MONTHYEARML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23187A4722023-06-30030 June 2023 56603-EN 56603 - Engine Systems, Inc., Report No. 10CFR21-0136, Rev. 0 Re Voltage Regulator Chassis ML23192A0622023-06-30030 June 2023 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance, Report No. 10CFR21-0136, Rev. 0 ML22301A1742022-10-28028 October 2022 Global Nuclear Fuel Americas, LLC (GNF) - Part 21 60-Day Interim Report Notification: GNF3 Raised Water Rod (SC-22-04 Rt) ML21260A0072021-09-0909 September 2021 Ametek Solidstate Controls, Notification of Potential Defect - 10CFR Part 21 Report Re Omron Timer Relay ML20304A1612020-10-14014 October 2020 Lake Engineering Co., Degraded Snubber SF1154 Hydraulic Fluid Batch No. 16DLVS852 Final Report Per 10 CFR Part 21 ML20097B6912020-03-20020 March 2020 Second Interim Notification Per 10 CFR Part 21: Degraded Snubber SF1154 Hydraulic Fluid Batch No. 16DLVS852 ML20042E2522020-01-31031 January 2020 EN 54485 Target Rock Redacted Update to Part 21 Report on Defect of Modification of Valve Component and Main Disc Lift Misadjustment ML20029D1612020-01-21021 January 2020 10 CFR Part 21 Report, Notification of a Defect Modification of a Valve Component and Main Disc Lift Misadjustment ML19199A0342019-07-0505 July 2019 Lake Engineering Co., Third Interim Notification Per 10 CFR Part 21 Degraded Snubber SF1154 Hydraulic Fluid Batch No. ZJS1518 ML19002A2042018-12-21021 December 2018 to Engine Systems, Inc., Part 21 Report Re Emd Fuel and Soakback Pumps - Potentially Undertorqued Cover Bolts ML18354A7422018-12-0404 December 2018 Engine Systems, Inc., Submittal of 1OCFR21 Reporting of Defects and Non-Compliance - Report No. 1OCFR21-0123, Rev. 0 - Emo Fuel and Soakback Pumps - Potentially Undertorqued Cover Bolts ML18353A4282018-11-30030 November 2018 Engine Systems, Inc., 10CFR21-0123, Rev. 0, for a 10CFR21 Reportable Condition on Emd Fuel and Soakback Pumps ML18078A5362018-01-31031 January 2018 Crane Nuclear, Inc. - Interim Report for 10 CFR Part 21 Investigation Report Notification of Xomox Plug Valve High Torsional Stress in Stem (Update) ML18039A2922018-01-24024 January 2018 Velan, Inc. - Corrected Notification for 4NPS Class 150 Through 900 Swing Check Valve Disc (Part Number 8205-012) ML18024A0032018-01-16016 January 2018 Velan Inc. - Part 21 Notification for Disc (Part Number 8205-012) in 4NPS Class 150 Through 900 Swing Check Valve ML17212A6282017-07-24024 July 2017 Lake Engineering Co. - Potentially Degraded Snubber SF1154 Hydraulic Fluid Second - Interim Notification Per 10 CFR Part 21 ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17165A4052017-06-0909 June 2017 Part 21 Report - Potential Minimum Wall Thickness Issue on Certain Posi-Seal Valves ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17026A4142017-01-20020 January 2017 C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling ML16313A0622016-10-18018 October 2016 C&D Technologies, Inc. - 10 CFR Part 21 Evaluation Regarding Terminal Welding Failure in 3DCU-9 Batteries ML16252A2742016-08-29029 August 2016 Azz/Nli - Part 21 Report - Potential Allen Bradley Timing Relay ML16243A4742016-08-26026 August 2016 Potential Part 21 Unqualified Component in Certain Allen Bradley Timing Relays ML16238A1862016-08-15015 August 2016 Update - Report of Potential l0CFR Part 21, Allen Bradley Timing Relay Model 700RTC-NRC Event Number 51030, Accession Number ML15134A016 ML16232A6042016-08-15015 August 2016 Potentially Unqualified Component in Certain Allen Bradley Timing Relays ML16154A2072016-05-26026 May 2016 Part 21, Azz/Nli Nuclear Logistics, Inc., Potentially Unqualified Component in Certain Allen Bradley Timing Relays Model 700RTC ML16194A1992016-05-25025 May 2016 Azz/Nli - Update - Report of Potential 10CFR Part 21, Allen Bradley Timing Relay Model 700RTC ML16111A4202016-04-0808 April 2016 Part 21 Report No. P21-04302015, Rev. 1 Regarding Potentially Unqualified Component in Certain Allen Bradley Timing Relays, Per Browns Ferry, Ginna, Millstone, Nine Mile Point, North Anna, Ft. Calhoun, Perry, River Bend, South Texas Project ML15317A3862015-11-0505 November 2015 Areva Tn - Follow-up Notification of Non-Reportable Condition, Per 10 CFR