IR 05000443/2019010

From kanterella
Jump to navigation Jump to search
Design Bases Assurance Inspection Report 05000443/2019010
ML19184A010
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 07/03/2019
From: Mel Gray
NRC Region 1
To: Nazar M
NextEra Energy Seabrook
References
IR 2019010
Download: ML19184A010 (21)


Text

July 3, 2019

SUBJECT:

SEABROOK STATION UNIT 1 - DESIGN BASES ASSURANCE INSPECTION INSPECTION REPORT 05000443/2019010

Dear Mr. Nazar:

On June 5, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Seabrook Unit 1 and discussed the results of this inspection with Mr. Eric McCartney, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low safety significance (Green) are documented in this report, all of which involved violations of NRC requirements. We are treating these violations as non-cited violations (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violations or significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Seabrook.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC Resident Inspector at Seabrook. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Mel Gray, Chief Engineering Branch 1

Docket No.: 50-443 License No.: NPF-86

Enclosure:

Inspection Report 05000443/2019010

Inspection Report

Docket Number:

05000443

License Number:

NPF-86

Report Number:

05000443/2019010

Enterprise Identifier: I-2019-010-0050

Licensee:

NextEra Energy Seabrook, LLC

Facility:

Seabrook Station Unit 1

Location:

Seabrook, NH 03874

Inspection Dates:

April 14, 2019 to May 04, 2019

Inspectors:

S. Pindale, Senior Reactor Inspector (Team Leader)

J. Ambrosini, Senior Emergency Preparedness Inspector

F. Arner, Senior Reactor Analyst

M. Orr, Reactor Inspector

J. Schoppy, Senior Reactor Inspector

C. Baron, NRC Mechanical Contractor

J. Nicely, NRC Electrical Contractor

Approved By:

Mel Gray, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting a design bases assurance inspection at Seabrook Unit 1 in

accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Improperly Sized Thermal Overload Relays for Throttling Motor-Operated Valves

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000443/2019010-01

Open

None

71111.21M

The team identified a finding of very low safety significance (Green) involving a Non-Cited

Violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, in that NextEra did

not adequately verify or check the adequacy of design, such as by the performance of design

reviews, by the use of alternate or simplified calculational methods, or by the performance of

a suitable testing program for several motor-operated valves (MOV). Specifically, NextEra

did not verify the thermal overload (TOL) protective devices on eight safety-related

emergency feedwater flow control MOVs were properly sized to support their safety function

of repetitive jogging/throttling during transients and postulated events.

Inadequate 4kV Breaker Testing

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000443/2019010-02

Open

None

71111.21M

The team identified a finding of very low safety significance (Green) involving a Non-Cited

Violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, in that NextEras test

program did not assure that all testing required to demonstrate that structures, systems, and

components will perform satisfactorily in service in accordance with written test procedures

that incorporate the requirements and acceptance limits contained in applicable design

documents. Specifically, NextEras six-year inspection, testing and preventive maintenance

procedure for 4kV safety-related breakers did not perform as-found electrical testing for

breaker functions prior to performing preventive maintenance activities. As such, breaker

degradation while in service may not be identified during the subsequent testing, and could

prevent the identification of deterioration toward an unacceptable condition.

Survivability of Equipment during a Postulated Design Basis Accident Coincident with

Degraded Offsite Power System Voltage

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000443/2019010-03

Open

None

71111.21M

The team identified a finding of very low safety significance (Green) involving a Non-Cited

Violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, in that NextEra did

not verify or check the adequacy of design for setting thermal overload (TOL) protective

devices, such as by the performance of design reviews, by the use of alternate or simplified

calculational methods, or by the performance of a suitable testing program. Specifically,

NextEra did not ensure that TOL protective device settings for specific motor-operated valves

(MOVs) would prevent safety-related loads from becoming damaged or unavailable during a

postulated design basis event involving a loss-of-coolant accident coincident with a degraded

voltage of the offsite power supply system.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IP) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21M - Design Bases Assurance Inspection (Teams)

The team evaluated the following components, permanent modifications, and operating

experience during the weeks of April 15, 2019, and April 29, 2019.

For the components, the team reviewed the attributes listed in Inspection Procedure 71111.21M, Appendix A, Component Review Attributes, such as those listed

below. Specifically, the team evaluated these attributes as per 71111.21M, Appendix B,

Component Design Review Considerations and 71111.21M, Appendix C, Component

Walkdown Considerations.

Design Review - Large Early Release Frequency (IP Section 02.02) (1 Sample)

Containment Recirculation Sump A Isolation Valve, 1-CBS-V8

Normal, abnormal, and emergency operating procedures

Consistency among design and licensing bases and other documents/procedures

System health report, maintenance effectiveness and records, and corrective action

history

Design calculations

Surveillance testing and recent test results

Testing of control system interlocks

Diagnostic testing methodology

Adequacy of electrical power supply for motor and controls

Thermal overload protection settings

The team used Appendix B guidance for Valves, Instrumentation, Electric Loads, and As-

Built System.

