ML093230261

From kanterella
Jump to navigation Jump to search
Response to Appeal of Final Significance Determination for a White Finding (NRC Inspection Report No. 05000325-09-12 and 05000324-09-012
ML093230261
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 11/18/2009
From: Reyes L
Region 2 Administrator
To: Waldrep B
Carolina Power & Light Co
References
EA-09-121, IR-09-012
Download: ML093230261 (12)


See also: IR 05000324/2009012

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET, SW, SUITE 23T85

ATLANTA, GEORGIA 30303-8931

November 18, 2009

EA-09-121

Mr. Benjamin C. Waldrep

Vice President

Carolina Power and Light Company

Brunswick Steam Electric Plant

P.O. Box 10429

Southport, NC 28461

SUBJECT: BRUNSWICK STEAM ELECTRIC PLANT- RESPONSE TO APPEAL OF FINAL

SIGNIFICANCE DETERMINATION FOR A WHITE FINDING (NRC

INSPECTION REPORT NO. 05000325/2009012 AND 05000324/2009012)

Dear Mr. Waldrep:

This refers to your letter dated October 13, 2009, in which you responded to the Nuclear

Regulatory Commissions (NRCs) Final Significance Determination of a White Finding and

Notice of Violation issued on September 14, 2009. The violation involved a failure to correctly

designate termination points for linking control power to the emergency diesel generator lockout

relay reset circuitry during the implementation of a design change. This resulted in the wiring for

the control relays being installed such that the emergency diesel generators could not be

operated locally as required by the Brunswick Safe Shutdown Analysis Report. The NRC

characterized the significance of the violation as White (i.e., a finding with low to moderate

increased importance to safety).

In your letter, you outlined six areas of contention as the bases for your appeal which you stated

met one of the appeal criteria in Inspection Manual Chapter (IMC) 0609, Attachment 2, Process

for Appealing NRC Characterization of Inspection Findings (SDP Appeal Process).

Specifically, in each of these six areas, you cited one or both of the following criteria from

section 3 of Attachment 2: a) the NRC staffs application of the significance determination

process was inconsistent with the applicable significance determination process guidance or

lacked justification; or b) the NRC staff did not consider actual (verifiable) hardware, procedures,

guidance, or equipment configuration identified at the regulatory conference or in writing prior to

the final significance determination.

Using the appeal guidelines described in IMC 0609, Attachment 2, your appeal was reviewed to

determine if it had sufficient merit to be forwarded to a formal appeal panel. Although not

required by these guidelines, our response to your appeal was reviewed by NRC staff in the

Office of Nuclear Reactor Regulation, knowledgeable of the significance determination process,

who were not involved in the preliminary or final significance determination. We have

concluded, in consultation with the NRCs Office of Nuclear Reactor Regulation, that none of the

six appeal contentions you raised met the criteria for further review. The NRCs analysis of

each of the six areas of contention in your appeal is enclosed.

_________________________ xG SUNSI REVIEW COMPLETE

OFFICE RII:DRS RII:DRS RII:DRS RII:DRP NRR RII:EICS RII:DRS

SIGNATURE * * * * RA

NAME R.Rodriguez G.MacDonald R. Nease R. Musser C. Evans K. Kennedy

DATE 11/13/2009 11/13/2009 11/16/2009 11/17/2009 11/ /2009 11/ 18/2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICE RII:ORA

SIGNATURE RA

NAME V. McCree

DATE 11/18/2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

CP&L 3

cc w/encl: Michael S. Williams

R. J. Duncan, II Manager, Training

Vice President Brunswick Steam Electric Plant

Nuclear Operations Progress Energy Carolinas, Inc.

Carolina Power & Light Company Electronic Mail Distribution

Electronic Mail Distribution

(Vacant)

Michael J. Annacone Manager

Director Site Operations License Renewal

Brunswick Steam Electric Plant Progress Energy

Progress Energy Carolinas, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Annette H. Pope

Edward L. Wills, Jr. Supervisor, Licensing/Regulatory Programs

Plant General Manager Brunswick Steam Electric Plant

Brunswick Steam Electric Plant Progress Energy Carolinas, Inc.