Part 21 ML15022A6502015-01-20020 January 2015 Letter from Steven R. Eisenberg USNRC 10CFR Part 21 Notification ML14337A0942014-11-24024 November 2014 Notification of Potential Part 21 - Lack of Proper Power Supply Indication ML14329A0632014-11-19019 November 2014 Notification of Potential Part 21 Re Lack of Proper Power Supply Indication ML14275A1622014-09-25025 September 2014 Notification of Potential Part 21 Report - Electromatic Relief Valve Excessive Wear ML14274A0522014-09-22022 September 2014 Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities ML14204A7072014-07-23023 July 2014 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV ML14210A0102014-07-23023 July 2014 Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve ML14204A7082014-07-23023 July 2014 Enclosure 2, Description of Closure Evaluation, Non-Proprietary Information - Class I (Public) ML14303A5262014-03-28028 March 2014 Interim Part 21 Report - Misaligned Separators in LCR-25 Standby Batteries ML13340A3822013-12-0505 December 2013 Part 21 Reportable Condition Notification: Failure of Relay Logic Card Modules in 2 Out of 4 Voters ML15022A6632013-09-27027 September 2013 CDI Non-Conformance Report No. 0343, Non-proprietary Version ML13238A2532013-08-21021 August 2013 Notification of Potential Part 21 Report - Foxboro Power Supply Potential Failures Due to Defective the Wraps and Holders ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13093A1532013-04-0202 April 2013 Part 21 Report - Foxboro Power Supply Potential Failures Due to Defective Tie Wraps and Holders ML13079A3202013-03-18018 March 2013 Notification of Potential Part 21 Interim Report Re Possible Deviation or Defect in Nuclear Qualified High Efficiency Particulate Air Filters ML13064A0122013-02-25025 February 2013 Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve ML13044A0752013-02-0808 February 2013 Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology ML13042A0962013-02-0808 February 2013 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Error in Main Steam Line High Flow Calculational Methodology ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers 2023-07-14
[Table view] Category:Letter
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds NMP2L2880, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 2024-09-04
[Table view] |
Text
ENGINE SYSTEMS, INC.
175 Freight Road Telephone: 252/977-2720 Rocky Mount. NC 27804 Fax: 252/446-1134 June 30, 2023 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001
Subject:
10CFR21 Reporting of Defects and Non-Compliance -
Engine Systems, Inc. Report No. 10CFR21-0136, Rev. 0 Voltage Regulator Chassis - Incorrect Bus Bar Installation P/Ns: 72-12300-100-ESI 72-14200-100-ESI 72-14000-100-6020
Dear Sir / Madam:
The enclosed report addresses a reportable notification for voltage regulator chassis, P/N's: 72-12300-100-ESI , 72-14200-100-ESI , and 72-14000-100-6020.
A copy of the report has also been mailed to our affected nuclear customers.
Please sign below, acknowledging receipt of this report, and return a copy to the attention of Document Control at the address above (or, fax to number 252/446-3830) within 10 working days after receipt.
Yours very truly, ENGINE SYSTEMS, INC.
Susan Woolard Document Control Coordinator Please let us know if ANY of your mailing information changes - name of recipient, name of company/facility, address, etc. Mark the changes on this acknowledgment form and send to us by mail or FAX to the number above.
RECEIVED: _ _ _ _ _ _ __
71 DATE:
Quality Performance With Pride
ENGINE SYSTEMS, INC.
175 Freight Road , Rocky Mount, NC 27804 Telephone: 252/977-2720 Fax: 252/446-1134 Report No. 10CFR21-0136 Rev. O: 06/30/23 10CFR21 REPORTING OF DEFECTS AND NON-COMPLIANCE COMPONENT: Voltage Regulator Chassis - Incorrect Bus Bar Installation P/Ns: 72-12300-100-ESI 72-14200-100-ESI 72-14000-100-6020 SYSTEM : Emergency Diesel Generator CONCLUSION: Reportable in Accordance With 10CFR21 Prepared By:
~;b Engineering Manager Date. ~/3o/t3 Reviewed By: ~ (U)-- Date: 6Lib /21 Quality Assurance Manager Quality Performance With Pride
Report No. 10CFR21-0136 Record of Revisions Page: 1 of 1 REV DATE PAGE DESCRIPTION 0 06/30/23 Initial issue.
