Inservice Inspection Report for Eleventh Refueling Outage
ML032130499
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 06/21/2003
From: Becker J
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DCL-03-074, OL-DPR-82
Download: ML032130499 (52)


Text

PacificGas and Electric Company James R.Becker Diablo Canyon Power Plant Vice President-Diablo Canyon PO. Box 56 Operations and Station Director Avila Beach, CA 93424 June 21, 2003 805.545.3462 Fax: 805.545.4234 PG&E Letter DCL-03-074 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-323, OL-DPR-82 Diablo Canyon Unit 2 Inservice Inspection Report for Unit 2 Eleventh Refueling Qutaae

Dear Commissioners and Staff:

In accordance with ASME Section Xl, paragraph IWA 6230, enclosed is the Diablo Canyon Inservice Inspection Report. This report provides the results of the Unit 2 eleventh refueling outage inservice inspections of Class I and 2 components and supports.

Sin rely, James R. ecker ddm/469/R0224756 cclenc: Thomas P. Gwynn David H. Jaffe David L. Prouix State of California, Pressure Vessel Unit cc: Diablo Distribution A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Calaway Comanche Peak

  • Diablo Canyon Palo Verde
  • Wolf Creek N

Enclosure PG&E Letter DCL-03-074 INSERVICE INSPECTION REPORT FOR DCPP UNIT 2 ELEVENTH REFUELING OUTAGE

Diablo Canyon Power Plant Unit 2 USNRC Docket No. 50-323 Operating License No. DPR-82 Commercial Operatio Date, March 13, 1986 Prepared By: _ I f ISI Specialists: Thomas L. Alcott, Terry G. Carraher, and Chris T. Beard Reviewed By:

Jame'El Hill, Lead ISI Specialist Approved By: i f T2> °,c, Patrick N6&nt, Manager NS SS Eng74 This report is submitted as required by ASME Boiler and Pressure Vessel Code,Section XI, to the United States Nuclear Regulatory Commission.

TABLE OF CONTENTS SECTION TITLE A. Introduction B. ASME Code Report Form NIS-1 (Basis of Summary)

1. Class 1
2. Class 2 C. Class 1 Components
1. Vessels
a. Reactor Vessel
b. Pressurizer
c. Steam Generators
2. Piping
3. Integral Attachments D. Class 2 Components
1. Vessels
a. Steam Generators
b. Heat Exchangers
2. Piping
3. Integral Attachments
4. Supports E. System Pressure Tests F. Preservice Inspection Items G. Repairs and Replacements
1. ASME Code Report Form NIS-2 (Indexed by System)

H. Containment Examinations

SECTION A INTRODUCTION

SECTION A INTRODUCTION Inservice inspection (ISI) of scheduled ASME Section XI Class I and 2 components and their supports at Pacific Gas and Electric Company's Diablo Canyon Power Plant (DCPP)

Unit 2 was completed during the eleventh refueling outage from February through March, 2003. The DCPP Unit 2 eleventh refueling outage (2RI 1) was the second outage in the second period within the second 10-year ISI interval.

In addition to the ASME Code examinations reported here, a 100% bare metal examination was conducted on the reactor vessel top head penetration nozzles. The reactor bottom head penetration nozzles also received a visual examination. No evidence of boric acid leakage was found. These examinations were reviewed by regional NRC staff, and results are on file at the plant site.

This report is submitted as required by ASME Section XI, paragraph IWA-6220, and is organized in several sections. An introduction is provided in Section A. Section B contains the completed ASME Code Report Form NIS-I for Class I and 2 components.

Sections C and D detail the Class I and 2 examinations performed, date of examination (for group items or for more than one type of examination performed, the date provided is the most recent examination date), any unusual conditions noted, corrective actions if required, and explanatory remarks.

System pressure tests on Class 1 and 2 systems conducted during the period following 2R10, and up to and including 2R1 1, are reported in Section E.

Preservice inspections were performed on certain components, as required after repairs or replacements. These items are detailed in Section F.

Section G of this report, Repairs and Replacements, contains the completed ASME Code Report Form NIS-2 for those 2R1 1 work packages closed prior to April 26, 2003 and for any pre-2RI 1 work packages closed after July 11, 2001. NIS-2 reports for 2R1 1 work packages that are closed after April 25, 2003 will be included in the next outage report.

Corrective actions and work order package documentation are on file at DCPP and are referenced by work order number in the NIS-2 reports.