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (5 Samples)

(1)

A Primary Component Cooling Water Pump, CC-P-11-A

Material condition and installed configuration (e.g., visual

inspection/walkdown)

Normal, abnormal, and emergency operating procedures

  • Consistency among design and licensing bases and other documents and

procedures

System health report, maintenance effectiveness and records, and corrective

action history

Control logic (pump trip)

Equipment/environmental controls and qualification

Design calculations

Surveillance testing and recent test results

The team used Appendix B guidance for Valves, Instrumentation, Electric Loads, and

As-Built System.

(2)

Service Water Train A Isolation of Secondary Loads, SWS-MOV-V4

Material condition and installed configuration (e.g., visual

inspection/walkdown)

Normal, abnormal, and emergency operating procedures

Consistency among design and licensing bases and other

documents/procedures

System health report, maintenance effectiveness and records, and corrective

action history

Design calculations

Adequacy of electrical power supply for motor and controls

Thermal overload protection settings

Surveillance testing and recent test results

The team used Appendix B guidance for Valves, Instrumentation, Electric Loads, and

As-Built System.

(3)

4160Vac Bus E5 and associated Emergency Diesel Generator A (electrical)

Material condition and installed configuration (e.g., visual

inspection/walkdown)

Normal, abnormal, and emergency operating procedures

Component health report, maintenance effectiveness and records, and

corrective action history

Coordination and interface with the transmission system operator

Design calculations (e.g., load flow, bus loading and voltage drop,

environmental temperature effects, degraded and loss of voltage protection,

protective relay and breaker settings and coordination, short circuit/breaker

duty analysis, and diesel generator loading)

Surveillance testing and recent test results

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses,

Cables, Electric Loads, Motor Control Centers (MCCs), and As-built system.

(4)

Supplementary Emergency Power System (Diesel Generator) Train A

Material condition and installed configuration (e.g., visual

inspection/walkdown)

Normal, abnormal, and emergency operating procedures

  • Consistency among design and licensing bases and other documents and

procedures

System health report, maintenance effectiveness and records, and corrective

action history

Design calculations (e.g., emergency diesel generator loading, voltage drop

analyses)

Surveillance testing and recent test results

Equipment protection from fire, flood, and water intrusion or spray

Heat removal cooling water and ventilation

Energy sources, fuel and air (e.g., engine start, operation, and control)

The team used Appendix B guidance for Valves, Pumps, Instrumentation, Electric

Loads, and As-Built System.

(5)

Turbine-Driven Emergency Feedwater Pump, FW-P-37A

Material condition and installed configuration (e.g., visual

inspection/walkdown)

Normal, abnormal, and emergency operating procedures

Consistency among design and licensing bases and other

documents/procedures

System health report, maintenance effectiveness and records, and corrective

action history

Design calculations

Surveillance testing and recent test results

Turbine overspeed protection

Pump steam binding protection

Exhaust stack tornado missile protection

Station blackout environmental conditions

The team used Appendix B guidance for Valves, Instrumentation, and As-Built

System.

Modification Review - Permanent Modifications (IP Section 02.03) (5 Samples)

(1)

EC 145024, Reconciliation of Methods Used for Determining RWST Minimum

Submergence Levels to Preclude Vortexing, Revision 0

(2)

EC 145372, EDG Lube Oil High Temperature Trip Setpoint Change, Revision 2

(3)

EC 284280, Increase in RCS Loop Tavg to Average Tavg Deviation Alarm Setpoint,

Revision 0

(4)

EC 291333, RC-V-122/124 Allowable Closure Time Increase, Revision 0

(5)

EC 287636, Diesel Air Handling Calculation MSVCS-FAG-09, Revision and Service

Environment Chart Update, Revision 0

Review of Operating Experience Issues (IP Section 02.06) (2 Samples)

(1)

NRC Information Notice 2005-30, Safe Shutdown Potentially Challenged by

Unanalyzed Internal Flooding Events and Inadequate Design, dated

November 7, 2005

(2)

NRC Information Notice 2016-05, Operating Experience Regarding Complications

from a Loss of Instrument Air, dated April 27, 2016

INSPECTION RESULTS

Improperly Sized Thermal Overload Relays for Throttling Motor-Operated Valves

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000443/2019010-01

Open

None

71111.21M

The team identified a finding of very low safety significance (Green) involving a Non-Cited

Violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, in that NextEra did

not adequately verify or check the adequacy of design, such as by the performance of design

reviews, by the use of alternate or simplified calculational methods, or by the performance of

a suitable testing program for several motor-operated valves (MOV). Specifically, NextEra did

not verify the thermal overload (TOL) protective devices on eight safety-related emergency

feedwater flow control MOVs were properly sized to support their safety function of repetitive

jogging/throttling during transients and postulated events.

