MONTHYEARIR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. ML24012A0652024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000321/20233012024-01-17017 January 2024 NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems IR 05000321/20234022023-11-29029 November 2023 Security Baseline Inspection Report 05000321/2023402, 05000366/2023402, and 07200036/2023401 NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal IR 05000321/20230112023-11-17017 November 2023 Biennial Problem Identification and Resolution Inspection Report 050003212023011 and 050003662023011 ML23324A4472023-11-14014 November 2023 302 Exam Approval Letter IR 05000321/20230032023-11-0202 November 2023 Integrated Inspection Report 05000321/2023003, and 05000366/2023003 IR 05000321/20234032023-10-26026 October 2023 Cyber Security Inspection Report 05000321/2023403 and 05000366/2023403 IR 05000321/20234012023-10-17017 October 2023 Security Baseline Inspection Report 05000321 2023401 and 05000366 2023401 ML23250A0472023-09-20020 September 2023 Request for Additional Information Regarding License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts in Technical Specifications Table 1.1-1, Modes ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report IR 05000321/20230052023-08-27027 August 2023 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 & 2 - Report 05000321/2023005 and 05000366/2023005 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 IR 05000321/20230022023-08-0808 August 2023 Integrated Inspection Report 07200036/2023001, 05000321/2023002, and 05000366/2023002 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23201A0292023-07-20020 July 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement ML23178A0012023-06-27027 June 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000321 2023403 and 05000366 2023403 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use IR 05000321/20230102023-06-0909 June 2023 Focused Engineering Inspection Report 05000321 2023010 and 05000366 2023010 NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 ML23123A2222023-05-0101 May 2023 Notification of Licensed Operator Initial Examination 05000321/2023301, and 05000366/2023301 IR 05000321/20230012023-04-26026 April 2023 Integrated Inspection Report 05000321/2023001 and 05000366/2023001 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-23-0179, National Pollutant Discharge Elimination System (NPDES) Permit Renewal2023-03-13013 March 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal ML23065A1092023-03-0808 March 2023 Correction of Relief Request HNP-ISI-RR-05-02 Allowing to Continue Operation with a Flaw Indication on One Reactor Pressure Vessel Closure Bolt Until December 31, 2025 ML23053A2182023-03-0303 March 2023 Correction of Amendment Nos. 321 and 266 Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program IR 05000321/20220062023-03-0101 March 2023 Annual Assessment Letter Edwin I. Hatch Nuclear Plant, Units 1 and 2 - NRC Inspection Report 05000321/2022006 and 05000366/2022006 NL-23-0101, Cycle 28 Core Operating Limits Report Version 12023-02-23023 February 2023 Cycle 28 Core Operating Limits Report Version 1 ML23034A2462023-02-21021 February 2023 Audit Summary for License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML22363A3932023-02-15015 February 2023 Issuance of Amendments Nos. 321 and 266, Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program ML22346A1482023-02-0909 February 2023 Issuance of Amendments 320 and 265, Regarding LAR to Revise Technical Specifications to Adopt TSTF-208 and Administrative Correction for Duplicate Technical Specifications 3.4.10 2024-01-31
[Table view] |
Inspection Report - Hatch - 2011006 |
---|
|
|
Text
UNITED STATES September 1, 2011
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 (REPORT 05000321/2011006 AND 05000366/2011006)
Dear Mr. Madison:
On August 9, 2011, the NRC completed its mid-cycle performance review of Edwin I. Hatch Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010 through June 30, 2011.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.
The NRC determined the performance at Hatch Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC=s Reactor Oversight Process (ROP)
Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green).
Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2012.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. In addition to ROP baseline inspection activities, we also plan on conducting Temporary Instruction (TI) 2515/177 Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, and Initial Operator License Examinations.
In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRCs processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed TI-183,
SNC 2 Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event, and TI-184, Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs) at your facility. Results of these inspections can be found here: http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, Mitigating Strategies, to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRCs Task Force made its recommendations to the Commission in its report, Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident.
The Commission is currently reviewing the Task Forces recommendations to determine whether additional actions may be warranted.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (404) 997-4548 with any questions you have regarding this letter.
Sincerely,
/RA/
James Hickey, Acting Chief Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321, 50-366 License Nos.: DPR-57, NPF-5 Enclosure: Hatch Inspection/Activity Plan (09/01/2011 - 12/31/2012)
cc w/encl: (See page 3)
________ML112440380________ X SUNSI REVIEW COMPLETE OFFICE RII:RDP RII:DRP RII:DRP SIGNATURE TXL /RA/ JAH /RA/ GSC /RA/
NAME TLighty JHikey GCroon DATE 08/25/2011 08/26/2011 08/28/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
SNC 3 cc w/encl: T. D. Honeycutt S. Kuczynski Regulatory Response Supervisor Chairman, President and CEO Southern Nuclear Operating Company, Inc.
Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution N. J. Stringfellow J. L. Pemberton Licensing Manager SVP & General Counsel-Ops & SNC Southern Nuclear Operating Company, Inc.
Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution L. P. Hill Jeffrey T. Gasser Licensing Supervisor Chief Nuclear Officer Southern Nuclear Operating Company, Inc.
Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution R. L. Gladney Paula Marino Licensing Engineer Vice President Southern Nuclear Operating Company, Inc.
Engineering Electronic Mail Distribution Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. L. Crumpton Administrative Assistant, Sr.
L. Mike Stinson Southern Nuclear Operating Company, Inc.
Vice President Electronic Mail Distribution Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc. Steven B. Tipps Electronic Mail Distribution Hatch Principal Engineer - Licensing Edwin I. Hatch Nuclear Plant Dennis Electronic Mail Distribution Vice President Edwin I. Hatch Nuclear Plant W. E. Duvall Southern Nuclear Operating Company, Inc. Site Support Manager Electronic Mail Distribution Edwin I. Hatch Nuclear Plant Electronic Mail Distribution T. E. Tynan Site Vice President Mr. Ken Rosanski Vogtle Electric Generating Plant Resident Manager Southern Nuclear Operating Company, Inc. Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Oglethorpe Power Corporation Electronic Mail Distribution M. J. Ajluni Nuclear Licensing Director Mark Williams Southern Nuclear Operating Company, Inc. Commissioner Electronic Mail Distribution Georgia Department of Natural Resources Electronic Mail Distribution B. D. McKinney, Jr.
Regulatory Response Manager (cc w/encl continued next page)
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
SNC 4 (cc w/encl continued) Reece McAlister Executive Secretary Lee Foley Georgia Public Service Commission Manager of Contracts Generation Electronic Mail Distribution Oglethorpe Power Corporation Electronic Mail Distribution Chairman Appling County Commissioners Arthur H. Domby, Esq. County Courthouse Troutman Sanders 69 Tippins Street, Suite 201 Electronic Mail Distribution Baxley, GA 31513 James C. Hardeman Amy Whaley Environmental Radiation Program Manager Engineer Environmental Protection Division Nuclear Generation Development and Georgia Department of Natural Resources Construction Electronic Mail Distribution Electronic Mail Distribution Al Frazier Emergency Response and Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution F. Allen Barnes Director Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James A. Capp Program Coordination Branch Chief Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution
SNC 5 Letter to Dennis from James Hickey dated September 1, 2011 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 (REPORT 05000321/2011006 AND 05000366/2011006)
Distribution w/encl:
C. Evans, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource ROP Assessment Institute of Nuclear Power Operations (INPO)