IR 05000456/2021002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2021002 and 05000457/2021002
ML21204A069
Person / Time
Site: Braidwood  
Issue date: 07/22/2021
From: Hironori Peterson
Region 3 Branch 3
To: Rhoades D
Exelon Generation Co, Exelon Nuclear
References
IR 2021002
Download: ML21204A069 (27)


Text

July 22, 2021

SUBJECT:

BRAIDWOOD STATION - INTEGRATED INSPECTION REPORT 05000456/2021002 AND 05000457/2021002

Dear Mr. Rhoades:

On June 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station. On July 13, 2021, the NRC inspectors discussed the results of this inspection with Mr. John Keenan, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects

Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2021002 and 05000457/2021002

Enterprise Identifier: I-2021-002-0063

Licensee:

Exelon Generation Company, LLC

Facility:

Braidwood Station

Location:

Braceville, IL

Inspection Dates:

April 01, 2021 to June 30, 2021

Inspectors:

D. Betancourt-Roldan, Senior Resident Inspector (Byron)

R. Bowen, Illinois Emergency Management Agency

J. Bozga, Senior Reactor Inspector

G. Edwards, Health Physicist

M. Holmberg, Senior Reactor Inspector

D. Kimble, Senior Resident Inspector (Braidwood)

P. Smagacz, Resident Inspector

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period operating at approximately 89 percent power with end-of-cycle power coast down operations in progress. On April 5, 2021, the unit was shut down for its planned 22nd refueling outage (A1R22). Following completion of refueling and other maintenance activities, the reactor was restarted and taken critical on April 23, 2021, and the main electrical generator was synchronized to the power grid on April 24, 2021. The unit reached full power operation on April 27, 2021. On May 22, 2021, power was reduced to approximately 85 percent to facilitate maintenance on the condensate system. Unit 1 returned to full power later that same day. Just after midnight on June 21, 2021, Unit 1 experienced an automatic trip from full power due to a lightning strike in the stations main switchyard during a severe thunderstorm. After post-trip checks verified that the condition of the unit was acceptable for restart, the reactor was taken critical in the evening on June 21, 2021, and the main electrical generator was synchronized to the power grid on the morning of June 22, 2021. The unit reached full power operation just before midnight on June 22, 2021, and remained operating at or near full power for the remainder of the inspection period.

Unit 2 began the inspection period operating at full power. On May 7, 2021, the unit reduced power to approximately 68 percent to facilitate replacement of a failed relief valve on the 23C Low Pressure (LP) Feedwater (FW) Heater. The unit returned to full power operation the following day, and with the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, it remained operating at or near full power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.

As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems during the weeks ending June 26 through June 30, 2021.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial physical alignment verifications of the following systems/trains:

(1) The spent fuel pool (SFP) cooling system while the Unit 1 reactor core was offloaded to the SFP for the A1R22 refueling outage, during the week ending April 17, 2021.
(2) The Unit 1 component cooling system (CC) during maintenance on 1CC9743A, during the week ending May 8, 2021.
(3) The 2A Emergency Diesel Generator (EDG) while the unit's station auxiliary transformer was undergoing planned maintenance, during the week ending May 15, 2021.
(4) The 2A Safety Injection (SI) Train while the 2B SI Train was out-of-service for maintenance, during the week ending June 19, 2021.

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

The inspectors evaluated system configurations during a complete physical alignment verification of the following system/train:

(1) The Unit 1 residual heat removal (RH) system, during the weeks ending April 10 through April 24, 2021. This activity completed the partial inspection sample that was documented in NRC Inspection Report 05000456/2021001; 05000457/2021001 (ADAMS Accession No. ML21106A208).

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting physical inspections and reviews to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) The Unit 1 Containment, 377' Elevation, Inside Missile Barrier area, during the week ending April 17, 2021.
(2) The Unit 1 Containment, 401' Elevation, Outside Missile Barrier area, during the week ending April 17, 2021.
(3) The Unit 1 Containment, 426' Elevation, during the week ending April 17, 2021.
(4) The Unit 1 Auxiliary Building, 330' Elevation, 1A/2A Essential Service Water (SX)

Pump Room while performing maintenance/hot work on 1A SX Pump, during the week ending April 17, 2021.

(5) The Unit 1 Containment, 401' Elevation, Inside Missile Barrier area while performing maintenance/hot work on reactor coolant pumps, during the week ending April 17, 2021.
(6) The Unit 1 Auxiliary Building, 383' Elevation, 1B Auxiliary Feedwater (AF) Pump Room, during the week ending May 8, 2021.
(7) The Unit 2 Switchgear area, 451' Elevation, Miscellaneous Electrical Equipment Room, during the week ending May 15, 2021.

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors verified the reactor coolant system boundary and risk significant piping system boundaries were appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from April 7, 2021 to April 16, 2021:

03.01.a - Nondestructive Examination and Welding Activities.

  • Welds 1 and 4, 1SX252 valve replacement, (Work Order (WO) 04817111-01)

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities.

  • Bare Metal Visual (VE) examination of the reactor vessel upper head penetrations nozzles 2, 5, 13 and 59

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities.

