Forwards Application for Amend to License DPR-59,revising Section 6.2.2.6 Re Administrative Controls for Normal Working Hours of Plant Staff Who Perform Safety Related Functions
ML20203J654
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 12/12/1997
From: James Knubel
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20203J657 List:
References
JPN-97-038, JPN-97-38, NUDOCS 9712220034
Download: ML20203J654 (2)


Text

.

. . 133 Men St*eet

. 6bhic l%es, New Yc7k 10001 -

914 c8L0840 0

914 287.3309 (FAX) -

h g gg bd(bl' fE0v[eNont ed CNef Nu$ar OHew .

December 12,1997 JPN 97 038

- United States Nuclear Regulatory Commission ATTN: Cocument Control Desk Mail Station P1-137 Washington, D.C. 20555

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50 333 License No. DPR-59 Proposed Changes to the Technical Specifications Regarding Administrative Controls for Normal Workina Hours (JPTS 97-005)-

Dear Sir:

This application for amendment to the James A. FitzPatrick Technical Specifications (TS) proposes to revise section 6.2.2.6 regarding the administrative controls for the normal working hours of plant staff who perform safety related functions.

TS section 6.2.2.6 establishes the normal work hours for operating personnel as, "...a normal 8-hour day,40 hour4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> week..." The proposed change revises this section to provide for, "... a normal 8 to 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> day, nominal 40-hour week..." In addition, associated changes are being made to Sections 4.5.F,4.5 Bases, and 4.7.A.7 for administrative clarification to maintain once per shift surveillance requirements at 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> intervals.

The signed original of the Application for Amendment to the Operating License is enclosed for filing. Attachment I to the applicat!on contains the proposed changes to the Technical

. Specifications. Attachment 11 contains the associated Safety Evaluation for the proposed changes. A mark-up of the affected Technical Specification pages is provided in Attachment lil.

A _ copy of this application and the associated attachments are being provided to the designated New York State officialin accordance with 10 CFR 50.91.

l 9712220034 971212 ..

ADOL 1 PDR ADOCK 05000333 p PDR

,G

. s . } j.

l

  • +.

I J :i o = There are no' commitments contalried in this submittal. If you have.any questions, please j

. contact Ms. C. D. Faison.-  !

~

. l Very truly you s,; ,

-- t 3-  :

J. Anubel. .

Senior Vice President and - i Chief Nuclear Officer: ,

att:- As stated : _{

cc:- :_U.S. Nuclear Regulatory Commission 1 475 Allendale Road -  !

. King of Prussia, PA 19406 l

Office of the Resident inspector (U.S. Nuclear Regulatory Commission P.O. Box 136 - i Lycoming, NY. 13093

~

Mr. Daniel H. Dorman, Project Manager  !

Project Directorate I 1 Division of Reactor Projects 1/IIJ U.S. Nuclear Regulatory Commission 2 s; Mail Stop 14 B2- j Washington, DC 20555-T Mr. F. William Valentino, President New York State Energy, Research and Development Authority -i Corporate Plaza West

286 Washington Avenue Extension ,