Notification of Triennial Fire Protection Baseline Inspection (NRC Inspection Report Nos. 05000325-04-010 and 05000324-04-010)
ML042170111
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 08/03/2004
From: Ogle C
Division of Reactor Safety II
To: Gannon C
Carolina Power & Light Co
References
IR-04-010
Download: ML042170111 (7)


See also: IR 05000324/2004010

Text

August 3, 2004

Carolina Power and Light Company

ATTN: Mr. C. J. Gannon

Vice President

Brunswick Steam Electric Plant

P. O. Box 10429

Southport, NC 28461

SUBJECT: NOTIFICATION OF TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

(NRC INSPECTION REPORT NOS. 05000325/2004010 AND

05000324/2004010)

Dear Mr. Gannon:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region II staff will conduct a triennial fire protection baseline inspection of your Brunswick

Steam Electric Plant in November, 2004. The inspection team will be led by Mr. Charles Payne,

Senior Reactor Inspector, of the Region II Office. The team will be composed of personnel

from the NRC Region II Office. The inspection will be conducted in accordance with the NRCs

baseline fire protection inspection procedure 71111.05.

The inspection objective will be to evaluate your fire protection program implementation with

emphasis on post-fire safe shutdown capability and the fire protection features provided to

ensure at least one post-fire safe shutdown success path is maintained free of fire damage.

The inspection team will focus their review on the separation of the systems and equipment

necessary to achieve and maintain safe shutdown and fire protection features of selected fire

areas.

On August 3, 2004, during a telephone conversation with Mr. Steve Tabor, Senior Licensing

Analyst, our respective staffs confirmed arrangements for a three-day information gathering

onsite visit and a two-week onsite inspection. The schedule for the inspection is as follows:

  • Information gathering onsite visit - Week of October 11-15, 2004
  • Week 1 of onsite inspection - November 1-5, 2004
  • Week 2 of onsite inspection - November 15-19, 2004

The purposes of the information gathering visit are to obtain information and documentation

needed to support the inspection, and to become familiar with the Brunswick fire protection

program, fire protection features, post-fire safe shutdown capabilities and plant layout. The

types of documents the team will be interested in reviewing, and possibly obtaining, are listed in

the Enclosure. Please contact Mr. Payne prior to preparing copies of the materials listed in the

Enclosure. The inspection team will try to minimize your administrative burden by specifically

identifying those documents required for inspection preparation.

CP&L 2

During the information gathering visit, the team will also discuss the following inspection support

administrative details - office space, specific documents to be made available to the team in its

office space, arrangements for reactor site access (including radiation protection training,

security, safety and fitness for duty requirements), and the availability of knowledgeable plant

engineering and licensing organization personnel to serve as points of contact during the

inspection.

We request that during the inspection weeks you ensure that copies of analyses, evaluations or

documentation regarding the implementation and maintenance of the Brunswick fire protection

program, including post-fire safe shutdown capability, be readily accessible to the team for its

review. Of specific interest are those documents which establish that your fire protection

program satisfies NRC regulatory requirements and conforms to applicable NRC and industry

fire protection guidance. Also, personnel should be available at the site during the inspection

who are knowledgeable regarding those plant systems required to achieve and maintain safe

shutdown conditions from inside and outside the control room (including the electrical aspects

of the relevant post-fire safe shutdown analyses), reactor plant fire protection systems and

features, and the Brunswick fire protection program and its implementation.

In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter

and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Your cooperation and support during this inspection will be appreciated. If you have questions

concerning this inspection, or the inspection teams information or logistical needs, please

contact Mr. Payne at (404) 562-4669, or me at (404) 562-4605.

Sincerely,

/RA: K. ODonohue for:/

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-325, 50-324

License Nos.: DPR-71, DPR-62

Enclosure: Triennial Fire Protection Inspection Support Documentation

cc w/encl:

W. C. Noll, Director

Site Operations

Brunswick Steam Electric Plant

Carolina Power & Light

Electronic Mail Distribution

(cc w/encl contd - See page 3)

CP&L 3

(cc w/encl contd)

David H. Hinds

Plant Manager

Brunswick Steam Electric Plant

Carolina Power & Light Company

Electronic Mail Distribution

James W. Holt, Manager

Performance Evaluation and

Regulatory Affairs PEB 7

Carolina Power & Light Company

Electronic Mail Distribution

Edward T. O'Neil, Manager

Support Services

Carolina Power & Light Company

Brunswick Steam Electric Plant

Electronic Mail Distribution

Lenny Beller, Supervisor

Licensing/Regulatory Programs

Carolina Power and Light Company

Electronic Mail Distribution

Steven R. Carr

Associate General Counsel - Legal Dept.

