IR 05000275/1982030
| ML20027D152 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 10/08/1982 |
| From: | Bishop T, Eckhardt J, Morrill P NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML20027D151 | List: |
| References | |
| 50-275-82-30, 50-323-82-14, NUDOCS 8210280330 | |
| Download: ML20027D152 (6) | |
Text
__
__ _____.
l
U. S. : UCI.FaP, PICUIMORY COS.ISSIC:?
PI C IO!! V Repor: !;o. 50-275/82-30'and 50-323/82-14 Docke: ::o. 50-275 and 50-323 License ;o. DPR-76 and CPPR-69 Safeguards croup Licensee:
Pacific Gas and Electric Company P. 0. Box 7442 San Francisco, California 94120 Facility :: ace:
Diablo Canyon Nuclear Power Plant
.
Inspection 1.ocation and Date(s):
(1) Stone and Webster Engineering Corporation Boston, Massachusetts September 14-15, 1982 (2) Teledyne Engineering Services, Waltham, Massachusetts -
S tember 15-16, 1982 n
bA #\\
h(/M7 //82_
Report by:
- 1 P. J/ Norr~ill, Re, tor Inspector Date Signed 0(bl10
/VS1 J. p. ~Eckhardt, Reac't}or Inspector Date S'igned Approved by:
l.
8, [Q8L T. W. Bishop, Chief, Rea@ tor Projects Branch, No. 2
' Date Signed
-
-*
Date Signed Su=:a ry:
"
,,,
.
Inspection during period of September 14-16, 1982 (Report Nos.
50-275/82-30 and 50-323/82-I4)
The inspectors examined implementation of the Independent Verification Program including independence and qualifications of personnel, implementation of Quality Assurance programs and Project Procedures, and work in progress as well as conducting discussions with personnel.
This inspection effort involved 48 inspector-hours by two NRC
.
inspectors.
RV Form 219 (2)
0210280330 821014 PDR ADOCK 05000275 C
.
..
DETAILS 1.
Persons Contacted Stone and Webster Engineering Corporation
- F. Sestak, Jr., Project Manager, Diablo Canyon Project and Chief Engineer, Power Engineering
- C. Richardson, Assistant Engineering Manager D. Shelton, Chief Engineer, Engineering Assurance J. E. Krechting, Lead Power Engineer
- J. Webb, Lead Engineering Assurance Engineer J. J. Jacques, Principal Engineer, AFW & CRVP Systems S. LaRiccia, Principal Engineer, Engineering Mechanical Division E. Henebeny, lead Electrical Engineer
- J. Kelley, Quality Assurance Engineer Denotes those present at the exit meeting on September 15,
1982.
Teledyne Engineering Services (TES)
- W. E. Cooper, Project Manager
- R. Wray, Assistant Project Manager, Seismic W. S. Moonan, Controller
- J. A. Cragin, Manager Project Administration C. G. Sprangers, Assistant Project Manager, QA R. D. Foti, Manager, Projects R. D. Ciatto, Civil / Structural, Team Leader
- L. C. Noriega, Assitant Project Manager, Stone and Webster J. H. Malohson, TES Quality Assurance J. M. Cantalupo, Project Administrator Denotes those present at the exit meeting on September 16,
1982.
2.
Verification of Independence for Technical Reviewers Region V inspectors continued to evaluate the independence of 'IDVP technical reviewers.
The purpose of this program is to assure that the individuals performing the IDVP will provide an objective, dispassionate technical judgement, based'soley on technical merit.
The following factors were considered in evaluating the question of independence:
1)
Whether the individuals involved had been previously hired by PG&E or Bechtel Power Corporation (BPC) to do similar design wor '
.
-2-2)
Whether any individual involved had been previously employed by PG&E or BPC (and the nature of the employment).
3)
Whether the individual owns or controls significant amounts of PG&E or BPC stock.
4)
Whether members of the present household of individuals involved are employed by PG&E or BPC.
