IR 05000346/1988012

From kanterella
Jump to navigation Jump to search
Insp Rept 50-346/88-12 on 880504-0802.Violations Noted.Major Areas Inspected:Series of Allegations Re Plant Operation, Including QC Manager Pressuring QC Inspector to Sign Maint Work Order to Accept Radiographs Not Meeting ASME Code
ML20245K006
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/21/1988
From: Barton T, Defayette R, Mccormickbarge, Ward K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20245J994 List:
References
50-346-88-12, NUDOCS 8907030246
Download: ML20245K006 (22)


Text

,

-

_ _ - _ _ _ _. _ -

h

...,

..

'

~

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

,

Report No. 50-346/88012(DRP)

. Docket No. 50-346 License No. NPF-3

.

Licensee: Toledo Edison Company Edison Plaza, 300 Madison Avenue j

Toledo, OH 43652

'

Facility Name: Davis-Besse Nuclear Power Station, Unit 1 Inspection At: Davis-Besse Site, Oak Harbor, Ohio Inspection Conducted: May 4, through August 2, 1988

.

0/ ff)

' '

J

)S k,

.

. Inspector:

. W. McCorm c - arg 7/ ll /

Date fA/h/

"

. D. Ward Date T[2/!sI

.B t

Date

. Approved By:

R e, Chi 9 d/

Reactor Projects, Section 3A DHe Inspection Summary Inspection on May 4, through August 2, 1988 (Report No. 50-346/88012(DRP))

Areas Inspected: Special, unannounced safety inspection with regard to a series of allegations related to the operation of the Davis-Besse facility.

Results: One violation with several examples was identified in Paragraph 2 for failure to follow procedures.

I

,

l l

ll$7030246800922 O

DOCK 05000346 PNU i

-. _ _. -. _ _ _ _ _ _ - _. _ - -

- _ _ _ _ _ _. _ -

.-

_ _... - _ _ _ _..._

_.

. - _. _ - - _ _

_ _.

_

__

_ _ _.

___ __ - _ -

q (3

'V SEP 2 21988

',f

Toledo Edison Company

.

We will gladly discuss any questions you have concerning this inspection.

Sincerely, Edward G. Greenman, Director Division of Reactor Projects Enclosure:

Inspection Report

No. 50-346/88012(DRP)

cc w/ enclosure:

L. Storz, Plant Manager

DCD/DCB(RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

Harold W. Kohn, Ohio EPA

James W. Harris, State of Ohio

Robert M. Quillin, Ohio

Department of Health

State of Ohio, Public

Utilities Commission

bccs J. L;cbe. -

, O C

l. CD ~ dLar, a6C.

B. C~bh4M NE'

Em Nsg - 234

Yes

Vb

Q

RIII

RIII

RIII Ye>

RIII

roge

RWh

dd W

/ZK t

/

McCormick-Barger/ jaw

DeFayette

Knop

ei

6G

man

c[lgfff(

]71

')l71

)

nlH

!

e c9,cs

__

_

i

- _

_ _

_

- _ _ _ _

L.'

O

O

I

f-

i

L

i

DETAILS

j

"

-

1.

persons Contacted

-

Toledo Edison Company

  • D. Shelton, Vice President, Nuclear
  • L. Storz, Plant Manager
  • P. Hildebrandt, Engineering General Director
  • R. Schrauder, Nuclear Licensing Manager
  • T. Myers, Nuclear Licensing Director
  • L. Ramsett, Director, Quality Assurance

G. Honma, Compliance Supervisor - Licensing

M. O'Reilly, Corporate Attorney

Other plant personnel were contacted during the inspection.

NRC

  • P. M. Byron, Senior Resident Inspector

h

D. C. Kosloff, Resident Inspector

R. W. DeFayette, Chief, Section 3A

  • J. W. McCormick-Barger, Reactor Inspector, Branch 3, DRP

.

2.

Allegation Reviews

Beginning in early 1988, the NRC received several allegations primarily

concerning activities associated with the Quality Control area.

The NRC

performed a series of inspections which included interviewing Quality

Assurance and Quality Control management personnel and approximately

one half of the Quality Control inspectors at the Davis-Besse site.

Additional allegations were obtained during the inspections. A

description of a portion of these allegations and the results of the

inspections of associated concerns are provided below or in Inspection

Report Number 50-346/88027.

a.

Allegation RIII-88-A-0003 (Closed)

(1) Concern: The Quality Control (QC) manager pressured a

QC inspector to sign a Maintenance Work Order (MWO) for

work on the control room emergency ventilation system,

even though it contained information that was a procedural

violation (non-approved post maintenance test instruction

for a time delay relay).

!

2

_ _ _ _ _ _ _

- _ - _ _ _

_

b

_ _ - - _ _ _ _ _ - - - - _

,

C

p

.

.

  • '

.NRC Review: The inspector contacted the QC inspector alleged to

-

be involved with the MWO. The QC inspector stated that the

control room emergency ventilation. system had been taken

out-of-service to perform periodic maintenance.. During post

maintenance testing, the test instructions provided in the MWO

did not work since plant personnel were unable to obtain

satisfactory test results. After plant personnel tried several

times to perform the test, an individual arrived on location

with an-unapproved vendor test instruction. Plant personnel

used those vendor instructions and with the QC inspector present

obtained satisfactory results. The QC inspector informed the

workers that they would have to incorporate the vendor

instructions into.the MWO, and reperform the test per the

revised MWO.

Plant personnel agreed to do so.

Later, the QC

inspector heard that plant management agreed to incorporate the

vendor test instructions into the MWO, but would not agree to

reperform the test since the QC inspector had previously

witnessed the test prior to it being. incorporated.

When the revised MWO was returned to the QC inspector for his

approval, he refused to sign it.

Later, the QC inspector was

informed that.the Quality Assurance (QA) Director, after

reviewing'the circumstances surrounding the matter, instructed

the QC supervisor to have the inspector sign the MWO based on

his witnessing of the test. prior to it being incorporated into

the MWO package. At this time the QC inspector signed the MWO.

The QC inspector stated that the QC manager was not, to his

knowledge, involved with the approval of the MWO in question.

The NRC inspector reviewed the MWO in question (MWO 3-87-1174-01)

and found that the MWO documented the performance of the

unapproved instructions prior to it being incorporated into the

MWO. This instruction was used to functionally check the timing

sequence of the oil failure safety control switch, PSL-28017,

and associated timer of the control room emergency ventilation

system condensing unit. The MWO had subsequently been revised

to incorporate the vendor instruction and was approved by

appi priate plant personnel and signed by the QC inspector.

Conclusion:

The allegation that the QC manager pressured a QC

inspector to. sign an MWO even though it contained information

that was a procedural violation (non-approved post maintenance

test instruction) was not substantiated. The test instruction

was approved (via review and approval of the revised MWO).

Also, there was no evidence found to link the QC manages to the

incident.

l

l

3

,

_ - _ _.. _ _ _ - _ _ _ _ _ _ - - - - - - - - - -

-

- __ ____--. - _ _ _ -. _ _ _ -.

__-

_._

_. _ _

._ _ _

_ - - _ - _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ - _ _ _ _

'

Q

.qO

.

e

i

However, the performance of the test on February 7,1987,' prior-

to it.being incorporated into the MWO package is a violation of

. Davis-Besse Nue' ear Group Procedure NG-DS-205 " Plant Maintenance,"

'~

dated November 23,'1986.

Section 6.7.4 of that procedure' states

that the Assistant Plant Manager, Maintenance, shall ensure that

only work specified in the maintenance work package is performed.

This is the first of three examples ~of a violation of 10 CFR 50,

. Appendix B,. Criterion V, which states -in part, that activities

affecting quality shall be accomplished in accordance with

documented instructions and procedures (346/88012-01A). The'

i

alleged decision made by the Quality Assurance Director to

.!

have the QC inspector sign the revised MWO is not considered '

safety significant since it was based on the QC inspector's

witnessiig of the acceptable performance of the test. The QC

inspector did state thet he felt pressured to sign the MWO;

however,.he stated that once the issue was raised to the Quality

Assurance Director's level, he saw no need to continue to press

the issue and subsequently signed the MWD.

This concern is

considered closed.

(2) Concern: The Quality Control (QC) manager was pressuring the

Authorized Nuclear Inspector (ANI) to accept radiographs of

welds on piping being fabricated for the Feed and Bleed

Modification to the Makeup System, even though the radiographs

did not meet ASME code requirements.

NRC Review.:

The inspector interviewed the Authorized Nuclear

i

Inspector (ANI) concerning the alleged pressuring of the ANI

by the QC manager.

The ANI indicated that on several occasions

the QC manager had pressured him to accept radiographs which

he had initially questioned. The ANI stated that in no case

had the QC manager succeeded in convincing him to accept a

suspect radiograph without first receiving back-up information,

such as the results of additional radiographs, or receipt and

review of the Toledo Edison's Corporate level III inspector's

interpretation of the original radiogroch.

The ANI also stated

that the QC manager had threatened to r wove him from the site

because of a confrontation between the QC manager and the ANI

over the interface between QC personnel and the ANI.

The ANI

felt this problem was apparently the result of the QC manager's

misunderstanding of the ANI's position, function, or relationship

at the Davis-Besse plant. A telephone call from the QC manager

to the ANI's management reportedly clarified the ANI's

relationship to the QC manager and resolved the issue regarding

'

the ANI

The inspector questioned nearly half of the QC inspection staff

concerning QC manager's pressuring of the ANI.