Progress Energy Carolinas, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Senior Resident Inspector

Benjamin C. Waldrep U.S. Nuclear Regulatory Commission

Vice President Brunswick Steam Electric Plant

Brunswick Steam Electric Plant U.S. NRC

Progress Energy Carolinas, Inc. 8470 River Road, SE

Electronic Mail Distribution Southport, NC 28461

Christos Kamilaris John H. O'Neill, Jr.

Director Shaw, Pittman, Potts & Trowbridge

Fleet Support Services 2300 N. Street, NW

Carolina Power & Light Company Washington, DC 20037-1128

Electronic Mail Distribution

Peggy Force

Joseph W. Donahue Assistant Attorney General

Vice President State of North Carolina

Nuclear Oversight P.O. Box 629

Carolina Power and Light Company Raleigh, NC 27602

Electronic Mail Distribution

Chairman

Brian C. McCabe North Carolina Utilities Commission

Manager, Nuclear Regulatory Affairs Electronic Mail Distribution

Progress Energy Carolinas, Inc.

Electronic Mail Distribution Robert P. Gruber

Executive Director

Phyllis N. Mentel Public Staff - NCUC

Manager, Support Services 4326 Mail Service Center

Brunswick Steam Electric Plant Raleigh, NC 27699-4326

Progress Energy Carolinas, Inc.

Electronic Mail Distribution

(cc w/encl contd - See page 4)

CP&L 4

(cc w/encl contd)

Brunswick County Board of Commissioners

P.O. Box 249

Bolivia, NC 28422

James Ross

Nuclear Energy Institute

Electronic Mail Distribution

Public Service Commission

State of South Carolina

P.O. Box 11649

Columbia, SC 29211

W. Lee Cox, III

(Acting) Section Chief

Radiation Protection Section

N.C. Department of Environmental

Commerce & Natural Resources

Electronic Mail Distribution

Warren Lee

Emergency Management Director

New Hanover County Department of

Emergency Management

230 Government Center Drive

Suite 115

Wilmington, NC 28403

Detailed Appeal Analysis

Carolina Power & Light provided a detailed analysis for six areas of contention as the bases for

their appeal which they stated met the appeal criteria in Inspection Manual Chapter (IMC) 0609,

Attachment 2, Process for Appealing NRC Characterization of Inspection Findings (SDP

Appeal Process). Specifically, in each of these six areas, CP&L cited one or both of the

following two criteria in section 3 of IMC 0609, Attachment 2: a) the NRC staffs application of

the significance determination process was inconsistent with the applicable significance

determination process guidance or lacked justification; or b) the NRC staff did not consider

actual (verifiable) hardware, procedures, guidance, or equipment configuration identified at the

regulatory conference or in writing prior to the final significance determination

In the licensees detailed analysis, enclosed with the letter, these six areas of contention were

associated with refinement areas. Below is NRCs review of each of the licensees six areas of

contention.

Appeal Area #1/Licensee Refinement Area #1 - Fire Ignition Frequencies

Licensees assertion: A sensitivity evaluation of electrical cabinets and main control boards

performed by CP&L staff, consistent with frequently asked question (FAQ) 08-0048 guidance

was not considered by the NRC. The licensee stated that the NRC did not consider their

sensitivity evaluation for determining ignition frequencies for electrical cabinets and main control

boards in the final significance determination. The licensee stated that this meets criterion 3.b.

of Inspection Manual Chapter (IMC) 0609, Attachment 2, as a basis for appeal.

NRCs conclusion: This assertion does not meet appeal criterion 3.b, in that this criterion is

based on plant hardware, procedures, or equipment configurations not being considered by the

NRC. Criterion 3.b. does not include the failure to consider a sensitivity analysis in the

significance determination process as a basis for appeal. However, the NRC reviewed the

licensees sensitivity evaluation, as initially performed, and determined it to be inadequate.

Specifically, CP&L did not use plant-specific data in performing the sensitivity evaluation as

directed by NUREG/CR-6850 and FAQ 08-0048. Therefore, the licensees appeal in this appeal

area does not merit further review.

