Insp Rept 50-029/96-03 on 960827-29.No Violations Noted. Major Areas Inspected:Operations,Rp Program,Including Operations,Staffing,Mgt & Licensee Experience in Identifying & Correcting Weaknesses Re Control of Radioactive MatlsML20129C963 |
Person / Time |
---|
Site: |
Yankee Rowe |
---|
Issue date: |
10/16/1996 |
---|
From: |
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
---|
To: |
|
---|
Shared Package |
---|
ML20129C923 |
List: |
---|
References |
---|
50-029-96-03, 50-29-96-3, NUDOCS 9610240165 |
Download: ML20129C963 (9) |
|
|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000029/19990021999-08-0404 August 1999 Insp Rept 50-029/99-02 on 990411-0714.One Violation Noted & Being Treated as Ncv.Major Areas Inspected:Safe Operation of Sf Pool,Radiological Controls,Organization & Mgt Controls & Auditing & C/As for Decommissioning Activities IR 05000029/19990011999-05-0505 May 1999 Insp Rept 50-029/99-01 on 990101-0411.No Violations Noted. Major Areas Inspected:Cold Weather Preparations for Spent Fuel Pool,Radiological Controls & self-assessment & Auditing & Corrective Actions for Decommissioning Activities IR 05000029/19980031998-10-0101 October 1998 Insp Rept 50-029/98-03 on 980601-0731.No Violations Noted. Major Areas Inspected:Decommissioning Activities,Including Mods to Spent Fuel Pool Bldg & Radiological Controls IR 05000029/19980011998-06-24024 June 1998 Insp Repts 50-029/98-01 & 50-029/98-02 on 980101-0331.No Violations Noted.Major Areas Inspected:Mod to SFP Bldg, Radiological Controls & Decommissioning Activities IR 05000029/19970021997-09-23023 September 1997 Insp Rept 50-029/97-02 on 970401-0814.No Violations Noted. Major Areas Inspected:Licensee Activities Re Decommissioning IR 05000029/19970011997-05-16016 May 1997 Insp Rept 50-029/97-01 on 970301-31.No Violations Noted. Major Areas Inspected:Facility Operations IR 05000029/19960041997-01-24024 January 1997 Insp Rept 50-029/96-04 on 961119-21.No Violations Noted. Major Areas Inspected:Insp Verified by Observation, Documentation Review &/Or Discussions W/Responsible or Involved Plant Staff IR 05000029/19960031996-10-16016 October 1996 Insp Rept 50-029/96-03 on 960827-29.No Violations Noted. Major Areas Inspected:Operations,Rp Program,Including Operations,Staffing,Mgt & Licensee Experience in Identifying & Correcting Weaknesses Re Control of Radioactive Matls IR 05000029/19930071993-12-28028 December 1993 Insp Rept 50-029/93-07 on 930826-1118.Violation Noted. Major Areas Inspected:Posting of Radiological Areas & Other Controls,Organization & Staffing,Exposure ALARA Program & Radiological Info Available to Workers IR 05000029/19930081993-11-0909 November 1993 Insp Rept 50-029/93-08 on 931018-19.No Violations Noted. Major Areas Inspected:Mgt Support & Audits Protected Area Barriers,Detection & Assessment Aids Protected Area Access Control of Personnel,Alarm Stations & Communications IR 05000029/19930051993-08-18018 August 1993 Insp Rept 50-029/93-05 on 930510-0731.No Violations Noted. Major Areas Inspected:Operations,Maint Engineering & Plant Support,Including Radiological Controls,Security,Fire Protection & Housekeeping & Administration IR 05000029/19920111993-02-0505 February 1993 Insp Rept 50-029/92-11 on 921114-930201.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Control, Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000029/19920101992-11-23023 November 1992 Insp Rept 50-029/92-10 on 921104-06.One Open Items Noted. Major Areas Inspected:Contamination Monitoring of Guardhouse,Postings & Other Controls,Radiological Control of Work in Progress & Organization & Staffing ML20127F1051992-11-23023 November 1992 Corrected Cover Page for Insp Rept 50-029/92-10 on 921104-06.No Radiological Safety Concerns or Violations Noted.Major Areas Inspected:Contamination Monitoring at Guardhouse,Postings & Other Controls Observed During Tours IR 05000029/19900231990-12-0505 December 1990 Insp Rept 50-029/90-23 on 901105-09.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Controls & Radiological Environ Monitoring Programs ML20062H0801990-11-19019 November 1990 Insp Rept 50-029/90-21 on 901015-19.Noncited Violation Noted.Areas Inspected:Response to Bulletin 79-14 Re Seismic Analysis of as-built safety-related Piping Sys IR 05000029/19900161990-11-0606 November 1990 Insp Rept 50-029/90-16 on 900821-1001.Violation Noted.Major Areas Inspected:Daytime & Backshifts in Areas of Plant Operations,Radiological Controls,Maint & Surveillance, Emergency Preparedness,Security IR 05000029/19900811990-09-28028 September 1990 Insp Rept 50-029/90-81 on 900709-20 & 0806-10.Weaknesses & Unresolved Item Noted.Major Areas Inspected:Maint Program IR 05000029/19900121990-09-24024 September 1990 Insp Rept 50-029/90-12 on 900619-0820.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Security,Engineering/Technical Support,Safety Assessment/Quality Verification & Repts ML20058D3651990-09-14014 September 1990 Insp Rept 50-029/90-17 on 900730-0803.No Violations Noted. Major Areas Inspected:Audit of Licensee Action in Response to Recommendation Described in Generic Ltr 88-17 ML20059K7171990-09-0707 September 1990 Insp Rept 50-029/90-14 on 900802-27.Violations Noted Re Failure to Demonstrate Emergency Diesel Generators Operability at Required Capacity Under Design Basis Conditions.Major Areas Inspected:Emergency Diesel Generator IR 05000029/19900131990-08-0303 August 1990 Insp Rept 50-029/90-13 on 900709-13.One Noncited Violation Noted.Major Areas Inspected:Implementation of Radiation Protection Program During Current Refueling Outage & Review of Training & Qualification of Contractor Technicians IR 05000029/19900111990-08-0101 August 1990 Insp Rept 50-029/90-11 on 900619-22.No Violations or Deviations Noted.Major Areas Inspected:Safety Injection Tank Design & Replacement Procedures Together W/Walkdown of Safety Injection Sys Pumps,Valves & Piping IR 05000029/19900091990-07-16016 July 1990 Insp Rept 50-029/90-09 on 900515-0618.No Violations Noted. Major Areas Inspected:Operational Safety,Plant Operations, Radiological Controls,Maint & Surveillance,Emergency Preparedness,Security & Engineering/Technical Support IR 05000029/19900051990-02-16016 February 1990 Physical Security Insp Rept 50-029/90-05 on 900207-09.No Violations Noted.Major Areas Inspected:Implementation of Safeguards