ML20062H080

From kanterella
Jump to navigation Jump to search
Insp Rept 50-029/90-21 on 901015-19.Noncited Violation Noted.Areas Inspected:Response to Bulletin 79-14 Re Seismic Analysis of as-built safety-related Piping Sys
ML20062H080
Person / Time
Site: Yankee Rowe
Issue date: 11/19/1990
From: Carrasco J, Gray E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20062H078 List:
References
50-029-90-21, 50-29-90-21, IEB-79-14, NUDOCS 9012040083
Download: ML20062H080 (6)


See also: IR 05000029/1990021

Text

l

,-

.

.=

.

4

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-29/90-21

Docket No.50-029

License No.

pPR-3

Licensee

Yankee Atomic Electric Company

580 Main street

Bolton. KA. 017a0-1398

Inspection att

Rowe. Massachusetts

!

Inspection conducted

5-19. 1990

//*/f * NO

Inspectort

el M

.

,

J. z. carrasco, React 6r Engineer, Materials

date

and Processes Section, EB, DRS

/

Approved by:

^N

/9 9v

'

E. H. Gray, Chief / Materials and Processes

date

Section, EB, DRS-

Insoection Summarvt Report 50-029/90-21

Area Insometed: Special, announced inspection by a region-based inspector of

!

licensee actions in response to NRC/IE Bulletin 79-14, Seismic Analysis of

As-built safety-Related Piping Systems; and verification of design analyses

and work performed in modifications affected by this bulletin.

Resultst-

i

1.

One previously unresolved item regarding the sample population of piping

i

supports to provide acceptable confidence level to assure the adequacy of

)

a portion of the original IE Bulletin 79-14 inspection scope remains open.

(see section 7.0)

~,'

2.

An unresolved item regarding an incomplete Low Precoure Safety Injection

j

(LPSI) stress analysis was openod.

(see section 5.0)

i

3.

One non-cited violation regarding a f ailure to document a non-conf ormance

regarding discrepancies between as installed pipe supports and the piping

j

support drawings by initiating a Non-conformance Report (NCR) on a timely

basis.

(see section 6.0)

l

l

l

l

4

{

!

l

,o nou,o u 9o112 %{g.,

,

ppR

ADOCEO'MK'h

!

l

O

- _ _ - _ .

__

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ .

.

.

.

.

.

DETAILS

1.0

Persons Contacted

Yankee Atomic Electric Company _(YAEC)

,

  • N.N. St. Laurent, Plant St.perintendent
  • R.M. Mitchell, Maintenance Manager
  • B.

Wood, Administrative Service Manager

  • D.R. Lefrancois, Senior Engineer
  • J.A. Kay, Technical Service Manager
  • B.W. Holmgren, Lead Mechanical Engineer
  • T.

Henderson, Assisti.nt Plant Superintendent

United States Nuclear Rotulatory Commission

T. Koshy, Senior Resident Inspector

M. Markley, Resident Inspector

  • denotes those who attended the exit meeting

,

2.0

Baekoround

IE Bulletin 79-14 was issued on July

2,

revised on July 18,

and

supplemented on August 15 and September 7,

1979.

The bulletin requested

licensees to take certain actions to verify that seismic analyses are

applicable to as-built plants.

To accomplish this objective, field

.erification of large bore safety class piping and pipe supports was

required.

At Yankee Nuclear power Station, the licensee contracted Cygna Energy

Services to perform the tasks required of IE Bulletin 79-14.

The only

piping in the scope of IED 79-14 which was not field verified by Cygna

'

Energy Service was the Safety Injection system.

For this piping system

including pipe supports, several discrepancies were reported on dif ferent

occasions. In order to correct these discrepancies, the licensee had re-

contracted Cygna to perform a: field verification and evaluation of this

particular cystem outside the vapor containment.

Driefly, in ttrms of system description, the safety Injection syssam at

Yankee Nuclear Power Station utilizes three high pressure and three ie..'

pressure safety injection pumps to move water from the Safety Injection

Tank to the four Main Coolant System loop cold lege following a loss-of-

coolant accident .

3.0

Inspection curnose and score

The purpose of thit inspection was to assess the -adequacy of the

licensee's corrective action for identified supports that had dif ferences

between the as-built and the as-designed condition. These discrepancies

were identified on the following systems: Low Pressure Safety Injection,

'

High Pressure Safety Injection, Cavity fill and spent Fuel Pit Cooling and

Pump. All these four systems made-up the Safety Injection System and are

located outside of the vapor Container in the Primary Auxiliary and. Diesel

Generator Duildings and are safety related.

L

To' implement the corrective action the licensee had re-contracted Cygna to

perfer.u the following specific tasks

(a)

Walkdown and to provide as-built drawings of the piping and the

supports.

