RIS 2000-06, Consolidated Line Item Improvement Process for Adopting Standard Technical Specifications Changes for Power Reactors

From kanterella
(Redirected from RIS 2000-06)
Jump to navigation Jump to search
Consolidated Line Item Improvement Process for Adopting Standard Technical Specifications Changes for Power Reactors
ML003693442
Person / Time
Issue date: 03/20/2000
From: Matthews D
Division of Regulatory Improvement Programs
To:
Matthews D
References
RIS-00-006
Download: ML003693442 (7)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555-0001 March 20, 2000

NRC REGULATORY ISSUE SUMMARY 2000-06 CONSOLIDATED LINE ITEM IMPROVEMENT PROCESS FOR

ADOPTING STANDARD TECHNICAL SPECIFICATIONS

CHANGES FOR POWER REACTORS

ADDRESSEES

All holders of operating licenses for nuclear power reactors, except those who have permanently ceased operations and have certified that fuel has been permanently removed from the reactor vessel.

INTENT

The U.S. Nuclear Regulatory Commission (NRC) is issuing this regulatory issue summary (RIS)

to inform the addressees of the opportunity to participate as applicants in the consolidated line item improvement process (CLIIP) for Technical Specifications (TS) amendments. The CLIIP

facilitates licensees adopting of NRC-accepted changes to the Standard Technical Specifications (STS) for their specific plant TS. This process is intended to streamline the license amendment review process involving NRC-accepted STS changes in order to increase NRC efficiency and reduce unnecessary regulatory burden. The NRC role in maintaining plant safety is achieved by the technical review of proposed changes to the STS as well as plant- specific applications to adopt NRC-accepted changes to the STS. In addition, the CLIIP is intended to increase public confidence by making NRCs work process more visible to its stakeholders.

The CLIIP improves the efficiency of the NRC licensing processes by reviewing and documenting STS change requests in a manner that supports subsequent license amendment applications. By soliciting comments from NRC stakeholders, the CLIIP enhances the visibility of the staffs review and revision processes for the STS as well as subsequent license amendment applications. Following the staffs resolution of public comments on a proposed change to the STS, the licensees may submit a license amendment application to adopt the NRC-accepted change by citing the relevant information which would have been made available. Each amendment application made as part of the CLIIP will be processed and noticed in accordance with applicable rules and NRC procedures.

This RIS does not create any new or changed NRC requirements or staff positions, and it requires no specific action or written response. Participation in the CLIIP is purely voluntary.

ML003693442

RIS 2000-06 March 20, 2000

BACKGROUND INFORMATION

The STS for the five vendor designs include Babcock & Wilcox (NUREG-1430), Westinghouse (NUREG-1431), Combustion Engineering (NUREG-1432), General Electric Boiling Water Reactor/4 (BWR/4) (NUREG-1433), and General Electric BWR/6 (NUREG-1434). The review of a proposed generic change to the STS is a multi-staged process designed to ensure that each STS remains internally consistent, maintains coherence among the various vendors STS,

and incorporates the knowledge and operating experience of the industry and the NRC.

Changes to the STS NUREGs, which are potentially applicable to multiple plants, are proposed to the NRC by the Nuclear Energy Institute (NEI) sponsored Technical Specification Task Force (TSTF) through publicly available submittals. The TSTF includes representatives from the four U.S. commercial nuclear power plant owners groups and NEI. The NRC staff reviews the changes to the STS proposed by the TSTF (referred to as TSTF changes) and will accept, modify, or reject them. Once TSTF changes are accepted, they are considered to be part of the STS. Individual licensees may propose to adopt the TSTF changes during a conversion to the STS or as a separate license amendment application.

The objective of the CLIIP is to improve the efficiencies in the processes for NRC review and licensees preparation of license amendment applications for NRC-accepted TSTF changes.

This is primarily accomplished through multiple licensees being able to use the approved safety evaluation prepared for the TSTF change in connection with amendment applications for specific plants. In an effort to make the NRC work processes more visible, the NRC staff will solicit stakeholder comments on the associated change to the STS, the staffs safety evaluation (SE), and the proposed no significant hazards consideration determination (PNSHCD) before finalizing its acceptance of a TSTF change. Following NRC acceptance of a TSTF change, licensees, as well as the NRC staff, will be able to use the relevant documentation from the NRC-accepted TSTF change in the preparation and processing of license amendment applications. Some of the features of CLIIP incorporate lessons learned from the staffs experiences during the development of the STS and related NRC Policy Statements on TS

improvements (e.g., issuing generic letters to announce the availability of line item improvements to TS).