Several QC

inspectors stated that the QC manager had and does, in their

opinion, harass the ANI.

However, the QC inspectors had never

known of a case where the ANI had given in to the QC manager's

pressure or harassment.

!

- - _ - _ _ _ - _ - - - _

___

_ - -

_ -. _ _ _ _ _ _ _

.

l

..

~ ~a

The QC manager was questioned concerning his alleged pressuring

l

of the ANI to accept unacceptable welds. He stated that several

L

times he had questioned the ANI's rejection of welds but had

'

~

never intended it to be considered as pressuring him to accept

substandard welds. He stated that he had responsibility for

the non-destructive examination (NDE) program'and felt it was

his responsibility to question the need to perform additional

NDE when he. felt it was unnecessary.

He stated that in all

cases, if the ANI continued to feel that additional. radiographs

were necessary, then they were performed without further delay.

Conclusion:

Interviews with the ANI, QC manager, and other QC

staff members indicated that the QC manager has questioned the

ANI concerning the ANI's rejection of welds previously approved

by the licensee's NDE contractor, but no information was provided

that would suggest that the ANI accepted substandard welds as.

a result of the QC manager's questions. Although the~QC manager

questioned the ANI's rejection of some radiographs approved by

the licensee's NDE contractor, the QC manager did not appear to

be pressuring the ANI into accepting welds that did not conform

i

to ASME code requirements; this appeared to be more of a matter

of radiograph interpretation disagreement discussions.

In

addition, all radiographs that were deemed to be unacceptable

by the ANI were reportably re-radiographer, and then reworked

or accepted based on acceptable new radiographs. This concern

is considered closed.

(3) Concern:

Several large completed MW0s were transmitted to QC

at 2:00 p.m. for its final review.

The QC manager instructed

two inspectors to review the packages (about two feet thick)

and not leave until it was done.

It was ' alleged.that this-

amount of work would normally take one inspector two days to

review.

NRC Review: The inspector contacted the QC inspectors alleged to

be involved with the. review of the work packages in question.

The

QC inspectors recalled their review of the MW0s and: stated that they

had already worked a full day when the QC manager told them that

the packages had to be reviewed prior to them leaving the site.

The QC inspectors stated that, as part of their approval, they had

to verify dimensional tolerances associated with design changes

and/or reinstallation of hardware.

The QC inspectors added

that these verifications were performed.

The inspectors stated

,

that they performed the required review. They also said that

the packages had been reviewed to a lesser extent previously

which helped in that the packages had been returned to the

plant staff to correct the earlier identified problems prior

to delivering them to QC for their final review.

Both

'

- _ _ _ _ _ - _ _ _ _ _ _ _.

_

._

-

.

F

s :-

d

a

t

.

,

.

"

QC inspectors felt that a better job could hu e been done, had

-

more time been allotted. An unsuccessful attempt to obtain-and

review the MW0s in question was made by the inspector, because

'

neither the alleger nor QC inspectors involved could recall the

-actual MWO numbers.

'

The inspector interviewed approximately half of the current QC

inspectors and asked if they felt that the work. load is or has

been excessive.

In general, the inspectors felt that the work-

,

load was not excessive but did state that in the past during the.

'l

end of outages work loads tended to increase resulting in long

work days.

The inspector also discussed this matter with the QC manager.

The QC Manager stated that, on occasion, packages are sent to

QC that are. critical path to other plant activities and have

required QC staff to work extra hours ~to accomplish the required

reviews. Management did not believe this was unrealistic, nor

did they expect the inspectors to do less than an adequate job.

Conclusion: The review performed above substantiated that the

time allotted to the QC inspectors to review the work packages

was restricted.

However, the inspectors directly involved with

the task stated that they did review the entire packages

including performing in-containment as-built verifications.

Based on lack of identification of specific deficiencies

associated with review of the packages, and the response

received from other QC inspectors concerning workload, this

concern is not safety significant and is considered closed.

(4) Concern: Two QC lead inspectors were demoted as a result of

expressing differences of opinion with the QC, manager at

meetings.

NRC Review: The inspector interviewed the two.QC inspectors

alleged to have been demoted.

Neither inspector identified a

specific example of them raising safety issues that would have

accounted for their demotions.

Both inspectors indicated that

their differences of opinion related to administrative matters.

Conclusion:

Based on lack of specific examples of the

inspectors' raising safety issues which could have resulted

in employment discrimination under 10 CFR 50.7, this concern

was not reviewed further and considered closed.

(5) Concern: A PCAQR was written on the use of a non-destructive

I

examination (NDE) cleaner with an expired shelf life. The QC

manager refused to sign the PCAQR and directed the PCAQR

initiator to continue to use the cleaner until the QC man?ger

could get the matter resolved.

4

- _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _-__--_

,_7

.--

,

.-.

._

_

__

_

-

.--

~

.

O

O

-

.

w :"

J

NRCReView: The inspector contasted the indiv'idual alleged'to

,

have Tnitiated the PCAQR. The individual. stated that he had

m

initiated a PCAQR.to' address -the expired two year shelf life of

'

.

NDE cleaner but it had not been. issued because the QC manager

had refused to sign it.. The individual stated that the QC

manager told him to continue using.the cleaner and subsequently

,

provided him with copies of two intra-company memoranda and a

letter from the vendor. This information stated that the NDE

cleaner shelf life was based on its ability to maintain its'-

D

aerosol and that as long as the aerosol pressure was sufficient

,

enough to dispense the cleaner in a spray and the. container did

not evidence any leakage of the contents, then the product had

an unlimited shelf. life.

The inspector obtained and reviewed copies of the memoranda'and

vendor letter and found them to agree with the QC inspector's

statements above and technically resolve the shelf life issue

(January 15, 1988 memo from the Engineering Assurance manager to;

the Quality control manager (QAD-88-40032), May 8, 1984 memo-

from a Toledo Edison employee to the QC supervisor, and an

.

April 30,1984 letter from.the NDE supply. vendor to Toledo

Edison). The inspector also contacted the QC manger and'

discussed the PCAQR issue. The QC manager vaguely-recalled.the

NDE cleaner fluid issue but did not recall a PCAQR being

prepared or his refusing to sign it.

l

Conclusion: The inspector was unable to substantiate the

concern that a PCAQR was not processed (as required per

Davis-Besse procedures). However, other examples of PCAQRs

not being appropriately processed by the QC manager were

discussed in Paragraphs 2.e.(2) and 3 of this report and a

potential violation of NRC requirements was identified.

Based

on interviews with the PCAQR initiator, the QC manager, and

a supervisor from QA's Engineering Assurance organization-

no technical concern with Davis-Besse's use of NDE cleaner

was found to exist. This concern is considered closed.

(6) Concern: AnAuditFindingReport(AFR)waswrittenagainst

QC for lack of qualification cards. At the next to last day

of the AFR responding period (120 days) new cards were produced

and the QC manager ordered inspectors to sign them in one day.

Most people just signed them rather than read the required

procedures first, since it would take three to four days to

read all the material.

NRC Review: The inspector interviewed nearly half of the

Davis-Besse QC inspectors and asked them if they were provided

adequate time to complete their qualification cards.

Inspectors

that were present during the period when the AFR was written

,

1

1

__.___m__

_

_ _ _. _

.

-

_

-

_ _ _ _ _

-_

_

. _ -

"

in

+

'

'

O

x

..

-(AFR No. AR-87-INSPT-01-04) concurred that.the QC manager had

instructed them to complete.their qualification cards prior.to

leaving work-that night. Some of the inspectors-refused to do

.;

so and were not reprimanded for their actions. Others

interviewed stated that they stayed at-work very late and

attempted to review each procedure.. These-individuals admitted

that th'ey had not read every word of each reading assignment,.

but stated that many of the assignments covered documents that

they had previously read and/or worked with:and ' felt that they-

were already familiar with-them. New inspectors arriving.onsite

since the audit finding indicated that they have been.provided

ample time to perform required actions as specified on their

qualification cards.

The inspector reviewed the qualification cards of selected QC

inspectors and found them to generally agree.with the above,

in that some were signed off in a one-to two day period and

others were not.

The inspector interviewed the QC manager and questioned him

concerning the qualification card matter. The manager stated

that'he was-told by QA to get the inspectors to complete the

cards prior to the 120 days responding period. He, therefore,

instructed his inspectors to stay as late as necessary to comply -

with the request. He also contacted the QA. department to obtain

relief. He stated that relief was provided in the form of the

grandfathering process for incumbent inspectors as discussed

below.

During review of the audit finding and qualification cards, the

' inspector noted that some qualification cards were not completed

in a timely manner (one file was found to still not be completed

nearly)eight months after the QC certification procedure was

issued. The licensee had pre

January 7,1988 (QAD-88-20007) pared a memorandum dated

, to the QA audit group stating

that incumbent inspectors would comply with QA certification

procedure (QADP 2.2, " Qualification and Certification of

Personnel Performing Quality Control Activities," dated

October 30, 1987) when the incumbents become due for

decertification. Although Paragraph 6.4.7 of QADP 2.2 allows

incumbent inspectors to be waived from completing the

" Performance Demonstration" portion of the QC Generic and

Discipline qualification cards, no such provision was provided

for waiving the reading requirement identified on the applicable

qualification cards.