!

(b)

Compare the as-built drawings against existing piping and support

drawings to identify the discrepant conditions.

l.

'

a

-

- -.

.-

--

.

.

.

.

.

3

(c)

Prepare a calculation for any non-conforming configuratione to

determine if the piping and supports are within design allowabAO

conditions.

4.0

Piolna and Ploe suonort Walkdown Procedure and Imolementation

The inspector determined that the piping and support walkdowns were

performed in accordance with Reference 5.2 (Attachment D) of the Cygna's

work instruction for the field verification of non-seismic piping systems

outside the vapor container. Attachment D is the Yankee Atomic Nuclear

Service Division, Procedure No. YR-WI-02, titled " Work Instructions for

Performing Field Walkdowns of Piping and Pipe Supports Systems."

In addition to these requiremente, several additional requirements were

outlined in this cygna procedure. For examples for piping walkdowns, the

support number noted on the piping isometric or piping layout drawings was

verified; the connection type,

e.g.,

bolted flange, welded, etc., was

noted at all termination polnte.

For pipe support walkdowns, the following additional requirements were

met, for example

the general condition of the support was examined;

conditions which are deemed to be nonconforming,

e.g.

deteriorated

members, loose connections, etc., were recorded. These and several other

requirements were clearly stated in the Cygna walkdown procedure, and they

were field implemented as discussed in the next section of this report.

The inspector found the walkdown procedure to be acceptable and adequate

for this particular task and properly implemented.

5.0

Findinas

In order to assess the licensee's corrective action of piping and support

discrepancies, the inspector randomly selected pipe supports from the

Safety Injection System outelde the vapor container (VC). Inside the VC

the Shutdown Cooling System was selected to assess the licensee's original

79-14 program.

The selected supporte in the~ Safety Injection were PRSL-SH-1,

PRSH-RH-15 and PRSH-SH-1. The selected supports in the Shut-down Cooling

System were PRCH-SND-4, PRCH-SND-3, PRCH-H4 and PRCH-SND-1. The review of

these supports included the following:

Visual Inspection of the supports to determine that tho physical

configuration was reflected in the design calculation.

General location to determine that the isometric drawing reflected

the physical location of the support along the pipe run.

Spot check of the calculation, tables, interaction equations, and

ketches for accuracy, unite, and consistency.

The inspector, with the licensee's responsible engineer, examined the

system

by

a

walk-through

inspection

to

determine

the

physical

configuration of the system.

The system appeared to be in good physical condition and in the ae-design

configuration.

The inspector found the selected supports to be adequate

to perform their safety functions.

The inspector reviewed the licensee's status reporte prepared by Cygna on

the Safety Injection System outside the vapor container.

As a result of

i

.

.

.

'

.

4

Cygna's review of the markups and the evaluat'.on of the HPSI System

Support, all piping in the HPSI system remains Code qualified despite the

configuration changes.

Cygna eval. ation on the Spent Fuel Pool Cooling piping and pipe supports,

indicates ihat, although there are configurational changes and support

substitutiot in the system, the piping and the supports were found to be

code-qualifaed in their as-built condition.

In the case tf LPSI Accumulator Tank Vent and Nitrogen Bottle Piping,

Cygna has com,ileted their evaluation showing that both systems are Code-

qualified in t'eir present configuration. However, the evaluation of the

discharge port.on of LPSI and the Cavity Fill Systems, is still in the

process of finat approval.

This evaluation is being done using Cygna

walkdown informa ion.

The licensee had informed the inspector that the

preliminary analysis showed that the system is within code allowable

stress values.

However, the licensee did not provide final and official

results of the analysis at the time of the exit meeting. Nevertheless, at

the exit meeting, the licensee formally committed to complete the review

of the stress analysis for the LPSI system prior October 26, 1990. Also,

corrective maintenance will be performed by the licensee on all supports

before December 31, 1990.

This is an unresolved item pending final NRC review (50-029/90-21-01).

6.0

railure to Initiato a Promet Non-conformance Report (NCR)

The inspector reviewed the findings of Cygna to deter.nine that several

discrepancies existed due to differences in the

field installed

configuration in comparison to the requirement of design as shown on the

piping drawing.

The safety significance of these discrepancies is low.

Nevertheless, these discrepancies were not properly documented via Non-

conformance Report (NCR) as required by the licensee's station procedure

(AP-0206). This is contrary to 10CFR Part 50, Appendix B, Section XV on

nonconforming materials, parts or components and section XVI on corrective

Action.

Tne licensee informed the inspector that NCRs have been initiated for

these supports.

These NCRs will be evaluated by the Plant operation

Review Committee by October 26, 1990. Maintenance requests (MRs) which

describe the corrective measures for these supports will be written and

issued by October 26, 1990.