5)
Whether any relatives are employed by PG&E or BPC in a management capacity.
To verify that the individual participants meet the established independence criteria the staff has reviewed conflict of interest statements, reviewed resumes, and confidentially interviewed participants.
The following is a summary of that effort.
a.
Conflict of Interest Statements The Region V inspectors reviewed conflict of interest statements of TES participants (20 statements) who have been assigned to the program since June 1,1982.
The conflict of interest statements of participants assigned prior to June 1,~1982 were evaluated previously. These 20 statements included statements of six individuals employed by consultants to TES. The organizations that these individuals represent are: J. W. Wheaton Technology; Hanse, Holley, Biggs, Inc. ; Alexander Kusko, Inc.; and Foster-Miller Associates. The conflict of interest statements signed by these individuals indicated that none of the individuals have any significant past or present involvement with PG&E or Diablo Canyon.
The conflict of interest statements did not include Bechtel Power Corporation.
TES plans to revise '.ne statements, adding Bechtel, and have the participants sign the revised statements.
In addition to the conflict of interest statements of the TES individuals, the Region V inspectors reviewed the conflict of interest statements of the Stone & Webster participants in the IDVP.
Sixty-six conflict of interest statements were reviewed which included all of the Stone & Webster participants with the exception of two individuals whose statements were not available at the time of the review. 'The conflict of interest statements signed by these individuals indicated that none of the individuals have any significant past or present involvement with PG&E or Diablo Canyon.
Similar to the TES conflict of interest statements, the Stone & Webster statemets did not include Bechtel; the statements will be revised to include Bechtel and will be resigned by the Stone & Webster participants.
!
l J
.
'
o
.3 -
b.
Resumes The professional resumes of key TES and Stone & Webster participants have been reviewed to give additional information regarding the question of independence. This effort included 14 resumes of TES personnel assigned to the program since June 1, 1982 (including consultants) and 36 resumes of Stone &
Webster personnel. The resumes indicated no employment history with either PG&E or Bechtel.
Additionally, the resumes were used to esaiua'te tne professional experience and competence of the participants.
The inspectors concluded that the TES and Stone & Webster individuals involved in the IDVP are competent and experienced in the matt'er's under review.
.
c.
Confidential Interviews
~
To further evaluate the question of. independence, the inspectors selected key participants in the IDVP and conducted confidential interviews with them. This effort included interviews ~with four TES personnel assigned to the program since June 1, 1982 and nine Stone & Webster personnel.
In' addition, twelve TES.
personnel assigned prior to June 1, 1982 were interviewed as discussed in paragraph 3.a of this, report.
In addition to the question of independence, the line of questioning included the possibility of pressure being applied to suppress findings.
Based on these interviews, the staff concluded that there is no conflict of interest between the participants in the IDVP and PG&E and Bechtel, and the participants feel no pressure to suppress possible findings.
3.
Examination of Corporate Financial independence a.
Teledyne Engineering Services (TES)
At the request of the NRR staff, the inspector questioned Teledyne personnel regarding potential conflict of interest regarding Bechtel Power Corporation and examined related Teledyne contractual documentation to verify the independence of Teledyne from Bechtel.
The inspector interviewed twelve lead personnel of the IDVP at Teledyne. All of these personnel stated that they perceived no problem for them in signing a " statement regarding potential or apparent conflicts of interest" which included Bechtel as well as PG&E.
However, some of the individuals also stated that they had worked on Bechtel contracts in the past or were currently involved in one or more Bechtel contracts although none of this other work was related to PG&E.
Based on these discussions the inspector determined that four Teledyne personnel were currently working on other Bechtel projects. These projects are described below:
-
.
r
..
-4-Project Scope and Contracting Office 3831 IE Bulletin 79-14 Pipe reanalysis for Davis-Besse - Bechtel, Gaithersberg 5282 Control rod drive design analysis for Limmerick - Bechtel, San Francisco 5504 Das Island LNG tank failure anlysis -
Bechtel, Great Britain Ltd.