Failure to comply with QADP 2.2 or revise

it to correspond with the "grandfathering process" proposed-in

the January 7,1988 memorandum described above is another

example of the violation described in Paragraph 2.a.(1)

<

(346/88012-01B).

i

l

8

__ _ _ _ _ _-_____ _

____O

_-

__

_-

._.

- _ _ _

}.

'&

,

.

Conclusion: The allegation was substantiated in that QC

management had requested that the inspectors complete their

qualification cards in a short period of time.

However, from

'

interviews with a large sample of inspectors, some inspectors

stated that they refused to comply with the request and others

maintained that they completed the cards based on either

reviewing the procedures or having been already familiar with

some of the procedures based on their previous experience with

them during performance of work activities.

It does not appear

that inspectors who refused to comply with the request received

disciplinary action. The Qualification cards were an

enhancement to the QC inspectors' training and certification

program, although inappropriately implemented, it was found to

provide assurance that QC inspectors receive uniform plant

indoctrination. Based on the above, this allegation has no

safety significance, other than as identified in the related

violation identified above.

This concern is considered closed.

b.

Allegation RIII-88-A-0010 (Closed)

(1) Concern:

The contract between a contract QC organization

and the Toledo Edison Company was due to expire and renewal

,

was uncertain.

This uncertainty was distracting the QC

i

inspectors and this may have led to unintentional errors.

(

Also QC coverage may be affected if the contract organization

i

leaves the site.

!

NRC Review:

Replacement of one contracting firm with another is

a common practice and some disruption in QC coverage can be

expected. The inspector interviewed most of the contract QC

inspectors associated with the contract in question, and was

!

consistently told that they continued to perform adequate

i

inspections. Management offered permanent employment to many of

the contract inspectors in question. This direct recruitment

.

effort and the extension of the contract resulted in the loss of

I

only a few of the contract inspectors.

In addition, the

transition from one contracting firm to another was particularly

smooth due to management's early recruitment of a new contractor,

q

and the delay of the 1988 outage.

New inspectors were found to

have been provided ample time to perform required training and

I

become familiar with the Davis-Besse plant.

j

i

Conclusion: This concern was not substantiated.

No evidence

of QC inspection degradation was provided or identified.

j

This concern is considered closed.

(2) Concern: A Davis-Besse employee furnished false information on

his resume.

_ __-__..

s

- - _ - - __

._

._

. - - -.

O.

D

..

'

.

.

NRC Review:.The inspector contacted the alleger to get specific

details concerning the resume infora tion that the alleger

believed to be false.

The information concerned the. time frame

"

that the employee spent at a nuclear power plant that was known

to have been cancelled. The concern was based on this public

knowledge and not on specific first. hand information.

The inspector obtained a copy of the employee's resume and.

determined that the resume indicated that the. employee worked

for a contract firm at the time in question and that during an

approximate threeLto four month period when the plant in-

question.was. cancelled, the. employee reportedly worked at the

plant.and at two other. power plant projects performing ~various

activities. The inspector contacted the utility with the-

cancelled plant and was. unable to obtain information about the

employee in question since he was a contractor and the utility

'did not maintain. personnel files on contractor' staff. -The

inspector contacted 'the contract firm and received affirmative.

information concerning the employee's employment with the firm

during the time frame in question. However, the contract firm

would not release any-information concerning the specific

activities performed by the employee.

In addition ~to the'above employment verification, the inspector

verified that certain other more extensive portions of the

resume were correct through discussions with NRC inspectors

. familiar with the individual.during various time frames. This

additional verification provided sufficient information to

conclude that the employee had appropriate experience for the

position held.

Conclusion:

Based on lack of specific first hand knowledge of

false information and the inspection described above, this

concern was not substantiated.

This concern is considered

closed.

(3). Concern:

Some painting applications that have been performed

at Davis-Besse do not conform to Davis-Besse painting / coating

procedures. These discrepancies have been identified in

nonconformance documents and accepted as-is without proper

justification and/or revisions to applicable painting

procedures.

It was alleged that areas of the plant were not

painted adequately or wrong paint was used and some areas were

not painted at all.

The bottom of pipe support base plates were

provided as examples of items that have been installed without

proper coatings (i.e., installed with prime coat only).

NRC Review: This concern was initially transmitted to the

licensee on June 14, 1988 (Attachment No. 1), for its review and

action and a response was received from the licensee dated

!

July 22, 1988 (Attachment No. 2).

l

-

_ - _ _ _ - _ - _ - - - _ - _ _ - _

_ - _ _ - _.

__. _ _ _ -

.__

-

__ _-______-__ _ _ _ - _ _ _ _ _ _ _ _ _ _

_ - - _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _-_

'

.;

o

O-

.

k

The inspector reviewed the licensee's response to the above

concern and obtained a copy of Potential Condition Adverse to

-

Quality Report (PCAQR) No. 88-0078. The PCAQR described in

general the same matters identified in this concern.

The

inspector also reviewed Davis-Besse Maintenance Procedure

MP-1701.48 (DB-MM-09637.06), " Application of Protective

Coatings Outside Containment," Revision 01, Dated August 25,

1987.

The. licensee's acceptance of the primer only painted pipe

support base plates was found to be in accordance with the

provisions of the maintenance procedure.

Section 5.1.6 of that

procedure allows the licensee to use design engineering approved

alternate painting techniques in lieu of-the procedure. The

licensee's_ design engineering group approved, in Request For

Assistance (RFA) 88-0237 initiated as a result of the

identification of the QC inspector's concern, the primer only

painting technique based on its limited application and lack of

exposure to corrosive environments of the surfaces in question.

Primer coat acceptance was further based on the Steel Structures

Painting Council's Painting Manual.

The inspector reviewed this

manual and determined that the licensee's actions were

technically based on the manuals statements concerning the

primers function as an anti-corrosion coating and that the

primer coated surfaces in question were protected from severe

environmental conditions for which a finish coat normally is

used for protection of the. primer coat. The allegation

concerning areas not painted or painted with the wrong paint

did not include specific examples.

From review of the specific

information provided for the allegation concerning the use of

primer coat only, which resulted.in that concern not being

substantiated, and lack of specific examples for the other

concerns, further review of the paint program was not performed.

The licensee's review and disposition of the above PCAQR

(No. 88-0078) was not thorough, in that the licensee should have

concluded that the MWO originator should have originated the

RFA requesting the painting deviation prior to issuing the MWO

and that the supports were installed prior to the RFA being

issued.

Rather than identifying the above procedural

deficiencies, the licensee concluded that the PCAQR should

be invalidated based on the MWO still being open and the

availability of the RFA process to resolve the concern. A

detailed review of the PCAQR processing and disposition program

'

will be performed at a later date. This activity and the above

discrepancy will be tracked as an unresolved item (346/88012-02).

11

i

_ _ _ _ _ _ _ _. _ _

__

__

_

,- ;g

,7

A

~

J:

.

,

Y

' Conclusion:. Based on.the review of the licensee's submittal

concerning this matter and the review of the licensee's

procedures, specification, _ and deficiency ' report (PCAQR), -this

.'

concern was not' substantiated.in that the' licensee's actions'to

accept. primer coat only painting was within.the licensee's

administrative program and based on information obtained_or

justified in industrial standards.

This concern is considered

closed.

'

(4) Concern: An insufficient amount of time was allotted for the

quality control inspectors to read documents' required for

qualification following the issuance of Toledo Edison Intra-

. Company Memorandum QAD-88-20030.

NRC Review: The memorandum in question concerns Quality-

Assurance's response to the auditing group for Audit Finding

AR-87-INSPT-01-04. This is the same. audit finding and concern

discussed in allegation RIII-88-A-0003, Paragraph 2.(a).(b).

Conclusion:

Based on the review discussed in Allegation

RIII-88-A-0003, Paragraph 2.a.(6), this matter was

substantiated and found to not have safety significance.

This concern is considered closed.

(5) Concern: Approximately 12 new contract QC inspectors were

given a certification test the week of February 8,1988; only

one passed. The contractor then gave copies of a test to the

.

inspectors (that failed) for them to study. The in,pectors

were then retested and all passed,

It was not known if all

the tests were the same.

NRC Review: The inspector contacted the only contract employee

who was alleged to have first hand knowledge of the allegation.

This individual could not recall any individual that had

been provided a copy of a test prior to taking'the.

qualification test.

At Davis-Besse, contract QC inspectors can be qualified by

the contractor, rather than the licensee, if the contractor's

organization is on the approved vendors' list and its

certification program has been approved by the Davis-Besse

QA group.

Because failed examinations are not maintained in the files and

the individual alleged to have had first hand information could

not support the allegation, the inspector could not identify

anyone who had failed examinations.. Interviews with about half

the contract QC inspectors revealed that they were required to

. -

-

.

.

.

.

.

-,

s7 7

o;

O

  • E

take a qualification test prior to being referred to the licensee

-

for: employment consideration. All those interviewed stated that

they passed on the first try without reviewing a copy of a test.

"

The QC. inspectors stated that had they failed the test,'they

would not have been' considered for employment nor would they.

have been allowed to retake the test for at least 30 days. The

QC ~ inspectors also stated that' they knew of no-incident.of a

f'

testing irregularity similar to that described above.

