IR 05000275/1982023

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-275/82-23 & 50-323/82-12 on 820721-23.No Noncompliance Noted.Major Areas Inspected:Followup on IE Circulars,Info Notices & Bulletins,Preoperational Testing & Monitoring Calibr
ML20062J819
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 07/30/1982
From: Book H, North H, Wenslawski F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20062J793 List:
References
50-275-82-23, 50-323-82-12, NUDOCS 8208160475
Download: ML20062J819 (6)


Text

.

U. S. NUCLEAR REGULATORY COMMISSION

REGION V

50-275/82-23 Report No. 50-323/82-12 50-275 DPR-76 Docket No. 50-323 License No. CPPR-69 Safeguards Group _

Licensee:

Pacific Gas and Electric Company P. O. Box 7442 San Francisco, California 94106 Facility Name:

Diablo Canyon Units 1 and 2 Inspection at: San Luis Obispo County, California Inspec'lon conducted: July 21-23, 1982 9/[V Inspectors:

-6

H.

S'. North, Radiation Specialist

/Datd Signed Approved by:

8 [b 7/afM2 u

F. A. Wenslawski, Chief, Reactor Radiation Protection Da'te Sfgned Section Approved by:

'

'

H. E. Book, Chief, Radiological Safety Branch Date Signed Summary:

Inspection on July 21-23, 1982 (Report Nos. 50-275/82-23 and 50-323/82-12)

Areas Inspected:

Followup, IE Circulars and Information Bulletin, preoperational testing and monitor calibration.

This inspection involved 20 inspector-hours onsite by one inspector.

Results:

Of the three areas inspected no items of noncompliance or deviations were identified.

820B160475 820730 PDR ADOCK 05000

___ _ _ _ _ _ _ _ _. __

>

.

.

DETAILS 1.

'Per'hons Contacted Station Staff

.

,

  • R. Thornberry, Plant Manager
  • R. Patterson, Plant Superintendent
  • J. Boots, Supervisor, Chemistry and Radiation Protection -(C&RP)

W. O'Hara, Senior, C&RP Engineer

  • R. Twiddy, OA Supervisor
  • R. Howe, Regulatory Compliance Engineer A. Taylor, C&RP Engineer T. Brake, Power Production Engineer General Construction M. Norem, Lead Startup Engineer W. Coley, Unit 1 Startup Engineer D. Harris, Unit 2 Startup Engineer R. Savard, Construction Engineer (* Denotes those present at the exit interview.).

2.

Followup, IE Circular and Information Bulletin The inspector verified that the licensee had received, reviewed and has taken or plans to take appropriate action with respect to:

IE Information Notice No. 82-18: Assessment of Intakes of' Radioactive I

Material by Workers - applicable to Units 1 and 2 (FW-06-16)

IE Circular No. 81-07:

Control of Radioactively Contaminated Material -

applicable to Unit 2 (IC-81-07)

l

.

IE Circular No. 81-09: Containment Effluent Water that Bypasses'

Radioactivity Monitor - applicable to Unit 2 (IC-81-09)

No items of noncompliance or deviations were identified.

3.

Preoperational Testing The status of preoperational tests selected for review was examined.

In' those cases where preoperational tests had been completed, approved and accepted by operations, test results were examined to assure that xhe test results were within the previously established acceptance

.

I

- _____-_ _ _ _.

._. _ - _ _

d

.

-2-criteria and, where applicable, deviations from acceptance criteria were properly identified and disposed in accordance with the licensee's administrative procedures. The following tests have been completed and accepted by operations:

Unit Test No.

Applicability Title and Comments 19.2.11 Addendum

Test New Reactor Cavity Sump Pumps (A)2 As originally designed and built.the reactor sump was equipped with centrifugal pumps in an area accessible only with difficul ty. An ALARA review identified the problem and proposed corrective action. This test was of the jet pumps installed to replace the centrifugal pumps. The jet pumps will require significantly less maintenance activity in the reactor sump area.-

23.lA2 1 and 2 Retest Control Room Vent Logic and Test New Control Room Pressurization System 23.3Al

Test Aux. and FHB Vent Logic due to Changes in CHPS 24.2A2

Preop. New 0, Analyzer (Gaseous Radwaste System)

"

19.2.1

Flush Closed Drain System 19.2.11

Flush and Preop. Containment Sump System 19.2.12

Flush and Preop. Spent Resin System 23.1,

Main Control Room Heating, Vent, and 23.1A1 and Air Conditioning System, and control 23.lA3 room pressurization system are the same tests as previously examined and documented in IE Inspection Reports 50-275/80-04, paragraph 5,50-275(323)/

!

81-05, paragraph 9 and 50-275(323)/

82-04, paragraph 6.