Progress Energy Service Company, LLC

Electronic Mail Distribution

John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge

2300 N. Street, NW

Washington, DC 20037-1128

Beverly Hall, Acting Director

Division of Radiation Protection

N. C. Department of Environment

and Natural Resources

Electronic Mail Distribution

Peggy Force

Assistant Attorney General

State of North Carolina

Electronic Mail Distribution

(cc w/encl contd - See page 4)

CP&L 4

(cc w/encl contd)

Chairman of the North Carolina

Utilities Commission

c/o Sam Watson, Staff Attorney

Electronic Mail Distribution

Robert P. Gruber

Executive Director

Public Staff NCUC

4326 Mail Service Center

Raleigh, NC 27699-4326

Public Service Commission

State of South Carolina

P. O. Box 11649

Columbia, SC 29211

David R. Sandifer

Brunswick County Board of

Commissioners

P. O. Box 249

Bolivia, NC 28422

Warren Lee

Emergency Management Director

New Hanover County Department of

Emergency Management

P. O. Box 1525

Wilmington, NC 28402-1525

Distribution w/encl.:

B. Mozafari, NRR

L. Slack, RII

OEMAIL

RIDSNRRDIPMIIPB

PUBLIC

OFFICE RII:DRS RII:DRP RII:DRS RII:DRS

SIGNATURE RA RA RA

NAME PAYNE FREDERICKSON ODONOHUE

DATE 08/ 3 /2004 08/ 3 /2004 08/ /2004 08/ 3 /2004

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

PUBLIC DOCUMENT YES NO

OFFICIAL RECORD COPY DOCUMENT NAME: C:\ORPCheckout\FileNET\ML042170111.wpd

Triennial Fire Protection Inspection Support Documentation

Note: This is a broad list of the documents the NRC inspection team may be interested

in reviewing, and possibly obtaining, during the information gathering site visit. The

current version of these documents is expected unless specified otherwise. Electronic

media is preferred, if readily available. (The preferred file format is searchable .pdf

files on CDROM. The CDROM should be indexed and hyperlinked to facilitate ease of

use. Please provide 5 copies of each CDROM submitted.) Information in lists should

contain enough information to be easily understood by someone who has a knowledge

of the technology. The lead inspector will discuss specific information needs with the

licensee staff and may request additional documents.

1. The Fire Protection Program document and the Fire Hazards Analysis.

2. The fire protection program implementing procedures (e.g., administrative controls,

surveillance testing, fire brigade).

3. The fire brigade training program document and the pre-fire plans for the selected fire

areas/zones (to be determined during information gathering visit).

4. The post-fire safe shutdown analysis, including system and separation analyses.

5. The alternative shutdown analysis.

6. Piping and instrumentation (flow) diagrams for the fire suppression systems.

7. Piping and instrumentation (flow) diagrams for the systems and components used to

achieve and maintain hot standby, and cold shutdown, for fires outside the control room.

8. Piping and instrumentation (flow) diagrams for the systems and components used to

achieve and maintain hot standby, and cold shutdown, in areas requiring alternative

shutdown capability.

9. Plant layout and equipment drawings which identify the physical plant locations of hot

standby and cold shutdown equipment.

10. Plant layout drawings which identify plant fire area and/or fire zone delineation, areas

protected by automatic fire suppression and detection, and the locations of fire

protection equipment for the selected fire areas/zones (to be determined during

information gathering visit).

11. Plant layout drawings which identify the general location of the post-fire emergency

lighting units.

12. Plant operating procedures used to, and describing, shutdown from inside the control

room with a postulated fire occurring in any plant area outside the control room

including, but not limited to, emergency, abnormal, normal and annunciator procedures.

Enclosure

2

13. Plant operating procedures used to implement the alternative shutdown capability from

outside the control room with a fire in either the control or cable spreading room (or any

other alternative shutdown area).

14. Maintenance and surveillance testing procedures for alternative shutdown capability

(including Appendix R emergency lights and communication systems) and fire barriers,

detectors, fire pumps and fire suppression systems.

15. Calculations and/or justifications that verify fuse/breaker coordination for the selected

fire areas/zones (to be determined during information gathering visit) that are fed off the

same electrical buses as components in the protected train. Also, a list of the

maintenance procedures used to routinely verify fuse/breaker coordination in

accordance with the post-fire safe shutdown coordination analysis.

16. A list of the significant fire protection and post-fire safe shutdown design change

descriptions (including their associated 10 CFR 50.59 evaluations) and Generic Letter

(GL) 86-10 evaluations.

17. A list of the protection methodologies (as identified in 10 CFR Part 50, Appendix R,

Section III.G) used to achieve regulatory compliance for the selected fire areas/zones

(to be determined during information gathering visit). That is, please specify whether 3-

hour rated fire barriers (Section III.G.2.a), 20-foot separation along with detection and

suppression (Section III.G.2.b), 1-hour rated fire barriers with detection and suppression

(Section III.G.2.c), or alternative shutdown capability (Section III.G.3) is used for the

selected fire areas/zones.

18. Procedures or instructions that govern the implementation of plant modifications,

temporary modifications, maintenance, and special operations, and their impact on fire

protection.

19. Organization chart(s) of site personnel down to the level of the fire protection staff.

20. Procedures or instructions that control the configuration of the fire protection program,

features, and post-fire safe shutdown methodology and system design.

21. A list of applicable codes and standards related to the design of plant fire protection

features and evaluations of code deviations (i.e., a listing of the NFPA code editions

committed to (Code of Record)).

22. The three most recent fire protection QA audits and/or fire protection self-assessments.

23. A list of open and closed fire protection problem identification and resolution reports

[also known as action reports/condition reports/problem reports/problem investigation

reports/NCRs/EARs] associated with fire protection or Appendix R safe shutdown for the

past three years.

Enclosure

3

24. A list of plant fire protection licensing basis documents (i.e., a list of the SERs and

change evaluations which form the licensing basis for the facilitys post-fire safe

shutdown configuration).

25. A list of fire protection or Appendix R calculations.

26. A list of fire impairments identified during the previous year.

27. A list of abbreviations/designators for plant systems.

Enclosure