The inspector also reviewed a sample of contract QC inspectors

qualification records and found no testing irregularities or

inspectors with weak backgrounds and/or experience.

Conclusion: Based on a lack of specific details and the review

identified above, the inspector was unable to substantiate the

concern. This concern is considered closed.

(6) Concern: Two new contract QC inspectors were certified as

Level 2. inspectors for disciplines.in which they had not.

previously worked. One was inappropriately certified as an

electrical inspector and the other as an instrumentation and

control (I&C) inspector.

NRC Review: As stated in the previous paragraph,'the licensee

had provisions in its procedures and contracts to accept the QC

certifications provided by its contractors. The licensee also

stipulated in its procedures and contracts that the Level.3

Inspectors (QC supervisors)'for the various disciplines had the

final say concerning certifications'and could require additional

testing, training, or other activities prior to accepting the

contractor provided certifications.

Interviews with the QC

supervisors revealed that during their reviews of the contract.

QC inspectors' resumes they identified several individuals with

backgrounds that did not seem appropriate for the inspectors'

certifications provided..The supervisors stated that the

contractor's bases for the inspectors' certifications were the

successful passing of the tests provided and~the inspectors'

prior work experience.

Since the I&C/ electrical test had few

questions concerning the I&C disciplines, passing the test based

,

l'

on a strong electrical background would be possible.

In

i

addition, the contractor accepted construction I&C inspection

experience as acceptable for the I&C certification. The

supervisors stated that operating plant I&C activities are

substantially different than that of construction I&C where

instrument tubing may be the activity witnessed by the I&C

inspector.

The supervisors prepared an I&C test that was designed to test

the new inspector's knowledge of operational I&C activities.

i

1,

,

o__

_ _ _ _ _ _

i

_ _ _ _ _ _

_ ___ __-_ - _ _ _ __

_ _ - _ _ -

@

O-

O

y

,

This-test was administrated to the'. contract I&C certified.

'QC inspectors. 'Most of the inspectors were found to have

significant weaknesses.in the I&C area. As'a result, the

"

supervisors limited these inspectors certifications to the

!

electrical discipline (the discipline where they possessed

I

adequate knowledge'and background). The supervisors also

l

required.that, in the future' the contractor provide.only I&C.

,

inspectors with strong' operational I&C experience. They also

closely reviewed. additional inspector resumes and qualification

submittals, prior to accepting the inspectors:for employment,

to assure well qualified I&C inspectors were being procured.

The inspector reviewed selected contract QC inspector

-

qualification records and found them to be.in accordance

!

with Davis-Besse procedures.. Employee. background information

appeared to be'in agreement with the certifications accepted

,

by the QC supervisors.

The individual' alleged to.have had first hand knowledge of the

concern could not substantiate the issue.

No specific example

of an inappropriately certified electrical QC inspector was

identified by the alleger or NRC inspector during this review.

Conclusion: This allegation was substantiated in that the

QC contractor was providing certified QC inspectors with

inappropriate backgrounds for the QC inspector task required by

the certifications at Davis-Besse. However, the QC supervisors

responsible for approving these certifications identified this

weakness and took appropriate corrective actions as provided

for in both the contractor contract and the QC qualification

procedures. Therefore, the licensee met its ' requirements and

there is no safety significance to this concern. This concern

is considered closed.

"

c.

Allegation No. RIII-88-A-0070 (Open)

Concern: QC procedures are not up-to-date with revised plant

procedures causing QC inspectors to not be in verbatim compliance

with QC procedures since activities required to be verified by QC

procedures may no longer be required by revised plant procedures.

QC procedures have many inconsistencies. QC management has not

been aggressive in correcting this problem.

Numerous specific examples of procedural problems were arovided

for Toledo Edison Quality Control Instruction (QCI) 3144, Revision 9,

dated May 22, 1986, "FCR/MWO Package Maintenance, Inspection and

Turnover," and QCI 3I03, Revision 13, dated May 22, 1986,

" Maintenance." These examples included specifying designated QC

i

personnel to perform activities that are currently being performed by

.

h-

)

1

_ _ _ _ _ - _ _ _

_.

n

O

-

,

U

t

..

s

1

other.than designated personnel (i.e., inspectors versus supervisors),

referencing or specifying the wrong and/or deleted.' procedures, and

requiring non-safety-related work activities that are currently not

being performed.

It was also alleged that other department's procedures (i.e.,

-Maintenance, Operations, etc.) have the same type problems and

are not being adequately corrected.

NRC Review: The inspector informed the licensee of these procedural

concerns and informed them of the specific problems provided.to the

inspector by the allegers.

In response to this concern the licensee

performed an audit of QC procedures and presented its findings to-

NRC Regional Management on August 18, 1988. The audit report included

'[

a review of all Davis-Besse QCI's and revealed numerous similar

-

findings as those described in the allegation.

In response to

Regional concerns about these QC procedural problems and the

possibility of similar problems in other departments (which was also.

alleged), the licensee committed to a number of corrective actions in

a letter dated August 26, 1988, to the NRC' Region III Regional

Administrator (Attachment 3).

In this letter, the licensee committed

to correct the known procedural problems, perform an extensive

interdisciplinary audit of Davis-Besse procedures, review the

procedure change process, and perform a root cause evaluation for

the procedural problems.

The licensee committed to complete these

activities by November 10, 1988.

Followup on the results of the

licensee's findings and corrective actions will be tracked as an

unresolveditem(346/88012-03).

During review of this item, the NRC inspector was informed that

the QC manager had attempted to direct his QC inspectors to violate

Nuclear Mission Procedure, NMP-QA-702, " Potential Condition Adverse

to Quality Reporting". This occurred when the licensee added section

6.1.14 to the PCAQR procedure to allow PCAQRs to be closed based on

the initiation of a 7 prefixed MWO.

Since 7 prefixed MW0s cannot be

voided, they would serve as the tracking mechanism for assuring that

the required work to resolve the PCAQR would be completed.

However,

section 6.8 stated that QC inspectors were to sign the PCAQRs only

after all corrective action work had been completed. When the QC

inspectors refused to sign the PCAQRs due to the procedural conflict

described above, the QC manager wrote an intra-company memorandum

dated August 24,1987 (QAD87-50173), to his staff directing them to

signoff on the PCAQRs if 7 previxed MW0s were initiated. The QC

manager also stated that the procedural conflict was brought to the

attention of Quality Systems (the QA group responsible for QA/QC

procedures) who would in the future be taking the appropriate steps

to revise the procedure to alleviate the conflict and better define

the intent of the procedure.

l

,

R

(

o

O.

..

'

The QC inspectors again refused to sign PCAQRs with 7 prefixed

-

MW0s until the procedure was changed.

Due to this management /

. inspector conflict, a. meeting was called with the QC organization

and the.QA Director. At the conclusion of the meeting, the QA

Director agreed to resolve the procedural conflict prior to

requiring QC inspectors to sign the PCAQRs.

.Since the QC inspectors refused to comply with the QC managers'

memorandum, and the QA Director agreed to change the procedure

prior to requiring QC inspectors to sign the pCAQRs in question,

no violation of NRC requirements was identified. However, the

QC manager's attempt to work through a procedural problem rather

than fix the problem first, may partially account for the

numerous procedural problems identified in the QC area.

Conclusion:.This concern was substantiated.

Numerous additional

examples of QC procedural deficiencies were identified by a

licensee' audit and the licensee has committed to an extensive

program to review procedures from all disciplines. The NRC

followup and enforcement actions associated with this concern

will be tracked per unresolved item 346/88012-03. This concern

is closed.

I

d.

Allegation No. RIII-88-A-0072 (Closed)

(1) Concern: QC inspectors only perform a percentage of weld

inspections for ASME Section III piping welds (50% for ASME

Class II and less than 50% for ASME Class III).

NRC Review: The inspector determined that Davis-Besse QC

inspectors perform 100% inspection on ASME Section III, Class I

welds. This includes fit-up (weld. preparation, pre-weld

cleanliness, alignment,.etc.).

For Class II at.least 50% of the

welds are inspected during fit-up and for Class III at least 10%

of the welds are inspected during fit-up. These percentages are

determined on a work package bases and could result in a greater

percentage of fit-up inspections being performed if, for

example, only one weld is required to be performed in the work

package.

In all cases, 100% of ASME Section III Class I, II

and III welds have at least a final visual weld inspection

performed. The licensee's program as described above was found

to be inaccordance with the requirements of the ASME code.

Conclusion: This allegation was substantiated in that ASME

Section III Class II and III welds may receive less than 100%

fit-up inspections. However, the licensee's program meets the

ASME requirements for weld inspections. Therefore, this concern

'

l

has no safety significance and is considered closed.

-

_ - - _ _

- _ - _.

r

1

l

,~

/l

(,)

g

-

v

..

.

l

(2) Concern: Non-destructive examinations (NDE) are being performed

)

at Davis-Besse by a contractor. The contractor submitted NDE

{

procedures to the licensee for approval. These procedures were

j

~

returned to the contractor with comments but never revised and

a

returned to the licensee for final approval. The contractor is

j

therefore currently working at Davis-Besse with procedures that

i

have not been formally approved by the licensee.

i

NRC Review: The inspector reviewed the procedures used by the

.