The CLIIP would allow efficient adoption of the TSTF changes by licensees that have converted to the STS, as well as by licensees that have not converted to the STS but have determined that the TSTF changes are applicable to their facilities. This process would streamline the documentation process for both the NRC and the licensees. Furthermore, stakeholder involvement would be fostered from the beginning of this process.

SUMMARY OF ISSUE

The purpose of the CLIIP is to streamline the license amendment review process involving TSTF changes applicable to multiple plants. By using a standardized process such as the CLIIP, the burden on an individual licensee would be reduced by saving resources in preparing license amendment applications and, at the same time, the NRC staff review process would become more efficient. The attached flow chart details the process flow for the CLIIP. There are three required participants in the process flow map: the NEI TSTF, the NRC staff, and the licensees. In addition, all NRC stakeholders are provided an opportunity to comment on a proposed TSTF change before NRC acceptance of the change, as well as to participate in the

RIS 2000-06 March 20, 2000 licensing process for each license amendment application. The major aspects of this process are summarized as follows:

1. The CLIIP will improve the efficient adoption of NRC-accepted TSTF changes by having the staff prepare and publish a safety evaluation (SE). A TSTF change request from the NEI TSTF will include a technical justification and a PNSHCD as part of the proposal.

The TSTF change process supports subsequent license amendment applications.

2. Following its preliminary review, the NRC staff will use a Federal Register notice (FRN)

and the NRC website to inform and solicit comments from NRC stakeholders regarding the proposed TSTF changes that will be incorporated into the CLIIP. The stakeholders will be provided with a description of the TSTF change, the staffs preliminary safety evaluation, and a PNSHCD. After the NRC staff resolves the public comments, another FRN and the NRC website will be used to notify NRC stakeholders if the TSTF change has been accepted by the NRC staff and, if accepted, that the TSTF change is available for adoption in proposed plant-specific license amendment applications.

3. The licensees desiring to adopt a specific TSTF change using the CLIIP will need to verify that the proposed change is applicable to their facilities. The NRC announcement and the staffs SE will specify any plant-specific verification or other information required in licensees applications. The licensees may apply for license amendments by citing the applicability of the PNSHCD and the SE for the accepted TSTF change and addressing any plant-specific information needed to support the staffs review. In order to obtain the maximum efficiency gains from the CLIIP, the NRC will recommend that the licensees submit their applications within a specified time following the FRN

announcing that the TSTF change has been accepted.

4. Each amendment application made as part of the CLIIP will be processed and noticed in accordance with applicable rules and NRC procedures. The NRC efficiency gains are achieved by reducing the plant-specific reviews for those changes that are common to multiple licensees.

By using this process, the CLIIP would allow licensees that have converted to the STS to efficiently adopt the accepted TSTF changes subsequent to the conversion. It would also facilitate efficient adoption of accepted TSTF changes as STS evolve for nonconverted plants.

Finally, with the licensees adoption of the uniform description of the proposed change, the PNSHCD, and the SE for a TSTF change request, the CLIIP would provide more disciplined and consistent adoption of the STS by way of a streamlined amendment process.

BACKFIT DISCUSSION

This RIS does not request any action or written response; therefore, the staff did not perform a backfit analysis.

RIS 2000-06 March 20, 2000

FEDERAL REGISTER NOTIFICATION

A notice of opportunity for public comment on this RIS was not published in the Federal Register because the CLIIP is simply a more effective and efficient application of existing regulations and NRC work processes. The process was developed with opportunities for input from stakeholders during public meetings. The CLIIP adds opportunities for the public to participate in the licensing process.

PAPERWORK REDUCTION ACT STATEMENT

This RIS does not request any information collection.

If there is any question about this RIS, please contact the persons listed below.

