May 2, 2022
SUBJECT:
SEABROOK STATION - INTEGRATED INSPECTION REPORT 05000443/2022001
Dear Mr. Coffey:
On March 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Seabrook Station. On April 21, 2022, the NRC inspectors discussed the results of this inspection with Mr. Brian Booth, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Matt R. Young, Chief Projects Branch 2 Division of Operating Reactor Safety
Docket No. 05000443 License No. NPF-86
Enclosure:
As stated
Inspection Report
Docket Number:
05000443
License Number:
Report Number:
Enterprise Identifier: I-2022-001-0055
Licensee:
NextEra Energy Seabrook, LLC
Facility:
Seabrook Station
Location:
Seabrook, New Hampshire
Inspection Dates:
January 1, 2022 to March 31, 2022
Inspectors:
C. Newport, Senior Resident Inspector
T. Daun, Resident Inspector
Approved By:
Matt R. Young, Chief
Projects Branch 2
Division of Operating Reactor Safety
SUMMARY
The NRC continued monitoring the licensees performance by conducting an integrated inspection at Seabrook Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Seabrook Station began the inspection period operating at 100 percent rated thermal power and remained at or near full power for the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) B emergency diesel generator after monthly surveillance run on March 1
- (2) DC distribution system during transfer of 'D' 125VDC bus to its alternate battery supply and back to its normal battery supply on March 1
- (3) A safety injection after quarterly flow and valve test on March 23
- (4) A turbine driven emergency feedwater pump after quarterly surveillance run on March 24
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Primary auxiliary building (PAB-F-3A-Z) on January 4 (2)
'A emergency diesel generator building (DG-F-2A-A) on February 14
- (3) Cable spreading room (CB-F-2A-A) on March 1
- (4) Unit 1 service water cooling tower (CT-F-2B-A) on March 20
- (5) Primary auxiliary building electrical chase (PAB-F-1G-A) on March 28
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the on-site fire brigade training and performance during an unannounced drill on March 22
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)
The inspectors evaluated internal flooding mitigation protections in the:
(1) 'A' and 'B' essential switchgear rooms on February 24
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance of the following activities in the control room:
- Main turbine valve testing on February 11
- Safety injection accumulator back leakage seating evolution on February 14
- Control rod operability testing on February 17
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a licensed operator requalification examination conducted in the plant-reference simulator on January 28
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (1 Sample)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:
- (1) Radiation monitoring system and associated a(1) action plan on March 8
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Elevated risk during unit auxiliary transformer and reserve auxiliary transformer relay calibrations on January 13
- (2) Yellow risk during 'B' emergency diesel generator semi-annual surveillance and inspection on January 25
- (3) Elevated risk during service water tower actuation logic testing on March 1
- (4) Elevated risk during 345kV line 369 outage on March 15
- (5) Yellow risk during A turbine driven emergency feedwater pump surveillance and switchyard work on March 24
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) SB-V-5 failed to stroke within expected range (AR 02418461) on February 10 (2)
'A' safety injection accumulator back leakage (AR 02418795) on February 14
- (3) Control building air trouble alarm (AR 02394323) on March 4 (4)
'B' containment building spray pump decreasing discharge differential pressure trend (AR 02418551) on March 17 (5)
'B' emergency diesel generator starting air system failure (AR 02426043) on March 30
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Swap of vital 125VDC power panel PP-113A breaker to new panel position
- (2) Replacement of 25Y1 relay with new style relay for the 'A' emergency diesel generator
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:
(1)
'C' primary component cooling water pump and motor following oil changes on January 11 (2)
'B' emergency diesel generator semi-annual fast start following inspection on January 25 (3)
'B' centrifugal charging pump coupling lubrication and testing on February 3
- (4) Safety injection discharge cross connect valve (SI-V-112) following motor-operated valve inspection and lubrication on February 17
- (5) A essential switchgear ventilation fan CBA-FN-19 belt replacement on March 29 (6)