Info & Personnel Access Control Programs at Corporate Ofc IR 05000029/19890111989-08-28028 August 1989 Insp Rept 50-029/89-11 on 890626-0731.Unresolved Items Noted Re Plant Operations Review Committee Actions to Address Task Force Investigation Results of 890725 Loss of Emergency Bus.Areas Investigated:Security & LERs IR 05000029/19890131989-08-23023 August 1989 Physical Security Insp Rept 50-029/89-13 on 890724-28.No Violations Noted.Major Areas Inspected:Action on Findings of NRC Regulatory Effectiveness Review,Mgt Support,Security Program Plan,Audits & Protected & Vital Area Physical IR 05000029/19890151989-08-15015 August 1989 Emergency Preparedness Insp Rept 50-029/89-15 on 890731-0803.No Violations Noted.Major Areas Inspected: Changes to Emergency Preparedness Program & Facilities, Equipment,Instrumentation & Supplies ML20246Q0301989-08-10010 August 1989 Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations or Deviations Noted.Major Areas Inspected: Corporate Engineering & Offsite Support for Plants & Implementation of Mods IR 05000029/19890121989-08-0101 August 1989 Insp Rept 50-029/89-12 on 890710-14.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys, Transportation & Liquid & Gaseous Effluents Programs, Including:Mgt Controls,Audits,Qa & Program Implementation IR 05000029/19890091989-07-25025 July 1989 Insp Rept 50-029/89-09 on 890522-0625.No Violations Noted. Major Areas Inspected:Daytime & Backshifts of Previous Insp Findings,Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & LERs IR 05000029/19890101989-07-20020 July 1989 Insp Rept 50-029/89-10 on 890705-07.No Violations Noted. Major Areas Inspected:Operational Radiological Environ Monitoring Program Including Mgt Controls & Licensee Program for QC of Analytical Measurements IR 05000029/19890061989-07-14014 July 1989 Insp Rept 50-029/89-06 on 890410-0521.Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & Radiological Controls IR 05000029/19890081989-07-0606 July 1989 Insp Rept 50-029/89-08 on 890530-0601.No Violations Noted. Major Areas Inspected:Fire Protection/Prevention Program, Including Program Admin & Organization,Admin Control & Combustibles & Admin Control of Ignition Sources IR 05000029/19890071989-06-0707 June 1989 Insp Rept 50-029/89-07 on 890524-26.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Changes in Radiation Protection Program & ALARA IR 05000029/19890021989-05-0404 May 1989 Insp Rept 50-029/89-02 on 890228-0410.No Unacceptable Conditions Noted.Major Areas Inspected:Operation Safety, Security,Plant Operation,Maint & Surveillance,Engineering Support & Radiological Controls IR 05000029/19890051989-05-0202 May 1989 Insp Rept 50-029/89-05 on 890403-07.No Violations Noted. Major Areas Inspected:Review of Util Actions on NRC Identified Previous Concern Re Generic Ltr 83-28,Item 2.2.2, Vendor Interface & commercial-grade Item Program IR 05000029/19890041989-04-25025 April 1989 Partially Deleted Insp Rept 50-029/89-04 on 890403-07 (Ref 10CFR73.21).Noncompliance Noted.Major Areas Inspected: Licensee Action on Findings in NRC Rer,Mgt Support,Security Program Plans & Audits & Power Supply IR 05000029/19890011989-03-29029 March 1989 Insp Rept 50-029/89-01 on 890118-0227.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings,Operational Safety Verification,Radiological Controls & Events Requiring Telephone Notification of NRC ML20235Y7951989-03-0202 March 1989 Insp Rept 50-029/88-22 on 881115-890117.Violations Noted. Major Areas Inspected:Licensee Action on Previous Insp Findings,Operational Safety Verification,Esf Sys Walkdown & Licensee Response to Selected Safety Issues ML20206C5391988-11-0202 November 1988 Onsite Regular & Backshift Insp Rept 50-29/88-16 on 880802- 1003.Major Areas Inspected:Licensee Action on Previous Inspector Findings,Operational Safety Verification, Radiological Controls,Plant Events & Maint Observations IR 05000029/19880191988-09-30030 September 1988 Insp Rept 50-029/88-19 on 880909.No Violations Noted.Major Areas Inspected:Circumstances Surrounding Waste Shipments 88-15 & 88-16 from Licensee Facilities to Barnwell,Sc IR 05000029/19880171988-09-23023 September 1988 Insp Rept 50-029/88-17 on 880815-18.No Violations Noted. Major Areas inspected:pre-outage Evaluation,Review of Prior Insp Findings & Observation of in-plant Radiological Controls,Including Mgt & Organization & Personnel Training IR 05000029/19880101988-09-13013 September 1988 Insp Rept 50-029/88-10 on 880601-0801.No Violations Noted. Major Areas Inspected:Licensee Action on Previous Inspector Findings,Operational Safety Verification,Radiological Controls & Events Requiring Telephone Notification to NRC IR 05000029/19880151988-09-0707 September 1988 Insp Rept 50-029/88-15 on 880815-18.No Violations Noted. Major Areas Inspected:Radiochemical Measurements Program Using NRC Mobile Measurements Lab & Licensee Whole Body Counting Facility,Including Confirmatory Measurements IR 05000029/19880141988-08-11011 August 1988 Insp Rept 50-029/88-14 on 880718-22.No Violations Noted. Major Areas Inspected:Implementation of Provisions of Inservice Test Program for Pumps & Valves,Test Procedures & Results & Results of May 1987 Integrated Leak Rate Test IR 05000029/19880131988-08-0303 August 1988 Partially Deleted Physical Security Insp Rept 50-029/88-13 on 880711-15 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Security Organization,Locks,Keys & Combinations,Physical Barriers & Vital Areas IR 05000029/19880121988-07-15015 July 1988 Insp Rept 50-029/88-12 on 880620-24.No Violation Noted.Major Areas Inspected:Radwaste Insp Program,Including Training of Personnel,Procurement of Packaging,Delivery to Carriers, Records & Repts,Waste Classification & Labeling IR 05000029/19880091988-06-21021 June 1988 Onsite Regular & Backshift Insp Rept 50-029/88-09.Violations Noted.Major Areas Inspected:Previous Insp Findings,Bimonthly Safety Sys Verification,Operational Safety Verification, Radiological Controls & Emergency Exercise IR 05000029/19880081988-06-0202 June 1988 Insp Rept 50-029/88-08 on 880426-28.No Violations Noted. Major Areas Inspected:Emergency Preparedness Insp & Observation of Licensee Annual Emergency Exercise Performed on 880426 1999-08-04