/RA/

David B. Matthews, Director Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Technical contacts: Tilda Y. Liu, NRR

301-415-1315 E-mail: tyl1@nrc.gov William D. Reckley, NRR

301-415-1323 E-mail: wdr@nrc.gov Attachments:

1. Consolidated Line Item Improvement Process (CLIIP) Flow Chart

2. List of Recently Issued NRC Regulatory Issue Summaries

Attachment 1 Consolidated Line Item Improvement Process (CLIIP) Flow Chart NEI TSTF NRC Licensees Announce the Solicit public comment Evaluate accepted Identify STS change(s) availability of the Review the proposed on the proposed TSTF TSTF change with applicability to accepted TSTF

TSTF change request change, PNSHCD, and request(s) and verify multiple plants change, associated SE by using an FRN applicability to the plant PNSHCD, and the SE

and the NRC website on the NRC website and in an FRN. The Yes announcement will include a recommended Submit a license Submit a TSTF change schedule for the amendment request request, including submittal of Proposed TSTF change (with information citing description of proposed amendment requests passes preliminary review? adherence to the change, PNSHCD, and (including required proposed change technical justification verifications, description, PNSHCD,

conditions, and SE, and commitments, etc.) addressing any plant- No specific information)

Reject the TSTF Issue FRNs for notice change request of consideration and opportunity for hearing for the license amendment Public comment(s) warrant Yes reconsideration of the applications proposed TSTF change?

No Disposition license amendment applications in Amend description of accordance with NRC

proposed change, regulations PNSHCD, and SE, as appropriate, to resolve public comment(s)

RIS 2000-06 March 20, 2000

FEDERAL REGISTER NOTIFICATION

A notice of opportunity for public comment on this RIS was not published in the Federal Register because the CLIIP is simply a more effective and efficient application of existing regulations and NRC work processes. The process was developed with opportunities for input from stakeholders during public meetings. The CLIIP adds opportunities for the public to participate in the licensing process.

PAPERWORK REDUCTION ACT STATEMENT

This RIS does not request any information collection.

If there is any question about this RIS, please contact the persons listed below.

/RA/

David B. Matthews, Director Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Technical contacts: Tilda Y. Liu, NRR

301-415-1315 E-mail: tyl1@nrc.gov William D. Reckley, NRR

301-415-1323 E-mail: wdr@nrc.gov Attachments:

1. Consolidated Line Item Improvement Process (CLIIP) Flow Chart

2. List of Recently Issued NRC Regulatory Issue Summaries See previous concurrence. DOCUMENT NAME: C:\320-ris.wpd To receive a copy of this document, indicate in the box C=Copy w/o attachment/enclosure E=Copy with attachment/enclosure N = No copy OFFICIAL RECORD COPY

OFFICE RTSB:DRIP Tech Editor DLPM SC:RTSB C:RTSB:DRIP

NAME TLiu* BCalure* WReckley* RDennig * WBeckner*

DATE 3 / 8 /00 03/ 07/00 3 / 8 /00 3 / 8 /00 3 / 9 /00

OFFICE DD:DLPM OGC REXB:DRIP C:REXB:DRIP D:DRIP

NAME SBlack* JRutberg* JShapaker LMarsh DMatthews DATE 3 / 9 /00 3 / 16 /00 3/20/00 3/20/00 3/20/00

Attachment 2 RIS 2000-06 March 20, 2000 LIST OF RECENTLY ISSUED

NRC REGULATORY ISSUE SUMMARIES

______________________________________________________________________________

Regulatory Issue Date of Summary No. Subject Issuance Issued to

______________________________________________________________________________

2000-05 Resolution of Generic Safety Issue 03/16/2000 All holders of OLs for nuclear

165, Spring-Actuated Safety and reactors, except those licensees Relief Valve Reliability who have permanently ceased operations and have certified that fuel has been permanently removed from the reactor vessel

2000-04 Operating Reactor Licensing 03/16/2000 All power reactor licensees Action Estimates

2000-03 Resolution of Generic Safety Issue 03/15/2000 All holders of OLs for nuclear

158: Performance of Safety- reactors, except for those Related Power-Operated Valves licensees who have permanently Under Design Basis Conditions ceased operations and have certified that fuel has been permanently removed from the reactor vessel

2000-02 Closure of Generic Safety Issue 02/15/2000 All holders of OLs for nuclear

23, Reactor Coolant Pump Seal reactors, except for those Failure licensees who have permanently ceased operations and have certified that fuel has been permanently removed from the reactor vessel

2000-01 Changes Concerning Foreign 02/01/2000 All holders of OLs for nuclear Ownership, Control, or reactors Domination of Nuclear Reactor Licensees

_________________________________________________________________________________

OL = Operating Licensing CP = Construction Permit