  • Boric Acid Leakage Evaluation on Component 1SI023A (adapter and instrument cap)
  • Corrective Actions to Leakage at Valve 1RC8042B (Issue Report (IR)

===04346974, AR 04391367)

  • Corrective Actions to Leakage Downstream of 1SI023A (IR 04345873)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

=

The inspectors observed and evaluated the following licensed operator activities in the control room:

(1) Various activities involving on-watch operations crews. These activities included, but were not limited to:
  • Shutdown of Unit 1 for the A1R22 refuel outage, during the week ending April 10, 2021.
  • Unit 1 reactor coolant system draining in support of A1R22 refuel outage reactor vessel head lift, during the week ending April 10, 2021.
  • Unit 1 reactor coolant pump startups for A1R22 refuel outage plant heat up, during the week ending April 24, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

The inspectors observed and evaluated the following licensed operator training activity:

(1) A complex casualty graded scenario involving a crew of licensed operators was observed in facility's simulator on May 25, 2021.

71111.12 - Maintenance Effectiveness

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance, as well as certain quality control activities, to ensure the following structure, system, and component (SSC) remains capable of performing its intended function:

(1) Maintenance effectiveness and performance history review of the 1/2RC8042 A-D 1.5-inch reactor coolant system equalization line manual isolation valves, during the weeks ending April 17 through May 29, 2021.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Evaluation of the work activities and risk associated with the emergent replacement of the 1RC8042D, 1.5-inch manual isolation valve as set forth in WO 4969069, during the week ending April 17, 2021.
(2) Evaluation of the work activities and risk associated with the planned replacement of the 1A SX Pump as set forth in WO 4934317, during the week ending April 17, 2021.
(3) Evaluation of the work activities and risk associated with emergent troubleshooting and repairs to the Unit 2 Control Bank A Rod Drive Power Supply Cabinet with the unit operating at full power as set forth in WO 5149593, during the week ending May 7, 2021.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples 1 Partial)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Evaluation of the operability of snubber 1RC01BD-B on the 1B Steam Generator following identification of a hydraulic oil leak as documented in IR 4417398, during the weeks ending April 24 through May 29, 2021.

(2)

(Partial)

Evaluation of the operability of the source range nuclear instruments with their high flux trips bypassed during reactor startup as documented in IR 4418688, during the weeks ending May 1 through June 26, 2021.

(3) Evaluation of the operability of Unit 2 Control Bank 'A' rods following receipt of a rod drive urgent failure alarm during semiannual testing as documented in IR 4421424, during the week ending May 7, 2021.
(4) Evaluation of the operability of the 1A Overpower Delta Temperature protection circuit following receipt of a spurious alarm as documented in IR 4421778, during the weeks ending May 7 through May 29, 2021.
(5) Evaluation of the operability of the 1B Overtemperature Delta Temperature and Delta Temperature protection circuits following receipt of spurious indications as documented in IR 4423535, during the weeks ending May 15 through May 29, 2021.
(6) Evaluation of the operability of the 2A Centrifugal Charging Pump due to recurring low differential pressure issues as documented in IR 4423535, during the weeks ending May 22 through June 5, 2021.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors reviewed and evaluated the following permanent change to the facility that was enacted on the Unit 1 and Unit 2 SX system. The inspectors reviews included an in-depth examination of the licensees use of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors, as it was applied to the SX system:

(1) Engineering Change (EC) 632945: 0SX115C Valve and Piping Carbon Fiber Wrap, during the weeks ending April 1 through June 30, 2021. This activity completed the partial inspection sample that was documented in NRC Inspection Report

===05000456/2021001; 05000457/2021001 (ADAMS Accession No.ML21106A208).

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01)===

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Comprehensive functional and operational testing of the 1A SX Pump following replacement of the pump rotating element as set forth in WO 4934317, during the week ending April 17, 2021.
(2) Comprehensive functional testing of the Unit 1 SI and residual heat removal systems following outage maintenance as set forth in WOs 4980282 and 4983054, during the week ending April 17, 2021.
(3) Functional and operational testing of the 1B Rod Drive Motor-Generator set following multiple actions to balance the motor-generator set as set forth in WO 1953140, during the week ending April 24, 2021.
(4) AF Train 1B testing following outage system maintenance as set forth in WO 4982132, during the weeks ending April 24 through May 1, 2021.
(5) Functional and operational testing of Unit 2 Control Bank 'A' control rods following emergent troubleshooting and repairs as set forth in WO 5149593, during the week ending May 7, 2021.
(6) Low power startup physics testing following reloading of the Unit 1 reactor core for Operating Cycle No. 23 as set forth in WOs 4987491 and 4977795, during the weeks ending April 24 through May 8, 2021.
(7) System leakage testing at normal operating primary pressure and temperature following return of the reactor coolant system to operation after reactor refueling as set forth in WOs 4985624 and 4985631, during the weeks ending April 24 through May 8, 2021.
(8) Functional and operational testing of the 1A EDG following maintenance as set forth in WO 5160533, during the week ending June 26, 2021.