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000029/19990021999-08-0404 August 1999 Insp Rept 50-029/99-02 on 990411-0714.One Violation Noted & Being Treated as Ncv.Major Areas Inspected:Safe Operation of Sf Pool,Radiological Controls,Organization & Mgt Controls & Auditing & C/As for Decommissioning Activities IR 05000029/19990011999-05-0505 May 1999 Insp Rept 50-029/99-01 on 990101-0411.No Violations Noted. Major Areas Inspected:Cold Weather Preparations for Spent Fuel Pool,Radiological Controls & self-assessment & Auditing & Corrective Actions for Decommissioning Activities IR 05000029/19980031998-10-0101 October 1998 Insp Rept 50-029/98-03 on 980601-0731.No Violations Noted. Major Areas Inspected:Decommissioning Activities,Including Mods to Spent Fuel Pool Bldg & Radiological Controls IR 05000029/19980011998-06-24024 June 1998 Insp Repts 50-029/98-01 & 50-029/98-02 on 980101-0331.No Violations Noted.Major Areas Inspected:Mod to SFP Bldg, Radiological Controls & Decommissioning Activities IR 05000029/19970021997-09-23023 September 1997 Insp Rept 50-029/97-02 on 970401-0814.No Violations Noted. Major Areas Inspected:Licensee Activities Re Decommissioning IR 05000029/19970011997-05-16016 May 1997 Insp Rept 50-029/97-01 on 970301-31.No Violations Noted. Major Areas Inspected:Facility Operations IR 05000029/19960041997-01-24024 January 1997 Insp Rept 50-029/96-04 on 961119-21.No Violations Noted. Major Areas Inspected:Insp Verified by Observation, Documentation Review &/Or Discussions W/Responsible or Involved Plant Staff IR 05000029/19960031996-10-16016 October 1996 Insp Rept 50-029/96-03 on 960827-29.No Violations Noted. Major Areas Inspected:Operations,Rp Program,Including Operations,Staffing,Mgt & Licensee Experience in Identifying & Correcting Weaknesses Re Control of Radioactive Matls IR 05000029/19930071993-12-28028 December 1993 Insp Rept 50-029/93-07 on 930826-1118.Violation Noted. Major Areas Inspected:Posting of Radiological Areas & Other Controls,Organization & Staffing,Exposure ALARA Program & Radiological Info Available to Workers IR 05000029/19930081993-11-0909 November 1993 Insp Rept 50-029/93-08 on 931018-19.No Violations Noted. Major Areas Inspected:Mgt Support & Audits Protected Area Barriers,Detection & Assessment Aids Protected Area Access Control of Personnel,Alarm Stations & Communications IR 05000029/19930051993-08-18018 August 1993 Insp Rept 50-029/93-05 on 930510-0731.No Violations Noted. Major Areas Inspected:Operations,Maint Engineering & Plant Support,Including Radiological Controls,Security,Fire Protection & Housekeeping & Administration IR 05000029/19920111993-02-0505 February 1993 Insp Rept 50-029/92-11 on 921114-930201.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Control, Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000029/19920101992-11-23023 November 1992 Insp Rept 50-029/92-10 on 921104-06.One Open Items Noted. Major Areas Inspected:Contamination Monitoring of Guardhouse,Postings & Other Controls,Radiological Control of Work in Progress & Organization & Staffing ML20127F1051992-11-23023 November 1992 Corrected Cover Page for Insp Rept 50-029/92-10 on 921104-06.No Radiological Safety Concerns or Violations Noted.Major Areas Inspected:Contamination Monitoring at Guardhouse,Postings & Other Controls Observed During Tours IR 05000029/19900231990-12-0505 December 1990 Insp Rept 50-029/90-23 on 901105-09.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Controls & Radiological Environ Monitoring Programs ML20062H0801990-11-19019 November 1990 Insp Rept 50-029/90-21 on 901015-19.Noncited Violation Noted.Areas Inspected:Response to Bulletin 79-14 Re Seismic Analysis of as-built safety-related Piping Sys IR 05000029/19900161990-11-0606 November 1990 Insp Rept 50-029/90-16 on 900821-1001.Violation Noted.Major Areas Inspected:Daytime & Backshifts in Areas of Plant Operations,Radiological Controls,Maint & Surveillance, Emergency Preparedness,Security IR 05000029/19900811990-09-28028 September 1990 Insp Rept 50-029/90-81 on 900709-20 & 0806-10.Weaknesses & Unresolved Item Noted.Major Areas Inspected:Maint Program IR 05000029/19900121990-09-24024 September 1990 Insp Rept 50-029/90-12 on 900619-0820.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Security,Engineering/Technical Support,Safety Assessment/Quality Verification & Repts ML20058D3651990-09-14014 September 1990 Insp Rept 50-029/90-17 on 900730-0803.No Violations Noted. Major Areas Inspected:Audit of Licensee Action in Response to Recommendation Described in Generic Ltr 88-17 ML20059K7171990-09-0707 September 1990 Insp Rept 50-029/90-14 on 900802-27.Violations Noted Re Failure to Demonstrate Emergency Diesel Generators Operability at Required Capacity Under Design Basis Conditions.Major Areas Inspected:Emergency Diesel Generator IR 05000029/19900131990-08-0303 August 1990 Insp Rept 50-029/90-13 on 900709-13.One Noncited Violation Noted.Major Areas Inspected:Implementation of Radiation Protection Program During Current Refueling Outage & Review of Training & Qualification of Contractor Technicians IR 05000029/19900111990-08-0101 August 1990 Insp Rept 50-029/90-11 on 900619-22.No Violations or Deviations Noted.Major Areas Inspected:Safety Injection Tank Design & Replacement Procedures Together W/Walkdown of Safety Injection Sys Pumps,Valves & Piping IR 05000029/19900091990-07-16016 July 1990 Insp Rept 50-029/90-09 on 900515-0618.No Violations Noted. Major Areas Inspected:Operational Safety,Plant Operations, Radiological Controls,Maint & Surveillance,Emergency Preparedness,Security & Engineering/Technical Support IR 05000029/19900051990-02-16016 February 1990 Physical Security Insp Rept 50-029/90-05 on 900207-09.No Violations Noted.Major Areas Inspected:Implementation of Safeguards Info & Personnel Access Control Programs at Corporate Ofc IR 05000029/19890111989-08-28028 August 1989 Insp Rept 50-029/89-11 on 890626-0731.Unresolved Items Noted Re Plant Operations Review Committee Actions to Address Task Force Investigation Results of 890725 Loss of Emergency Bus.Areas Investigated:Security & LERs IR 05000029/19890131989-08-23023 August 1989 Physical Security Insp Rept 50-029/89-13 on 890724-28.No Violations Noted.Major Areas Inspected:Action on Findings of NRC Regulatory Effectiveness Review,Mgt Support,Security Program Plan,Audits & Protected & Vital Area Physical IR 05000029/19890151989-08-15015 August 1989 Emergency Preparedness Insp Rept 50-029/89-15 on 890731-0803.No Violations Noted.Major Areas Inspected: Changes to Emergency Preparedness Program & Facilities, Equipment,Instrumentation & Supplies ML20246Q0301989-08-10010 August 1989 Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations or Deviations Noted.Major Areas Inspected: Corporate Engineering & Offsite Support for Plants & Implementation of Mods IR 05000029/19890121989-08-0101 August 1989 Insp Rept 50-029/89-12 on 890710-14.