section 4 of Attachment 2 to SECY-00-0198, Status Report on Study of Risk-Informed Changes to the Technical Requirements of 10 CFR Part 50 (Option 3) and Recommendations on Risk-Informed Changes to 10 CFR 50.44 (Combustible Gas Control), found that the hydrogen monitors were not risk-significant. Therefore, the NRC staff finds that hydrogen monitoring equipment requirements no longer meet any of the four criteria in 10 CFR 50.36(c)(2)(ii) for retention in TSs and, therefore, may be relocated to other licensee-controlled documents.
However, because the monitors are required to diagnose the course of beyond DBAs, each licensee should verify that it has, and make a regulatory commitment to maintain, a hydrogen monitoring system capable of diagnosing beyond DBAs. The elimination of Post-Accident Sampling System requirements from some plant-specific TSs (and associated CLIIP notices) indicated that during the early phases of an accident, safety-grade hydrogen monitors provide an adequate capability for monitoring containment hydrogen concentration. The NRC staff has subsequently concluded that Category 3 hydrogen monitors also provide an adequate capability for monitoring containment hydrogen concentration during the early phases of an accident.
3.2 Oxygen Monitoring Equipment1 STS and plant-specific TS currently require oxygen monitoring to verify the status of the inert containment. Combustible gases produced by beyond DBAs involving both fuel-cladding oxidation and core-concrete interaction would be risk-significant for plants with Mark I and II containments if not for the inerted containment atmospheres. If an inerted containment was to become de-inerted during a beyond DBA, then other severe accident management strategies, such as purging and venting, would need to be considered. The oxygen monitors are needed to implement these severe accident management strategies. Oxygen concentration also appears extensively in the emergency procedure guidelines/severe accident guidelines of plants with inerted containment atmospheres.
With the elimination of the design-basis LOCA hydrogen release, the oxygen monitors are no longer required to mitigate DBAs and, therefore, the oxygen monitors do not meet the definition of a safety-related component as defined in 10 CFR 50.2. RG 1.97 recommends that, for inerted containment plants, the oxygen monitors be Category 1 which is intended for key variables that most directly indicate the accomplishment of a safety function for DBA events.
As part of the rulemaking to revise 10 CFR 50.44, the Commission found that Category 2, as defined in RG 1.97, is an appropriate categorization for the oxygen monitors, because the monitors are required to verify the status of the inert containment.2 Oxygen monitoring is not the primary means of indicating a significant abnormal degradation of the reactor coolant pressure boundary. Oxygen monitors have not been shown by a probabilistic risk assessment to be risk-significant. Therefore, the NRC staff finds that oxygen monitoring equipment 1
NMP Unit 1 does not have oxygen monitoring requirements in its TS. However, this section of the model SE is included as background for the Regulatory Commitment to maintain an oxygen monitoring system to verify status of the inerted containment.
2 While discussing the designation of the oxygen monitors as Category 2, the NRC acknowledged in the final rule (68 FR 54123) that the monitors need not be qualified in accordance with 10 CFR 50.49. The amended rule implements performance-based requirements for hydrogen and oxygen monitors to be functional, reliable, and capable of continuously measuring the appropriate parameter in the beyond DBA environment.
requirements no longer meet any of the four criteria in 10 CFR 50.36(c)(2)(ii) for retention in TSs and, therefore, may be relocated to other licensee-controlled documents.
However, for plant designs with an inerted containment, each licensee should verify that it has, and make a regulatory commitment to maintain, an oxygen monitoring system capable of verifying the status of the inert containment. In addition, separate requirements for primary containment oxygen concentration will be retained in TSs for plant designs with an inerted containment. The basis for retention of this requirement in TSs is that it meets Criterion 2 of 10 CFR 50.36(c)(2)(ii) in that it is a process variable, design feature, or operating restriction that is an initial condition of a DBA or transient analysis that either assumes the failure of or presents a challenge to the integrity of a fission product barrier. This is based on the fact that calculations typically included in Chapter 6 of Updated Final Safety Analysis Reports (UFSARs) assume that the primary containment is inerted, that is, oxygen concentration < 4.0 volume percent, when a design-basis LOCA occurs.
4.0 VERIFICATIONS AND COMMITMENTS As requested by the NRC staff in the notice of availability for this TS improvement, the licensee has addressed the following plant-specific verifications and commitments.
4.1 Each licensee should verify that it has and make a regulatory commitment to maintain a hydrogen monitoring system capable of diagnosing beyond design-basis accidents.
The licensee has verified that it has a hydrogen monitoring system capable of diagnosing beyond DBAs. The licensee has committed in its application to maintain the hydrogen monitors within its UFSAR. The licensee will implement this commitment as part of the implementation of the amendment.
4.2 For plant designs with an inerted containment, each licensee should verify that it has and make a regulatory commitment to maintain an oxygen monitoring system capable of verifying the status of the inert containment.
The licensee has verified that it has an oxygen monitoring system capable of verifying the status of its inerted containment (post-accident monitoring function).
The licensee has committed in its application to maintain the oxygen monitors within its UFSAR. The licensee will implement this commitment as part of the implementation of the amendment.
The NRC staff finds that reasonable controls for the implementation and for subsequent evaluation of proposed changes pertaining to the above regulatory commitments are provided by the licensees administrative processes, including its commitment management program.
The NRC staff has determined that the commitments do not warrant the creation of regulatory requirements which would require prior NRC approval of subsequent changes. The NRC staff has agreed that NEI 99-04, Revision 0, Guidelines for Managing NRC Commitment Changes, provides reasonable guidance for the control of regulatory commitments made to the NRC staff (see Regulatory Issue Summary 2000-17, "Managing Regulatory Commitments Made by Power Reactor Licensees to the NRC Staff," dated September 21, 2000). The commitments should be controlled in accordance with the industry guidance or comparable criteria employed by a
specific licensee. The NRC staff may choose to verify the implementation and maintenance of these commitments in a future inspection or audit.
5.0 STATE CONSULTATION
In accordance with the Commission's regulations, the New York State official was notified of the proposed issuance of the amendment. The State official had no comments.
6.0 ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and changes surveillance requirements. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (71 FR 40749). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
7.0 CONCLUSION
The staff has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: E. Thomas Date: October 2, 2006