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors reviewed licensee activities and evaluated licensee performance associated with Unit 1 Refuel Outage A1R22, during the weeks ending April 10 through May 1, 2021.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 1 Refuel Outage A1R22 emergency core cooling system full flow testing for charging and safety injection as set forth in WO 4983054, during the weeks ending April 10 through May 15, 2021.
(2) Sequencer testing for the 1A EDG for the A1R22 refuel outage as set forth in WO 4803148, during the weeks ending April 10 through May 15, 2021.
(3) Full load rejection testing for the 1A EDG for the A1R22 refuel outage as set forth in WO 4836102, during the weeks ending April 24 through May 29, 2021.
(4) Loss of essential 4 KV bus response testing for the 1A EDG for the A1R22 refuel outage as set forth in WO 5067469, during the weeks ending April 24 through May 29, 2021.

Inservice Testing (IP Section 03.01) (1 Sample)

(1) Observation and assessment of Unit 1 main steam safety valve setpoint testing as set forth in WO 5067469, during the weeks ending April 3 through May 29, 2021.

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1)1BwOSR 3.6.1.1-9: Primary Containment Type C Local Leak Rate Testing for the Unit 1 chemical and volume control system, during the weeks ending April 10 through April 17,

RADIATION SAFETY

71124.02 - Occupational ALARA Planning and Controls

Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (3 Samples)

The inspectors reviewed as low as reasonably achievable practices and radiological work controls.

(1) The inspectors evaluated items associated with Radiation Work Permit BW-01-21-00613 and associated ALARA documentation for Reactor Head Disassembly and Reassembly during the spring 2021 outage.
(2) The inspectors evaluated items associated with Radiation Work Permit BW-01-21-00623 and associated ALARA documentation for Reactor Cavity Decon during the spring 2021 outage.
(3) The inspectors evaluated items associated with Radiation Work Permit BW-01-21-00612 and associated ALARA documentation for Core Barrel Inservice Inspection (ISI) and all Associated Work Valve Repairs/Inspections during the spring 2021 outage.

Radiation Worker Performance (IP Section 03.04) (1 Sample)

The inspectors evaluated radiation worker and radiation protection technician performance during:

(1) Fuel move activities.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (1 Sample)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1) Unit 1/2 Control Room Emergency Ventilation System.

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Portable high-efficiency particulate air (HEPA) ventilation system used on Reactor Vessel Head Stanchion.

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to external dosimetry that is used to assign occupational dose.

Internal Dosimetry (IP Section 03.03) (2 Samples)

The inspectors evaluated the internal dosimetry program implementation.

(1) Intake Investigation Form; Plant ID #7080; 04/22/2020 @1300 hours.
(2) Intake Investigation Form; Plant ID #5132; 04/22/2020 @1200 hours.

Special Dosimetric Situations (IP Section 03.04) (2 Samples)

The inspectors evaluated the following special dosimetric situation:

(1) Dose assessment for a declared pregnant worker in 2019.
(2) Dose assessment for a declared pregnant worker in

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors reviewed and verified selected portions of the licensee's performance indicator submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 03.04)===

(1) Unit 1 (April 1, 2020 - March 31, 2021)
(2) Unit 2 (April 1, 2020 - March 31, 2021)

MS06: Emergency AC Power Systems (IP Section 03.05) (2 Samples)

(1) Unit 1 (April 1, 2020 - March 31, 2021)
(2) Unit 2 (April 1, 2020 - March 31, 2021)

MS07: High Pressure Injection Systems (IP Section 03.06) (2 Samples)

(1) Unit 1 (April 1, 2020 - March 31, 2021)
(2) Unit 2 (April 1, 2020 - March 31, 2021)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors conducted a semiannual review of the licensees corrective action program (CAP) for potential adverse trends that might be indicative of a more significant safety concern during the weeks ending June 5 through June 30, 2021. A specific trend related to the Unit 1 Main Steam Isolation Valve (MSIV) Bypass Valves' operation is documented in the Results Section of this report.

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Follow-up (IP Section 03.01)

The inspectors assessed licensee performance related to the following events:

(1) Review and tracking of licensee actions during the COVID-19 National Emergency declaration as set forth by the President of the United States, during the weeks ending May 15 through June 12, 2021.
(2) Review and assessment of the licensee and plant response to the Unit 1 automatic reactor trip on June 21, 2021, due to a main electrical generator lockout/load rejection as documented in NRC Event Notification55320, during the weeks ending June 26 through June 30, 2021.
(3) Review and assessment of the loss of emergency response facility capability due to degradation of the Technical Support Center (TSC) ventilation system on June 24, 2021, as documented in NRC EN 55325, during the weeks ending June 26 through June 30,

INSPECTION RESULTS

Observation: Trend in Unit 1 Main Steam Isolation Valve Bypass Valve Operation 71152 The inspectors performed a review of plant issues, particularly those entered into the licensees CAP over the past several months. During their review, the inspectors noted a trend on Unit 1 involving the operation of MSIV Bypass Valves (1MS101A-D). Upon further inspection, the trend was noted to extend back a few years in time and seemed to be particularly evident most recently on the 1MS101B and 1MS101C valves. Specific CAP entries reviewed by the inspectors included, but were not limited to:

  • IR 3968314; 1MS101C "A" Solenoid Replacement - Extent of Condition.
  • IR 4256475; 1MS101B Would Not Open when Demanded from its Control Switch.
  • IR 4427859; 1MS101C Failed to Open when Demanded from Control Switch.