Description: The team noted that the safety-related emergency feedwater flow control MOVs

FW-FV-4214A/B through FW-FV-4244A/B (eight valves) have a design function for repetitive

jogging/throttling during transients and postulated design basis events. In calculation

9763-3-ED-00-28-F-CALC_009, NextEra selected TOLs based on the MOVs having three

normal strokes to provide capability to recover from a mis-positioned MOV and provide

protection of the MOV thermal limit during locked rotor conditions. However, the calculation

methodology did not consider the design function of jogging/throttling the MOVs in sizing the

TOL protective devices. TOL sizing calculations only addressed the MOV thermal limit

function and the capability to recover from a mis-positioned MOV. Further, the team noted

that there was not operator guidance or documented limitations regarding the maximum

number of times each MOV can be cycled. As a result, the safety function of the MOVs was

not ensured as the installed TOL protective devices could potentially actuate and cause

spurious or unexpected tripping of the affected MOVs during postulated events. The team

concluded the calculation methodology did not consider the design function that

jogging/throttling MOVs have specific thermal overload performance requirements; and that

sizing the TOLs required a unique I2t evaluation methodology to ensure that the valves

would be able to perform the required number of jogging operations without tripping the

TOLs. The I2t methodology considers specific electrical current values (I) for specific times (t)

as an MOV responds to jogging/throttling demand signals.

NRC Regulatory Guide 1.106 Revision 1, to which NextEra is committed in UFSAR

Sections 1.8, 8.1.5.3 and 8.3.1.1, states in Regulatory Position C.2, that the trip setpoint of

the TOL protection devices should be established with all uncertainties resolved in favor of

completing the safety-related action. NRC Generic Letter 89-10, Supplement 1, provides

additional guidance in Question 15, which states that licensees should review design basis

information for each MOV in the program to identify whether, when and how often an MOV

must be opened or closed.

Because the TOL sizing calculations only addressed the MOV thermal limit function and the

capability to recover from a mis-positioned MOV, the resulting TOL design could have

resulted in a spurious or unexpected actuation of the TOL protective devices and potentially

prevented the MOV from performing a safety function to function during transients and

postulated events.

Corrective Actions: NextEra performed a detailed analysis using the I2t methodology, and

determined an appropriate limit for which the affected emergency feedwater MOVs could be

throttled without adversely affecting the valves. The team reviewed the results and verified

that they bounded the expected number of times operators may cycle these valves, and

current MOV operability was not adversely affected. NextEra also plans on developing

operator guidance regarding limitations and actions associated with the maximum number of

times the affected valves can be throttled.

Corrective Action Reference: AR 02312915

Performance Assessment:

Performance Deficiency: NextEras failure to properly verify or check the adequacy of design,

such as by the performance of design reviews or by the use of alternate or simplified

calculational methods, for several MOVs was a performance deficiency within their ability to

foresee and correct, and which should have been prevented. Specifically, NextEra did not

verify the TOL protective devices on eight safety-related emergency feedwater flow control

MOVs were properly sized to support their safety function of repetitive jogging/throttling

during transients and postulated events.

Screening: The team determined this finding was more than minor because it was associated

with the Design Control attribute of the Mitigating Systems cornerstone and affected the

cornerstone objective of ensuring the availability and reliability of systems that respond to

initiating events to prevent undesirable consequences.

Significance: The team assessed the significance of the finding using IMC 0609.04, Initial

Characterization of Findings, and IMC 0609, Appendix A, Exhibit 2, Mitigating Systems

Screening Questions. The team determined that this finding was a deficiency affecting the

design or qualification of a mitigating structure, system or component, where the structure,

system or component maintained its operability or functionality. Therefore, the team

determined the finding to be of very low safety significance (Green).

Cross-Cutting Aspect: None

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires that design

control measures shall provide for verifying or checking the adequacy of design, such as by

the performance of design reviews, by the use of alternate or simplified calculational

methods, or by the performance of a suitable testing program.

Contrary to the above, as of May 3, 2019, NextEras design control measures did not provide

for verifying or checking the adequacy of design of the TOLs for eight safety-related

emergency feedwater flow control MOVs that had a jogging/throttling design function. As a

result, NextEra could not assure the affected MOVs could perform their design safety

function.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2.a of the Enforcement Policy.

Inadequate 4kV Breaker Testing

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000443/2019010-02

Open

None

71111.21M

The team identified a finding of very low safety significance (Green) involving a Non-Cited

Violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, in that NextEras test

program did not assure that all testing required to demonstrate that structures, systems, and

components will perform satisfactorily in service in accordance with written test procedures

that incorporate the requirements and acceptance limits contained in applicable design

documents. Specifically, NextEras six-year inspection, testing and preventive maintenance

procedure for 4kV safety-related breakers did not perform as-found electrical testing for

breaker functions prior to performing preventive maintenance activities. As such, breaker

degradation while in service may not be identified during the subsequent testing, and could

prevent the identification of deterioration toward an unacceptable condition.

Description: The team reviewed NextEras activities associated with preventive maintenance

and testing of safety-related 4kV breakers. In particular, the team evaluated whether the

breaker testing activities were capable of detecting breaker degradation.