23.2

Vent-Area H Elev. 100'0", 115'0",

I 128'0", and 163'6" 23.8

Misc. V and AC Startuo Data

__ __ _ _ _ _ - _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ _ - _ - _ _ _ _ -.

,

-

.

$

-3-Of the preoperational tests selected for review the following remain incomplete:

Unit 1

19.2.12 Flush and Preop. Spent Resin System

,

23.3 Aux & Fuel Handling Buildings Vent. Preop. Test (80-04-01)

Unit 2 1.6 Reactor Coolant System Chemistry Control 1.9 Preop. Test of Communications System 11.1 NSSSSS Flush

11.2 NSSSSS Functional Test 23.3 Aux. and Fuel Handling Buildings Vent. Precp. Test 23.10 Preop. Cont. H Purge System g

,

24.2 Preop. Test Gaseous Waste System 37.22 Radiation Monitoring System Noise 38.4 Radiation Monitoring System (82-12-01).

,

No items of noncompliance or deviations were identified.

!

4.

Area, Process and Effluent Monitor Calibration l

Paragraph 5 of IE Inspection Report Nos. 50-275/81-16 and 50-275/82-04 identify FSAR and non FSAR identified monitor calibration procedure and calibration status. At the time of the inspection the following FSAR identified monitors were uncalibrated:

,

1-R-24 Plant Vent Iodine Monitor 1-R-25 Control Room Ventilation Intake 1-R-26 Control Room Ventilation Intake Monitors I-R-25 and 26 which had been calibrated were water damaged

'

during the January 1982 storms. These instruments have been repaired and were due for recalibration in the near future. The Plant Vent

!

Iodine Monitor, I-R-24, requires resolution of certain problems before it can be calibrated.

It is noted that some of the monitors are common

to both Units. With the exception of such monitors and fuel handling building area monitors, Unit 2 monitors are uncalibrated.

(81-05-02)

The installation and calibration status of non FSAR identified monitors l

was discussed with the licensee, i

i

.

,

y

,

o-s

,-w--

9-e.

. - - --

,


*-e

.

,

.

-4-

'

~

Tm Designation Location / System

' Status-Foot note

'

Area RE-30,31 Conta'inment Area Monitor (.High-(5)(6)

Range ion chamber)

RE-34 Plant Vent Monitor ALARA Area (5)

Monitor RE-35 Plant Vent Iodine Sampler ALARA Area (6)

Monitor RE-36 Iodine Grap Sample (FHB) Area Monitor

.(7)

RE-41 Gas Decay Tank Area Monitor (1, 2-1)

(4)

RE-42 Gas Decay Tank Area Monitor (1, 2-2)

(4 RE-43 Gas Decay Tank Area Monitor (.1, 2-3)

(4 RE-48 Post Accident Sampling Room (Sentry (4 System)

RE-60 TSC Office Area Monitor (3).

RE-61 TSC Ops Center /RMS Area Monitor (3)

RE-62 TSC Computation Center Area Monitor (3)

RE-63 TSC NRC Office Area Monitor (3)

RE-64 TSC HVAC Equipment Room Area Monitor (3)

RE-65 TSC Laboratory Area Monitor (3)

RE-71-74 Main Steam Line Monitors (5)(6)

Gas RE-29 Plant Vent Gross Gamma Monitor (5)(6)

RE-33 Plant Vent Noble Gas Monitor (4)

RE-51-54 Control Room Ventilation Intake (5)(6)_

Air Monitors (Control Room Pressurization System)

RE-67 TSC Noble Gas Monitor (3).

RE-69 TSC Laboratory' Noble Gas Monitor (3).

Air Particulate RE-66 TSC Air Particulate Monitor (3)

RE-68 TSC Laboratory Air Particulate (3)

Monitor Iodine RE-32 Plant Vent Iodine Monitor (3)

i Liquid RE-16 Condensate Demineralizer Regenerant (2)

Solution Effluent Monitor l

(1)NotInstalled l

(2) Installed - Not released by construction (3) Installed - released by construction l

(4) Calibration Procedure in Draft

!

(5) Calibration Procedure approved (6) Calibrated (7) See Note l

l l

l

,

,

- -

..

.

,

,

.

-

=,,

,

.

,

.

-

'

5-

-

,

RE-36 Iodine Grab Sample (FHB) Area Monitor, this iodine sampler has been redesignated RX-40.

No items of noncompliance or deviations were identified.

.

5.

Facility Tour During the inspection the access control area, post accident sampling system area, radwaste evaporator and radwaste ' solidification areas of the auxiliary. building were toured.

No items of noncompliance or deviations were identified.

6.

Exit Interview

.

,

At the conclusion of the inspection the results of the inspection were summarized for those individuals denoted in paragraph 1.

The licensee

,!

was informed that no items of noncompliance or deviations had been identified.