While the inspectors noted that these issues were exclusively limited to the open direction stroke of the valves, which is not part of the components safety function, the recurring nature of issues in the open direction without a thorough understanding of the trend might suggest the presence of an underlying component reliability issue.

The inspectors did not identify any findings or violations of NRC requirements in the course of their review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 13, 2021, the inspectors presented the integrated inspection results to Mr. J. Keenan, Site Vice President, and other members of the licensee staff.
  • On April 16, 2021, the inspectors presented the Radiation Protection inspection results to Mr. J. Keenan, Site Vice President, and other members of the licensee staff.
  • On April 16, 2021, the inspectors presented the Inservice inspection results to Mr. J. Keenan, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

243133

2DG01KB-Y1 East End Bell Oil Leak 12 DPM When Diesel

Running

05/24/2019

4306628

1RH8703B has Evidence of Packing Leak

2/29/2019

4367735

1A RH Pump has Boric Acid Buildup on Pump Seal/Bowl

09/06/2020

4367738

1B RH Pump has Boric Acid Buildup on Pump Seal/Bowl

09/06/2020

4374335

1RH610 Unsat Grease Inspection

10/05/2020

4374466

Boric Acid Residue in 1RH01PA Pump Bowl

10/05/2020

4378052

1B RH Pump Flow Requires IR for Tracking

10/20/2020

22278

2A DG Turbocharger Spindown not be Performed as

Scheduled

05/07/2021

22966

2DG01KA-C, 2A DG Jacket Water Pump is Leaking

05/11/2021

Procedures

BwOP CC-E1

Electrical Lineup Unit 1 Operating

BwOP CC-M1

Operating Mechanical Lineup Unit 1

BwOP DG-E3

Electrical Lineup Unit 2A Diesel Generator

BwOP DG-M3

Operating Mechanical Lineup Unit 2A Diesel Generator

BwOP FC-M1

Operating Mechanical Lineup Unit 1

BwOP RH-6

Placing the RH System in Shutdown Cooling

BwOP RH-8

Filling the Reactor Cavity for Refueling

BwOP RH-E1

Electrical Lineup Unit 1 Operating

BwOP RH-M1

Operating Mechanical Lineup Unit 1 1A RH Train

BwOP RH-M2

Operating Mechanical Lineup Unit 1 1B Train

BwOP SI-E2

Electrical Lineup Unit 2 Operating

BwOP SI-M2

Operating Mechanical Lineup Unit 2

71111.05

Fire Plans

Pre-Fire Plan 1

Fire Zone 1.1-1; Containment 377'-0" Elevation Unit 1

Containment Missile Shield Area

Pre-Fire Plan 6

Fire Zone 1.2-1; Containment 401'-0" Elevation Unit 1

Annular Area

Pre-Fire Plan 9

Fire Zone 1.3-1; Containment 426'-0" Elevation Unit 1

Containment Upper Area

Pre-Fire Plan 96

Fire Zone 11.1A-0; Auxiliary Building 330' Elevation, Unit 1

Auxiliary Building Basement (1A/2A SX)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Pre-Fire Plan No.

137

Fire Zone 11.4A-1; Auxiliary Building 383' Elevation, Unit 2

Auxiliary Feedwater Pump Diesel Room

Pre-Fire Plan No.

Fire Zone 5.4-2; Switchgear Area 451' Elevation, Division 22,

MEER and Battery Room

Procedures

BwAP 1110-1

Fire Protection Program System Requirements

BwAP 1110-3

Plant Barrier Impairment Program

BwOP PBI-1

Plant Barrier Impairment Program Pre-Evaluated Barrier

Matrix

CC-AA-201

Plant Barrier Control Program

ER-AA-600-1069

High Risk Fire Area Identification

ER-BR-600-1069

Site List of High Risk Fire Areas Braidwood Unit 1 and

Unit 2

OP-AA-201-004

Fire Prevention for Hot Work

OP-AA-201-008

Pre-Fire Plan Manual

OP-AA-201-009

Control of Transient Combustible Material

OP-AA-201-012-

1001

Operations On-Line Fire Risk Management

Pre-Fire Plan No.

Fire Zone 1.1-1; Containment 401'-0" Elevation Unit 1

Containment Missile Shield Area

71111.08P

Corrective Action

Documents

29240

OSP-X 1RC01R NDE Results for 1RV-03-002 Reactor Head

Weld

04/20/2018

272501

Notification of Code Nonconformance for Replacement SGs

08/16/2019

4345873

BA Leak Downstream 1SI023A

05/26/2020

4346974

Leak Found during Robot Inspection of U1 CNTMNT - IMB

1RC8042B

05/31/2020

4391367

1RC8042B Exhibiting a Different Leak Path

2/20/2020

480489

Boric Acid Accumulation Bottom of Pressurizer (Investigate

Source)

04/19/2006

480489

Boric Acid Accumulation Bottom of Pressurizer (Investigate

Source)

