Letter Sequence RAI |
---|
|
|
MONTHYEARML0519903452005-07-13013 July 2005 License Amendment Request: Technical Specification Improvement Regarding Steam Generator Tube Integrity Using the Consolidated Line Item Improvement Process Project stage: Request ML0528403722005-10-17017 October 2005 Request for Additional Information Regarding Steam Generator Tube Integrity Requirements Project stage: RAI ML0533900822005-11-29029 November 2005 Response to Request for Additional Information - License Amendment Request: Technical Specification Improvement Regarding Steam Generator Tube Integrity Using the Consolidated Line Item Improvement Process Project stage: Response to RAI ML0535602122005-12-23023 December 2005 Supplemental Request for Additional Information (RAI) Regarding Steam Generator Tube Integrity Requirements Project stage: RAI ML0602401112006-01-20020 January 2006 Response to Request for Additional Information - License Amendment Request: Technical Specification Improvement Regarding Steam Generator Tube Integrity Using the Consolidated Line Item Improvement Process Project stage: Response to RAI ML0605300372006-02-13013 February 2006 Supplement to License Amendment Request: Technical Specification Improvement Regarding Steam Generator Tube Integrity Project stage: Supplement ML0604600892006-03-0909 March 2006 Amendment Steam Generator Tube Integrity Project stage: Other ML0606900552006-03-0909 March 2006 Units, 1 and 2, Tech Spec Pages for Amendments 278 and 255 Steam Generator Tube Integrity Project stage: Acceptance Review ML0726202152007-09-28028 September 2007 Correction to Amendment Nos. 278 and 255 Steam Generator Tube Integrity Project stage: Other 2005-07-13
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 ML23289A1202023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20230502023-09-29029 September 2023 Special Inspection Report 05000317/2023050 and Preliminary White Finding and Apparent Violation ML23272A1032023-09-29029 September 2023 Condition Prohibited by Technical Specifications Due to Inoperable Nuclear Instrumentation at Very Low Power IR 05000317/20234012023-09-18018 September 2023 Cyber Security Inspection Report 05000317/2023401 and 05000318/2023401 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23240A3872023-08-28028 August 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23228A1002023-08-15015 August 2023 Notification of Readiness for NRC 95001 Inspection ML23188A0402023-08-0808 August 2023 Issuance of Amendment Nos. 346 and 324 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML23214A1572023-08-0707 August 2023 Correction to the Renewed Facility Operating License Page 3 in Amendment No 345 IR 05000317/20230022023-08-0303 August 2023 Integrated Inspection Report 05000317/2023002 ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 ML23186A0372023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 340 and 318 IR 05000317/20233012023-07-12012 July 2023 Initial Operator Licensing Examination Report 05000317/2023301 and 05000318/2023301 IR 05000317/20230122023-07-10010 July 2023 Commercial Grade Dedication Report 05000317/2023012 and 05000318/2023012 ML23180A2362023-06-29029 June 2023 Correction of Errors on Technical Specification Pages RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23156A6752023-06-20020 June 2023 Request for Withholding Information from Public Disclosure for Proposed Alternative to the Requirements for Repair/Replacement of Saltwater System Buried Piping 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24012A0492024-01-11011 January 2024 Request for Additional Information Regarding Final Response to Generic Letter 2004-02 ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23160A0222023-06-0606 June 2023 NRR E-mail Capture - Calvert Cliffs - Long Term Coupon Surveillance Program RAI ML23156A0102023-06-0404 June 2023 NRR E-mail Capture - Calvert Cliffs - RAI License Amendment Request for Emergency Desiel Generator ML22179A2112022-06-28028 June 2022 Notification of Conduct of a Fire Protection Team Inspection ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22091A2392022-04-0101 April 2022 NRR E-mail Capture - Calvert Cliffs - Formal RAI for Proposed Alternative for Examinations of Certain Pressurizer Welds ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21287A0322021-10-13013 October 2021 Request for Additional Information Re Proposed Alternative for Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML21287A0932021-10-0505 October 2021 Request for Additional Information: Calvert Cliffs 1 & 2 LAR to Revise Spent Fuel Pool Cooling - Shutdown Cooling Systems Licensing Basis (EPID L-2021-LLA-0112) (Email) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21187A2232021-07-29029 July 2021 Temporary Instruction 2515/194 Inspection Documentation Request ML21180A1562021-06-28028 June 2021 Request for Additional Information Regarding License Amendment Request Concerning Containment Sump ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21130A0382021-05-21021 May 2021 Memo to File - Draft Request for Additional Information Relief Request CISI-03-01 Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21053A3142021-02-22022 February 2021 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000317/2021010 and 05000318/2021010 ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML20275A0032020-09-30030 