HNP-17-061, Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses

From kanterella
Jump to navigation Jump to search

Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses
ML17201A035
Person / Time
Site: Harris Duke energy icon.png
Issue date: 07/20/2017
From: Bradley Jones
Duke Energy Progress
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
HNP-17-061
Download: ML17201A035 (3)


Text

Bentley K. Jones Director, Organizational Effectiveness Harris Nuclear Plant 5413 Shearon Harris Road New Hill, NC 27562-9300 10 CFR 50.90 July 20, 2017 Serial: HNP-17-061 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Shearon Harris Nuclear Power Plant, Unit 1 Docket No. 50-400/Renewed License No. NPF-63

Subject:

Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses

References:

1. Duke Energy letter, Shearon Harris Nuclear Power Plant, Unit 1, License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses, dated June 28, 2017 (Agencywide Document Access and Management System (ADAMS)

Accession No. ML17193B165).

2. Letter from S. Burns (NRC) to E. Ginsberg (NEI), dated July 14, 2010 (ADAMS Accession No. ML101960180)

Ladies and Gentlemen:

By letter dated June 28, 2017 (Reference 1), Duke Energy Progress, LLC (Duke Energy),

submitted a License Amendment Request (LAR) proposing changes to the Technical Specifications (TS) for the Shearon Harris Nuclear Power Plant, Unit 1 (HNP). The proposed amendment would modify the TS for fuel storage criticality to account for the use of Metamic neutron absorbing spent fuel pool rack inserts and soluble boron for the purpose of criticality control in the Boiling Water Reactor (BWR) storage racks that currently credit Boraflex.

Following the submittal of Reference 1, Duke Energy was notified of an issue with its reporting of the ADAMS Accession Number associated with Reference 2. The accession number provided in both the cover letter and Attachment 1 (Section 2.3) of Reference 1 was ML01960180. The correct ADAMS Accession Number for the referenced letter is ML101960180. Please utilize this corrected reference information in place of that in the original submittal.

The content of this supplemental correspondence does not change the No Significant Hazards Consideration provided in Reference 1.

No regulatory commitments are contained in this letter.

U.S. Nuclear Regulatory Commission Page 2 HNP-17-061 In accordance with 10 CFR 50.91(b), HNP is providing the state of North Carolina with a copy of this supplemental correspondence.

Should you have any questions regarding this submittal, please contact Jeffery Robertson, HNP Regulatory Affairs Manager, at (919) 362-3137.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on July , 2017.

Sincerely, Bentley K. Jones cc: J. Zeiler, NRC Sr. Resident Inspector, HNP W. L. Cox, III, Section Chief N.C. DHSR M. Barillas, NRC Project Manager, HNP C. Haney, NRC Regional Administrator, Region II