'B' emergency diesel generator following replacement of barring device relay on March 31
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:
Surveillance Tests (other) (IP Section 03.01) (4 Samples)
(1)
'A' emergency diesel generator monthly surveillance on January 10
- (2) Supplemental emergency power system quarterly surveillance on January 20
- (3) Bus 6 unit auxiliary transformer synch check relay calibration on January 26
- (4) Service water cooling tower makeup pump operability 18-month surveillance on March 10
In-service Testing (IP Section 03.01) (1 Sample)
(1) 'A' residual heat removal quarterly flow and valve stroke test on January 11
71114.06 - Drill Evaluation
Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated the conduct of a routine, full participation emergency planning drill on February
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===
- (1) For the period January 1, 2021 through December 31, 2021
IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
- (1) For the period January 1, 2021 through December 31, 2021
IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)
- (1) For the period January 1, 2021 through December 31, 2021
===71152A - Annual Follow-up Problem Identification and Resolution
Annual Follow-up of Selected Issues (Section 03.03)===
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Evaluation of licensed reactor operator staffing levels
- (2) Evaluation of preventative maintenance schedule changes and work planning processes
INSPECTION RESULTS
Observation: Licensed Reactor Operator Staffing Levels 71152A The inspectors performed a review of staffing levels of licensed reactor operators after the unexpected retirement and departure of several licensed reactor operators. The inspectors reviewed NextEras plans for restoration of the desired number of licensed reactor operators and NextEras plans for the use of licensed senior reactor operators to stand reactor operator watch positions when necessary, and verified that NextEras plan is currently maintaining minimum required licensed operator staffing levels.
Observation: Evaluation of Preventative Maintenance Schedule Changes and Work Planning Processes 71152A The inspectors performed a review of NextEras work control processes and efforts to streamline their preventative maintenance schedules and periodicity. As part of this review, the inspectors attended daily and weekly work planning meetings, reviewed corrective action documents, reviewed planning and justification documents for preventative maintenance schedule changes, and discussed these items with site work planning staff.
The inspectors noted three examples of preventative maintenance items that were improperly classified with a functional importance determination of non-critical (FID-N), a classification that allows for planned preventative maintenance work to not be completed if no deficiencies have been noted against the system. The three examples involved components that were not normally energized or actuated and as such, would not manifest a deficiency that would be documented in the corrective action program and trigger preventative maintenance to be performed. Each of these three components were used to either mitigate the impacts of a flooding event or by operators to take action in the event of a flooding event in various spaces in the plant. Each of the three FID-N classified maintenance items passed their associated surveillance tests when subsequently tested. The inspectors also noted an example of preventative maintenance important to safety and/or with risk significance being extended with insufficient justification. In 2019, the four pump discharge and suction pressure gauge calibration preventative maintenance activities for both trains of containment building spray were extended from a periodicity of 18 months to 4 years. NextEra justified the change after a review of the last four completions of each of the preventative maintenance activities noted only one case of instrument drift. While these instruments are not used by operations during normal or emergency plant operations, they do provide data used to justify operability during scheduled system surveillance testing.
Finally, the inspectors noted that site daily work planning meetings and communications often lacked clarity. Examples included, in several cases, daily planned work added or cancelled with short notice, daily site PRA risk classified as yellow when the primary risk driver for the yellow risk categorization not planned or performed and several instances where daily PRA risk increased on short notice, even though the drivers for the increase in risk consisted of planned maintenance activities known to the organization well in advance.