04/19/2006

Miscellaneous

ASME Weld Data Record, Weld 1 and Weld 4 - I SXA9A

04/11/2021

ASME Weld Data Record, Weld 6-1 and Weld 11-1 -

1RC8042B

04/12/2021

B. Connolly-VT Level II, Certification

01/11/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

R. Kramer - VT Level III, Certification

01/29/2020

J. Jenning - UT Level II, Certification

2/03/2020

B. Knoff - UT Level II, Certification

01/29/2021

J. Simpson - UT Level II, Certification

01/06/2021

WPS 1-1-GTSM-PWHT

PQR A-001

10/19/1998

PQR A-002

03/09/1999

PQR 1-50C

01/03/1984

Rod Ticket - Field Welds 1,2,3,4 (WO 04817111-01)

04/11/2021

WPS 8-8-GTSM

PQR 1-51A

2/28/1983

PQR 4-51A

09/12/1986

2S Evaluation of BACC Leakage

(AR 04345873), 1SI023A D/S Adapter and Instrument

Cap-SI PMPS INJECTION HDR TO LOOP 3 COLD LEG

INST ISOL TO 1FT-S1051

06/22/2020

2S Evaluation of BACC Leakage (AR 04345861)

1PS9356A-RC Loop Sample Inside Isolation VLV Assembly,

PS, A Train

06/18/2020

Evaluation of BACC Leakage 1RC8042B

(AR 04346974 & AR 04391367) - RC Loop 1B Equalization

Line Main Isolation VLV

07/09/2020

CB1404

Welder Certification Record

10/26/2020

D9350

Welder Certification Record

09/29/2020

EPRI PDQS No.

2

WDI-STD-1165, Revision 3 Addenda 0

01/21/2021

NDE Reports

04981252-01

VT-2 Visual Examination - 1 RC-27 and 1 RC-20

04/14/2021

21-MT-11

Magnetic Particle Examination-Welds 1,2,3, and 4

09/11/2021

21-PT-010

Liquid Penetrant Examination-Field Weld# 6-1, Line

1RC22AB 1-1/2"

04/14/2021

21-PT-011

Liquid Penetrant Examination-Field Weld# 11-1, Line

1RC22AB 1-1/2"

04/14/2021

A1R22-UT-001

Ultrasonic Examination-1RC-16-02

04/10/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

A1R22-UT-002

Ultrasonic Examination-1RC-35-02

04/10/2021

A1R22-UT-003

Ultrasonic Examination-1RC-35-04

04/10/2021

A1R22-UT-005

Ultrasonic Examination-1PZR-01-N3

04/13/2021

A1R22-UT-006

Ultrasonic Examination-1PZR-01-N2

04/13/2021

A1R22-UT-023

1RV-03

04/16/2021

A1R22-UT-035

Ultrasonic Examination-1MS-04-37

04/15/2021

A1R22-UT-036

Ultrasonic Examination-1MS-04-38

04/15/2021

A1R22-UT-037

1FW-04-37

04/16/2021

A1R22-UT-038

Ultrasonic Examination-1MS-04-34

04/15/2021

A1R22-UT-039

Ultrasonic Examination-1MS-04-35

04/15/2021

A1R22-UT-040

Ultrasonic Examination-1MS-04-36

04/15/2021

A1R22-UT-041

Ultrasonic Examination-1FW-04-35

04/15/2021

A1R22-UT-042

Ultrasonic Examination-1FW-04-34

04/15/2021

A1R22-UT-043

1SG-05-SGC-02

04/16/2021

A1R22-UT-046

1FW-04-38

04/16/2021

A1R22-VEN-002

1RC01R Top Head BMV

04/15/2021

ANALYSIS LOG

  1. WN22-01

1RV-01-022 (DM) / 1 RV-01-030 (SS)

04/16/2021

ANALYSIS LOG

  1. WN338-01

1RV-01-029 (DM) / 1RV-01-037 (SS)

04/16/2021

ANALYSIS LOG#

WN158-01

1RV-01-025 (DM) / 1RV-01-033 (SS)

04/16/2021

Procedures

ER-AA-335-002

Liquid Penetrant (PT) Examination

ER-AA-335-003

Magnetic Particle (MT) Examination

ER-AA-335-015-

2013

VT-2 Visual Examination in Accordance with ASME 2013

ER-AA-335-030

Ultrasonic Examination of Ferritic Piping Welds

ER-AA-335-031

Ultrasonic Examination of Austenitic Piping Welds

ER-AA-335-034

Manual Ultrasonic Examination of Reactor Pressure Vessel

Welds

ER-AA-335-035

Manual Sizing of Ultrasonic Indications in Reactor Pressure

Vessel Welds

ER-AA-335-049

Ultrasonic Examination in Accordance with Section V,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Article 4