Basis for NRCs conclusion: As described in the final significance determination letter of

September 14, 2009, the NRC accepted the use of revised fire ignition frequencies (FIFs) for

fire probabilistic risk assessments (PRAs) with the following provision: the fire PRA must

include a sensitivity evaluation of the risk and delta-risk results to evaluations performed using

the current bin FIFs in NUREG/CR-6850. Specifically, NUREG/CR-6850 directs licensees

performing a fire PRA to divide the FIFs by the number of ignition sources within a bin to obtain

plant specific data. In lieu of obtaining plant specific data in this manner, CP&L developed a

ratio of fire bin FIFs between NUREG/CR-6850 and EPRI 1016735, and then applied this ratio

as a reduction to the IMC 0609, Appendix F, FIFs used by NRC. CP&L staff performed walk-

downs to obtain plant-specific data; however, this was done after the NRC issued its final

determination on September 14, 2009. Furthermore, the NRC concluded that incorporating the

revised FIFs per FAQ 08-0048 would not change the final risk characterization.

Enclosure

2

Appeal Area #2/Licensee Refinement Area #3- Source Applicability

Licensees assertion: The NRC did not provide justification for considering high energy arcing

fault (HEAF) fire scenarios for Common Substations C and D and Substations 1L and 2L. The

licensee contended that electrical cabinets of Common Substations C and D and Substations 1L

and 2L contain no mechanical connections and, therefore should not be counted as potential

fire sources. The licensee stated that this meets criterion 3.a of IMC 0609, Attachment 2 as a

basis for appeal.

NRCs conclusion: The NRC disagrees with the licensees assertion that there was no

justification for considering HEAF fire scenarios for Common Substations C & D, and

Substations 1L and 2L. In the final significance determination, the NRC provided clear

justification for the modeling assumptions used for Common Substations C and D, and

Substations 1L and 2L which followed applicable guidance in IMC 0609, Appendix F. The

licensees appeal in this appeal area does not meet criterion 3.a.

The NRC recognized that the licensee could have asserted that actual internal configurations of

Common Substations C and D end cabinets were not considered, which would be addressed by

criterion 3.b. Pictures provided by the licensee subsequent to the regulatory conference

showing mechanical connections were of adjacent cabinets, and were not appropriately labeled

as such. Although provided in a timely manner, the licensee did not provide equipment

configuration information adequate for NRC to consider in its significance determination.

Therefore criterion 3.b was not met.

The licensees appeal in this appeal area does not meet either criterion 3.a or 3.b of IMC 0609,

Attachment 2; therefore does not merit further review by an appeal panel.

Bases for NRCs conclusion: During the regulatory conference held on July 28, 2009, the

licensee disagreed with the NRCs modeling of Common Substations C and D end cabinets as

general electrical cabinets, and agreed to provide additional information regarding their internal

configurations. Prior to the issuance of the final significance determination, the license provided

numerous pictures of cabinet internals. The pictures were poorly labeled and the NRC

assumed that the cabinet internals showing electrical terminations were those of Common

Substations C and D end cabinets, which were the subject of discussion during the regulatory

conference. Based on this, the NRC revised its final significance determination to model

Common Substations C and D end cabinets as bus ducts, which was the closest fit per IMC 0609, Appendix F. As such, only HEAF fire scenarios were considered in the significance

determination. The NRC justified this approach in the final significance determination through

the use of applicable guidance in IMC 0609, Appendix F; therefore, appeal criterion 3.a was not

met for Common Substation C and D.

Upon receipt of this appeal, discussions with licensee staff, and further review of the

photographs that CP&L staff provided, the NRC learned that the pictures showing electrical

terminations were of adjacent transformer cabinets, not Common Substations C or D end

cabinets. The NRC reviewed the licensees appeal using criterion 3.b, and determined that it

was not met, as the licensee did not provide adequate equipment configuration information for

NRC to use in its final significance determination. Regardless of whether appeal criteria were

met, the NRC performed a sensitivity analysis assuming Common Substations C and D end

cabinets were not potential fire sources, and determined that the risk reduction was negligible

and would not change the significance characterization of the violation.

Enclosure

3

With respect to Substations 1L and 2L, during the regulatory conference held on July 28, 2009,

the licensee disagreed with the NRCs modeling of Substations 1L and 2L end cabinets as

general electrical cabinets, and agreed to provide additional information regarding their internal

configurations. Prior to the issuance of the final significance determination, the license provided

additional information showing that Substations 1L and 2L end cabinets contained disconnect

switches. The NRC revised its significance evaluation to model Substations 1L and 2L end

cabinets as breakers, which was the closest fit per IMC 0609, Appendix F. As such, both fire

and HEAF scenarios were considered in the NRCs final significance determination. In their

appeal, the licensee contended that the disconnect switches should not be considered as an

ignition source. The characterization of Substations 1L and 2L end cabinets was justified in the

final significance determination through the use of applicable SDP guidance. Therefore, appeal

criterion 3.a was not met for Substations 1L and 2L.