NDE contractor and found that they were approved by the licensee

I

with comments. The comments were attached to the front of the

NDE procedures and were minor in nature.

In accordance with the

licensee's contract with the NDE contractor, use of the

procedures with the comments attached is allowed. The contractor

is supposed to eventually incorporate the licensee's comments

and resubmit the procedures to the licensee for its final

l

approval. This had been done prior to the inspector's review.

Conclusion:

This allegation was substantiated in that the

contractor's NDE procedures were being used prior to the

licensee's final approval. However, the contractual agreement

between the licensee and the contractor allowed the contractor

l

to perform work in accordance with the procedures and the

attached licensee's comments.

This was a contractual rather

than a safety matter. This concern is considered closed.

(3) Concern:

Final approval of the weld travelers is performed

by the NDE contractor. This may not be in accordance with the

ASME code. Although the licensee need not have a qualified NDE

expert to approve the NDE performed by the contractor, the

licensee nevertheless should be approving the completed weld

travelers.

NRC Review: The inspector reviewed a sample of the licensee's

completed weld traveler packages and procedures related to weld

travelers.

The inspector also met with licensee representatives

associated with the Davis-Besse weld program to discuss this

concern.

From these reviews and discussion with licensee

representatives, the inspector learned that the NDE required by

the weld travelers is performed and signed off on the traveler

by the NDE contractor.

However, the final review of the weld

traveler is performed by the licensee's QC supervisor and the

licensee's special piping inspector.

The licensee's NDE

contractor's review and app-oval of NDE performed by the

contractor based on its approved NDE program is in accordance

I

with the ASME code requirements.

- - - _

_.

e-

-

0

'-

..

y

~

p

Conclusion: This allegation was not substantiated in that

<

'

although the NDE contractor does sign off the traveler for NDE

'#

performed and reviewed by its organization, it does not perform

the final approval. of the weld, traveler. Although the method

,

currently used by the license to perform and review NDE is

.

acceptable, as a further program enhancement, the licensee

stated that it is attempting to hire a qualified Level'III NDE,

inspector to review the NDE contractor's work. This concern is

considered closed.

e.

Allegation No. RIII-88-A-0073 (Closed)

(1) Concern:

During early to mid-1987, a QA audit of QC activities'

was performed.

During this audit, one of the auditors (a. TED

contractor) was informed of problems in the QC area. After

being informed of these problems, the auditor allegedly informed

a QC inspector that he (the auditor) was told that he would lose

his contract if..he did not provide an audit report of the QC

area with little or no audit findings.

Subsequent to this

conversation, an audit report was issued with only one.or two

minor-QC related discrepancies identified.

Issues raised by the-

individuals were not addressed in the audit report.

NRC Review: The inspector interviewed the individuals alleged

to have provided problems to the auditor concerning the QC area.

Two of the three individuals could not recall any specific

concerns that they may have provided to the auditor but

remempered having general discussions with the auditor

concerning QC activities. The third individual stated that

he expressed concerns to the auditor about the QC manager's

decision to discard the QC office's copies of Facility Change

Request (FCR) packages, which were duplicates that were kept

around just in case a package in the field was lost. The

individual did not inform the auditor and apparently was not

aware that maintaining duplicate FCR packages was a procedural

requirement. The individual did state to the auditor that it

was a good idea to keep the copies around since if the field

package is lost, the associated inspection program must be

,

repeated.

The inspector interviewed the QA auditor in question concerning

the audit report of QC activities (Audit Report

No. AR-87-INSPT-01).

The auditor vs.rified that he was involved

in conducting the QC audit, and was partially involved with

Audit Finding Report (AFR) No. 11, the only finding concerning

the QC department. This finding was not related to the FCR

package issue. The auditor stated that he had received concerns

from QC staff, but in his judgement, they held no significance

or bases for a findin l

_

-__ _ _ _ _

f

o

O

,..

'When specifica11y' asked about'his alleged statement to a QC

L

'

inspector.concerning losing his contract if;he did not issue a

relatively clear audit report, the auditor denied that he made

_

~

that statement. The auditor said he may have stated that if he

reported findings that were not based on plant requirements, he

might lose his contract..The auditor stated that his management

expected only findings that were solidly based and would hold up'

under plant management's scrutiny.

Subsequent to the above interviews, the inspector determined

'

that procedure QCI 3144, "FCR/MWO Package Maintenance,

Inspection and Turnover," Revision 9, dated May 22, 1986, did

require that QC maintain duplicate FCR packages. The inspector

recontracted the QC auditor and asked him if he was aware of this

procedural requirement.

The auditor stated he.was not and would

~have processed an AFR if he had known of the procedural

requirement. The above issue concerning lack of procedural

comp 1.iance is addressed in Paragraph 2.c. of this report.

A review of the audit report and associated audit report

checklist indicated that although QCI 3144 was part of the scope -

of the audit, inspection-of the. duplicate FCR packages was not a

checklist item.

Conclusion:

The inspector was unable to substantiate that.the

QC auditor was told that he would lose his contract if he did

not provide an audit report of the QC area with little or no

l

audit findings. Since the only' concern specifically identified

by the individuals to the QA auditor was not a regulatory

requirement and not identified to the auditor as a procedural

requirement, it seemed reasonable for the auditor to assume that

it was a concern that lacked a technical bases for an AFR.

Based on the above, this concern is closed.

(2) Concern No. 2: A QC inspector was informed by a plant worker

that a steamline (not in use) located internal.to the High

Pressure Condenser (HPE-7-1) had broken welds and cracks. The

QC inspector inspected the area, took pictures of the damaged

pipe, wrote a surveillance report on the discrepancy, and

notified the shift supervisor and his QC supervisor

(subsequently the QC manager) of the problem.

The QC supervisor

instructed the alleger to write a Potential Condition Adverse to

Quality Report (PCAQR) identifying the discrepancy.

The QC

inspector prepared the PCAQR and attended a meeting with

engineering and plant management to discuss the PCAQR in

question.

During the meeting, the QC inspector was chastised

for writing the PCAQR possibly because it would delay the plant

start-up (mode change).

i

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

_

___

._.

_

_

. _ _

_ _ _ _ _ _ _ _ - _ _ _ _

_ _ __ -______ _ ___ _

__

[:' ;,;

o

O

4.

!

As a result of the meeting, the-QC supervisor wrote "Not Issued"

across the PCAQR.and told the QC inspector to " tuck this away in

'

.'.

your files." The steamline broken welds and cracks were

subsequently identified by engineering in a non-PCAQR document

(either an MWO or FCR) along with an engineering justification

for not repairing the steamline until the next outage.

NRC Review: During. the NRC inspector's initial visit to

Davis-Besse, the inspector asked the QC manager, who was the

QC supervisor identified above during the timeframe of the.

steamline weld break / crack incident, if he had ever not

processed a PCAQR that had been generated by his inspectors.

At that time, the manager stated that he had never, to his

recollection, not processed a PCAQR report initiated by his

' inspectors. During a subsequent interview, the QC manager

stated that he did stop the issuance of the PCAQR in question

based on the mutual agreement.of engineering, plant management,

and himself that a PCAQR was not needed.

The inspector contacted the QC inspector involved with the

matter and obtained the voided PCAQR in question, a copy of

an intra-company memorandum (File: T2.1 SUS 043-03, NES:

87-30065), dated May 14, 1987, from system engineering to the QC

supervisor documenting engineering's actions associated with the

broken welds / cracks of the used piping in the High Pressure

,

condenser, and a copy of the Work Request (WR) that tracked the

piping discrepancy and its scheduled 1988 refueling outage

repair activity.

The i_nspector reviewed the above described documents and found

them to generally agree with the described concern in that the

PCAQR was marked "Not Issued," and a note was attached informing

the QC inspector to " tuck this away in your files" and signed

with the QC supervisor's initials.

The inspector determined that the handling of the PCAQR was not

in accordance with the administrative procedure for processing

PCAQRs. Nuclear Mission Procedure NMP-QA-702, " Potential

Condition Adverse to Quality Reporting," dated May 25, 1986,

Section 6.2.3, " Processing," states in part that, "Following

supervisory review, all PCAQ reports shall be hand carried to

the shift supervisor for numbering, logging, and completion of

those sections of Part 1 that apply, but were not addressed,

and determination of their deportability." By not processing

the PCAQR, the QC supervisor violated the above stated procedure

requirement. This is the third example of a procedural

violation and the first of two examples of a violation of the

PCAQR processing requirements (50-346/88012-01C, Example 1).

i

_ _ - _ - - _

-

_

_ _ - _

-

_ _ _ _

-__

-_

_ _ _ _ _ _ - _

_

--

_

_

.

-_

- _ _

.

fa !

Conclusion: This concern was substantiated. As described

above.a violation of NRC requirements was. identified for not

h

.

processing the PCAQR in accordance with procedures. The

'

licensee's corrective actions will be reviewed under the

violation's. tracking number. - The' inspector did.not identity a

y

safety concern with engineering',s decision to delay repairing

the unused piping until-_the 1988 refueling outage. This concern

is considered closed.

3.

Followup on Prr.ypusly Identified Item (Closed) Unresolved Item

'

(346/88027-03)

Improper. handling of a.PCAQR concerning Ray Chem rework activities.

