App to SALP Repts 50-456/88-01 & 50-457/88-01 for Dec 1986- 1987 Assessment Period
ML20154D864
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 05/10/1988
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20154D862 List:
References
50-456-88-01, 50-456-88-1, 50-457-88-01, 50-457-88-1, NUDOCS 8805200012
Download: ML20154D864 (3)


Text

o .

.

-

,

J APPENDIX SALP 7 SALP BOARD REPORT U.S. NUCLEAR REGULATORY COMMISSION

REGION III

SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE 50-456/88001; 50-457/88001 Inspection Report N Commonwealth Edison Company Name of Licensee Braidwood Station Name of Facility ~

December 1, 1986 through December 31, 1987 Assessment Period 8805200012 880510 PDR ADOCK 05000456 O DCD

.

.

j #

  • '

, l

6 Summary of Meeting with Commonwealth Edison Company on April 5, 1988

.

The findings and conclusions of the SALP Board documented in Inspection

'

Report Nos. 50-456/88001; 50-457/88001 were discussed with the licensee on April 5, 1988, at the Braidwood Station Training Building. The licensee's regulatory performance was presented and found acceptable in each functional are The following individuals attended the meeting:

Commonwealth Edison Company

'

C. Reed, Senior Vice President, Nuclear Operations T. J. Maiman, Vice President, PWR Operations L. DelGeorge, Assistant Vice President, Licensing and Technical Support K. L. Graesser, General Manager, PWR Operations K. L. Kofron, Production Superintendent, Braidwood S. C. Hunsader, Nuclear Licensing Administrator P. L. Barnes, Regulatory Assurance Supervisor R. E. Aker, Radiation / Chemistry Supervisor, Braidwood L. E. Davis, Assistant Superintendent, Technical Services '

G. R. Masters, Assistant Superintendent, Operations R. C. Ward, Services Superintendent, Byron D. E. Paquette, Assistant Superintendent, Maintenance G. Vanderheyden, Operations Training Supervisor R. Legner, Senior Operating Engineer R. A. Flessner, Administrative Engineer, PWR Operations D. Demos, Joliet District Superintendent G. W. Nelson, Assistant Technical Staff Supervisor B. R. Shelton, PWR Engineering Manager M. E. Lohmann, Project Construction and Startup Superintendent R. D. Kyrouac, Station Quality Assurance Superintendent H. P. Studtmann, Director of Quality Assurance (Maintenance)

U. S. Nuclear Regulatory Commission, Region III C. J. Paperiello, Deputy Regional Administrator E. G. Greenman, Director, Division of Reactor Projects R. M. Lickus, Chief, State and Government Affairs W. L. Forney, Chief, Reactor Projects Branch 1 J. M. Hinds, Jr., Chief, Reactor Projects Section 1A T. M. Tongue, Senior Resident Inspector, Braidwood T. E. Taylor, Resident Inspector, Braidwood G. A. Van Sickle, Project Inspector, Reactor Projects Section 1A Comments Received from Licensee In a telephone conversation with G. A. Van Sickle of the NRC on May 5, 1988, P. L. Barnes, Braidwood Regulatory Assurance Supervisor, stated that Commonwealth Edison has no comments addressing the specific content of the report. Because there are no comments, this tppendix coritains no changes to the SALP Repor _ . _ _ . _ - _ _ _ _ .

. .

. . .

.

g C. Regional Administrator's Conclusions Based on Consideration of Licensee Comments Braidwood's overall ratings in all functional areas have not changed.

,