As documented in UFSAR Section 8.1.5.2, NextEra is committed to IEEE 308-1971,

Standard Criteria for Class IE Electric Systems for Nuclear Power Generating Stations, and

IEEE Standard 338-1975, Standard Criteria for the Periodic Testing of Nuclear Power

Generating Station Class 1E Power and Protection Systems. IEEE 308-1971 states that

tests shall be performed at scheduled intervals to detect the deterioration of the system

toward an unacceptable condition (Section 6.3, Periodic Equipment Tests); and IEEE

Standard 338-1975, states that functional tests shall assure that the tested equipment is

capable of performing its design function (Section 6.3.2, Functional Tests). The team noted

that NextEra's 4kV power circuit breaker maintenance procedure LX0558.01 4.16kV Breaker

Inspection, Testing and PM, which is performed on a six-year frequency, did not perform as-

found electrical testing for breaker functions, such as breaker timing, and reduced voltage

testing of the trip/close coils prior to inspecting, cleaning, and lubricating the

breakers. NextEra implemented the mechanical and electrical portions of the procedure

separately and sequentially. The team reviewed the procedure and noted the mechanical

portion of the activity was preventive maintenance (inspecting, cleaning, lubricating) and was

typically performed prior to the electrical/testing portion. The team determined that the nature

and sequence of the activities pre-conditioned the breakers prior to performing the

electrical/testing part of the procedure. Since there was no as-found testing performed prior

to the preventive maintenance, the team concluded the sequence of the activities performed

could mask breaker degradation and prevent the identification of deterioration toward an

unacceptable condition as specified in IEEE 308-1971 and 338-1975.

In addition to the IEEE 308-1971 and 338-1975 standards, the team noted NRC Information Notice 97-16, Preconditioning of Plant SSCs before ASME Code In-service Testing or

Technical Specification Surveillance addressed this issue. Specifically, the document

discussed instances where a surveillance procedure contained instructions requiring

technicians to inspect, clean, and lubricate several breakers before performing the as-found

testing of several breaker functions; but since those functions could have been affected by

the cleaning and lubrication, the test results did not represent the as-found condition of the

breakers.

Corrective Actions: NextEra plans to evaluate their 4kV breaker preventive maintenance and

testing process to ensure as-found testing is appropriately performed. The team verified

there were no instances where the affected 4kV breakers had significantly degraded toward

unacceptable performance notwithstanding the lack of as-found testing.

Corrective Action Reference: AR 02312582

Performance Assessment:

Performance Deficiency: NextEras failure to assure that testing required to demonstrate that

structures, systems, and components will perform satisfactorily in service in accordance with

written test procedures that incorporate the requirements and acceptance limits contained in

applicable design documents was a performance deficiency within their ability to foresee and

correct, and which should have been prevented. Specifically, NextEra did not perform

periodic equipment tests in a manner such that they would effectively detect the deterioration

of the equipment toward an unacceptable condition.

Screening: The team determined this finding was more than minor because it was associated

with the Equipment Performance attribute of the Mitigating Systems cornerstone and affected

the cornerstone objective of ensuring the availability and reliability of systems that respond to

initiating events to prevent undesirable consequences. The finding was also more than minor

because if left uncorrected, it would have the potential to lead to a more significant safety

concern.

Significance: The team assessed the significance of the finding using IMC 0609.04, Initial

Characterization of Findings, and IMC 0609, Appendix A, Exhibit 2, Mitigating Systems

Screening Questions. The team determined that this finding was not a deficiency affecting

the design or qualification of a mitigating structure, system or component, did not represent a

loss of system and/or function, and did not represent an actual loss of function. Therefore,

the team determined the finding to be of very low safety significance (Green).

Cross-Cutting Aspect: None

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires that test program

shall be established to assure that all testing required to demonstrate that structures,

systems, and components will perform satisfactorily in service is identified and performed in

accordance with written test procedures which incorporate the requirements and acceptance

limits contained in applicable design documents.

Contrary to the above, as of May 3, 2019, NextEra did not assure that all testing required to

demonstrate that structures, systems, and components will perform satisfactorily in service in

accordance with written test procedures which incorporate the requirements and acceptance

limits contained in applicable design documents. Specifically, NextEras six-year inspection,

testing and preventive maintenance procedure for 4kV safety-related breakers did not

perform as-found electrical testing for breaker functions prior to performing preventive

maintenance activities. As such, breaker degradation while in service may not have been

identified during the subsequent testing and could prevent the identification of deterioration

toward an unacceptable condition as specified by industry standards.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with

Section 2.3.2.a of the Enforcement Policy.

Survivability of Equipment during a Postulated Design Basis Accident Coincident with

Degraded Offsite Power System Voltage

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000443/2019010-03

Open

None

71111.21M

The team identified a finding of very low safety significance (Green) involving a Non-Cited

Violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, in that NextEra did

not verify or check the adequacy of design for setting thermal overload (TOL) protective

devices, such as by the performance of design reviews, by the use of alternate or simplified

calculational methods, or by the performance of a suitable testing program. Specifically,

NextEra did not ensure that TOL protective device settings for specific motor-operated valves

(MOVs) would prevent safety-related loads from becoming damaged or unavailable during a

postulated design basis event involving a loss-of-coolant accident coincident with a degraded

voltage of the offsite power supply system.

Description: The team evaluated the Seabrook design related to a postulated design basis

event coincident with a degraded voltage of the offsite power supply system. In particular, the

team evaluated whether safety-related equipment, which would automatically block load

during such an event, was properly designed and maintained to ensure the equipment would

function as expected. During the postulated scenario, it is assumed that voltage would

remain degraded (less than the second level undervoltage setpoint but above the lower, loss

of voltage setpoint) until the associated time delay of about 11 seconds would ultimately

transfer the electrical power supply to the onsite power system automatically.