Appeal Area #3/Licensee Refinement Area #5 - Motor Control Center Fire Growth Rates

Licensees assertion: The motor control centers (MCCs) meet the guidance in NUREG/CR-6850

and FAQ 08-0042 to be considered well-sealed. The licensee stated that the NRC did not

provide justification for characterizing the MCCs as not being well-sealed, which meets

criterion 3.a of IMC 0609, Attachment 2, as a basis for appeal.

NRCs conclusion: The licensees assertion does not meet appeal criterion 3.a, in that the

NRCs final significance determination evaluation was consistent with applicable guidance in

NUREG/CR-6850 and IMC 0609, Appendix F, and was justified through the use of that

guidance. These MCCs cannot be considered well-sealed due to the openings in the

cabinets, as well as closing mechanisms on the cabinets which would allow an internal fire to

propagate outside of its boundaries. The NRC also considered criterion 3.b in this appeal area,

and concluded that it was not met, because actual MCC configurations were considered in the

final risk determination. The licensees basis for appeal does not meet either criterion 3.a, or

criterion 3.b.

Bases for NRCs conclusion: The licensee contends that the NRC did not provide adequate

justification in treating the MCCs as not being well-sealed, which they stated would meet

appeal criterion 3.a of IMC 0609, Attachment 2. Further, the licensee stated that the NRC only

considered weather-proof cabinets to be well-sealed. The NRC justified the characterization of

the MCCs by applying the guidance in NUREG/CR-6850 and IMC 0609, Appendix F. Using this

guidance, these MCCs cannot be considered well-sealed due to the openings in the MCCs, as

well as the closing mechanisms on the cabinets which would allow an internal fire to propagate

outside of its boundaries. The licensee also stated that only the upper half of the MCC sections

should be considered for fires that could impact overhead cables. The NRC determined that it

was not reasonable to assume that a fire within a closed cabinet could not propagate to other

areas within the same cabinet. The NRC determined that postulated fires can grow, and

therefore does not agree with the licensees contention that only the upper half of MCC sections

would be capable of affecting overhead cable trays. Subsequent to the regulatory conference,

FAQ 08-0042 was issued. The NRC considered the MCC configurations relative to that FAQ,

and determined that it was not applicable. The NRC justified the characterization of the MCCs

in the final significance determination through the use of applicable SDP guidance; therefore

appeal criterion 3.a was not met.

In reviewing this appeal area, the NRC also considered the applicability of criterion 3.b to IMC 0609, Attachment 2, which states that actual verifiable plant hardware or equipment

configuration identified at the regulatory conference or prior to the issuance of the final

significance determination was not considered by the NRC. Ultimately, the NRC determined

Enclosure

4

that this criterion was not met, because actual MCC configurations were considered in the final

significance determination.

Appeal Area #4/Licensee Refinement Area #6 - Solid Bottom Trays

Licensee Assertion: The NRC did not follow the guidance in NUREG/CR-6850 regarding cable

damage delay for solid bottom cable trays, and did not provide justification in using a 5-minute

time delay for damage to cables in solid bottom electrical cable trays. The licensee claimed this

met criteria 3.a of IMC 0609, Attachment 2, as a basis for appeal.

NRCs conclusion: This assertion does not meet appeal criterion 3.a, in that the NRC applied

the guidance in NUREG/CR-6850 and Sandia National Laboratory Report SAND 77, as

appropriate, to the actual circumstances, which was fully justified in the final significance

determination. Therefore, the licensees appeal in this appeal area does not merit further

review.

Bases for NRCs conclusion: Based on the guidance in NUREG/CR-6850, the NRC agreed that

some cable damage time delay credit should be given for cables located in solid bottom trays.