The second example of.the Quality Control department's mishandling

of a PCAQR that was initiated by a QC inspector was. brought to the

'NRC's attention?as part of allegation RIII-88-A-0067 and documented

,

.in inspection Report 50-346/88027. This example concerned a PCAQR

. written on July 10, 1986, to-document a QC inspector's concern.about

deficiencies with Raychem splice documentation identified'in'

maintenance Work Order 1-86-0991-04. This PCAQR was' reviewed by QC

management and inappropriately invalidated in that the invalidated

PCAQR was not'sent to the shift supervisor for his review and

subsequently forwarded to the PCAQR Review Board. This is the

second of two examples of a violation (50-346/88012-01C

Example 2)-.

4.

. Unresolved Items

Unresolved items are matt a s about which more information is required

in order to ascertain whether they are acceptable items, violations, or

deviations. Two unresolved items disclosed during this inspection were

discussed in Paragraphs 2.b and 2.c.

5.

Exit Interview

The inspector met with licensee representatives (denoted in Paragraph 1)

at the conclusion of the inspection on September 1,1988, and summarized

the scope and findings of the inspection. The inspector also discussed

the likely informational content of the' inspection report. The licensee

acknowledged the information and did not identify any of the information

disclosed during the inspection as proprietary.

Attachments

1.

Letter f rom Region III to Toledo Edison dated June 14, 1988.

2.

Letter from Toledo Edison to Region III dated July 22, 1988.

3.

Letter from Tolede Edison to Region III dated August 26, 1988.

l

= _

_ _ _ - _ _ _ _.

_ - _ _ _ _ _ _ _ _ _

_ - - -

___

(

f'T

g m Ahtachment No. I to

..

,

,,

j

e.

'

q)

()Dur/xtion Report 346/88012

l

s

..

,

.)

y

!

'

-

.

Docket No. 50-346

.1JUN 1419BB

. Toledo Edison Company

ATTN: Mr. Donald Shelton-

Vice President Nuclear

Edison Plaza

-300 Madison Avenue

Toledo, OH 43652

Gentlemen:

The NRC recently received several allegations concerning activities at the

Davis-Besse Nuclear Power Plant.

for your review and followup.

Details of these allegations are provided

-

The NRC requests that results of your reviews and dispositions of these

matters be. submitted to Region III within 30 days of the date of this letter.

The enclosure to this letter is considered exempt from disclosure according to

section 2.790 of the NRC's " Rules of Practice", Part 2, Title 10,, Code of

Federal Regulations, and will not be placed in the NRC Public Document-Room.

Therefore, the results of your review and the dispositions of these matters

should' provide an equivalent degree of protection.

-Your cooperation with us is appreciated. We will gladly discuss any questions

you have concerning this information.

Sincerely,

~~hi4${an:3EyI*.0.Ortc5?#~

sk{ardi.Gr~eenman, Director

E

Division of Reactor Projects

Enclosure:

As Stated

l

cc w/o enclosure:

L. Storz, Plant Manager

DCD/DCB (RIDS)

Licensing Fee Management Branch

' Resident Inspector, RIII

Harold W. Kohn, Ohio EPA

James W. Harris, State of Ohio

Robert M. Quillin, Ohio

Department of Health

State of Ohio, Public

i

Utilities Commission

i

En0=E conTA= 10 crx z.avu) uinri sTERIAc 8/h'd

i

-

910sf

oom

>.#,.o

9(jfs, *

v vn 4 wiL LY

e

l

l

_ _ _ _ _ _ _ _ _ _ _ - _

_

( ~.

.'

[

.

.

Enclosure

Specific Details of Allegations

.

Allegation Number RIII-88-A-0010

'

It has been alleged that some work that is being performed in the plant does

not conform to Davis-Besse painting / coating procedures, and that these

discrepancies have been identified in non-conformance documents and accepted

I

as-is without proper justification and/or revisions to applicable painting

procedures.

It is alleged that areas of the plant were not painted adequately

or wrong paint was used and some areas were not painted at all. The bottom of

pipe support base plates were provided as examples of items that have been

installed without proper coatings (i.e., installed with prime coat only).

The NRC requests that you review previous and current painting practices

against your approved procedures and determine if there exists a disagreement

between the two.

In addition, a walk down of modification activities

conducted since the beginning of the June 9, 1986 outage, should be conducted

to detennine if appropriate painting applications have been performed.

If

accessible or inaccessible areas have not been properly painted per

Davis-Besse required procedures, provide your planned corrective actions or

justification for accepting the as-found conditions of the unpainted surfaces.

Allegation Number RIII-88-A-0012

It has been alleged that General Electrical and Mechanical (GEM) employees

use metal tools (e.g. hacksaws) to trim excessive fire barrier sealing

material,

In one case it was alleged that insulation on an electrical cable

was accidentally cut, causing an electrical short (Note: This may have been

the cause of the October 23, 1987 partial loss of EHC control power).

The

matter was reviewed by the Operations Department to determine the cause of

the electrical short, but the GEM employee did not mention the use of the

hacksaw.

It was also alleged that procedures did not allow the use of metal

tools, only plastic or fiberglass; however, GEM employees have used and still

use metal tools because the allowed tools do not work.

The NRC requests that you review plant fire barrier sealant trimming practices

to determine if the above activities are occurring, and if so, take appropriate

corrective actions.

!

y g-"-

9m p

" [p 1 y

"-

-

~

It

_ il f

~

,Li

.:d J_. U. l-

W

'

Sh/d

..

-,.

_ _ _ _ _ _ _ _ _

Xctachment No. 2 to

'

pection Report 346/88012

q

, * *

l

,

i

'

TOLEDO

EDISON

J

.

t. Canterer eneroy Comoanv

DONAu) C. SHELTON

e,.cenc-w.e

S' 2*S-23 3

Docket No. 50-346

License No. NPF-0

Serial No. 1-815

July 22, 1988

United States Nuclear Regulatory Commission

Document Control Desk

Vashington, D. C.

20555

Subject:

Response to Allegations Concerning Activities at the Davis-Besse

Nuclear Power Plant

Gentlemen:

Toledo Edison (TED) received your letter dated June 14, 1988 (Log 1-1833)

which contained allegations concerning:

1) adherence to painting / coatings

procedures (Allegation No. RIII-88-A-0010); and 2) the use of knives and

,

'

hacksaw blades in the installation of electrical conduit sealant (Allegation

No. RIII-88-A-0012).. 9 requested, TED has performed a review of the concerns

'.

and provides the follcving information.

Based on our discussion with

Mr. R. DeFayette on July 14, 1988 the response to these allegations was

extended to July 22, 1988.

Allegation No. RIII-88-A-0010

Toledo Edison has reviewed the concerns raised regarding paint / coating

I

practices at Davis-Besse. The review indicated that the alleger's concerns

l

Vere documented via Potential Conditions Adverse to Quality (PCA0) Reports and

l

Requests for Assistance (RFA) process. The concerns range from installation

l

of pipe supports with a coating of primer alone to an Appendix R fire door

being painted the wrong color.

The specific concern of pipe support base plates being installed without

proper coatings was reviewed with the following conclusion:

I

The coating procedure directs plant personnel to initiate an RFA

requesting additional information and clarification of the

instructions given when a specific situation is not addressed in the

procedure. Therefore, RFAs were initiated by Toledo Edison's Quality

Control and Facility Modification Departments requesting clarifi-

cation of the coating specification and procedure.

JUL 2 919884

> ~,, J

.z,p.

cr o 4 o4

<

-i

.c.

~r u e v n a,. ;

!

THE TOLEOO EDISON COMPANY

EOISON PLAZA

200 MAOISON AVENUE

TOLEDO. OHIO 43652

. _ _. _ _ _ _ _ _ _.

.

I

g.

-

-_

)

t[

.,%

p

~

r

!

i

.

U

v

Dockat No. 50-346

!

License No. NPF-3

l

',

Serial No. 1-815

i

Page 2

j

I

One RFA requested clarification of whether paint / coating was required

j

a

for installation of steel (pipe supports and base plates) when the

surfaces would not be exposed or accessible.

The other RFA requested

a clarification pertaining to acceptability of primer coat alone for

inaccessible areas. A coating system is generically composed of a

y

primer coat and a top coat. These two RFAs were evaluated and

'

responded to in approximately the same time frame.

Design Engineering reviewed these RFAs addressing the concerns of

what surfaces require what type of protective coating. The

i

evaluation concluded that base plates outside containment having only

a primer coat on the inaccessible areas as a protective coating are

acceptable. This is based on the Steel Structures Painting Council

(SSPC), Steel Structures Painting Hanual (SSPM) which is the accepted

standard in protective anti-corrosion coatings. Chapter 1.2 of the

SSPM states that the primer is the critical element in most coating

systems.

The primer is the most important for preserving the

metallic state of the substrate (surface metal).

It also states that

the finish coat provides color and protects the primer from the

environment so the primer can perform its function (inhibit

corrosion) without being degraded. The RFA response concluded the

primer coat provides sufficient protection against corrosion due to

the limited exposure to the corrosive environments these surfaces

i

vill be subject to.

There have been other concerns, as noted in the allegation letter, of doors

and structural steel being installed in the plant without the proper coating

system being applied. These concerns have been documented via our PCAQ

system, addressed, and reviewed by both the PCAO Review Board and by Toledo

Edison Quality Assurance and no further actions were considered necessary.