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys, Transportation & Liquid & Gaseous Effluents Programs, Including:Mgt Controls,Audits,Qa & Program Implementation IR 05000029/19890091989-07-25025 July 1989 Insp Rept 50-029/89-09 on 890522-0625.No Violations Noted. Major Areas Inspected:Daytime & Backshifts of Previous Insp Findings,Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & LERs IR 05000029/19890101989-07-20020 July 1989 Insp Rept 50-029/89-10 on 890705-07.No Violations Noted. Major Areas Inspected:Operational Radiological Environ Monitoring Program Including Mgt Controls & Licensee Program for QC of Analytical Measurements IR 05000029/19890061989-07-14014 July 1989 Insp Rept 50-029/89-06 on 890410-0521.Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & Radiological Controls IR 05000029/19890081989-07-0606 July 1989 Insp Rept 50-029/89-08 on 890530-0601.No Violations Noted. Major Areas Inspected:Fire Protection/Prevention Program, Including Program Admin & Organization,Admin Control & Combustibles & Admin Control of Ignition Sources IR 05000029/19890071989-06-0707 June 1989 Insp Rept 50-029/89-07 on 890524-26.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Changes in Radiation Protection Program & ALARA IR 05000029/19890021989-05-0404 May 1989 Insp Rept 50-029/89-02 on 890228-0410.No Unacceptable Conditions Noted.Major Areas Inspected:Operation Safety, Security,Plant Operation,Maint & Surveillance,Engineering Support & Radiological Controls IR 05000029/19890051989-05-0202 May 1989 Insp Rept 50-029/89-05 on 890403-07.No Violations Noted. Major Areas Inspected:Review of Util Actions on NRC Identified Previous Concern Re Generic Ltr 83-28,Item 2.2.2, Vendor Interface & commercial-grade Item Program IR 05000029/19890041989-04-25025 April 1989 Partially Deleted Insp Rept 50-029/89-04 on 890403-07 (Ref 10CFR73.21).Noncompliance Noted.Major Areas Inspected: Licensee Action on Findings in NRC Rer,Mgt Support,Security Program Plans & Audits & Power Supply IR 05000029/19890011989-03-29029 March 1989 Insp Rept 50-029/89-01 on 890118-0227.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings,Operational Safety Verification,Radiological Controls & Events Requiring Telephone Notification of NRC ML20235Y7951989-03-0202 March 1989 Insp Rept 50-029/88-22 on 881115-890117.Violations Noted. Major Areas Inspected:Licensee Action on Previous Insp Findings,Operational Safety Verification,Esf Sys Walkdown & Licensee Response to Selected Safety Issues ML20206C5391988-11-0202 November 1988 Onsite Regular & Backshift Insp Rept 50-29/88-16 on 880802- 1003.Major Areas Inspected:Licensee Action on Previous Inspector Findings,Operational Safety Verification, Radiological Controls,Plant Events & Maint Observations IR 05000029/19880191988-09-30030 September 1988 Insp Rept 50-029/88-19 on 880909.No Violations Noted.Major Areas Inspected:Circumstances Surrounding Waste Shipments 88-15 & 88-16 from Licensee Facilities to Barnwell,Sc IR 05000029/19880171988-09-23023 September 1988 Insp Rept 50-029/88-17 on 880815-18.No Violations Noted. Major Areas inspected:pre-outage Evaluation,Review of Prior Insp Findings & Observation of in-plant Radiological Controls,Including Mgt & Organization & Personnel Training IR 05000029/19880101988-09-13013 September 1988 Insp Rept 50-029/88-10 on 880601-0801.No Violations Noted. Major Areas Inspected:Licensee Action on Previous Inspector Findings,Operational Safety Verification,Radiological Controls & Events Requiring Telephone Notification to NRC IR 05000029/19880151988-09-0707 September 1988 Insp Rept 50-029/88-15 on 880815-18.No Violations Noted. Major Areas Inspected:Radiochemical Measurements Program Using NRC Mobile Measurements Lab & Licensee Whole Body Counting Facility,Including Confirmatory Measurements IR 05000029/19880141988-08-11011 August 1988 Insp Rept 50-029/88-14 on 880718-22.No Violations Noted. Major Areas Inspected:Implementation of Provisions of Inservice Test Program for Pumps & Valves,Test Procedures & Results & Results of May 1987 Integrated Leak Rate Test IR 05000029/19880131988-08-0303 August 1988 Partially Deleted Physical Security Insp Rept 50-029/88-13 on 880711-15 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Security Organization,Locks,Keys & Combinations,Physical Barriers & Vital Areas IR 05000029/19880121988-07-15015 July 1988 Insp Rept 50-029/88-12 on 880620-24.No Violation Noted.Major Areas Inspected:Radwaste Insp Program,Including Training of Personnel,Procurement of Packaging,Delivery to Carriers, Records & Repts,Waste Classification & Labeling IR 05000029/19880091988-06-21021 June 1988 Onsite Regular & Backshift Insp Rept 50-029/88-09.Violations Noted.Major Areas Inspected:Previous Insp Findings,Bimonthly Safety Sys Verification,Operational Safety Verification, Radiological Controls & Emergency Exercise IR 05000029/19880081988-06-0202 June 1988 Insp Rept 50-029/88-08 on 880426-28.No Violations Noted. Major Areas Inspected:Emergency Preparedness Insp & Observation of Licensee Annual Emergency Exercise Performed on 880426 1999-08-04