The failure to initiate a prompt NCR constitutes a violation.

However,

the violation is not being cited because the criteria specified in

Jection V.A of the enforcement policy were satisfied.

7.0

rollow-un on Previouelv Identified Itemg

tonen) Unresolved Item 50-029/90-04-01

The-inspector reviewed'the licensee's follow-up action, in terms of the

licensee's committment to the NRC during a previous inspection.

The

committment was made to perform certain actions in order to assure the

!

adequacy of the YAEC original (1979-80) inspection.

On June 1990, the licensee committed to include some systems originally

L

inspected by Cygna to determine the adequacy of the implementation of

l

Bulletin 79-14.

The inspector found that the number of supports selected

I

in the sample by the licensee to fulfill this commitment was not enough to

provide an acceptable level of confidence for their program under IEB 79-

14.

_

_ - - _ . - - _ _ _ _ _ .

.

. . ,

.

.

..

.

5

,

1

In response to this finding the licensee committed to conduct a similar

verification on an expanded basis outside the containment.

The

confirmatory walkdowns will commence before the end of the year and will

be completed prior to April 1, 1991.

The size of the sample population

that will be reverified, will be at least ten percent of the total number

of supports- selected originally under IEB 79-14.

Therefore, the

unresolved item 50-029/90-04-01 will remain open, until the NRC reviews

the licensee's reverification program.

8.0

Documents reviewed

91564.004

Cigna Transmittal of Isometries and Support Drawings for

the LPSI and Cavity Fill Systems, dated July 12, 1990.

.

91564.005 Rev.1

Cigna Status Report - LPSI Accumulator Tank Vent and

Nitrogen Bottle Piping, dated July 24, 1990.

91564.001

Cigna Status Report

HPSI System Supporte, dated

-

July 3, 1990.

91564.007

Cygna Status Report - Spent Fuel Pool Cooling Piping and

Supports, dated July 31, 1990.

91564.006

Cygna Status Report - Safety Injection Piping Associated

with Heater E-21 and Pump P-69, dated July 31, 1990.

Yankee Atomic - Bolton Memorandum subject Nonconformance


Report (NCR)89-016 and 89-017.

AP-206,Rev.11

Station Procedure on "Nonconformance Rer;.c" - dated

July 1990.

Cygna Work Instruction for Field Verification of Non-


Seismic Piping Systems outside the Vapor Container,

dated May 10, 1990.

80023-PI-1204

Earthquake Engineering Systems (EES), Piping Isometric

SitT.2 of 3

- Safety Injection Piping, part-4.

80023-PI-1203

EES Safety Injection Piping, part 3.

SHT.5 of 5

80023-PI-1202

ESS. Safety Injection Piping, part 2.

SHT.4 of 4

Rsv. 2

80025 PI-1202

ESS Safety Injection Piping, part 2.

SHT.3

t,*

4

Cygna Pipe Support Evaluation, System SI-207, Support


No. PRSH-SH-1, dated 10-11-89.

Cygna Pipe Support Evaluation, System SI-207, support


No..PRSH-RH-15, dated 10-9-89.

Cygna Pipe Support Evaluation, System SI-207, Support


No.PRSH-SH-1, dated 10-13-89.

Cygna Pipe Support Evaluation, System SC-121, Shutdown

~~--

Cooling Piping Supporte dated t-8-88, Support No. PRCH-

SND-1 (data point 160).

,

l

- . .

.

.

..

,

6

Cygna Pipe Support Evaluation, System SC-121, Shutdown


Cooling Piping, Support No. PRCH-H4 (data point 18).

Cygna pipe Support Evaluation, System SC-122, Shutdown


,

Cooling Piping, Support No. PRCH-SND-3 (data point 16) .

91564 SHT.B-22

Cygna Isometric Disposition for Spent Fuel Pool.

91564 SHT.B-5

Cygna Isometric Disposition for LPSI.

91564 SHT.B-22

Cygna Isometric Disposition for HPSI.

Safety Injection System P& ids

M-7-1,2,3.


BYR-90-139

Letter from J.

K. Thayer (YAEC) to T. T. Martin (NRC)

dated October 24, 1990 regarding pipe stress and pipe

support planned activities.

'

9.0

Unresolved items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable, violations or deviations.

Unresolved items identified during this inspection are discussed in

paragraphs 5.0 and 7.0.

10.0 Exit Meetina

The inspector met with licensee representatives (see Paragraph 1) at the

end of the inspection on October 19, 1990.

The inspector summarized the

purpose and scope of the inspection and identified the inspection

findings. At no time during this inspoction was written material provided

to the licennee by the inspectors.