Toledo Edison believes that the guidance given pertaining to coatings of

structural steel is in conformance with the intent of the Steel Structures

Painting Council guidance and does not believe there exist discrepancies

between current practices and approved procedures. Therefore, TED believes

that the PCAQs and RFAs were generated in accordance with approved procedural

requirements and have been dispositioned appropriately and therefore no

further action is warranted.

Allegation No. RIII-88-A-0012

As stated in this allegation the use of metal tools has been an approved

method for trimming excess sealing material from around conduits. The use of

hacksaw blades and knives is permitted by Maintenance Procedure (MP) 1405.03,

" Installation of Silicone Foam / Caulk Penetration Sealing Systems", for the

purpose of trimming excess sealant material.

The events surrounding the

specific allegation concerning the October 23, 1987 partial loss of

Electro-Hydraulic Control (EHC) control power for the main turbine generator

were incorrectly reported by the alleger. The partial loss of EHC control

power was determined to be caused by the damaged cable insulation. This

occurred when the craft personnel vere attempting to push the cable back into

a conduit fitting while performing vork on the penetration. The cause of the

cable damage was attributed to the conduit fitting having sharp edges.

A

__-_

. _ _

__

l-

o

io

,

-Dockat No. 50-346

License No. NPF-3

Serial.No. 1-815

.

-Page 3

. review of the October 23, 1987 partial loss of EHC control power was

'

documented in Potential Condition Adverse to Quality (PCAQ) Report No.87-589.

.As part of the corrective actions for PCAQR 87-589 several additional

requirements were generated for sealing conduits. These include checking

fittings for sharp edges and pulling rather than pushing cables back into the

~

conduit when required. In addition to the root cause corrective actions,

several other-program enhancements were identified during the review of this

PCAOR.

One of the enhancements made was prohibiting the use of knives and

'

hacksaw blades-in trimming excess sealant from conduits. The root cause

corrective' actions and the additional enhancements have.been added to

procedure MP 1405.03. The use of knives and hacksav blades continues to be

permitted for trimming sealant in areas other than conduit. Therefore, TED

believes that there are no further actions required concerning this

allegation.

Very trul yours,

fh%bd

v

JCS/ sag

cc:- DB-1 Resident Inspector

A;<B;9 Davis;1 Regional-Administrator?'

~

~

A. V. DeAgazio, NRR DB-1 Project Manager

)~

.

l

l

___ - -_____-_________ _ ___- _

_ - _ _ _ _ _ _ _ _ -

4',

tachment No. 3 to

'

'

p)

ion Report 346/88012

j

s

b

,

-

'

TOLEDO

j

EDISDN-

{

,

A Cameror Energy Cermany

DONALD C, SH LT t

"

Vee Pescem-rwer r

/*

,

Id19} P49 P300 -

Docket No. 50-346f

'

.

License No. NPF-3

/

Serial No. 1-829

(

August 26, 1988

.

Mr. A. B. Davis, Regional Administrator

Region III

799 Roosevelt. Road

Glen Ellyn, IL 60137

Subject: Toledo Edison's Action Plan on Procedures

,

Dear Mr. Davis

On August 18, 1988, a meeting was held at the NRC Region III office between

Toledo Edison (TE) and members of your staff.

The purpose of the meeting was

to discuss the ongoing NRC Region III inspection in the Davis-Besse Quality

Assurance / Quality Control areas.

Subsequent to the meeting,

Mr. Robert V. DeFayette of your staff discussed the following NRC concerns by

telephone with Toledo Edison, representatives on August 23, 1988:

1)

Quality Control Instructions (0CIs) are not.being adequately

controlled;

,

2)

OC inspectors are not promptly initiating the process to resolve

identified procedural deficiencies;

'

3)

Procedural compliance has not' been thoroughly assessed for the entire

Nuclear Group;

i

4)

Adherence to the procedure change process has not been evaluated for

the entire Nuclear Group;

5)

The root cause of the procedural compliance concern has not been

. evaluated.

As discussed with your staff, TE vill take the following actfons.

1.

The remaining Quality Control Instructions (OCIs) vill be superseded by

Quality Asst.rance Division Procedures (OADPs).

Concurrently with

superseding the OCIs, all OADPs vill be reviewed and identified

THE TOLEDO EDISON COMPANY

EDISON PLAZA

300 MAOISON AVENUE

TOLEDO. OHIO 43652

O t' e 4, h ( v,%

O J w p ; h &p

Q)[g *

. _ _ _ _ _ - _ _ _ _ _ _ _

_

_

__

L

l

!

)-

l Dock 2t.'No.50-346O

O

1'

-

'

.

.i

Liccnsa No. NPF-3

Serial No. 1-829

R

'Page 2

)

deficiencies vill be corrected.

0ADPs that are revised or which

supersede OCIs vill be approved by September 1, 1988 and become effective

'

,

by September'8, 1988, following required training,

j

.2.

In conjunction'vith the change from QCIs to 0ADPs and the revision of

'

identified QADP deficiencies, the OA Division vill conduct retraining on

the PCR process. This retraining vill re-emphasize the need to promptly

initiate actions to correct identified procedural deficiencies.

Retraining vill be completed by September 16, 1988.

Additionally, if the

results of the audit indicate other divisions are having similar

problems, retraining vill be conducted for those divisions as well.

3.

Toledo Edison vill conduct an interdisciplinary audit to assess

procedural compliance and the overall administration of. toe procedure

program. The audit vill analyze a representative sample oi procedures to

determine if the procedures are functionally adequate (capable of being

^

followed), and whether identified procedural deficiencies have had

,

corrective actions initiated

(i.e., via Procedure Change Requests or

Potential Condition Adverse to Quality Reports).

If it is determined

that a corrective action has not been initiated, the necessary

corrective action vill be taken and the cause of the failure to take this

action vill be determined.

A minimum sample of 125 procedures (4% of the population) vill be

selected for the audit.

Procedures vill be selected from each Nuclear

,

Group Division. The sample vill include recently revised procedures,

older working level procedures and administrative procedures.

The audit

vill be conducted by a team of individuals knowledgeable in the procedure

program and audit practices.

This audit is scheduled to begin on September 6, 1988 and vill be

completed by October 14, 1988.

An audit report vill be issued by

October 28, 1983.

4.

The current procedure change process at Davis-Besse requires individuals

from all departments, including OA, to stop work and notify their

supervisor whenever a technical deficiency is discovered in a procedure

that they are following.

Procedures found to contain such deficiencies

are required to be corrected prior to continuing work.

The individual discovering a deficiency is required to submit a Procedure

Change Request (PCR) form.

Processing time for accepted PCRs is a

function of the number of change requests currently in the system.

However, each department and division has the ability to expedite the

change process for any procedure deemed to require immediate attention.

Procedure changes and revisions can, and have been, processed in as

little as one day.

If the audit results indicate that the time required to change or revise

a procedure, using the current procedure change nrocess. is a contributor

to procedural noncompliance, TE vill revise the change process such that

the processing time is reduced.

_ - _ _ _ _ _ _ - _ _ _. _

-

r--

]

\\

e,,

,e

...

'~)

( )5

]

,..

g

Docket No. 50-346 ;

~

Licensa'No. NPF-3

,

...

Serial No. 1-829

j

Page 3

]

.

'

.

5.

A root cause evaluation vill be conducted to determine the reason for the

Increase in procedural noncompliance, which has been identified by TE's

'

Trend Report.

Much of the information necessary to. perform this

evaluation vill be obtained during the audit process described above.

i

Evaluation of this information vill begin upon completion of the audit

(October 14, 1988) and will ba completed by November 10, 1988.

Your

staff vill then be notified of the results.

Please contact Mr. R. V.

Schrauder, Nuclear Licensing Manager, at

(419) 249-2366 if there are any questions.

Sincerely

yours,

)(

kb

Ab #s,,

l

p

GH/CFH/ tit

ces'DB-1 Resident Inspector

A. V. DeAgazio. Proj ect Manager

Document Control Desk

.

i

.

t

mm._

_ _ _. _ _ _ _.. _ _ _ _ _ _. _

-

.

_

- -

- _ _- ___

,

'

Q

-

.

,

i sacFOR m

-

u.S. NUCLEAR REGULATOJY COMMISSION

PRINCIPAL INSPECTOR (N;me. Est. kSt. Sna mee md,s/)

"'

INSPECTOR'S REPORT

^* -

  1. b

,,

REVIEWER

J

),

e-

Office of Inspection and Enforcement

g.

flP pO-U P / / O

n

i

" ** k 1)

klo d _

T.C.. % %J

-* T n n, n

u)

m'dw M h, ver e F

T

'

LICENSEE / VENDOR

DOCKET NO 18 dioetsiOR LICENSE

TYPE

NO.18Y PRODUCTil13 detal

NO.

S E O.

MO.

YR.

'

fn)n

f$OA

[rw /Ls n

h f O O O O } N N

$S

S

/

M - MOOlFY

'k,j h _ h y p

_

l'

D - DELETE

C

R - REPLACE

D

I,f*!(Of }J ? h

2T "' # 1

-

'

i

'

1' -

PERCD OF INVESilGATION / INSPECTION

INSPECTION PERFORMED BY

ORGANIZATION CODE OF REGON/MO CONDUCT.

FROM

TO

M

1 - REGIONAL OFFICE STAFF

IOTHER

mp-WeeWyMarpowneReonetmg?* Mrcode)

"'

'b

y

MO.