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000029/19990021999-08-0404 August 1999 Insp Rept 50-029/99-02 on 990411-0714.One Violation Noted & Being Treated as Ncv.Major Areas Inspected:Safe Operation of Sf Pool,Radiological Controls,Organization & Mgt Controls & Auditing & C/As for Decommissioning Activities IR 05000029/19990011999-05-0505 May 1999 Insp Rept 50-029/99-01 on 990101-0411.No Violations Noted. Major Areas Inspected:Cold Weather Preparations for Spent Fuel Pool,Radiological Controls & self-assessment & Auditing & Corrective Actions for Decommissioning Activities IR 05000029/19980031998-10-0101 October 1998 Insp Rept 50-029/98-03 on 980601-0731.No Violations Noted. Major Areas Inspected:Decommissioning Activities,Including Mods to Spent Fuel Pool Bldg & Radiological Controls IR 05000029/19980011998-06-24024 June 1998 Insp Repts 50-029/98-01 & 50-029/98-02 on 980101-0331.No Violations Noted.Major Areas Inspected:Mod to SFP Bldg, Radiological Controls & Decommissioning Activities IR 05000029/19970021997-09-23023 September 1997 Insp Rept 50-029/97-02 on 970401-0814.No Violations Noted. Major Areas Inspected:Licensee Activities Re Decommissioning IR 05000029/19970011997-05-16016 May 1997 Insp Rept 50-029/97-01 on 970301-31.No Violations Noted. Major Areas Inspected:Facility Operations PNO-I-97-026, on 970427,Yankee Atomic Electric Will Begin Shipment of Reactor Vessel for Disposal.First Phase of Shipment Will Involve Heavy Haul Truck from Rowe,Ma Site to Railway Approx Six Miles Away Near Hoosac Tunnel1997-04-25025 April 1997 PNO-I-97-026:on 970427,Yankee Atomic Electric Will Begin Shipment of Reactor Vessel for Disposal.First Phase of Shipment Will Involve Heavy Haul Truck from Rowe,Ma Site to Railway Approx Six Miles Away Near Hoosac Tunnel IR 05000029/19960041997-01-24024 January 1997 Insp Rept 50-029/96-04 on 961119-21.No Violations Noted. Major Areas Inspected:Insp Verified by Observation, Documentation Review &/Or Discussions W/Responsible or Involved Plant Staff IR 05000029/19960031996-10-16016 October 1996 Insp Rept 50-029/96-03 on 960827-29.No Violations Noted. Major Areas Inspected:Operations,Rp Program,Including Operations,Staffing,Mgt & Licensee Experience in Identifying & Correcting Weaknesses Re Control of Radioactive Matls ML20059D6441993-12-28028 December 1993 Notice of Violation from Insp on 930826-1118.Violation Noted:On 930826,inspector Found Several Examples of High Radiation Areas Where Licensee Did Not Barricade or Properly Control Access to Prevent Inadvertent Entry IR 05000029/19930071993-12-28028 December 1993 Insp Rept 50-029/93-07 on 930826-1118.Violation Noted. Major Areas Inspected:Posting of Radiological Areas & Other Controls,Organization & Staffing,Exposure ALARA Program & Radiological Info Available to Workers PNO-I-93-070, on 931208,last Four SGs from Yankee Rowe Plant Transported by Heavy Hauler Truck & Trailer to Rail Line Approx Six Miles from Plant.One Protester Observed.States of Ma & VT Informed1993-12-0909 December 1993 PNO-I-93-070:on 931208,last Four SGs from Yankee Rowe Plant Transported by Heavy Hauler Truck & Trailer to Rail Line Approx Six Miles from Plant.One Protester Observed.States of Ma & VT Informed PNO-I-93-067, on 931207,painted-over School Bus Containing Protestors from Citizen Awareness Network & Greenpeace Blocked Yankee Rowe Access Route in Effort to Prevent Off Site Transport of Third of Four SGs1993-12-0707 December 1993 PNO-I-93-067:on 931207,painted-over School Bus Containing Protestors from Citizen Awareness Network & Greenpeace Blocked Yankee Rowe Access Route in Effort to Prevent Off Site Transport of Third of Four SGs ML20059M5771993-11-15015 November 1993 PNO-1-93-064A:on 931116 & 17,util Plans to Ship Two of Four Steam Generators from Plant to Radwaste Depository at Barnwell,Sc.Licensee Will Evaluate Weather Conditions on Morning of Transportation.Commonwealth of Ma Informed IR 05000029/19930081993-11-0909 November 1993 Insp Rept 50-029/93-08 on 931018-19.No Violations Noted. Major Areas Inspected:Mgt Support & Audits Protected Area Barriers,Detection & Assessment Aids Protected Area Access Control of Personnel,Alarm Stations & Communications IR 05000029/19930051993-08-18018 August 1993 Insp Rept 50-029/93-05 on 930510-0731.No Violations Noted. Major Areas Inspected:Operations,Maint Engineering & Plant Support,Including Radiological Controls,Security,Fire Protection & Housekeeping & Administration IR 05000029/19920111993-02-0505 February 1993 Insp Rept 50-029/92-11 on 921114-930201.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Control, Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000029/19920101992-11-23023 November 1992 Insp Rept 50-029/92-10 on 921104-06.One Open Items Noted. Major Areas Inspected:Contamination Monitoring of Guardhouse,Postings & Other Controls,Radiological Control of Work in Progress & Organization & Staffing ML20127F1051992-11-23023 November 1992 Corrected Cover Page for Insp Rept 50-029/92-10 on 921104-06.No Radiological Safety Concerns or Violations Noted.Major Areas Inspected:Contamination Monitoring at Guardhouse,Postings & Other Controls Observed During Tours IR 05000029/19900231990-12-0505 December 1990 Insp Rept 50-029/90-23 on 901105-09.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Controls & Radiological Environ Monitoring Programs ML20062H0801990-11-19019 November 1990 Insp Rept 50-029/90-21 on 901015-19.Noncited Violation Noted.Areas Inspected:Response to Bulletin 79-14 Re Seismic Analysis of as-built safety-related Piping Sys PNO-I-90-096, on 901109,reactor Manually Tripped Following Receipt of Alarms Indicating Automatic Scram Occurred1990-11-0909 November 1990 PNO-I-90-096:on 901109,reactor Manually Tripped Following Receipt of Alarms Indicating Automatic Scram Occurred ML20197H7151990-11-0606 November 1990 Notice of Violation from Insp on 900821-1001.Violation Noted:Corrective Action Implemented as Result of Failures of Emergency Lighting Surveillance Test Failed to Preclude Repetition of Failures IR 05000029/19900161990-11-0606 November 1990 Insp Rept 50-029/90-16 on 900821-1001.Violation Noted.Major Areas Inspected:Daytime & Backshifts in Areas of Plant Operations,Radiological Controls,Maint & Surveillance, Emergency Preparedness,Security ML20058D2871990-10-19019 October 1990 Notice of Violation from Insp on 900802-27.Violation Noted:Failure to Adequately Test EDGs After Major Overhaul IR 05000029/19900811990-09-28028 September 1990 Insp Rept 50-029/90-81 on 900709-20 & 0806-10.Weaknesses & Unresolved Item Noted.Major Areas Inspected:Maint Program IR 05000029/19900121990-09-24024 September 1990 Insp Rept 50-029/90-12 on 900619-0820.