ER-AP-331

Boric Acid Corrosion Control (BACC) Program

ER-AP-331-1001

Boric Acid Corrosion Control (BACC) Inspection Locations,

Implementation, and Inspection Guidelines

ER-AP-331-1002

Boric Acid Corrosion Control Program Identification

Screening and Evaluation

ER-AP-335-001

Bare Metal Visual Examination for Nickel Alloy Materials

WDI-STD-1165

Automated Ultrasonic Examination of the Remote Inservice

Inspection of Reactor Vessel

Nozzle to Safe End, Nozzle to Pipe, and Safe End to Pipe

Welds Using the Athena Phased Array System

71111.11Q Operability

Evaluations

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

Procedures

OP-AA-101-111-

1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

OP-AA-101-113-

1006

4.0 Crew Critique Guidelines

OP-AA-103-102

Watch-Standing Practices

OP-AA-103-102-

1001

Strategies for Successful Transient Mitigation

OP-AA-103-103

Operation of Plant Equipment

OP-AA-104-101

Communications

OP-AA-111-101

Operating Narrative Logs and Records

OP-AA-300

Reactivity Management

TQ-AA-10

Systematic Approach to Training Process Description

TQ-AA-150

Operator Training Programs

TQ-AA-155

Conduct of Simulator Training and Evaluation

TQ-AA-201

Examination Security and Administration

TQ-AA-306

Simulator Management

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

71111.12

Corrective Action

Documents

1354708

A1R16 (1RC8042B Boric Acid Leakage Refurbish or

Replace)

04/16/2012

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1355845

1RC8042B will not Close

04/08/2012

24573

OSP-A Boric Acid Dry on Valve 1RC8042B (Clean)

04/09/2018

Engineering

Changes

394386

Engineering Review of Flowserve Test Report TAL-20820,

Revision 2, for a 1.5-Inch ASME Class 1878 Stainless Steel

Y-Pattern Globe Valve for Braidwood Station

08/28/2013

Procedures

ER-AA-310-1001

Maintenance Rule 18-10 Scoping

ER-AA-310-1002

Maintenance Rule Functions Safety Significant

Classification

ER-AA-320

Maintenance Rule Implementation per NEI 18-10

ER-AA-320-1003

Maintenance Rule 18-10 Failure Definitions

ER-AA-320-1004

Maintenance Rule 18-10 Performance Monitoring and

Dispositioning Between (a)(1) and (a)(2)

Work Orders

5046086

1RC8042B Replace Valve

04/10/2021

71111.13

Corrective Action

Documents

4414349

Pre-Freeze NDE UT Readings Below 87.5% Tmin

1SXA9A-6"

04/06/2021

4414530

Replacement 1A SX Pump Shaft Scratches/Defects

04/06/2021

4414564

1RC8042D Unable to Close Loop Unable to be Drained

04/06/2021

Drawings

M-60, Sheet 2

Reactor Coolant Loop 2 Unit 1

BC

Engineering

Changes

388765

Freeze Line on 1RC22AB-1 1/2" to Isolate 1FE-0428

04/18/2012

Procedures

BwMP 3100-094

Removal and Installation of Flood Seal Opening Barriers

Work Orders

4934317

Replace 1SX01PA in A1R22

04/08/2021

4969069

1RC8042D Difficult to Operate Replace Valve

04/12/2021

5149593

Unexpected 2-10-C6, Rod Control Urgent Failure, SER

No. 2165

05/05/2021

71111.15

Corrective Action

Documents

2530091

Anomaly in Unit 2 Pressurizer Level / VCT Level Trend

07/19/2015

4417398

14-OSP-X Post-Maintenance Testing: 1RC01BD-B Steam

Generator Snubber Found Leaking at 60 Drops per Minute

04/18/2021

21424

Unexpected 2-10-C6, Rod Control Urgent Failure, SER#

2165

05/04/2021

21660

2-10-C6, Rod Control Urgent Failure, SER# 2165

05/05/2021

21778

Unexpected Alarms 1-10-A5 and 1-14-A1 for OPDT

05/05/2021

23270

Unexpected Annunciator: Ovation System Trouble

05/13/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

23503

Corrective Action to 1TY-0441A3

05/13/2021

23535

Unexpected Alarm 1-14-B5 and 1-4-A3

05/14/2021

24225

2A CV Pump Significantly Weaker than 2B CV Pump

05/18/2021

24510

1C OTDT Rescaling Required

05/19/2021

Procedures

2BwOSR 3.5.5.1

Unit Two RCS Seal Injection Flow Surveillance

BwAR 1-10-A5

OPDT High Rod Stop C-4

BwAR 1-14-A1

OPDT High Reactor Trip Alert

BwOP RP-9

Disabling and Restoring Source Range Nuclear Instruments

BwVP 312-6

Reactor Coolant System Temperature Instrumentation Delta

T and Tave Normalization

ER-AA-600-1012

Risk Management Documentation

OP-AA-106-101-

1006

Operational Decision Making Process

OP-AA-108-111

Adverse Condition Monitoring and Contingency Planning

OP-AA-108-115

Operability Determinations (CM-1)