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On April 21, 2022, the inspectors presented the integrated inspection results to Mr. Brian Booth, Site Vice President and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
2420138
2420180
Miscellaneous
Operator Aid #93-
21
Tr. B Vital DC Batteries and Chargers
09/13/2017
Procedures
OS1048.16
Vital Bus 11D Operation
Revision 18
OX1405.07
Safety Injection Quarterly and 18 Month Pump Flow and
Valve Test
Revision 23
OX1426.19
Aligning DG 1B Controls for Auto Start
Revision 7
OX1436.02
Turbine Driven Emergency Feedwater Pump Quarterly and
Monthly Valve Alignment
Revision 35
Work Orders
40776798
40779667
40779680
Drawings
CB-F-2A-A
Control Building-Cable Spreading Rooms and Mechanical
Rooms (Sheet 7 of 12)
04/04/2014
PAB-F-1G-A
PAB Vertical Electrical Chase (Sheet 19 of 20)
04/20/2001
Procedures
Revision 6
Fire Response
Revision 3
OS1200.00
Response to Fire or Fire Alarm Actuation
Revision 28
OS1200.00A
Fire Hazards Analysis for Affected Area/Zone - Appendix A
Revision 26
Corrective Action
Documents
2418585
2420493
Miscellaneous
C-S-1-21805
CW System Seismic Indiced Flooding in TB and Impact on
A ESWGR
Revision 0
Work Orders
40762974
Corrective Action
Documents
2415013
2416319
2421536
Corrective Action
Documents
2421502
Procedures
IS1672.902
Service Water Train B Tower Actuation Logic Test
Revision 1
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Guarded Equipment
Revision 40
Online Aggregate Risk
Revision 7
Risk Management Program
Revision 3
Work Activity Risk Management
Revision 22
Corrective Action
Documents
2199973
2394323
2416196
2418461
2418551
2418795
2418881
2426043
Drawings
1-SI-B20450
Safety Injection System Low Head Injection (Accumulators)
Detail
2/05/2007
Procedures
OX1456.81
Operability Testing of IST Valves
Revision 41
Work Orders
40773154
40779376
40816313
Corrective Action
Documents
00195174
2360336
Engineering
Changes
00144967
DG-1A Relay 25Y1 Replacement
Revision 002
Work Orders
294978
Corrective Action
Documents
2417929
2419087
2423106
2426043
Drawings
1-NHY-310857-
e94-8b
Emerg Diesel Gen 1-B Start Circuit No. 1 Schematic
Diagram
Revision 7
1-NHY-310857-
e94-8c
Emerg Diesel Gen 1-B Start Circuit No. 2 Schematic
Diagram
Revision 10
11871652
Wiring Diagram Power Unit
Revision 14
Procedures
LS0569.16
Diagnostic Testing of Rising Stem MOVs
Revision 29
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
MS0523.48
Sheave Alignment and Belt Tensioning
Revision 3
OS1026.09
Operation of DG 1B
Revision 35
OX1456.01
Charging Pump A & B Quarterly Flow and Valve Stroke Test
and 18 Month Remote Position Indication Verification
Revision 18
Work Orders
40738401
40770880
40802707
40821523
40821594-02
40821594-03
40821594-04
Corrective Action
Documents
2415794
2416677
2416679
2416778
2419424
2420981
Procedures
LS0563.31
UAT Synchronism Check Relay PM
Revision 3
OX1416.18
Portable Tower Makeup Pump Operability 18 Month
Surveillance Test
Revision 0
Work Orders
40764039
40766967
40770424
40770425
71151
Miscellaneous
LIC-21005
Documentation Supporting the Seabrook Station NRC 1st
Quarter 2021 Performance Indicator Submittal
04/27/2021
LIC-21006
Documentation Supporting the Seabrook Station NRC 2nd
Quarter 2021 Performance Indicator Submittal
07/27/2021
LIC-22001
Documentation Supporting the Seabrook Station NRC 4th
Quarter 2021 Performance Indicator Submittal
2/28/2022
LIC-22004
Documentation Supporting the Seabrook Station NRC 3rd
Quarter 2021 Performance Indicator Submittal
2/17/2022
Corrective Action
2340882
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Documents
2390449
2401831
2418515