Information Notice 1994-90, Transient Resulting in a Reactor Trip and Multiple Safety Injection System Actuations at Salem
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
December 30, 1994 NRC INFORMATION NOTICE 94-90: TRANSIENT RESULTING IN A REACTOR TRIP
AND MULTIPLE SAFETY INJECTION SYSTEM
ACTUATIONS AT SALEM
Addressees
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information
notice to alert addressees to the events associated with the loss of
circulating water at Salem Nuclear Power Plant, Unit 1, on April 7, 1994, that
led to a reactor trip followed by multiple automatic actuations of the safety
injection system. It is expected that recipients will review the information
for applicability to their facilities and consider actions, as appropriate, to
avoid similar problems. However, suggestions contained in this information
notice are not NRC requirements; therefore, no specific action or written
response is required.
Description of Circumstances
On April 7, 1994, at 10:00 a.m., Salem, Unit 1 was in Mode 1 at 73-percent
power. Public Service Electric and Gas Company (the licensee) was operating
the unit at reduced power because river detritus (marsh grass) had fouled the
circulating water intake structure causing a reduction in condenser cooling
efficiency. In response, the operators decreased the power level of Unit 1 to
approximately 60 percent because of an increase in condenser back pressure
caused by grass fouling of the traveling screens at the intake structure. In
response to an impending loss of circulating water, the operators began
reducing load by 1 percent per minute. However, in rapid succession, several
of the Unit 1 traveling screens became clogged with grass, causing the
associated pumps to trip, until only 1 circulating water pump remained
running. As the pumps were lost from service, operators increased the rate of
the load reduction to 8 percent per minute.
Operators attempted to reduce unit load as rapidly as reactor power was being
decreased by insertion of control rods and addition of boron. The effort
caused a power mismatch that resulted in a slight, but continuing, increase in
reactor coolant temperature. In response, the nuclear shift supervisor
directed the operator controlling reactor power to go to the electrical
distribution control panel and shift plant electrical loads to offsite power
sources. Although operators believed that the plant was stable, they failed
P/)p
rz Woee
dD. Soqo
7W/2 30
9412270233 I
&lcj-r u1 I/S/95
KJ~
December 30, 1994 to recognize that reactor power was still decreasing because of the delayed
effect of a previous addition of boron. This caused a reversal of the power
mismatch and resulted in reactor coolant system (RCS) temperature decreasing
to below the minimum temperature at which criticality is allowed. The
operators attempted to restore RCS temperature by increasing reactor power
from approximately 7 percent to 25 percent.
However, since power had been
below 10 percent, the power range "high neutron flux-low setpoint" trip had
been automatically reinstated, establishing 25-percent reactor power as the
trip setpoint. When power reached 25 percent, the reactor automatically
tripped.
Almost immediately, train 'A" of the safety injection (SI) logic actuated on a
high steam flow signal coincident with low RCS temperature.
(Later
investigation revealed that the high steam flow signal was actually the result
of a pressure wave created in the main steam lines when the turbine stop
valves closed as a result of the turbine trip).
In response to the reactor
trip and safety injection, the operators entered the plant emergency operating
procedures.
The SI logic did not reposition all necessary components to the
expected, post-actuation position because the initiating signal was so short.
The operators manually repositioned the affected components to their proper
positions. At 11:00 a.m., the licensee declared an unusual event based on a
"manual or automatic emergency core cooling system actuation with a discharge
to the vessel." When the operators took action to reset the SI logic, they
discovered that train "B" of the SI logic had not actuated, indicating an
apparent logic error.
As the operators were attempting to stabilize the plant, the RCS continued to
heat up because of reactor decay heat combined with reactor coolant pump heat.
Steam generator pressure increased but was not automatically relieved by the
steam generator atmospheric relief valves because of a pre-existing condition
that prevented the proper automatic operation of the valves.
Concurrently, because of RCS heatup and the volume of water added by the safety injection, the pressurizer filled to a solid condition, and the pressurizer power- operated relief valves cycled several hundred times to control RCS pressure.
A short time later, steam generator pressure increased in the "11" and "13"
steam generators to the safety valve lift setpoint.
The opening of a safety
valve caused a rapid cooldown and depressurization of the RCS that was
magnified by the solid condition of the system.
RCS pressure rapidly reached
the automatic SI setpoint of 1755 psig, and since train "B" of the SI logic
had remained armed, a second automatic SI actuation occurred. At about the
same time, operators manually initiated safety injection in response to the
rapidly decreasing RCS pressure.
After the second safety injection, operators
remained in the emergency operating procedures, and continued their attempts
to stabilize plant conditions. The pressurizer relief tank rupture disk
actuated because of increasing tank pressure caused by the volume of RCS water
relieved to the pressurizer relief tank from the pressurizer power-operated
relief valves.