Work Orders

5150129

Unexpected Alarms 1-10-A5 and 1-14-A for OPDT

05/06/2021

71111.18

Procedures

ER-AA-569

CFR 50.69 Program

ER-AA-569-1001

CFR 50.69 Active Component Risk Significance Insights

ER-AA-569-1002

CFR 50.69 Passive Component Categorization

ER-AA-569-1003

CFR 50.69 Risk Informed Categorization for Structures,

Systems, and Components

ER-AA-569-1004

CFR 50.69 Alternative Treatment Implementation Process 4

ER-AA-569-1005

Integrated Decision Decision-Making Panel for Risk Informed

SSC Categorization Duties and Responsibilities

ER-AA-569-1006

Requirements for Immediate, Interim and Periodic

Performance Monitoring Reviews

ER-AA-569-1007

Job Familiarization of 50.69 Project Team and Site

Personnel

71111.19

Corrective Action

Documents

4417074

1A SX Pump Test Results

04/16/2021

4418193

17-OSP-A 1B Rod Drive Generator Breaker Trip

04/22/2021

Procedures

BwOSR

5.5.8.AF-3B

Group A IST Requirements for Unit One Diesel Driven

Auxiliary Feedwater Pump

1BwOSR 3.7.5.7-

Unit One Train B Auxiliary Feedwater Flow Path Operability

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Non-Routine Surveillance (Following Cold Shutdown)

1BwOSR 3.8.1.2-

Unit One 1A Diesel Generator Operability Surveillance

1BwOSR

5.5.8.CV-8

Comprehensive Inservice Testing (IST) Requirements for

Unit 1 Charging Pumps and Safety Injection System

Charging Check Valve Stroke Test

1BwOSR

5.5.8.SX-6A

Comprehensive Inservice Test (IST) Requirements for 1A

Essential Service Water Pump (1SX01PA)

BwVS 500-6

Low Power Physics Testing

BwVS TRM

3.1.h.1

Low Power Physics Data Interpretation

ER-AA-330-001

Section XI Pressure Testing

Work Orders

1953140

1RD02E Rebuild or Replace Rod Drive Motor-Generator

Set Motor

04/06/2021

4793485

1AF01PB ASME 1BwOSR 5.5.8.AF-3B

04/21/2021

4896029

PMT Leak Check 1AF01AB Luble Oil Cooler

04/21/2021

4977795

Low Power Physics Data Interpretation

04/23/2021

4982132

Train B AF Flowpath Operability Following Cold Shutdown

04/21/2021

4983054

CV Cold Leg Check Valve Test 1BwOSR 5.5.8.CV-8

04/07/2021

4985624

Class 1 System Leakage Test (Ascending Mode 3)

04/22/2021

4985631

Class 2/3 System Leakage Test (Ascending Mode 3)

04/22/2021

4987491

Low Power Physics Test Program with Dynamic Rod Worth

Measurement

04/23/2021

4987492

Moderator Temperature Coefficient Low Power Physics

Testing

04/23/2021

26352

1B AF Pump Function Run (ASME)