In the final significance determination, the NRC determined the appropriate cable damage time

delay credit to be 5 minutes. It is the NRCs view that data from actual test fires documented

NUREG/CR-6850 must be applied when it is appropriate (i.e., when the tested configuration is

similar to the actual in-plant configuration being modeled). The NRC concluded that it was not

reasonable to assume that IEEE-383 cables in solid bottom trays would never ignite in a

postulated fire. As stated in the final significance determination, the NRC used NUREG/CR 6850, Sandia National Laboratory Report SAND77, and actual cable tray configuration to reach

an informed assumption that there would be a 5-minute delay prior to cable damage.

In addition, the delay time for damage for solid bottom tray barriers was a risk modeling

assumption in the SDP analysis, and the basis for limiting the credit to 5 minutes was discussed

with the licensees staff and addressed in the final significance determination letter. The NRC

followed the relevant guidance and the assumptions in question represent a justified risk

modeling assumption which is not appealable. Therefore, the licensees assertion did not meet

appeal criterion 3.a of IMC 0609, Attachment 2.

Appeal Area #5/Licensee Refinement Area #7 - Non-Suppression Probability

Licensee Assertion: The licensee provided four areas of contention in appeal area #5: (a) the

NRC staff did not consider the timeline for non-suppression probability provided by CP&L; (b)

the NRC provided no justification for the 3-minute cable damage delay for coated, qualified

cable; (c) the NRC did not discuss how the fire timeline and fire growth was determined and

when the detection occurs; and (d) the NRCs timeline does not identify when the credit for solid

bottom trays and flame retardant coating starts. The licensee stated that this meets criteria 3.a

and 3.b. of IMC 0609, Attachment 2, as a basis for appeal.

NRCs conclusion: None of the four contentions described in this assertion meet appeal criteria

3.a or 3.b; therefore, the licensees appeal in this appeal area does not merit further review.

Contention (a): Failure to consider the licensees timeline for non-suppression does not meet

either appeal criteria 3.a or 3.b. With respect to criterion 3.a, the NRC followed appropriate

guidance and justified the non-suppression probability. Regarding criterion 3.b, the NRC

considered plant hardware and equipment configurations in developing the non-suppression

probability. Furthermore, the NRC considered the licensees timeline, but disagreed with it.

Enclosure

5

Contention (b): The licensees contention that the NRC did not provide justification for the 3-

minute cable damage delay does not meet appeal criterion 3.a or 3.b. With respect to criterion

3.a, the NRC followed appropriate guidance and justified the 3-minute cable damage delay for

coated, qualified cables using actual cable and cable tray configurations and fire test data in

developing the 3-minute cable damage delay. Regarding criterion 3.b, the NRC considered

actual plant hardware and equipment configurations to develop the 3-minute cable damage

delay.

Contention (c): The failure to discuss how the fire timeline and fire growth was determined and

when the detection occurs does not meet appeal criterion 3.a or 3.b. With respect to criterion

3.a, the NRC developed the fire-growth timeline consistent with applicable guidance in

accordance with IMC 0609, Appendix F, and provided a summary of the results in the final

significance determination. Regarding criterion 3.b, the NRC considered plant hardware,

equipment configurations (actual cable and cable tray configurations), and fire test data in

developing the fire-growth timeline used in the final significance determination.

Contention (d): The failure to identify when credit for solid bottom trays and fire retardant

coatings starts does not meet either criterion 3.a or 3.b. With respect to criterion 3.a, the NRC

determined how much credit to give for cable coatings and solid bottom trays consistent with

applicable guidance in IMC 0609, Appendix F. Regarding criterion 3.b, the NRC considered

actual cable and cable tray configurations, and test data in determining how much credit to give

for cable coatings and solid bottom trays in the final significance determination.

Bases for NRCs conclusion

Contention (a): The NRC considered the licensees proposed timeline for non-suppression

probability, but disagreed with it. With respect to criterion 3.a, the NRC followed appropriate

guidance in IMC 0609, Appendix F and NUREG/CR-6850, and justified the methodology used in

developing the non-suppression probability used in the final significance determination. The

NRC used appropriate guidance to develop non-suppression probability; therefore, the licensee

did not meet appeal criterion 3.a. Regarding criterion 3.b, the NRC considered actual plant

hardware, procedures and equipment configurations (cable and cable tray configurations) in

developing the non-suppression probability used in the final significance determination. The

NRC used actual plant configuration to determine non-suppression probability; therefore, the

licensee did not meet appeal criterion 3.b. The licensees appeal in this area did not meet any

of the appeal criteria listed in IMC 0609, Attachment 2.Furthermore, the failure to consider the

licensees timeline does not meet any of the appeal criteria listed in IMC 0609, Attachment 2.