December 30, 1994 The operators controlled plant pressure using the charging and letdown
provisions of the chemical and volume control system because normal RCS
pressure control was not available due to the solid condition of the system.
At 1:16 p.m., licensee management declared an alert to ensure activation of
the Salem Technical Support Center to provide the Salem operators with
additional technical assistance to support cooldown of the plant.
Accordingly, the Technical Support Center was fully staffed.
At 3:11 p.m., the operators established a steam bubble in the pressurizer
using pressurizer heaters.
At 4:30 p.m., operators restored pressurizer level
to the normal band and returned level control to automatic. They subsequently
exited the emergency operating procedures and used the integrated operating
procedures to cool the plant down to Mode 4 (Hot Shutdown), which was achieved
at 1:06 a.m. on April 8, and then to Mode 5 (Cold Shutdown), which was
achieved at 11:24 a.m. on the same day.
Discussion
On April 8, 1994, the NRC dispatched an Augmented Inspection Team to
investigate the event. The results of that inspection were documented in NRC
Inspection Report 50-272/94-80, dated June 24, 1994. Although several issues
emerged from the NRC investigation of this event, three specific aspects are
of particular concern.
These aspects are discussed below.
Solid State Protection System Logic Mismatch: During the first SI actuation, the "A" and "B" logic trains of the solid state protection system were
mismatched.
Train "A" sensed and responded to conditions representative of a
steam line break accident, namely a low RCS temperature coincident with a high
steam line flow.
Although these conditions were real indications, the RCS low
temperature was due to operator error and the high steam flow was a transient
signal induced by a pressure wave resulting from the closure of the turbine
stop and control valves. This transient signal had a duration of about 30
milliseconds, which system response testing later showed was sufficient for
certain portions of the "A" logic to respond, but of insufficient duration for
the "B" logic to respond.
The logic mismatch appears to be a result of the
variations in response sensitivity to the steam flow input relays.
The
licensee modified the design to require a longer signal duration before the
logic is actuated so that such transient signals would not result in an
undesired safety injection.
Nuclear Instrument Rod Shadowing:
Before the initial reactor trip, when the
operators were raising reactor power to restore RCS temperature, the
intermediate range and power range nuclear instruments were not in agreement
with respect to indicated power.
The intermediate range detectors were
"trailing" the power range by about 5 to 10 percent. This led to a condition
in which the reactor was tripped at the 25-percent power range setpoint before
the rod block signal was received from the intermediate range detectors at
20-percent power. The discrepancy between the power and intermediate range
nuclear instruments was apparently due to "rod shadowing."
December 30, 1994 The combination of the cool RCS and the rod pattern resulting from the down
power maneuver shielded the intermediate range detectors, causing the
instruments to indicate a lower power than the power range detectors.
Although this bias was within an acceptable envelope for detector operability, the response of the instruments was not initially understood.
This led to
concern that the nuclear instruments were not properly operating.
Control Room Command and Control:
Before the initial reactor trip, shift
management directed staff to support actions necessary to restore circulating
water.
The Shift Technical Advisor, a senior reactor operator assigned to the
work control station, was directed to assist in the restoration of affected
equipment. The extra duty reactor operator was directed to assist at the
intake structure.
The senior shift supervisor was initially in the control
room area, but subsequently left to go to the turbine building. This
deployment of licensed operators led to minimal staffing of the control room
at the onset of the transient.
During this time, the operators were preparing to take the unit turbine off
line, and the reactor controls operator was directed by the shift supervisor
to initiate actions to transfer plant electrical loads.
This led to the
reactor controls watch station not being staffed during a reactivity change.
The RCS began to cool as a result of a slight power mismatch between the
reactor and the turbine.
When the shift supervisor first discovered this
mismatch, he began to raise reactor power to restore temperature, which led to
a momentary loss of the command oversight function. He subsequently
recognized the need to maintain an overall command posture and stopped
withdrawing control rods. However, he continued to allow the reactor controls
operator to swap the electrical loads and the RCS temperature continued to
decrease. When the reactor controls operator completed the electrical plant
realignment, the shift supervisor then directed him to raise reactor power to
restore RCS temperature. The shift supervisor did not discuss the fact that
he had manipulated the control rods with the reactor controls operator, and
his direction to the relatively inexperienced operator lacked specificity (how
far or how fast to raise power). The operator subsequently raised reactor
power until the 25-percent power trip was reached.
Related Generic Communications
NRC Information Notice 94-55, "Problems with Copes-Vulcan Pressurizer
Power-Operated Relief Valves," August 4, 1994.