The team determined UFSAR Section 8.3.1.1.b.4.(b) stated if the second level undervoltage

protection activation occurs coincidentally with an accident signal, the unit auxiliary

transformer and reserve auxiliary transformer incoming line breakers are automatically tripped

after a time delay to prevent spurious operation due to transients such as starting of large

motors. That scenario would result in a total loss of voltage to the 4kV bus. That action, in

turn, would result in connecting to and sequencing onto the associated emergency diesel

generator.

NRC Branch Technical Position PSB-1, Adequacy of Station Electric Distribution System

Voltages, dated July 1981, stated in part that the time delay associated with the second level

of undervoltage protection should be of limited duration such that the permanently connected

Class 1E loads will not be damaged.

NRC Regulatory Issue Summary (RIS) 2011-12, Revision 1, Adequacy of Station Electric

Distribution System Voltages, was issued to clarify the NRC staffs technical position on

existing requirements. RIS 2011-12 stated the time delay (at which the Class 1E buses

should automatically separate from the offsite power supply) chosen should be optimized to

ensure that permanently connected Class 1E loads are not damaged under sustained

degraded voltage conditions, such as a sustained degraded voltage below the degraded

voltage relay setting for the duration of the time delay setting.

NRC Regulatory Guide 1.106 Revision 1, to which NextEra is committed in UFSAR Sections

1.8 and 8.1.5.3, stated in Regulatory Position C.2, the trip setpoint of the TOL protection

devices should be established with all uncertainties resolved in favor of completing the safety-

related action.

The team determined NextEra did not ensure that safety-related MOV loads that would

require starting during a postulated accident coincident with a degraded grid condition

(second level undervoltage protection), had been verified to ensure the associated MOV

protective devices (i.e., TOLs) would not trip so as to complete the associated safety-related

action. The team observed in calculation 9763-3-ED-00-28-F-CALC_009, minimum trip times

at a locked rotor condition were not evaluated to ensure the safety function would be met if an

MOV stalled as the result of a degraded voltage condition. In particular, NextEra did not

ensure that the TOL design for the associated 17 MOVs that would block load in that scenario

were adequate to ensure the MOV safety functions would be accomplished for this scenario

(i.e., the MOVs could have been subject to a transient degraded voltage, and possibly stall

under certain conditions).

In response to the team's questions, NextEra staff demonstrated that the 4kV emergency

buses were historically operated well above the degraded voltage relay setpoint, and have

not seen a sustained undervoltage condition. In addition, the offsite power system was

historically maintained above its rated 345kV voltage level. Operating procedure controls

have been in place, and NextEra confirmed actual offsite power voltage levels have been

functional and adequate to ensure the affected components and systems were not adversely

impacted by this finding (five year operating history reviewed). In considering this issue,

NextEra staff concluded that full qualification was not demonstrated. In accordance with their

procedures, NextEra staff completed a prompt operability determination and developed

interim actions pending final resolution of this issue. The team discussed the technical details

and reviewed NextEras analyses and prompt operability determination, and found NextEras

actions to be reasonable and appropriate.

Corrective Actions: NextEra staff performed detailed analyses and completed a prompt

operability determination in response to this issue. Several compensatory interim actions

were implemented to ensure that plant operators would take appropriate proactive actions

based on specific conditions, including direction to declare both offsite power sources

inoperable and entering the applicable technical specifications in the event Seabrook is

notified of a post-contingent voltage condition of less than 345kV. Post-contingent voltage is

the calculated voltage to which the grid would degrade in the event of a trip of

Seabrook. Plant operators will also implement an additional action if the grid degrades further

to immediately energize the two safety-related 4kV buses from the emergency diesel

generators to ensure a degraded grid condition will not adversely affect the specific MOVs

powered from safety buses. NextEra plans to implement additional, permanent corrective

actions based on the results of their continuing evaluation of this issue.

Corrective Action Reference: AR 02312943

Performance Assessment:

Performance Deficiency: NextEras failure to properly verify or check the adequacy of design,

such as by the performance of design reviews or by the use of alternate or simplified

calculational methods, for 17 MOVs that are block loaded was a performance deficiency

within their ability to foresee and correct, and which should have been prevented. Specifically,

NextEra did not properly size TOL protective devices for 17 MOVs that would be required to

operate during a postulated design basis event coincident with a degraded voltage

condition. As a result, NextEra did not demonstrate assurance that the MOVs would not

become damaged or rendered unavailable during the postulated scenario.

Screening: The team determined this finding was more than minor because it was associated

with the Design Control attribute of the Mitigating Systems cornerstone and affected the

cornerstone objective of ensuring the availability, reliability and capability of systems that

respond to initiating events to prevent undesirable consequences.

Significance: The team assessed the significance of the finding using IMC 0609.04, Initial

Characterization of Findings, and IMC 0609, Appendix A, Exhibit 2, Mitigating Systems

Screening Questions. The team determined that this finding was a deficiency affecting the

design or qualification of a mitigating structure, system or component, where the structure,

system or component maintained its operability or functionality. While this issue involved the

qualification of several TOL protective devices during a particular degraded grid condition

coincident with postulated design basis accident scenarios described in Chapter 15 (Accident

Analyses) of the UFSAR, the affected MOVs were determined to be capable of performing

their safety function, given the numerous equipment failures, conservative assumptions and

specific system configurations that would have to occur to cause a deterministic system

failure. Therefore, the team determined the finding to be of very low safety significance

(Green).