Contention (b): With respect to criterion 3.a, the NRC followed appropriate guidance and

justified the 3-minute cable damage delay for coated, qualified cables using actual cable.

Specifically, the NRC reviewed fire testing referenced by NUREG/CR-6850 applicable to these

passive fire protection features and determined that the licensee did not appropriately

characterize the test data in their evaluation. Limitations in the test data relative to the credit for

solid bottom cable tray barriers is discussed above in appeal item #4 above. The NRC used

appropriate guidance to determine cable damage delay; therefore, the licensee did not meet

appeal criterion 3.a. Regarding criterion 3.b, the NRC considered actual cable and cable tray

configurations, and fire test data referenced by NUREG/CR-6850 in developing the 3-minute

cable damage delay used in the final significance determination. The NRC used actual plant

configuration to determine cable damage delay; therefore, the licensee did not meet appeal

criterion 3.b. The NRC concluded that solid bottom trays and cables sprayed with Flame-

Master 71A or Flame-Master 77 flame retardant coatings will not prevent fire ignition, fire

Enclosure

6

Growth, or cable damage, but will delay the onset of ignition, propagation and cable damage,

allowing more time for fire brigade response. The licensees appeal in this area did not meet

any of the appeal criteria listed in IMC 0609, Attachment 2.

Contention (c): With respect to criterion 3.a, the NRC developed the fire-growth timeline

consistent with applicable guidance in IMC 0609, Appendix F, and provided a summary of the

results in the Phase 3 SDP and final significance determination. As stated in the final

significance determination, the NRC used NUREG/CR 6850, IMC 0609, and actual plant

configurations to determine how much credit should be given to fire retardant coatings and solid

bottom trays in delaying cable ignition. The NRC developed the fire-growth timeline consistent

with IMC 0609 Appendix F and NUREG 1805, Fire Dynamics Tools, which is referenced in

IMC 0609. Fire detection and suppression was used to develop non-suppression probability

also in accordance with IMC Appendix F and NUREG 1805. The NRC used the fire-growth

timeline and the non-suppression probability in calculating 17 different fire scenarios. The

results were provided in Summary Table 2 (for the MCR) and Summary Table 3 (for the cable

spreading room) in the final significance determination. The NRC performed a spreadsheet

analyses to calculate time of detection for all scenarios with results <1 minute. In accordance

with IMC 0609, Appendix F, the results were rounded up to 1 minute, and were used for

calculating the probability of non-suppression. The NRC used appropriate guidance in

developing the fire-growth timeline; therefore, the licensees appeal in this area did not meet

appeal criterion 3.a. Regarding criterion 3.b, the NRC used actual cable and cable tray

configurations in developing the fire-growth timeline used in the final significance determination.

The NRC used actual plant configuration in developing the fire-growth timeline; therefore, the

licensees appeal in this area did not meet appeal criterion 3.b. The licensees appeal in this

area did not meet any of the appeal criteria listed in IMC 0609, Attachment 2.

Contention (d): With respect to criterion 3.a, the NRC determined how much credit to give for

cable coatings and solid bottom trays consistent with applicable guidance in IMC 0609,

Appendix F. As discussed above in appeal area #4 and appeal area #5, contention (c), delay

credit for solid bottom trays and fire retardant coatings was incorporated into the final

significance determination as cable damage time delay. As stated in the final significance

determination, the NRC used NUREG/CR 6850, IMC 0609, and actual plant configurations to

determine how much cable damage delay credit should be given to fire retardant coatings and

solid bottom trays. The NRC developed time-to-damage consistent with IMC 0609, Appendix F

and NUREG 1805, Fire Dynamics Tools, which is referenced in IMC 0609. The NRC used

appropriate guidance in determining how much credit to give for cable coatings and solid bottom

tray; therefore, the licensees appeal in this area did not meet appeal criterion 3.a. Regarding

criterion 3.b, the NRC considered actual cable and cable tray configurations, and test data in

determining how much credit to give for cable coatings and solid bottom trays in the final

significance determination. The NRC used actual plant configuration is determining how much

credit to give for cable coatings and solid bottom trays; therefore, the licensees appeal in this

area did not meet appeal criterion 3.b. The licensees appeal in this area did not meet any of

the appeal criteria listed in IMC 0609, Attachment 2.