September 2020 Request for Additional Information Regarding Alternative Request Re Inservice Inspection Impracticality (L-2020-LLR-0089) ML20167A2532020-06-15015 June 2020 Second Request for Additional Information Regarding License Amendment Request Concerning Emergency Diesel Generator Surveillance Requirements for Frequency and Voltage Tolerances ML20157A0782020-06-0505 June 2020 Request for Additional Information Regarding License Amendment Request Concerning Emergency Diesel Generator Surveillance Requirements for Frequency and Voltage Tolerances ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H0132020-05-14014 May 2020 IP 71111.17T (50.59) List of Documents Request ML20083F5892020-03-21021 March 2020 Request for Additional Information Regarding License Amendment Request Concerning Reactor Coolant Pump Flywheel Inspection Program ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19261B2202019-09-18018 September 2019 Request for Additional Information Regarding Final Response to Generic Letter 2004-02 ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19155A1612019-06-11011 June 2019 Changes to Draft Request for Additional Information Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Systems, Structures and Components ML19155A1272019-06-0404 June 2019 Request for Additional Information Regarding Request to Adopt 10 CFR 50.69 Risk Informed Categorization and Treatment of Systems, Structures, and Components ML19070A0192019-03-11011 March 2019 Request for Additional Information Regarding Exemption Request from 10CFR50.46(A)(1) to Support Resolution of GSI-191 ML19025A1202019-01-24024 January 2019 NRR E-mail Capture - Calvert Cliffs, Fitzpatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing ML18347A3972018-12-13013 December 2018 Request for Additional Information Regarding Relocation of Emergency Operation Facility ML18138A1372018-05-22022 May 2018 Plants, Units 1 and 2 - Request for Additional Information Regarding Risk Informed Technical Specification Completion Times (CAC Nos. MF7415 and MF7416; EPID L-2016-LLA-0001) ML18128A3842018-05-0808 May 2018 Plants, Units 1 and 2 - Draft Request for Additional Information Regarding Risk-Informed Technical Specification Completion Times (CAC Nos. MF7415 and MF7416; EPID L-2016-LLA-0001) ML18102A2372018-04-12012 April 2018 NRR E-mail Capture - Calvert Cliffs, Ginna, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Action Level Schemes (EPID-L-2017-LLA-0237) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17345A0912018-01-19019 January 2018 Plants, Units 1 and 2 - Request for Additional Information Regarding Alternative Request SI-RR-01, Rev. 0 (CAC Nos. MG0068 and MG0069; EPID L-2017-LLR-0078) ML17346A9092017-12-21021 December 2017 Request for Additional Information Regarding Risk-Informed Technical Specification Completion Times (CAC Nos. MF7415 and MF7416; EPID L-2016-LLA-0001) ML17331B1342017-12-12012 December 2017 2, and R.E. Ginna Nuclear Power Plant - Request for Additional Information - Regarding ML17304A9412017-11-13013 November 2017 Request for Additional Information Regarding Risk-Informed Technical Specification Completion Times (CAC Nos. MF7415 and MF7416; EPID L-2016-LLA-0001) ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17075A0152017-03-16016 March 2017 E-mail from R. Guzman to E. Villar - Calvert Cliffs Unit Nos. 1 and 2 - Request for Additional Information License Amendment Request - Control Room Emergency Ventilation System ML17062A4912017-03-0303 March 2017 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative to RPV Threads in Flange Examination (CAC Nos. MF8712-MF8729) ML16222A1252016-08-0909 August 2016 Request for Additional Information - Relief Request No. RR-ISI-04-11, 2016/08/08 E-mail from R.Guzman to T.Loomis ML15299A2792015-11-0303 November 2015 Request for Additional Information Regarding Relief Request for Dissimilar Metal Butt Welds ML15230A0322015-08-13013 August 2015 Request for Additional Information Regarding the National Association Standard 805 License Amendment Request Fire Protection 2024-01-11
[Table view] |
Text
December 23, 2005 Mr. George Vanderheyden, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2 -
SUPPLEMENTAL REQUEST FOR ADDITIONAL INFORMATION (RAI)
REGARDING STEAM GENERATOR TUBE INTEGRITY REQUIREMENTS (TAC NOS. MC8067 AND MC8068)
Dear Mr. Vanderheyden:
By letter dated July 13, 2005, Calvert Cliffs Nuclear Power Plant, Inc. (the licensee) requested a change to the Technical Specifications (TSs) for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 regarding steam generator tube integrity. Specifically, the licensee requested changes consistent with TS Task Force (TSTF) Change Traveler, TSTF-449, Steam Generator Tube Integrity, Revision 4.
On November 29, 2005, the licensee responded to a request for additional information (RAI) from the Nuclear Regulatory Commission (NRC) staff dated October 17, 2005. The NRC staff has reviewed the information provided in the November 29 response and has determined that additional information is needed to complete its review. The specific questions are provided in the enclosed RAI. This RAI was discussed with your staff on December 14, 2005, and it was agreed that the licensees response would be provided within 30 days from the date of this letter.
If you have any questions, please contact me at 301-415-1457.