Cross-Cutting Aspect: None

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires that design

control measures shall provide for verifying or checking the adequacy of design, such as by

the performance of design reviews, by the use of alternate or simplified calculational

methods, or by the performance of a suitable testing program.

Contrary to the above, as of May 3, 2019, NextEras design control measures did not provide

for verifying or checking the adequacy of design to ensure connected Class 1E loads would

not be damaged or become unavailable for a postulated design basis event coincident with a

degraded voltage condition.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with

Section 2.3.2.a of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On May 3, 2019, the team presented the preliminary results of the Design Bases

Assurance Inspection to Mr. Eric McCartney, Site Vice President, and other members of

NextEra staff. After further in-office review, the final results of this inspection were

presented to Mr. McCartney and the other NextEra staff via telephone on June 5, 2019.

Documents Reviewed

Calculations

4.3.07-12F, PCCW Head Tank Overflow and Pump Suction Line Sizes and Pump NPSH

Analysis, Revision 4

6.01.42.01, Control Building Elevation 21-6 and 50-0 4kV Switchgear Areas, Battery Rooms,

MG Set Rooms and Cable Spreading Room Ventilation, Revision 7

9763-3-ED-00-01-F, Short Circuit Current Calculation, Revision 9

9763-3-ED-00-02-F, Voltage Regulation, Revision 14

9763-3-ED-00-23-F, Medium Voltage Protective Relay Coordination, Revision 6

9763-3-ED-00-28-F, Motor Control Center Protection, Revision 9

9763-3-ED-00-45-F, Control Building Heat Load Calculation, Revision 5

9763-3-ED-00-66-F, Control Circuit Voltage Drop, Revision 5

9763-3-ED-00-83-F, Diesel Generator Loading, Revision 17

C-S-1-20801, Emergency Feedwater System Flow Study, Revision 1

C-S-1-20805, EFW Pump Pressure at Overspeed Trip, Revision 1

C-S-1-20811, EFW System Maximum Operating Pressure, Revision 0

C-S-1-20815, Low Suction Pressure Setpoint for Securing EFW Pumps, Revision 0

C-S-1-20823, EFW Pump IST Performance Requirements, Revision 0

C-S-1-20824, Emergency Feedwater Pump Exhaust Stack - Tornado Missiles, Revision 0

C-S-1-28076, Accidental RCS Depressurization Analysis, Revision 0

C-S-1-28137, Emergency Feedwater System High Flow Isolation Setpoint Analysis, Revision 0

C-S-1-45071, EFW Piping Qualification for Overpressurization, Revision 2

C-S-1-80903, MOV Differential Pressure Calculations, Revision 1

C-S-1-80904, MOV Thrust, Actuator Capability and Torque Switch Setpoint Calculations,

Revision 4

C-S-1-83704, Hydraulic Modeling of PCCW Flow Distribution, Revision 3

C-S-1-83805, CBS-V8/V14 Bonnet Pressure Calculation, Revision 0

C-S-1-83807, Determination of Delta-P, CBS-V8 and V14, Revision 0

C-S-1-83808, Post-LOCA Heatup of Valves CBS-V8 and V14, Revision 0

C-S-1-84213, Appendix R Timing Calculations for Reactor Coolant Inventory Control, Revision 2

C-X-1-21802, Expansion Joint Rupture in the Circulating Water System Located in the Turbine

Building, Revision 3

FP98328, Required Thrust and Weak Link Calculations, Revision B

FP98522, Actuator Sizing and Valve Weak Link Analysis, Revision 0

SBC-128, Technical Specifications, Setpoints and Allowable Values, Revision 17

Engineering Evaluations and Modifications

10CFR50.59 Screen 2004-286, Substitution of Enhanced Operator Action for Turbine Building

Scuppers, Revision 0

10CFR50.59 Screen 2015-50, Fukushima SEPS Components Seismic Upgrades, Revision 0

10CFR50.59 Screen 2015-51, Fukushima SEPS Foundations, Enclosures, and Exhaust

Seismic Upgrades, Revision 0

10CFR50.59 Screen 2016-229, Diesel Air Handling Calculation MSVCS-FAG-09 Revision and

Service Environment Chart Update, Revision 0

DCR 03-002, Supplemental Emergency Power System, 10/17/05

DCR 96-0016, PCCW Heat Exchanger Replacement, Revision 1

DCR 97-0027, Condensate Storage Tank Valve Room Heater, Revision 3

EC 145024, Reconciliation of Methods used for Determining RWST Minimum Submergence

Levels to Preclude Vortexing, Revision 0

EC 145372, EDG Lube Oil High Temperature Trip Setpoint Change, Revision 2

EC 277469, 1-SW-V-4 Running Current Change, Revision 0

EC 282825, Fukushima SEPS Components Seismic Upgrades, Revision 1

EC 283031, Equivalent Design Package for SEPS-DG-2-A Exhaust System Material, Revision 2

EC 284280, Increase in RCS Loop Tavg to Average Tavg Deviation Alarm Setpoint, Revision 0