Appeal Area #6/Licensee Refinement Area #8 - Alternative Safe Shutdown (ASSD)

Implementation

Licensees assertion: The NRC staff did not consider simulator scenarios and operator

interviews, nor was there a justification for why this information was not considered in

determining the entry point into the ASSD procedure for fires in main control room (MCR) panel

XU-2. The licensee stated that this met criteria 3.a and 3.b. of Inspection Manual Chapter 0609,

Attachment 2, as a basis for appeal.

Enclosure

7

NRCs conclusion: The licensees appeal in this area does not meet criterion 3.a, or criterion

3.b; therefore, does not merit further review. Regarding criterion 3.a, the NRC followed

applicable guidance and provided justification for the modeling assumptions used in determining

the ASSD entry point for fires in the MCR. Furthermore, in accordance with criterion 3.a, issues

involving the staffs modeling assumptions are not appealable. Regarding criterion 3.b, the

NRC considered actual MCR panel configurations in developing modeling assumptions used to

determine the entry point into the ASSD.

Basis for NRCs conclusion: The NRC disagrees with the licensees assertion that the NRC did

not consider simulator scenarios and the operator interviews in its determination of the

alternative safe shutdown (ASSD) entry point. The NRC reviewed and considered the simulator

scenarios and operator interviews, but had concerns regarding the use of this data, because of

operators knowledge of the issue prior to the interviews. This performance deficiency was

known by the licensees staff since the fall of 2008, and operators were well aware of the risk of

implementing procedure 0-ASSD-02 in light of this violation.

As stated in the final significance determination, the NRC risk analysts used the following risk

modeling assumption: that 10% of fires would remain unsuppressed and grow to the point

where enough ASSD equipment an/or instrumentation is damaged such that the senior control

operator would choose to enter the ASSD procedures. Regarding criterion 3.a, the NRC

followed applicable guidance and provided justification for the modeling assumptions used in

determining the ASSD entry point for fires in the MCR. The NRC justified the assumptions used

in the final significance determination through the use of applicable SDP guidance; therefore

appeal criterion 3.a was not met. Furthermore, in accordance with criterion 3.a, issues involving

the staffs modeling assumptions are not appealable. Regarding criterion 3.b, the NRC

considered actual MCR panel configurations in developing modeling assumptions used to

determine the entry point into the ASSD procedures. The 10% ASSD factor was developed

based on a review of MCR panel configurations and potential spurious equipment actuation and

instrument failure due to fire-damaged cables. This damage could affect both onsite and offsite

power. Because the NRC used actual plant configurations in determining the entry point into

ASSD procedures, appeal criterion 3.b was not met.

Although the likelihood is low, a fire in MCR panel XU-2 could damage normal offsite power

feeder breaker controls to the emergency buses and breaker controls for emergency diesel

generators, including MCR cross-tie breaker controls. The NRC concluded that this would meet

the ASSD entry criteria. The NRC followed applicable NRC guidance and used actual plant

equipment configurations in developing justified risk modeling assumptions. Furthermore risk

assumptions are excluded from the appeal criteria. The licensees appeal in this area did not

meet any of the appeal criteria listed in IMC 0609, Attachment 2.

Enclosure

Letter to Benjamin C. Waldrep from Luis A. Reyes dated

SUBJECT: BRUNSWICK STEAM ELECTRIC PLANT- RESPONSE TO APPEAL OF FINAL

SIGNIFICANCE DETERMINATION FOR A WHITE FINDING (NRC

INSPECTION REPORT NO. 05000325/2009012 AND 05000324/2009012),

Distribution w/encl:

C. Evans, RII EICS

L. Slack, RII EICS

OE Mail (email address if applicable)

RIDSNRRDIRS

PUBLIC

R. Pascarelli, NRR (Regulatory Conferences Only)

RidsNrrPMBrunswick Resource

L. Wert, RII DRP

J. Munday, RII DRP

R. Musser, RII DRP

K. Kennedy, RII DRS

H. Christensen, RII DRS

F. Brown, NRR

M. Ashley, NRR

M. Cunningham, NRR

S. Weerakkody, NRR