DAY

YR,

MO.

DAY

YR.

2 - RESIDENT INSPECTOR

__ RE GION

DIVISION

BRANCH

C

O zJ

Dl2 9l7

3 + PERFORMANCE APPRAISALTEAM

}

ag V

7. j 'g, M y's.c

  • gt

" E y;.Q e

%Q l"R34Vpu_ Qg y

g3

,}

.. gg

y

s

a

a

,,

REGIONAL ACTION

TYPE OF ACTIVITY CONDUCTED icheck one bom onlyt

(Check one bon oni l.

Y

02 - SAFETY

06 - MGMT. VISIT

10 - PLANT SEC.

14 - INOUIRY

1 - NRC FORM 501

03 - INCIDENT

' 07 - SPECIAL

11 - INVENT.VER,

15 - INVESTIGATION

2 - REGIONAL OFFICE LETTER

04 - ENFORCEMENT

08 - VENDOR

12 - SHIPMENT / EXPORT

MCMT. AUDIT

09 MAT ACCT.

13_ iMs+0n T

M cr, p 3

g.,

7 3 ;

-

o

.je;

ij,

r

v

s

7 ", r t.pj* ;

37 3

IN5 PECIlON slN VESTaGATION F ADAG5

(Check one how onivl

ygyAL NUMBER

ENFORCEMENT CONFERENCE

REPORT CONT AIN 2390

LETTER OR REPORT TR ANSMITTAL DATE

OF VIOLATONS AND

HELD

INFORMATION

A

B

C

D

DEVIATONS

NRC FORM 591

REPORT SENT

I

1 - CLEAR

OR REG

TOHO FOR

LETTER IS SUED

ACTION

Y

2 - VOLATON

3 - DEVIATION

A

B

C

D

A

B-C

D

A

B

C

D

MO.

DAY

YR.

MO.

DAY

YR.

4 - VIOLATION & MVIATON

gl

,

,

,

1 - YES

1 - YES

l

l

l

l

l

l

9 j Tfd, QA?fj-y Q ;i t.g

c.4041 g y lj

' g - a % ',.- a r

T

<>~

r 43

p

44, 4:

50

a,

,

MODULE INFORM ATION

MOOut F INFORM ATION

N

MODULE NUMBER INSP.

6g W

MODULE REO. FOLLOWUP

[E,,$

MODULE NUMBER INSP.

yg W

VODULE REO FOLLOWUP

E

b

$k8

b

E

hrs $

k 8

E

E

  1. $

c 'tr83 55e=

  1. 5

5

  1. @

t 55e

g

  1. !

>

.

s-ng$

E $ 5

h

,

h%

5I

Nt I

E

l E !% hl

Y$

.

a!% 5I

$8

k_ n$ $ $

h S 5 E$$$

$I

$

$$

E

It'

s

e8R:

I a5

EE

$: s

I

m

I 2 5

E,

es

E!

ea

s gs

r8E

csu

E!

! 5: 3iobio.3l6 *

I

noi3

liila

i i

i

i

i liil^

liiI

.

i i

i i

i

l

l

lie I

"

i

i i

i i

i

i i

e i

i

l9

l

,

,,

,,

, lg

l

C

C

,,

,,

,

,

lI l

!

lf

l

U

i l

1 i

t t

t t

i

I

e

g 5 1/iloi i4l

a

liQo

,,

,

l

liile

liil

i

i

i

i i

i liii

^

lt

l

"

I t

e i

i

i t

i i

1 i

t

l

l i

I I

I

I

I

I I

I I

l

l

l

ll

l

U

t 1

e r

i

t i

e a

f

lB

l1

!

l

i

l i

t i

i 1

I

i f

i

i

i i

f f

f i

f

l

g g

, g

g l[, l

e

I f

a l

i

1 1

lt

!

C

1 i

e i

I

I t

1 I

I I

I

i

!t

l

U

t t

t I

I

I I

l 1

i i

!

_

liil*

le

l,il^

i n

1 i

,

i

i

i

ii

i,

i liil

-

i

i

lI

ll

l

i

ii

t I

i

l

1 1

1 t

t

t 1

I t

f

f I

I f

i t

i

1 1

9 CIRCtf SEQUENCE IF

l

!

D

D

'

I

VIOLATION OR DEVIATION

j j

i )

i l l l l

l l

l l

l l l l l

_

_

>

-

,

,

o

.

.

!

()

V

'

-

-

  • **RC ponWES A

DOCKET NO (8 e

I.EPORT

MODULE NUMBE A

'

si OR U.CE.NSE

i

ig

NO cev PaOD

iniso on >

,

,o.

,,0.

,,, ;,,

INSPECTOR'S REPORT

o 7

) o o 3 4

C.

B 2 o p

(D *"*" S"' "'" oa " To",dSto

o

,

(Continuation)

e

,

,

,

,

,

,

,c

j

Office of Inspection and Enforcement

)(

R

C

8o

VOLATON OR DEVIATCN fnter up 10 N00 Characters I6r each item. If Me teel OECeeds tha, number, it will be necessery to paraphrase. Limit lines 10 50 characters each. )

1.

10 CFR 50, Appendix B, Criterion V, " Instructions, Frocedures, and

i

Drawings," requires in part that activities affecting quality be

,

accomplished in accordance with appropriate procedures. This requirement

is implemented by the Toledo Edison Company Nuclear Quality Assurance

Manual, Section 5, Paragraph 5.4.1.1 which states in part that activities

,

that affect quality shall be accomplished in accordance with procedures.

6.

1.

Nuclear Group Procedure NG-DS-205, " Plant Maintenance," dated

,~

November 25, 1986, Paragraph 6.7.4, " Scope of Work," states, in

part, that the Assistant Plant Manager, Maintenance, shall ensure

that only work specified in the Maintenance Work Package is to be

i

g

[

performed.

10.

'

Contrary to the above, on February 7, 1987, the Assistant Plant Manager

u.

failed to ensure that only work specified in the Maintenance Work Package

was performed in that after plant staff unsuccessfully attempted to

perform a functional check of the timing sequence of the oil failure

"

u

safety control switch, PSL-2807, and associated ti,ner for the control

"-

room emergency ventilation system condensing unit per Maintenance Work

i

n

Order 3-87-1174-01, they obtained an uncontrolled manufacture's

instruction for, testing the time delay and conducted this test prior

"

to incorporating it into the work package.

17.

2.

Quality Assurance Division Procedure (QADP) No. 2.2 (QA-QC-07002.02),

"

" Qualification and Certification of Personnel Performing Quality Control

f

Activities," Revision 1, dated October 16, 1987, Paragraph 6.4.3,

a

requires, in part, that individuals who meet the education and experience

requirements for a specific level and discipline, and who have been

previously certified in that discipline shall be qualified based on, among

a

other things, completion of Generic and Discipline qualification cards.

,

i

Contrary to the above, on July 14, 1988, the inspector determined that

n

several Davis-Besse certified QC inspectors had not completed the

qualification cards, identified above, or had not completed them in a

timely manner.

a

"

3.

Toledo Edison Company procedure, NMP-QA-702 R1, dated May 25, 1986,

" Potential Condition Adverse to Quality Reporting," Section 6.2.3,

n

" Processing," states in part that, "Following supervisory review, all

"

PCAQ reports shall be hand carried to the shift supervisor for numbering,

logging, completion of those sections of part 1 that apply, but were not

a

addressed, and determination of their deportability."

,

,

l

D

.

1

2

j

c

- _ - _ _

'

.

.

-

.

.

RTPOv1T

MODULE NUMBER

.

,

M'[Mc'mascgORMMA

DOCKET NO.(8bcTn13ognsi

ns)OR UCENSE

No. ienRo

yo.

,,g.

,,

, l

gg,

,

A

viol ATON SEVERITV OR DEv TON

I

o-

INSPECTOR'S REPORT

C'

. (Continuation)

3

.

.

.

4c

'

Office of Inspection and Enforcement

p

_eo_

c

-, - R -, -..

-,.... -,,... -

~,..

-...., -.. ~.. _

..,

1.

2.

Section 6.3.3, " Technical Support Department Review," states in part

'-

that, "following deportability determination, the PCAQ report shall be

j

- 4.

forwarded to the Plant Technical Support Department for review and

submittal to the PCAQ Review Board."

j

e.

a.

Contrary to the above, on May 14, 1987, a Potential Condition

j

Adverse to Quality Report (PCAQR) was written by a Quality Control

l

inspector concerning the HP E-7-1 Condenser internal steamline

j

s.

'

weld and pipe cracks. The PCAQR was reviewed by his supervisor,

but not delivered to the shift supervisor or to the PCAQR Review

,

Board for review and processing.

b.

Contrary to the above, on July 10, 1986, a PCAQR was written

k

11.

by a QC inspector concerning deficiencies with Raychem splice

'

'2-

documentation identified in MWO 1-86-0991-04. The PCAQR was

u

reviewed by the QC supervisor, but not delivered to the

shift supervisor or to the PCAQR Review Board for review

' * -

and processing.

,,

<

Collectively, these v.iolations have been categorized as a Severity Level IV

problem (Supplement I).

i,.

,

19

'

21,

22-

24

26

28

30

32

34

..

S$

u.S. NUCLEAR REGULATORY COMMissloN

I