04/21/2021

5160533

1A Diesel Generator Operability Monthly

06/21/2021

71111.20

Corrective Action

Documents

4413057

APS Electrician Received Electrical Arc Flash Burns

03/31/2021

4414344

01-OSP-A A1R22 GL 88-05 Minor BACC Results for Mode 3

Descending

04/06/2021

Miscellaneous

A1R22 Shutdown Safety Plan

BR1C22-08.0

Braidwood 1 Cycle 22 Coastdown Reactivity Plan

03/09/2021

Procedures

1BwGP 100-1

Plant Heat up

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1BwGP 100-2

Plant Start up

1BwGP 100-3

Power Ascension 5% to 100%

1BwGP 100-4

Power Descension

1BwGP 100-5

Plant Shutdown and Cooldown

1BwGP 100-6

Refueling Outage

1BwOS TRM

2.5.b.1

Unit One Containment Loose Debris Inspection

BwAP 1450-1

Access to Containment

BwGP 100-4

Power Descension

BwVS TRM

3.1.h.1

Core Reload Sequence and Verification

ER-AA-600-1043

Shutdown Risk Management

HU-AA-1211

Pre-Job Briefings

LS-AA-119

Fatigue Management and Work Hour Rules

MA-AA-716-008-

1008

Reactor Services: Refuel Floor FME Plan

OP-AA-108-108

Unit Restart Review

OP-AA-108-110

Evaluation of Special Tests or Evolutions

OP-AA-300-1520

Reactivity Management - Fuel Handling, Storage, and

Refueling

OU-AA-103

Shutdown Safety Management Program

- 22

OU-AA-103-1001

Shutdown Safety Plan Independent Review

71111.22

Corrective Action

Documents

4413124

1MS016C - Pre A1R22 Testing as Found Outside

Acceptance Range

03/31/2021

4413146

Unexpected Annunciator: 1D-14: Fire Alarm

03/31/2021

4413531

1MS014C - Unsat Testing

04/01/2021

4413543

Unit 1 Trend Main Steam Safety Valves Lift Exceedance -

A1R22

04/01/2021

4413654

1MS015C - Unsat Testing

04/02/2021

4413656

1MS015A - Unsat Testing

04/02/2021

Procedures

1BwOSR 3.6.1.1-

Primary Containment Type C Local Leakage Rate Test of

Chemical and Volume Control System

1BwOSR

1A Diesel Generator Full Load Rejection and Simulated

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

3.8.1.10-1

Safety Injection in Conjunction with Undervoltage During

Load Testing

1BwOSR

3.8.1.11-1

1A Diesel Generator Loss of Emergency Safety Features

Bus Voltage with No Safety Injection Signal

1BwOSR

5.5.8.CV-8

Comprehensive Inservice Testing (IST) Requirements for

Unit 1 Charging Pumps and Safety Injection System

Charging Check Valve Stroke Test

BwMP 3305-003

Main Steam Safety Valve Testing Using Setpoint Verification

Device

BwOP DG-1

Diesel Generator Alignment to Standby Condition

BwOP DG-11

Diesel Generator Startup and Operation

BwOP DG-12

Diesel Generator Shutdown

BwOSR 3.8.1.19-

1A Diesel Generator Emergency Core Cooling System

Sequencer Surveillance

ER-AA-321

Administrative Requirements for Inservice Testing

Work Orders

4803148

1A Diesel Generator 24-Hour Load Test and Emergency

Core Cooling System Sequencer Surveillance

04/20/2021

4817382

1A Diesel Generator Loss of Emergency Safety Features

Bus Voltage with NO Safety Injection

04/20/2021

4836102

1A Diesel Generator Safety Injection Signal Override of Test

Mode

04/20/2021

4983054

OP CV Cold Leg Check Valve Test 1BwOSR

5.5.8.CV-8

04/07/2021

5066993

As Found LLRT 1CV8152 and 1CV8160 1BwOSR

3.6.1.1-9

04/09/2021

5067469

IST - 1MS013s/014s/015s016s/017s

03/31/2021

71124.02

ALARA Plans

BW-01-21-00612 Core Barrel ISI and all Associated Work Valve

Repairs/Inspections

BW-01-21-00613

Reactor Head Disassembly and Reassembly

BW-01-21-00623

Reactor Cavity Decon

71124.03

Corrective Action

Documents

254289

0EA01C SCBA Compressor has a Small Leak

06/04/2019

263013

Mask Fit not Completed for Licensed Operator

07/10/2019

04370062

Evaluate Need for SCBA Kits in the Unit 1 and Unit 2

Containment Access Facility

09/17/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

MSA SCBA/Firehawk Monthly Inspection

03/2021

Procedures

RP-AA-825-101-

1001

Operation and use of The MSA Firehawk Self-Contained

Breathing Apparatus (SCBA)

RP-AA-870-1003

Testing Portable HEPA Filter Units

71124.04

Calibration

Records

RP-AA-232-1001

FASTSCAN Calibration Acceptance Criteria

2/24/2021

RP-AA-700-1235

PM-12 Calibration Data Sheet

07/08/2020

Corrective Action

Documents

268944

NOS ID 2018 Bioassay Program Periodic Measurement not

Performed

08/01/2019

Radiation

Surveys

RP-AA-220

Intake Investigation Form; 7080

04/22/2020

RP-AA-220

Intake Investigation Form; 5132

04/22/2020

Self-Assessments PI-AA-126-1001-

F-01

Radiation Protection Dosimetry and Occupational Dose

Assessment

10/31/2019

71151

Miscellaneous

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for High Pressure

Injection;

04/01/2020 -

03/31/2021

NRC Performance Indicator Data; Mitigating Systems

Safety System Functional Failures

04/01/2020 -

03/31/2021

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for Emergency AC

Power

04/01/2020 -

03/31/2021

71152

Corrective Action

Documents

3968314

1MS101C "A" Solenoid Replacement Extent of Condition

01/30/2017

4130120

OSP-A, 1MS101C will not go Open

04/24/2018

201555

1MS101B Failed to Stroke

2/09/2018

256475

1MS101B would not Open when Demanded from its Control

Switch

06/13/2019

27859

1MS101C Failed to Open when Demanded from its Control

Switch

06/07/2021

Procedures

NO-AA-10

Quality Assurance Topical Report (QATR)

- 97

PI-AA-120

Issue Identification and Screening Process

PI-AA-125

Corrective Action Program (CAP) Procedure

PI-AA-125-1001

Root Cause Analysis Manual

PI-AA-125-1003

Corrective Action Program Evaluation Manual

71153

Corrective Action

4430406

Multiple MCR Alarms Received Due to Adverse Weather

06/20/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

4430440

Indication Lost for 1MS-147A Following Unit 1 Reactor Trip

06/21/2021

4430441

Unit 1 Reactor Trip Load Reject

06/21/2021

4430442

Unexpected Annunciator: 1-4-D5

06/21/2021

4430444

A/D MSIV Room Fire Alarm Following Reactor Trip

06/21/2021

4430446

N35 and N36 Appear to be Undercompensated

06/21/2021

4430586

4.0 Critique Unit Reactor Trip Due to Generator Load Reject

06/21/2021

4430895

Need WO Generated for Testing Station Site Grounding

System

06/22/2021

4431283

0VV23C has a Sheared Belt

06/24/2021

4432865

Braidwood Site Ground Testing

07/01/2021

Procedures

1BwGP 110-4T4

Reactor Trip Post Response Guideline

OP-AA-106-101-

1001

Event Response Guidelines

OP-AA-108-108

Unit Restart Review

OP-AA-108-114

Post Transient Review

Work Orders

1685480

0VV23C Perform Belt Inspection

08/09/2017

5164828

0VV23C has a Sheared Belt

06/24/2021