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Security,Engineering/Technical Support,Safety Assessment/Quality Verification & Repts ML20058D3651990-09-14014 September 1990 Insp Rept 50-029/90-17 on 900730-0803.No Violations Noted. Major Areas Inspected:Audit of Licensee Action in Response to Recommendation Described in Generic Ltr 88-17 ML20059K7171990-09-0707 September 1990 Insp Rept 50-029/90-14 on 900802-27.Violations Noted Re Failure to Demonstrate Emergency Diesel Generators Operability at Required Capacity Under Design Basis Conditions.Major Areas Inspected:Emergency Diesel Generator IR 05000029/19900131990-08-0303 August 1990 Insp Rept 50-029/90-13 on 900709-13.One Noncited Violation Noted.Major Areas Inspected:Implementation of Radiation Protection Program During Current Refueling Outage & Review of Training & Qualification of Contractor Technicians IR 05000029/19900111990-08-0101 August 1990 Insp Rept 50-029/90-11 on 900619-22.No Violations or Deviations Noted.Major Areas Inspected:Safety Injection Tank Design & Replacement Procedures Together W/Walkdown of Safety Injection Sys Pumps,Valves & Piping IR 05000029/19900061990-07-24024 July 1990 Exam Rept 50-029/90-06OL on 900619-21.Exam Results:All Three Candidates Passed Exams & Issued Licenses IR 05000029/19900091990-07-16016 July 1990 Insp Rept 50-029/90-09 on 900515-0618.No Violations Noted. Major Areas Inspected:Operational Safety,Plant Operations, Radiological Controls,Maint & Surveillance,Emergency Preparedness,Security & Engineering/Technical Support PNO-I-90-042, on 900519,security Discovered Unauthorized Firearm Behind Seat of Contractor Truck in Protected Area. Driver Stated Weapon Hidden Under Numerous Other Items & Slipped His Mind.Firearm Almost Rusted Closed1990-05-21021 May 1990 PNO-I-90-042:on 900519,security Discovered Unauthorized Firearm Behind Seat of Contractor Truck in Protected Area. Driver Stated Weapon Hidden Under Numerous Other Items & Slipped His Mind.Firearm Almost Rusted Closed IR 05000029/19900051990-02-16016 February 1990 Physical Security Insp Rept 50-029/90-05 on 900207-09.No Violations Noted.Major Areas Inspected:Implementation of Safeguards Info & Personnel Access Control Programs at Corporate Ofc IR 05000029/19890111989-08-28028 August 1989 Insp Rept 50-029/89-11 on 890626-0731.Unresolved Items Noted Re Plant Operations Review Committee Actions to Address Task Force Investigation Results of 890725 Loss of Emergency Bus.Areas Investigated:Security & LERs PNO-I-89-073, on 890825,when Tagging Removed on 5-inch Diameter Bypass Line,Pressure Boundary Leakage Discovered from Defect in Socket Weld Connection Between Vent & Bypass Lines.Plant Shutdown.Leakage Rate Less than 1 Gpm1989-08-25025 August 1989 PNO-I-89-073:on 890825,when Tagging Removed on 5-inch Diameter Bypass Line,Pressure Boundary Leakage Discovered from Defect in Socket Weld Connection Between Vent & Bypass Lines.Plant Shutdown.Leakage Rate Less than 1 Gpm IR 05000029/19890131989-08-23023 August 1989 Physical Security Insp Rept 50-029/89-13 on 890724-28.No Violations Noted.Major Areas Inspected:Action on Findings of NRC Regulatory Effectiveness Review,Mgt Support,Security Program Plan,Audits & Protected & Vital Area Physical PNO-I-89-071, on 890816,licensee Began Controlled Power Reduction to 20% of Rated Power to Investigate Leaking Inlet Flange of Safety Valve Located on Bypass Line of Main Coolant Loop 2.Flange Become Encrusted W/Solidified Boron1989-08-17017 August 1989 PNO-I-89-071:on 890816,licensee Began Controlled Power Reduction to 20% of Rated Power to Investigate Leaking Inlet Flange of Safety Valve Located on Bypass Line of Main Coolant Loop 2.Flange Become Encrusted W/Solidified Boron IR 05000029/19890151989-08-15015 August 1989 Emergency Preparedness Insp Rept 50-029/89-15 on 890731-0803.No Violations Noted.Major Areas Inspected: Changes to Emergency Preparedness Program & Facilities, Equipment,Instrumentation & Supplies ML20246Q0301989-08-10010 August 1989 Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations or Deviations Noted.Major Areas Inspected: Corporate Engineering & Offsite Support for Plants & Implementation of Mods IR 05000029/19890031989-08-0909 August 1989 Requalification Exam Rept 50-029/89-03OL on 890620-30.Exam Results:Six Senior Reactor Operators (SRO) & Six Reactor Operators Passed Exams.Three SROs Failed One or More Portions of Exams IR 05000029/19890121989-08-0101 August 1989 Insp Rept 50-029/89-12 on 890710-14.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys, Transportation & Liquid & Gaseous Effluents Programs, Including:Mgt Controls,Audits,Qa & Program Implementation IR 05000029/19890091989-07-25025 July 1989 Insp Rept 50-029/89-09 on 890522-0625.No Violations Noted. Major Areas Inspected:Daytime & Backshifts of Previous Insp Findings,Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & LERs IR 05000029/19890101989-07-20020 July 1989 Insp Rept 50-029/89-10 on 890705-07.No Violations Noted. Major Areas Inspected:Operational Radiological Environ Monitoring Program Including Mgt Controls & Licensee Program for QC of Analytical Measurements ML20247B0801989-07-14014 July 1989 Notice of Violation from Insp on 890410-0521.Violation Noted:Licensee Failed to Properly Restore Circuitry Configuration of Module in Control Room Main Fire Panel During Surveillance Testing IR 05000029/19890061989-07-14014 July 1989 Insp Rept 50-029/89-06 on 890410-0521.Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & Radiological Controls IR 05000029/19890081989-07-0606 July 1989 Insp Rept 50-029/89-08 on 890530-0601.No Violations Noted. Major Areas Inspected:Fire Protection/Prevention Program, Including Program Admin & Organization,Admin Control & Combustibles & Admin Control of Ignition Sources IR 05000029/19890071989-06-0707 June 1989 Insp Rept 50-029/89-07 on 890524-26.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Changes in Radiation Protection Program & ALARA IR 05000029/19890021989-05-0404 May 1989 Insp Rept 50-029/89-02 on 890228-0410.No Unacceptable Conditions Noted.Major Areas Inspected:Operation Safety, Security,Plant Operation,Maint & Surveillance,Engineering Support & Radiological Controls 1999-08-04
[Table view] |
Text
- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _ - _ _ .
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Docket N License N DPR-03 Report N /96-03 Licensee: Yankee Atomic Electric Company 580 Main Street Bolton, Massachusetts 01740-1398 Facility Name: Yankee Nuclear Power Station Location: Rowe, Massachusetts Dates: August 27-29,1996 Inspector: J. Nick, Radiation Specialist Approved By: J. White, Chief Radiation Safety Branch, Division of Reactor Safety 9610240165 961016
'
PDR ADOCK 05000029
.