5534 Acceptance criteria development for high strengh bolts for Palo Verde -
Bechtel, Los Angeles 5571 Testing of concrete anchor bolts, generic - Bechtel, San Francisco The inspectors discussed these projects and the extent of TES Bechtel business with the TES IDVP Project Manager and TES Controller.
This disucssion and review of the TES computer print-out of current projects confirmed that TES is currently involved only in the five projects listed above with Bechtel.
The inspectors also observed that at_ this time TES has 254 projects of which approximately, 244.are active.
In FY 1981 TES had a total of 261 projects of which.five were with Bechtel while in FY 1980 TES had seven Bechtel projects.
The TES billing to Bechtel for these projects was.$1,824,000 in FY 1980 and $1,234,000 in FY 1981.
The total Teledyne Corporation, business for FY 1981 was $3,237,600,000.. Although the company has a policy to not reveal division totals the inspectors estimate that the TES total annual business is between $20,000,000 and-
$40,000,000.
b.
Stone and Webster Engineering Corporation
,
l Similiar inspector interviews with the Stone and Webster Project Manager and Assistant Engineering Manager indicated that there were no contracts or financial connection between Stone & Webster Engineering Corporation and Bechtel.
4.
IDVP procedures and implementation The inspector examined Stone and Webster IDVP related procedures in conjection with the Phase II program plan, reviewed work in progress, and interviewed Stone and Webster personnel to verify that appropriate procedures were developed and implemented consistent with regulatory
,
'
requirements, and that the procedures were being followed.
The following procedures were examined.
!
!
-
-
__
_
.
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
.
'
.
-
.,
.
,
t
^
'
_5_
_
,
-
..
,,
~
.
Project Procedures:
-
1-1-2 dated 9/9/82 " Identification of Project Procedures" 4-1-2 dated 8/26/82 " Project Quality Assurance Plan" 5-1-2 dated 9/9/82 " Preparation and Control of Project Calculations" 5-2-0 dated 8/2/82 " System Design Verification Program" 5-3-2 dated 9/9/82 " Independent Design Verification Procedure" 5-4-1 dated 9/10/82 " Field Verification" 5-5-0 dated 8/23/82 " Sketches" 6-2-? dated 7/14/82 " Outgoing Correspondence" 6-3-2 dated 7/16/82 " Incoming Correspondence" 6-4-1 dated 5/14/82 " Conferences" 6-6-3 dated 8/23/82 " Document Control" 6-7-0 dated 7/26/82 " Reports" 7-1-1 dated 9/9/82 " Project files" The inspector also examined the items listed below:
Appendix D of the Phase II Program Management Plan Dated June 18. 1982 (Rev. 0) and Section 2.4 of the Phase II Program management plan.
Stone and Webster working drawings (Mark-ups) for the reevaluation of the pipe break outside containment sources and targets.
Stone and Webster working drawings (Mark-ups) for the reevaluation of cable tray separation.
Stone and Webster computer runs for assessment of electrical circuit / circuit breaker adequacy.
Stone and Webster field walk down data / verification results.
The inspector also examined the Stone and Webster file system for the Diablo Project and discussed the documentation and work in progress with the engineers and supervisors actually doing the work. Based on these examinations and discussions, the inspector concluded that Stone and Webster personnel had prepared adequate procedures consistent with the Phase II program plan and that these procedures were being followed.
While at Teledyne Engineering Services, the inspector also examined the TES QA audit summary of Stone and Webster conducted July 30, 1982. The inspector verified that the audit was in accordance with the TES QA program and that the findings resulted in appropriate corrective actions.
5.
Exit Interview At the conclusion of each segment (by dates and locations) of the inspection the inspectors met with appropriate representatives of the entities inspected to explain the scope and findings of the inspection.
.
.
.
- _ _ _ _ _ _. _ _ _.- - - - - - - - - - ---