Sincerely,
/RA/
Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318
Enclosure:
RAI cc w/encl: See next page
ML053560212 OFFICE LPLI-1/PM LPLI-1/LA CSGB/BC LPLI-1/BC NAME PMilano SLittle AHiser RLaufer DATE 12/14/05 12/22/05 12/14/05 12/23/05 REQUEST FOR ADDITIONAL INFORMATION REGARDING STEAM GENERATOR TUBE INTEGRITY CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-317 AND 50-318 By letter dated July 13, 2005, as supplemented on November 29, 2005 (Agencywide Documents Access and Management System Accession Nos. ML051990345 and ML053390082, respectively), Calvert Cliffs Nuclear Power Plant, Inc. (the licensee) submitted an application for changes to the Technical Specifications (TSs) for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2. The licensee requested changes in accordance with Task Force (TSTF) Change Traveler 449, Steam Generator Tube Integrity (TSTF-449). The Nuclear Regulatory Commission (NRC) staff has reviewed the information that the licensee provided and determined that additional information is required in order to complete the evaluation.
- 1. In its November 29, 2005, letter, the licensee indicated that the current and proposed TSs operational primary-to-secondary leakage limit is 100 gallons per day (gpd) per steam generator (SG) at hot plant conditions. This leakage rate value is also the value assumed in the main steam line break accident (MSLB) analysis. In addition, the licensee indicated that the current licensing basis assumes no accident induced primary-to-secondary leakage. The NRC staff finds from these statements that the licensee may be using the term accident induced primary-to-secondary leakage to refer only to leakage induced by the accident (i.e., leakage from flaws that were not leaking during normal operation).
The NRC staff and the industry (through Technical Specification Task Force Change Traveler 449, Revision 4 (TSTF-449)) have used the term accident induced leakage to include any primary-to-secondary leakage existing prior to the accident in addition to the primary-to-secondary leakage induced during the accident. This was done, in part, because with today's technology it is not possible to distinguish whether the leakage during a design-basis accident (DBA) is coming from flaws that were leaking during normal operation or whether the leakage is coming from flaws that were not leaking during normal operation.
The NRC staff recognizes that plants have assumed that the leak rate during a DBA (such as an MSLB) is the same as the leak rate during normal operation. However, it is important to ensure that neither of these limits are exceeded. As a result, it may be necessary to ensure that the operational leak rate is kept well below the operational leak rate limit since the leak rate experienced during a DBA may be higher than that observed during normal operation. This increase in leak rate can be a result of either:
(1) the higher differential pressure associated with a DBA causing the leak rate from flaws leaking during normal operation to leak at higher rates or (2) the higher loadings associated with a DBA causing a flaw that was not leaking during normal operation to leak during the accident.
Enclosure
Although the operating experience with SGs at Calvert Cliffs (and with similarly designed SGs) has been good, it is possible in the future that operating leakage will be observed and that the licensee may be postulating observed leakage during a DBA. As a result, even with the response to leakage outlined in the November 29, 2005, letter, it is not clear that the licensee will not exceed the accident-induced leakage limit (which historically has been used to include both operating leakage and accident-induced leakage). For example, if a licensee was projecting to observe an accident-induced primary-to-secondary leak rate of 30 gpd and had a current 40 gpd operational primary-to-secondary leak rate, the leak rate during DBAs could be greater than 100 gpd. This is because the operational primary-to-secondary leak rate may double to 80 gpd due to the increase in the differential pressure associated with the accident. When this leakage is combined with your projected accident-induced leak rate of 30 gpd, the total leak rate during the DBA would be 110 gpd, which is greater than that assumed in the DBA analysis. The NRC staff notes that it is most likely not feasible using current technology to ascertain whether the operating leak rate is a result of flaws also projected to leak during a DBA.
Discuss the licensees plans to:
- a. Use the industry accepted definition of accident-induced leakage and modify the proposed TS Bases to be consistent with this definition. If the industry accepted definition will not be used, discuss the plans for modifying the proposed accident-induced leakage rate limit to account for operational leakage.
- b. Modify plant procedures to ensure that the accident-induced leak rate limit will not be exceeded as a result of the higher leak rates that may be observed during a DBA (as a result of inducing "new" leakage or as a result of the higher driving force for leakage). Alternatively, discuss any plans (including the technical basis) for modifying the normal operating and accident-induced leakage limit to address these effects.
- 2. In the table on Page 2 of the September 21, 2005, application, the operational primary-to-secondary leakage limit and accident-induced primary-to-secondary leakage limit are provided. Both limits are 100 gpd per SG measured at room temperature. In November 29, 2005, letter, the operational and accident-induced primary-to-secondary leakage limits are 100 gpd per SG measured at hot plant conditions. Discuss this apparent discrepancy.
Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 cc:
President Patricia T. Birnie, Esquire Calvert County Board of Co-Director Commissioners Maryland Safe Energy Coalition 175 Main Street P.O. Box 33111 Prince Frederick, MD 20678 Baltimore, MD 21218 Carey Fleming, Esquire Mr. Roy Hickok Sr. Counsel - Nuclear Generation NRC Technical Training Center Constellation Generation Group, LLC 5700 Brainerd Road 750 East Pratt Street, 17th floor Chattanooga, TN 37411-4017 Baltimore, MD 21202 Lou Larragoite Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Mr. R. I. McLean, Administrator Radioecology Environ Impact Prog Department of Natural Resources Nuclear Evaluations 580 Taylor Avenue Tawes State Office Building Annapolis, MD 21401 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Kristen A. Burger, Esquire Maryland People's Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD 21202-1631