_
G ,
PDR 3
l
.
I Report Details 01 Summary of Facility Operations On October 12,1995, the Commission served Memorandum and Order CLl-95-14 to Yankee Atomic Electric Company (YAEC) concerning activities at the Yankee Nuclear )
Power Station (NPS) in Rowe, Massachusetts. The Order states, in part, that "the l NRC's approval of the Yankee NPS Decommissioning Plan cannot be accorded further I legal effect, pending an [ adjudicatory] hearing opportunity," and, that in accordance with the pre-1993 interpretation of the decommissioning regulations, "the Commission expects YAEC not to conduct any further ' major' dismantling or decommissioning activities until final approval of its [ decommissioning] plan after completion of the hearing process." Based upon issuance of this Order, the inspector observed YAEC's activities during routine inspections on August 27 through 29,1996 to ascertain what work activities were in progress and if these activities were in compliance with the Orde Technical guidance and established written criteria for what constituted " major" facility dismantling or decommissioning activities were previously provided to YAEC in a letter dated November 2,1995. The letter stated, that "YAEC could proceed with activities (such as additional decontamination, component disassembly, and shipment and I storage of spent fuel), if these activities: (1) are permitted by the POL and l 10 CFR 50.59, and (2) do not materially and demonstrably affect the methods or options available for decommissioning or substantially increase the cost of decommissioning." Consequently, the inspector determined that all the work activities observed on August 27 through 29,1996, were in accord with this guidance and consequently satisfied compliance with the October 12,1995 Orde The inspector verified by observation, documentation review, and/or discussions with responsible or involved plant staff, that the activities on the current work schedule were the only jobs working. No safety concerns were identified by the inspector and appropriate radiological and industrial safety practices were observed for those jobs in- I progres O2 Operations O2.1 Facility Tours l The inspector toured radiological controlled areas (RCAs) within the vapor containmen The inspector noted operating air sampling equipment in various areas. Personnel dosimetry was worn by all workers in the area. Workers were in the vapor containment, outsido the bioshield, removing mechanical and electrical components (duct-work, conduit, cables, and fan units). The inspector observed that high radiation area (HRA) and locked high radiation area (LHRA) controls were satisfactory. All areas were posted, barricaded, and locked as required by NRC regulations and Technical l Specifications. The posting and labelling of radioactive material were satisfactor Very good radiological controls were provided by health physics technician coverage for jobs / activities in RCA _ _ _ _ _ _
_ - _ _ __ -_ _
\
The inspector toured most of the RCAs outside the vapor containment including the primary auxiliary building (PAB), the service building, the radioactive waste processing (compactor) building, the potentially contaminated area (PCA) storage building (a storage / staging area for potentially contaminated equipment and materials), and the PCA warehouse attached to the radwaste processing buildin Workers were observed assembling a temporary waste processing system near the ion exchange pit. The temporary waste processing system included holding tanks and an evaporator which were planned to replace the existing waste evaporator syste Other electrical and mechanical systems removal was continuing in the Primary Auxiliary Building (PAB). All radiation areas (ras) and HRAs were posted and barricaded as required. Locked HRAs were maintained locked with appropriate warning signs. Housekeeping in contaminated areas was good, and contamination control was evident by the use of " step-off pads", personnel monitoring equipment (friskers), and contaminated area postings at the boundaries. No safety or NRC regulatory concerns were noted by the inspecto .2 Current Activities Asbestos abatement work was continuing on the secondary side in the turbine buildin Some secondary and support systems removal had been started. The water treatment system had been dismantled and the space was being reconfigured for use by the site survey team. A temporary gatehouse had been established to allow renovation of the main gatehouse. The licensee plans to move the control room functions to the gatehouse to consolidate activities with the security organization. The engineering design change request for moving the control room functions had not been finalized as of the period of this inspectio Other work planned for 1996 included completion of the jobs mentioned above. At the time of this inspection, no new activities were planned pending the approval of the Decommissioning Plan by the NRC or later submittal in writing to the NRC regarding new planned activitie Planning was continuing for the reactor vessel removal project. Actual removal, packaging, and shipment of the reactor vessel was planned to begin after approval of the Decommissioning Plan by the NR R1 Plant Support - Radiological Controls Program R1.1 Oraanization Inspection Scooe (83722)
The inspector reviewed the radiation protection program organization through interviews with personnel and a review of licensee documents.
i
.
J
____ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
. .. . .
.
3 Observations and Findinas The radiation protection department had a direct reporting relationship to the plant manager. This change was made effective in the past 2 years and provided clear direction and accountability from the plant manager. The licensee's organization was not large and complex, and the radiation protection manager previously had access to the plant manager; however, the change was symbolic in elevating the radiation protection program and worker protection to a higher management level. This change had ensured management attention and support for the radiation protection progra The Radiation Protection / Chemistry Manager maintained six areas of responsibility, including operational radiation protection, radwaste, technical, final status survey, ALARA, and chemistry / environmental. The personnel supervising these areas were well qualified and experienced for their position Conclusions The licensee had no significant changes to the organization that could affect the ability to control radiation and radioactive materials. Mirior decreases in the number of contractor personnel were noted. No safety concerns were note R1.2 Staffino Inspection Scope (83722) -
The inspector reviewed the staffing of the radiation protection program through interviews with personnel and a review of licensee document Observations and Findinas The majority of workers on the Rowe site were contractor employees. Yankee Atomic Energy Corporation (YAEC) provided oversight and supervision of the contractor employees for radiological work activities. Eight YAEC employees provided this oversight for approximately 60 contract radiation protection technicians. Many of the contract employees were long term employees or had worked at the site in the pas The YAEC staff's control of work activities was very good, and staff involvement was continuous. This control ensured proper direction to the contractor employee The inspector reviewed the records of initial and continuing periodic refresher training for the radiation protection technicians. With the exception of one individual, all technicians were listed as attendees at the required training. The licensee's staff determined that the one individual had been missed due to an isolated error in the attendance system. The staff was considering actions to prevent recurrence of this erro .. . . . . -
.
.. .
.
.. ..
.
__
. - . . - . - . _ _ _ _ _ _ _ _ . _ - _ _ _ - - _
,
l i
a l
l The inspector also reviewed the lesson plans for the training sessions. The quality of the training was very good and included important program changes, industry events, and basic information refresher Conclusions Plant management ensured proper staffing, training, and direction of personnel for the l effective control of radiation and radioactive materials. Personnel were qualified for the l positions and no safety concerns were note R1.3 Radiation Protection Manaaement insoection Scope (83722)
The inspector reviewed the management of the radiation protection program through examination of procedures, memorandum, and other licensee documentation, and interviews with personne Observations and Findinas
.
