December 2014 - Shearon Harris Generic Fundamentals Examination Results
ML15013A523
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 01/08/2015
From: Gerald Mccoy
NRC/RGN-II/DRS/OLB
To: Griffith D
Duke Energy Progress
References
Download: ML15013A523 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 8, 2015 Duke Energy Progress, Inc.

ATTN: Mr. Donald L. Griffith Training Manager Harris Energy & Env. Center Shearon Harris Nuclear Power Plant P. O. Box 327, State Road 1127 New Hill, NC 27562-0165

SUBJECT:

SHEARON HARRIS - NRC GENERIC FUNDAMENTALS EXAMINATION RESULTS

Dear Mr. Griffith:

On December 10, 2014, the U.S. Nuclear Regulatory Commission (NRC) administered the generic fundamentals examination (GFE) of the written operator licensing examination to employees of your facility. Enclosed with this letter are copies of the final answer key, the grading results for your facility, and copies of individual answer sheets for each of your employees. Please forward the results to the individuals along with the copies of their respective answer sheets. A PASS in the RESULTS column indicates that the individual achieved a passing grade of 80 percent or better on the GFE, while a FAIL indicates that the individual failed the examination.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter without its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

If you have any questions concerning this examination, please contact me at (404) 997-4551.

Sincerely,

/RA/

Gerald J. McCoy, Chief Operations Branch 1 Division of Reactor Safety Docket No.: 50-400 License No.: NPF-63

Enclosures:

(See Page 2)

D. Griffith 2

Enclosures:

1. Final Answer Key
2. Examination Results Summary
3. Individual Answer Sheets cc w/o encls.:

Duke Energy Progress, Inc.

ATTN: Mr. Benjamin C. Waldrep Vice President Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165 Duke Energy Progress, Inc.

ATTN: Mr. John D. Dufner Plant General Manager Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

D. Griffith 2

Enclosures:

1. Final Answer Key
2. Examination Results Summary
3. Individual Answer Sheets cc w/o encls.:

Duke Energy Progress, Inc.

ATTN: Mr. Benjamin C. Waldrep Vice President Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165 Duke Energy Progress, Inc.

ATTN: Mr. John D. Dufner Plant General Manager Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165 LETTER W/O ENCLS X PUBLICLY AVAILABLE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER: ML15013A523 X SUNSI REVIEW COMPLETE OFFICE RII:DRS SIGNATURE GJM NAME GMCCOY DATE 1/ 8 /15 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL REORD COPY