HNP-11-043, Initial Exam 2011-301 General Correspondence

From kanterella
Jump to navigation Jump to search
Initial Exam 2011-301 General Correspondence
ML112660358
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 09/22/2011
From: Schwindt S
Progress Energy Carolinas
To: Widmann M
Division of Reactor Safety II
References
05-400/11-301, 05-400/11-302, HNP-11-043
Download: ML112660358 (7)


Text

Progress Energy April 26, 2011 SERIAL: HNP-1 1-043 Mr. Malcolm Widmann, Region II United States Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, GA 30303-893 1 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50-400/RENEWED LICENSE NO. NPF-63 LICENSED OPERATOR INITIAL EXAMINATIONS 05000400/2011302 OUTLINES

Dear Mr. Widmann:

Enclosed are the proposed examination outlines for the Reactor and Senior Reactor Operator Initial Examinations to be administered at the Harris Nuclear Plant during the weeks of July 11 and July 18, 2011. This submittal complies with the requirement identified in your letter dated March 14, 2011, to furnish the outlines by April 27, 2011. The enclosed materials shall be withheld from public disclosure until after the examinations are complete.

If you have any questions regarding these materials, please contact Mr. Archie Lucky at (919) 362-3386.

Sincerely, Simon Schwindt Supervisor Licensed Operator Requalification Training Harris Nuclear Plant SS/mgw Enclosures C: Mr. J. D. Austin (NRC Senior Resident Inspector, HNP) w/o Enclosures Mr. V. M. McCree (NRC Regional Administrator, Region II) w/o Enclosures Mrs. B. L. Mozafari (NRR Project Manager, HNP) w/o Enclosures Progress Energy Carolinas, Inc.

Harris Nuclear Plant P. 0. Box 165 New Hill, NC 27562

Mr. Malcolm Widmann SERIAL: HNP-1 1-043 be: (w/o Enclosures)

Mr. D. L. Griffith Mr. E. J. Kapopoulos, Jr.

Mr. A. W. Lucky Ms. T. M. Midgette Mr. M. G. Wallace Nuclear Records Licensing File

Progress Energy June 2, 2011 SERIAL: HNP-11-048 Mr. Malcolm Widmann, Region II United States Nuclear Regulatory Commission 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50-400/RENEWED LICENSE NO. NPF-63 LICENSED OPERATOR INITIAL EXAMINATIONS 05000400/2011302

Dear Mr. Widmann:

Enclosed are the proposed written examinations, operating tests, and supporting reference materials for the Reactor and Senior Reactor Operator Initial Examinations to be administered at the Harris Nuclear Plant during the weeks of July 11 and July 18, 2011. In a letter dated March 14, 2011, you requested these materials be provided by May 27, 2011. Based on communications between Mr. Gerald Laska (NRC) and Mr. Archie Lucky (PEC) on May 26, 2011, these materials are now being provided by June 3, 2011. The enclosed materials shall be withheld from public disclosure until after the examinations are complete.

If you have any questions regarding these materials, please contact Mr. Archie Lucky at (919) 362-3386.

Sincerely, Simon Schwindt Supervisor Licensed Operator Requalification Training Harris Nuclear Plant SS/mgw Enclosures C: Mr. J. D. Austin (NRC Senior Resident Inspector, HNP) w/o Enclosures Mr. V. M. McCree (NRC Regional Administrator, Region II) w/o Enclosures Mrs. B. L. Mozafari (NRR Project Manager, HNP) w/o Enclosures Progress Energy Carolinas, inc.

Harris Nuclear Plant P. 0. Box 165 New Hill, NC 27562

Mr. Malcolm Widmann SERIAL: HNP-1 1-048 be: (w/o Enclosures)

Mr. D. L. Griffith Mr. E. J. Kapopoulos, Jr.

Mr. A. W. Lucky Ms. T. M. Midgette Mr. M. G. Wallace Nuclear Records Licensing File

Progress Energy July 25, 2011 SERIAL: HNP-11-074 Mr. Malcolm Widmann, Region II United States Nuclear Regulatory Commission 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50-400/RENEWED LICENSE NO. NPF-63 REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATIONS 05000400/2011302

Dear Mr. Widmann:

Enclosed is the post-examination package for the Reactor and Senior Reactor Operator Initial Examinations given at the Harris Nuclear Plant July 11, 2011, through July 20, 2011.

Included from the administration of the Written Examination are the student cover sheets, answer sheets, master examinations, an answer key, a log of applicant questions and answers, and the student seating chart. Also, pertaining to the RO Written Examination, are three post-examination comments (Question #26, #48 and #49).

If you have any questions regarding this submittal, please contact Mr. Simon Schwindt at (919) 362-3527.

Sincerely,

/cotty Scott Superintendent Operations Training Harris Nuclear Plant JMS/mgw Enclosures c: Mr. J. D. Austin (NRC Senior Resident Inspector, HNP) w/o Enclosures Mr. V. M. McCree (NRC Regional Administrator, Region II) w/o Enclosures Mrs. B. L. Mozafari (NRR Project Manager, HNP) w/o Enclosures Progress Energy Carolinas. Inc.

Hairis Nuclear Plant P. 0 Box 165 New Hill, NC 27562 L 26

Mr. Malcolm Widmann SERIAL: HNP-l 1-074 be: (w/o Enclosures)

Mr. D. L. Griffith Mr. M. G. Wallace Mr. W. D. Gunter Mr. S. Schwindt Mr. W. Jefferson, Jr. Mr. F. L. Womack Mr. E. J. Kapopoulos, Jr. Licensing File(s) (2 copies)

Mr. B. C. McCabe Nuclear Records Ms. T. M. Midgette

HNP Licensed Operator Written Exam question #26 Post Exam Comment Comment for question # 26 is both answers A and B are correct. In the HNP EOP users guide the bases for the 100°F/hr cooldown rate limit is stated as follows: EOPs that provide instructions for plant cooldown and depressurization to cold shutdown conditions limit the RCS cooldown rate to 100°F/hr consistent with the Tech Spec limits for Modes I 3. This basis confirms answer A is correct. The stem of the question states that an EPP-009 Post LOCA Cooldown and Depressurization is in progress. The bases document for EPP-009 (ES-I .2),

states that the maximum cooldown rate of 100°F/hr will preclude violation of the Integrity Status Tree thermal shock limits. FRP-P.1, RESPONSE TO IMMINENT PRESSURIZED THERMAL SHOCK, would be the procedure entered if the Integrity Status Tree limits were violated which would also make answer B Correct. Since the stem of the question did not specify whether the basis for the limit of 457°F at 0630 or the basis for the limit in EPP-009 was desired, either answer could be considered correct based on the reference used to answer the question. EPP 009 basis document was not referenced in the development of this question and this new technical information supports accepting both answers as correct.

Attached:

HNP Written Exam question # 26 EPP-009, Post LOCA Cooldown and Depressurization Rev 18 page 12 EOP Users Guide Rev 30 page 46 ES-i .2 HP-Rev 2 page 81