This information notice discusses cracking of plug material, severe wear
of plugs and cages, and a problem with the misalignment and galling of a
stem in the power-operated relief valves discovered as a result of valve
inspection subsequent to the April 7, 1994, event.
NRC Information Notice 94-36, "Undetected Accumulation of Gas in Reactor
Coolant System," May 24, 1994.
This information notice discusses lack of operator awareness of an
accumulation of nitrogen in the reactor vessel head during cooldown and
depressurization of the RCS subsequent to the April 7, 1994, event.
December 30, 1994
This information notice requires no specific action or written response.
If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
rian K. Grimes, Director
Division of Project Support
Office of Nuclear Reactor Regulation
Technical contacts:
Robert J. Summers, RI
(609) 935-3850
Eric J. Benner, NRR
(301) 504-1171 Attachment:
List of Recently Issued NRC Information Notices
hiW
54-r
11JcGi.
,7-"4
K>
Attachment
December 30, 1994 LIST OF RECENTLY ISSUED
NRC INFORMATION NOTICES
Information
Date of
Notice No.
Subject
Issuance
Issued to
94-89
94-88
94-87
94-86
94-85
94-40,
Supp. 1
94-84
89-25, Rev. 1
94-83
Equipment Failures at
Irradiator Facilities
Inservice Inspection
Deficiencies Result in
Severely Degraded Steam
Generator Tubes
Unanticipated Crack in a
Particular Heat of
Alloy 600 Used for
Westinghouse Mechanical
Plugs for Steam Generator
Tubes
Legal Actions Against
Thermal Science, Inc.,
Manufacturer of Thermo-Lag
Problems with the
Latching Mechanism
in Potter and Brumfield
R1O-E3286-2 Relays
Failure of a Rod Control
Cluster Assembly to Fully
Insert Following a Reactor
Trip at Braidwood Unit 2
Air Entrainment in Terry
Turbine Lubricating Oil
System
Unauthorized Transfer of
Ownership or Control of
Licensed Activities
Reactor Trip Followed by
Unexpected Events
12/28/94
12/23/94
12/22/94
12/22/94
12/21/94
12/15/94
12/02/94
12/07/94
12/06/94
All U.S. Nuclear Regulatory
Commission irradiator
licensees.
All holders of OLs or CPs
for pressurized water
reactors.
All holders of OLs or CPs
for nuclear power reactors.
All holders of OLs or CPs
for nuclear power reactors.
All holders of OLs or CPs
for nuclear power reactors.
All holders of OLs or CPs
for nuclear power reactors.
All holders of OLs or CPs
for nuclear power reactors.
All fuel cycle and material
licensees.
All holders of OLs or CPs
for nuclear power reactors.
OL = Operating License
CP = Construction Permit
IN 94-XX
November xx, 1994
This information notice requires no specific action or written response.
If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Project Support
Office of Nuclear Reactor Regulation
Technical contacts:
Robert J. Summers
(609) 935-3850
Eric J. Benner
(301) 504-1171 Attachment:
List of Recently Issued NRC Information Notices
E-mailed to John White and Robert Summers of Region I for review on 10/21/94.
OFC
OECB:DOPS
PUB:ADM
SC/OECB:DOPS
BC/SRXB:DSSA
NAME
EBenner
Tech Ed*
EGoodwin*
RJones*
DATE 11/14/94
110/17/94
110/24/94
,10/26/94
-.
.I.
OFC
OECB:DOPS
BC/OECB:DOPS
D/DOPS
NAME
RKiessel*
AChaffee*
BGrime
DATE 11/02/94
11/16/94
/
/94
[OFFICIAL RECORD COPY]
DOCUMENT NAME:
S:\\DOP S SEC\\SALEM.IN
IN 94-XX
November xx, 1994
This information notice requires no specific action or written response.
If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
I
Brian K. Grimes, Director
Division of Projects Support
Office of Nuclear Reactor Regulation
Technical contact:
Robert J. Summers
(609) 935-3850
Eric J. Benner
(301) 504-1171 Attachment:
1.
List of Recently Issued NRC Information Notices
E-mailed to John White and Robert Summers of Region I for review on 10/21/94.
OFC lOECB:DOPS
PUB:ADM
SC/OECB:DOPS
BC/SRXB:DSSA
NAME
EBenner
Tech Ed*
EGoodwin*
RJones*
DATE 1
11/14/94
10/17/94
10/24/94
110/26/94
_ j
OFC
OECB:DOPS
BC/OLCB:DOPS
D/DOPS
NAME
RKiessel*
e
BGrimes
DATE 111/02/94
1/
1 n/94 J / /94
-- --
-
-I
maAEI-
II AIA&Ir
P - % r I
LU[ICLIAL KtLUKU LUfYJ
MUUUMtN I NAMLI;
U ; \\ Cd JB1\\SALEM.IN
K>j
IN 94-XX
November xx, 1994
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Projects Support
Office of Nuclear Reactor Regulation
Technical contact:
Eric J. Benner
(301) 504-1171 Attachment:
1.