EC 286883, Replace CC-P-11-A Motor with Rewound Motor, Revision 1

EC 287231, Equivalent Design Package for SEPS-DG-2-A Alternator Guard Cover Plate,

Revision 0

EC 291333, RC-V-122/124 Allowable Closure Time Increase, Revision 0

EE-91-07, Engineering Evaluation 91-07, dated 11/21/91

EQF 600-20-02, Medium Voltage Rewound Large AC Motors Electrical EQ File, Revision 4

LN0196, Inrush Current for a 11NA1 Actuator, 5/2/19

SEC15023-N7747, EQ Supplemental Report for Seabrook 700 HP CCW Pump Motor,

Revision 0

Corrective Action ARs

05-13283

05-11758

00108591

00124852

00157729

00219030

00222271

00222952

00391503

01695541

01761439

01764360

01789108

01862758

02081772

02132107

02150398

02153536

02169116

02169596

02256422

02269582

02270102

02277088

02289002

02291116

02310616

02310694

02310735*

02310800*

02310928

02310929

02310959*

02311034*

02311078*

02311079*

02311107*

02311247*

02311634

02311727*

02311729*

02311731*

02311860*

02311899

02312144

02312150

02312273*

02312286

02312365

02312367*

02312540

02312582*

02312590*

02312617*

02312622*

02312672*

02312764

02312824

02312826

02312876*

02312915*

02312943*

02312974*

02312985

  • AR written as a result of this inspection

Design and Licensing Bases

DBD-CC-01, Design Basis Document, Primary Component Cooling Water System, Revision 7

DBD-SW-01, Design Basis Document, Service Water System, Revision 8

LRAP-M021, Closed Cycle Cooling Water System Aging Management Program Basis

Document, Revision 2

SBN-903, Letter to NRC, Resolution of Power System Branch Confirmatory Items, 11/27/85

Drawings

10120177, EDG Voltage Dip Curve, 12/27/77

1-CC-B20205, Primary Component Cooling Loop A Detail, Revision 27

1-NHY-202069, Diesel Generator Building Plans Above Grade General Arrangement,

Revision 16

1-NHY-250000, Data Sheets for Motor-and Air-Operated Valves and Dampers, Revision 86

1-NHY-300219, Service Environment Chart, Revision 29

1-NHY-310002, Electrical Distribution One-Line Diagram, Revision 45

1-NHY-310007, 4160V Switchgear Bus 1-E5 One-Line, Revision 21

1-NHY-310013, 480V Unit Substation Buses E-51 and E-52 One-Line, Revision 22

1-NHY-310024, 480V MCC 1-E512, Revision 31

1-NHY-310027, 480V MCC 1-E521, Revision 34

1-NHY-312070, 4160V Supplemental Emergency Power System One-Line, Revision 1

1-NHY-503270, PCCW Pumps Logic Diagram, Revision 9

1-NHY-506194, Pumps P-11C and P-11A Loop A Control Loop Diagram, Revision 14

FP 23694, Pressures and Temperatures, DG Systems, Revision 1

FP35364, SEPS Generator Enclosure 2A Drawings, Revision 10

PID-1-FW-B20688, Emergency Feedwater System Details, Revision 12

PID-1-SEPS-B20953, SEPS Diesel Generator Fuel System Detail, Revision 0

PID-1-SEPS-B20954, SEPS Diesel Generator Cooling Water System Detail, Revision 1

PID-1-SI-20448, Safety Injection System - Low Head Injection, Revision 15

Procedures

D4702, EFW Pump A Suction Header Pressure Low, Revision 3

D6569, DG A Lube Oil Temp High, Revision 12

D6619, DG B Lube Oil Temp High, Revision 10

D7193, RWST Level LO-LO, Revision 5

E-0, Reactor Trip or Safety Injection, Revision 57

E-1, Loss of Reactor or Secondary Coolant, Revision 44

E-2, Faulted Steam Generator Isolation, Revision 27

E-3, Steam Generator Tube Rupture, Revision 45

ECA-0.0, Loss of all AC Power, Revision 54

EE-04-024, Operator Action Response Times Assumed in the UFSAR, Revision 4

ES 1850.003, Motor-Operated Valve Performance Monitoring, Revision 15

ES-0.2, Natural Circulation Cooldown, Revision 38

ES-1.2, Post LOCA Cooldown and Depressurization, Revision 40

ES-1.3, Transfer to Cold Leg Recirculation, Revision 30

F4232, PCCW Pumps A and C Running, Revision 2

F7494, PCCW Pump A Trip, Revision 5

FR-C.1, Response to Inadequate Core Cooling, Revision 28

FR-H.1, Response to Loss of Secondary Heat Sink, Revision 37

LS0563.58, Trip Check Procedure for EDG Switchgear Breakers, Revision 3

LX0558.01, 4.16kV Breaker Inspection, Testing and PM, Revision 16

ON 1242.01, Loss of Instrument Air, Revision 16

ON 1242.02, Loss of Containment Instrument Air, Revision 13

ON1061.01, Operation of SEPS, Revision 12

ON1061.07, SEPS Maintenance Run, Rev. 7

OS1006.04, Operation of the Containment Spray System, Revision 27

OS1012.03, Primary Component Cooling Water Loop A Operation, Revision 25

OS1026.01, Operation of DG 1A, Revision 30

OS1036.01, Aligning the Emergency Feedwater System for Automatic Initiation, Revision 25