Report No. 10CFR21-0136 Revision: 0 Date: 06/30/23 Page: 1 of 4 Pursuant to 10 CFR 21.21(d)(4), ESI is presenting the required information as follows:
(i) Name and address of the individual or individuals informing the Commission.
John Kriesel Dan Roberts Engineering Manager Quality Manager Engine Systems Inc. Engine Systems Inc.
175 Freight Rd. 175 Freight Rd.
Rocky Mount, NC 27804 Rocky Mount, NC 27804 (ii) Identification of the basic component supplied within the United States which fails to comply or contains a defect.
Voltage regulator chassis with the following part numbers:
- 72-14000-100-6020 (iii) Identification of the firm supplying the basic component which fails to comply or contains a defect.
Engine Systems Inc. (ES/)
(iv) Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect of failure to comply .
Copper bus bars are used at rectifier diode pigtail connections CR1, CR2, CR3, CR4, and CR7 to provide a common connection point for associated wiring to minimize the number of conductors on a single fastener. It is intended for the conductors to clamp directly to the bus bar, thereby maintaining a low resistance conduction path between components. ES/ has determined the bus bars were installed incorrectly whereby the conductors are not clamped in direct contact, resulting in current flow through the stainless steel fasteners. This configuration is undesired and will result in unnecessary heat generation which may lead to failure of the connection and therefore failure of the automatic voltage regulator (A VR) assembly. The A VR is relied upon to automatically regulate emergency diesel generator (EOG) terminal voltage. Failure of the AVR would impact ability of the EOG to perform its safety-related function and therefore may impact the nuclear plant's ability to manage safety-related loads during an emergency event.
(v) The date on which the information of such defect or failure to comply was obtained.
May 17, 2023 (vi) In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.
The extent of condition is limited to the following voltage regulator assemblies:
Customer PO ESI Sales Qty Part Number Customer C of C Date Number Order Shipped 72-12300-100-ESI Constellation Energy - Nine Mile Point 00702105 8003195 2 March 1, 2021 72-14200-100-ESI Avaltec I CFE - Laguna Verde (Div Ill) 1879-20 I 700507054 8003429 2 May 16, 2021 72-14000-100-6020 Avaltec I CFE - Laguna Verde (Div 11) 1966 / 700519535 8003506 2 October 25, 2022 Table 1: Voltage Regulator Assemblies Affected
Report No. 10CFR21-0136 Revision: 0 Date: 06/30/23 Page: 2 of4 (vii) The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
For affected users:
- Voltage regulators installed:
Bus bar installation should be corrected immediately by restacking the components to ensure direct contact with all conductors. See section viii below for details.
- Voltage regulators in inventory (not installed):
The bus bar installation should be corrected prior to installation. If desired, the customer may perform on site or the voltage regulator chassis may be returned to ES/ for rework.
For ES/:
The shop traveler used for the build-up of voltage regulator chassis will be enhanced to provide additional guidance and a verification will be added to ensure proper installation of the bus bar. This is in process and will be incorporated for future builds prior to shipment.
(viii) Any advice related to the potential defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
Photos below show an example of an incorrectly installed bus bar (photo 1) and one that is correctly installed that ensures proper conduction (photo 2). Photos and figures on the following pages provide additional information.
Ring lug terminals are not in direct contact with copper bus bar and rely on conduction through the fasteners.
g terminals are in direct with copper bus bar, no on conduction through rs.
Report No. 10CFR21-0136 Revision: 0 Date: 06/30/23 Page: 3 of4 WIR E DIOD E LUG \ / PIGTAIL
\ !
\ I COPP ER
\ \
I I
BUS BAR
\ i
- 1/4 - 20 BOLT
if FLAT WASHER FLAT WASHER l NUT J
/ tj \ FLAT WAS HER
"/ 4" GLAS TIC LOCK WASHER FLAT WASHER J Figure 1: Cross Section - Incorrect Bus Bar Install (Note bus bar is not in direct contact with wire lug and diode pigtail)
WIRE DIODE LUG-\ PIGTAIL COPPER
\ \
BUS BAR l * /4 - 20 BOLT i .......,ef LOCK ~ FLAT WASHER FLAT WASHER ____/ j I 1/4" GLASTIC LOCKWASHER . I FLAT WASH ER_J Figure 2: Cross Section - Correct Bus Bar Install (Note wire lug, diode pigtail, and bus bar stacked in direct contact)
Report No. 10CFR2 1-0136 Revision: 0 Date: 06/30/23 Page: 4 of4 Figure 3 and photo 3 below show location of the bus bars on the voltage regulator chassis.
0 0
Location of the five bus bars at rectifier diodes CR1 , CR2, CR3, CR4, & CR7 Figure 3: Outline Drawing - Chassis Upper Half