List of Recently Issued NRC Information Notices
E-mailed to John White and Robert Summers of Region I for review on 10/21/94.
OFC
OECB:DOPS
l PUB:ADM
SC/OECB:DOPS
BC/SRXB:DSSA
NAME
EBenner
Tech Ed*
EGoodwin*
RJones*
DATE
11 /c2/94
10/17/94 j10/24/94
110/26/94
1 T
Ifi- nrC
gFErpfnPS
. ,
RC/OECB:DOPS
D/DOPS
____-1 t
-
-- --.
NAME
RKi tsel A
AChaffee
BGrimes
DATE _V)//I94 I
/
/94
/ /94
..-
fr.r
-1
[OFFICIAL RECORD COPY]
UUUvlMMI
NAMt:
U : Xr J
B1\\SALEM.IN
v)
IN 94-XX
November, xx, 1994 shift supervisor was initially in the control room area, but subsequently left
to go to the turbine building.
This deployment of licensed staffing led to
minimal staffing of the control room at the onset of the transient. During this
time, the operators were preparing to take the unit turbine off-line, and the
reactor controls operator was directed by the shift supervisor to initiate
actions to transfer plant electrical loads. This led to the reactor controls
watch station not being manned during a reactivity change. The RCS began to cool
as a result of a slight power mismatch between the reactor and the turbine. When
first identified by the shift supervisor, he began to raise reactor power to
restore temperature, which led to a momentary loss of the command function. The
shift supervisor subsequently recognized the need to maintain an overall command
posture and stopped withdrawing control rods. However, he continued to allow the
reactor controls operator to swap the electrical loads and RCS temperature
continued to degrade.
When the reactor controls operator completed the
electrical plant realignment, the shift supervisor then directed him to raise
reactor power to restore RCS temperature. This direction was not specific as to
how far to raise power, which, coupled with the operator's inexperience, led to
the operator raising reactor power until reaching the 25 percent power trip.
Related Generic Communications
-
NRC IN 94-55, 'Problems with Copes-Vulcan Pressurizer Power-Operated
Relief Valves,' August 4, 1994.
-
NRC IN 94-36,
Undetected Accumulation of Gas in Reactor Coolant
System," May 24, 1994.
This information notice requires no specific action or written response. If you
have any questions about the information in this notice, please contact the
technical contact listed below or the appropriate Office of Nuclear Reactor
Regulation (NRR) project manager.
Brian K. Grimes, Director
Division of Projects Support
Office of Nuclear Reactor Regulation
Technical contact:
Eric J. Benner
(301) 504-1171 Attachments:
1.
List of Recently Issued NRC Information Notices
E-mailed to John White and Robert Summers of Region I for review on l1/19/94.
OFC
OECB:DOPS
PUB:ADM
l SC/OECB:DOPS
SRXB:DSSV
NAME EBenner Wi
X Tech Ed A M
c iiEGoodwi n 1iJ
I
DATE eA
//gV/94
10 /
rt1/94
/94
-
11 OFC I BC/SRXB:DSSin I BC/OECB:DOPS I D/DOPS
I
NAME RJoneb %I/ I
AChaffee
BGrimes
DATE
g
94 /
/ /94
/ /94
[O. I A -
- -
Y
O
E
A E
.,
A
.
-..
[OFFICIAL RECORD COPYJ
DOCUMENT NAME:
U:XLJBl\\SALtM.IN
W
December 30, 1994
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
WOW 1gd.
le-by
Kdo
L Omet
Brian K. Grimes, Director
Division of Project Support
Office of Nuclear Reactor Regulation
Technical contacts:
Robert J. Summers, RI
(609) 935-3850
Eric J. Benner, NRR
(301) 504-1171 Attachment:
List of Recently Issued NRC Information Notices
DOCUMENT NAME:
94-90. IN
- See previous concurrences
E-mailed to John White and Robert Summers of Region I for review on 10/21/94.
OFC
OECB:DOPS
PUB:ADM
SC/OECB:DOPS
BC/SRXB:DSSA
NAME EBenner
Tech Ed*
EGoodwin*
RJones*
DATE 111/14/94
1 10/17/94
10/24/94
_
/710/26/94 OFC
OECB:DOPS
BC/OECB:DOPS
l~
-
IF
-e-
-
-
NAME
RKiessel*
AChaffee*
DATE 11/02/94
11/16/94 j12/Z7/94
[OFFICIAL RECORD COPY]