IR 05000029/1999002

From kanterella
Jump to navigation Jump to search
Insp Rept 50-029/99-02 on 990411-0714.One Violation Noted & Being Treated as Ncv.Major Areas Inspected:Safe Operation of Sf Pool,Radiological Controls,Organization & Mgt Controls & Auditing & C/As for Decommissioning Activities
ML20210R167
Person / Time
Site: Yankee Rowe
Issue date: 08/04/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20210R146 List:
References
50-029-99-02, NUDOCS 9908170045
Download: ML20210R167 (23)


Text

.....

..

,

U.S. NUCLEAR REGULATORY COMMISSION REGION 1-Docket No.

50-29 License No.

DPR-03 Report No.

50-29/09-02 Licensee:

Yankee Atomic Electric Company 580 Main Street i

Bolton, Massachusetts 01740-1398 Facility Name:

Yankee Nuclear Power Station Location:

Rowe, Massachusetts Dates:

April 11,1999 -' July 14,1999

- Inspectors:

J. Nick, Lead Inspector, Region 1

- M. Fairtile, Project Manager, NRR

,

L. Pittiglio, Project Manager, NMSS

' E. Abelquist, ORISE j

l Approved by:

Ronald R. Bellamy, Chief Decommissioning and Laboratory Branch Division of Nuclear Materials Safety, RI

,

i 9908170045 990804 gDR ADOCK 05000029 PDR m

.

.

EXECUTIVE SUMMARY Yankee Facility NRC Inspection Report No. 50-29/99-02 Inspections were conducted to determine whether the decommissioning activities carried out at the Yankee (Rowe) facility were conducted safely and in accordance with NRC requirements. This report covers a three-month period of inspection. Areas reviewed included safe operation of the spent fuel pool, radiological controls, organization and management controls, and auditing and corrective actions for decommissioning activities. This inspection period also included independent measurements and reviews conducted by the Oak Ridge Institute for Science and Education (ORISE) on behalf of the NRC to assess the adequacy of the licensee's final status survey plan.

The survey results were received by NRC on June 28,1999. In general, programs were effective for protecting the safety of workers during dismantiement and decommissioning activities.

The licensee provided good controls for radiation exposure; however, there was one licensee-identified non-cited violation for failure to control access to a high radiation area. Very good controls for radioactive materials and contamination, surveys and monitoring during decommissioning work activities were observed. No other significant safety concems were identified.

I The licensee's new condition reporting process was effective in identifying and resolving employee concems. Commitment tracking and corrective action tracking were effective to ensure tasks were completed in a timely manner. The procedure tracking system was effective in helping to coordinate timely revisions of procedures. The site organization and staffing levels were appropriate for site decommissioning activities. No violations or significant safety concems were identified.

Effective procedures and processes to protect the safety of the spent fuel were implemented by the licensee. The licensee had adequate instructions for spent fuel pool make-up trending, spent fuel pool instrumentation, and chemistry controls.

l The licensee's final status survey program was consistent with NRC guidance. Results from ORISE independent measurements and samples were generally consistent with background levels and the licensee's results. However, some areas for improvement were noted for the final status survey program, including the need for further determination of site-specific maximum detectable concentrations and documentation in completed survey pac'Kages. These areas for improvement will be reviewed when the confirmatory survey process continues. NRC and ORISE will visit the site in the future to take additional measurements and compare data with the licensee's program.

ii

-

._

,

,

,

SUMMARY OF SURFACE ACTIVITY LEVELS TURBINE BUILDING YANKEE NUCLEAR POWER STATION (YNPS)

ROWE, MASSACHUSETTS I

!

Surface Activity Range Removable Activity Range l

Survey Number of (dpm/100 cm )

(dpm/100 cm )

2 l

Package #

Measurements

'

Beta Beta

TB005

-950 to 1,200-5 to 5 TB006

-400 to 580-5 to 3

_.

TB007

-820 to 1,500-3 to 6

,

TB013

-540 to 1,900-4 to 12 TB015

-970 to 430-4 to 4 TB017

-840 to 400-4 to 3 TB019

- 460 to 2,000-4 to 20 i

Catwalk

-7 to 220-1 to 3

-s i

A1-9

II

~ e

'

.

,.

,

!.

-

.

TABLE 4

!

,

RADIONUCLIDE CONCENTRATIONS IN SOIL TURBINE BUILDING YANKEE NUCLEAR POWER STATION (YNPS)

ROWE, MASSACHUSETTS Radionuclide Concentration (pCilg)

l Co40 Cs-137 Office Building # 1

<0.1

<0.1 Office Building # 2

<0.1

<0.1 l

Office Building # 3

<0.1.

<0,1 TB007 # 1 0.1 * 0.1'

<0.1

l TB007 # 2 0.2 * 0.1 0.5 * 0.1 TB009 # 1

<0.1

<0.1 TB009 # 2

<0.1

<0.1 TB010

<0.1

<0.1 TB011 # 1

<0.1

<0.1 TB011 # 2

<0.1

<0.1 TB012 # 1 -

<0.1

<0.1 TB012 # 2

<0.1

<0.1

' Uncertainties are total propagated uncertainties at the 95% confidence level.

l l

i A1-10 l

,

L..