As stated in section R1.2 of this Report, the Radiation Protection / Chemistry Manager had six areas of responsibility. Control of work activities was well coordinate Effective management controls and oversight were implemented through the use of procedures, internal memoranda, staff meetings, and facility tours. The management team was effective in planning, organizing, and directing radiological controls and associated program Conclusions The inspector determined that the radiation protection management had adequate responsibility, authority, and support to ensure effective control of radiation and radioactive material. No violations or significant safety concerns were identifie R1.4 Identification and Correction of Weaknesses Insoection Scope (8372 The inspector reviewed the licensee's experience in identifying and correcting weaknesses related to the control of radiation and radioactive materials through examination of records and interviews with licensee personne !
l
- _ . - _ _ _ .-. _ _ _ _ _ ._.....__ ._ __ __ _. _ _ _-- _.- _ _ __ __ _
. .
.
<
r
"
i
' Qbservations and Findinas
, The licensee provided several methods for identification and correction of program
'
weaknesses including the radiological occurrence reporting system, internal reviews, and oversight committee The licensee's radiation protection staff had written several radiological occurrence i reports (RORs) during 1996. Four RORs were written earlier in the year and had been rev'ewed during previous NRC inspections. All RORs documented minor procedure i violations. The inspector reviewed the corrective actions and noted that timely and
'
technbally acceptable corrective actions were implemented for these deficiencies to ,
prevent recurrenc j l Internal reviews were performed on a periodic basis to probe specific areas of the radiation protection program for weaknesses. The inspgetor had previously reviewed I internal assessments of the occupational safety program, the ALARA program, and the '
technical program. Periodic reviews were also performed on radiological occurrence 1 reports to identify common trends or root causes. These reviews resulted in ;
recommendations to prevent recurrenc i l Conclusions :
i The inspector concluded that the licensee had effectively identified and corrected areas of weakness within the radiation protection program. No significant safety items or violations were identified in this are R1.5 Audits and Aooraisals insoection Scooe (83722)
The inspector reviewed the licensee's programs and systems for auditing and appraising the program for control of radiation and radioactive materials through examination of records and interviews with licensee personne Observations and Findinas There had been no new audits of the radiation protection program since the last inspection; however, the inspector noted recent audits of the special nuclear materials control program, the training program, the industrial safety program, the environmental program, the REMP/RETS/ODCM programs, and the corrective action syste Appropriate and timely corrective actions had been taken by the licensee's staff for the minor deficiencies and weaknesses that were identified during the audits performed by the quality assurance grou The quality assurance group was continuing to perform surveillance of radiological work activities and waste shipments. The inspector reviewed surveillance report regarding various radiological work activities. The surveillance reports indicated that the implementation of the radiation protection program was satisfactory.
,
,---.w-- e ., - ~ - - , - -
.-- ,, , --w -- ,
. _ .__ . _ _ _ - . _ _ _ _ _ _ _ . ._
I 6 Conclusions The inspector concluded that the audit, self-assessment, and corrective action programs were continuing to identify problem areas and improve the quality of the radiation protection program. No violations were identified in this are R1.6 Maintainina Occupational Radiation Exoosures ALARA Inspection Scope (83100)
i Through interviews with personnel and review of several documents, the inspector ;
- examined the program to maintain personnel exposures ALAR Observations ad Findinas )
.
.
The personnel working at the Rowe site received a total radiation exposure of
- approximately 81 person-rem during the period from January 1,1996 through
- August 26,1996, as measured by thermoluminescent dosimeters (TLDs) and pocket '
ion chambers (PICS). The projected total exposure during 1996 was 91 person-rem for routine work and support of decontamination and decommissioning activities.
,
Additional exposure was projected for dismantlement of the reactor vessel, the main j coolant system, various other systems in the vapor containment, balance of plant systems, and other structures. Some additional exposure was projected for asbestos abatement end radioactive waste shipments. The total dose to personnel working on i
all activities at the Rowe site for the period from 1993 through August 1996 was approximately 486 person-rem. The total dose for decommissioning and dismantlement
) activities, including support work, was approximately 440 person-re i Conclusione
,
The licensee continued to maintain ALARA reports for exposure tracking and trending.
l Total occupational radiation exposure for the year to date was less than the projected total for the yea R2.0 Radioactive Material Shioments Insoection Scoce (86750)
The inspector reviewed licensee records and interviewed personnel to determine the scope of radioactive material shipments from the Rowe sit Observations and Findinas Many radioactive waste and radioactive material shipments were sent from the Rowe site to waste processing or disposal facilities during the period from May 15,1996 through August 15,1996. The licensee was continuing to use various vendors for volume reduction, incineration, reclamation, and decontamination of radioactive materials. Various other radioactive material shipments were made from the facility including contaminated protective !
clothing for laundering and radioactive samples for laboratory analysi . . - . - . - - .--..---- _ . - - . .. .. .-- . - - -
.
7 Conclusions The licensee continued to ship radioactive materials to various vendors and disposal facilities. Licensee records were well maintained and no safety concerns or violations of regulations were note X1 Exit Meeting Sumn'ary The inspector met wi*h the licensee representatives denoted below at the conclusion of the on-site inspection w August 29,1996. The inspector summarived the purpose, scope, and findings of the inspection. The licensee representatives acknowledged the inspection finding i i
!
I
!
I l
1
. _ _ _ - . . _ . _ . . . _ _ _ . _ - _ _ _ _ _ _ _ . _ . . . _ _ _ _ . _ . - _ _ . . _ _ . _ - . . _ . _ _ _ _ _ . _ _ . _ . _ _ _ . . . _ . . _
- ,
o i
8 .
. !
'
l PARTIAL LIST OF PERSONS CONTACTED i
Licensee i
! *G. Babineau, Radiation Protection and Chemistry Manager
- W. Blackadar, Radiation Protection Engineer
-
- H. Breite, YNSD, Lead Engineer j 'W. Cox, YNSD, Radiation Protection Engineer l l *N. Fetherston, Maintenance and Construction Manager l 2 J. Gedutis, Chemistry i *R. Greenfeld, Radiation Protection Engineer
'R. Grippardi, YAEC, Quality Assurance Supervisor
'
l'
- "K. Heider, Site Manager l *S. Litchfield, Health and Safety Supervisor
-
- R. Mellor, YNSD Decommissioning Manager (via telephone)
'
S. Mullet, Radiation Protection Technician ,
- J. Pelletier, Yankee Atomic j *S. Racz, Training Coordinator j 'A. Trudeau, Quality Services Group Senior Engineer i e
'M. Vandale, Radiation Protection Senior Engineer ,
] F. Williams, Operations Manager :
~
!
l
- Denotes those individuals participating in the exit briefing held on August 29,199 I INSPECTION PROCEDURE USED
,
IP 83722: Radiation Protection, Plant Chemistry, and Radwaste: Organization and Management Controls
ITEMS OPENED, CLOSED, AND DISCUSSED Opened I NONE Closed NONE l Discussed
.
NONE