OS1036.04, Emergency Feedwater Pump B Operation, Revision 4

OS1090.05, Component Configuration Control, Revision 74

OS1200.00, Response to Fire or Fire Alarm Actuation, Revision 25

OS1212.01, PCCW System Malfunction, Revision 14

OS1216.01, Degraded Ultimate Heat Sink, Revision 23

OS1246.02, Degraded Vital AC Power, Revision 21

OS1456.99, Cold Leg Recirculation Valve Interlock Surveillance, Revision 0

OX1401.03, RCS Vent Path Block Valve Quarterly, Cold Shutdown, and 18-Month Surveillance

Test, Revision 14

OX1406.13, Containment Recirculation Sump Valve Cold Shutdown Test, Revision 13

OX1436.02, Turbine-Driven EFW Pump Quarterly and Monthly Valve Alignment, Revision 29

OX1436.13, Turbine-Driven EFW Pump Post Cold Shutdown or Post Maintenance Surveillance

and Comprehensive Pump Test, Revision 42

OX1456.81, Operability Testing of IST Valves, Revision 36

OX1456.86, Operability Testing of IST Pumps, Revision 18

OX1461.04, SEPS Monthly Availability Surveillance, Revision 12

SM 7.20, Control of Time Critical Operator Actions and Time Sensitive Actions, Revision 12

SOO 19-002, Interim Guidance for Resetting RMO, Revision 0

Functional, Surveillance and Modification Acceptance Testing

01209321-03, 1-CC-P-11-A Motor Replacement PMT, performed 11/17/16

1-CC-P-11A Pump/Motor Inboard/Outboard Bearing Oil Sample Analysis Trending, 2015-2018

40312073, MOV Diagnostic Testing Summary Report, 1-CBS-V-8, performed 10/13/15

IS1616.420, CC-T-2171A PCCW LP-A Supply Header Temperature Control Calibration,

performed 12/11/17

IS1616.430, CC-T-2197A PCCW LP-A Supply Header Temperature Control Calibration,

performed 10/21/14

LS0558.04, 4.16kV Circuit Breaker Refurbishment, performed 10/8/13

LS0563.151, 1-CC-P-11-A Trip Checks, performed 11/16/16

LS0563.22, Testing of Agastat 120Vac (7000 Series) TDPU Timing Relays, performed 10/19/17

LS0564.34, 4160V Static Motor Testing (1-CC-P-11-A), performed 11/15/16

LS0564.38, 4160V Dynamic Motor Monitoring (1-CC-P-11-A), performed 11/17/16

LX0558.01, 4.16kV Breaker Inspection, Testing and PM (EDE-BKR-06), performed 6/21/17

OS1412.13, PCCW Train A Quarterly Operability, 18-Month Position Indication and

Comprehensive Pump Testing, performed 7/19/18 and 1/23/19

OX1401.03, RCS Vent Path Block Valve Quarterly, Cold Shutdown, and 18-Month Surveillance

Test, performed 6/19/18

OX1426.22, EDG 1A 24-Hour Load Test and Hot Restart Surveillance, performed 11/15/17

OX1426.23, EDG 1B 24-Hour Load Test and Hot Restart Surveillance, performed 1/31/18

OX1426.32, Diesel Generator 1B 36-Month Operability Surveillance, performed 4/25/17

OX1426.34, Diesel Generator 1A 36-Month Operability Surveillance, performed 10/24/18

OX1461.04, SEPS Monthly Availability Surveillance, performed 2/19/19, 3/18/19 and 4/23/19

V1435744, 1-SEPS-DG-2A Engine Sump Analysis, performed 11/6/17

Vendor Documents and Specifications

9763-006-238-5, Specification for Primary Component Cooling Water Pumps, Revision 6

FP 34938, Limitorque Vendor Manual, Revision 26

FP 53455, Primary Component Cooling Pump Vendor Technical Manual, Revision 14

FP35465-16 C808-2, Cummins Engine Company Troubleshooting and Repair Manual, Power

Generation Control Systems, QSK78 Series Engines, Volume 1, 7/30/04

SPEC-E-008, FPL Motor Repair/Refurbishment/ Rewind Requirements Specification,

Revision 11

Miscellaneous

SBK 16-005, Seabrook Nuclear Oversight Report - Maintenance, 9/27/16

SBK 17-003, Seabrook Nuclear Assurance Report - Design Engineering, 6/7/17

SBK 18-003, Seabrook Nuclear Assurance Report - Maintenance, 8/10/18

System Health Report, Diesel Generator System, Q1-2019

System Health Report, Electrical Distribution, Q1-2019

System Health Report, Primary Component Cooling Water, Q4-2018

System Health Report, Supplemental Emergency Power System, Q4-2018

Maintenance Work Orders

01209321

01211490

40207426

40235293

40270599

40312331

40365253

40397424

40397426

40433610

40446081

40490341

40493088

40493090

40493095

40497320

40498960

40498985

40510286

40514497

40531858

40534102

40534290

40539735

40539776

40539778

40547372

40550706

40550718

40584858

40611075

40611076

40611077