Containment exams are reported in Section H.

SECTION B ASME CODE REPORT FORM NIS-1

FORM NIS-1 OWNER'S REPORT FOR INSERVICE INSPECTIONS As required by the Provisions of the ASME Code Rules

1. Owner Pacific Gas & Electric Company. 77 Beale St.. San Francisco, CA 94106
2. Plant Diablo Canyon Power Plant. P.O. Box 56. Avila Beach, CA 93424
3. Plant Unit Two 4. Owner Certificate of Authorization (if required) N/A
5. Commercial Service Date 03/13/86 6. National Board Number for Unit N/A
7. Component Inspected ASME Code Class I Items Component or Manufacturer or Installer Manufacturer or State or Province National Board Appurtenance Installer Serial No. No. No.

Reactor Vessel Combustion Engineering/ CE 68201 12962-85 21359 Westinghouse Steam Gen 2-1 Westinghouse 1161 N/A 68-89 Steam Gen 2-2 Westinghouse 1162 N/A 68-90 Steam Gen 2-3 Westinghouse 1163 N/A 68-91 Steam Gen 2-4 Westinghouse 1164 N/A 68-92 Pressurizer Westinghouse 1171 N/A 68-106 Class I Valves Various N/A N/A N/A Class I Supports Various N/A N/A N/A Class I Piping M.W. Kellogg/ Pullman N/A N/A N/A

4. 4. I Note: Supplemental sheets in form of lists, sketches, or drawings may be used pDvided (1) size is 8 /2 in. x 11 in., (2) information in items I through 6 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-I (back)

8. Examination Dates 02/03 to 03/03
9. Inspection Period Identification: Second
10. Inspection Interval Identification: Second
11. Applicable Edition of Section XI 1989 Addenda None
12. Date/Revision of Inspection Plan: December 2002. Revision 2
13. Abstract of Examinations and Tests. Include a list of examinations and tests and a statement concerning status of workrequired for current interval. Refer to 1SI Report
14. Abstract of Results of Examinations and Tests. Refer to ISI Report
15. Abstract of Corrective Measures. Refer to ISI Report We certify that a) the statements made in this report are correct, b) the examinations and tests meet the Inspection Plan as required by the ASME Code,Section XI, and, c) corrective measures taken conform to the rules of the ASME Code,Section XI.

Certificate of Authorization No. (if applicable) N/A Expiration Date N/A Date 6 1 /3 20 _ Signed Engineering ManagerBy S Owner Patrick Nugent/

CERTIFICATE OF INSERVICE INSPECTION 1,the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California and employed by H. S. B. . & 1. Co. of Harford. CT have inspected the components described in this Owners' Report during the period 2/03

_______to 3/03 . and state that to the best of my knowledge and belief, the Owner has performed examinations and tests and taken corrective measures described in this Owners' Report in accordance with the Inspection Plan and as required by the ASME Code,Section XI.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and tests, and corrective measures described in this Owners' Report.

Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.

Commissions CA 1828, NB 9990 A.N.I.C.

Insp r's Signature/Kenny Kim National Board, State, Province and, endorsements.

Date 9 20 (I

FORM NIS-1 OWNER'S REPORT FOR INSERVICE INSPECTIONS As required by the Provisions of the ASME Code Rules

1. Owner Pacific Gas & Electric Company. 77 Beale St.. San Francisco, CA 94106
2. Plant Diablo Canyon Power Plant, P.O. Box 56. Avila Beach, CA 93424
3. Plant Unit Two 4. Owner Certificate of Authorization (if required) N/A
5. Commercial Service Date 03/13/86 6. National Board Number for Unit N/A
7. Components Inspected ASME Code Class 2 Items Component or Manufacturer or Installer Manufacturer or State or Province National Board Installer Serial No. No. No.

Appurtenance Class 2 Piping Various N/A N/A N/A Supports Class 2 Piping M.W. Kellog/ Pullman N/A N/A N/A Power Steam Generator Westinghouse 1161 N/A 68-89 2-1 RHR Heat Engineers and Fabricators S-15588-C N/A 1112 Exchanger 2-1 Company Note: Supplemental sheets in form of lists, sketches, or drawings may be used, provided (1) size is 8 /2 in. x 11 in., (2) information in items I through 6 on this report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at thetop of this form.

FORM NIS-i (back)

8. Examination Dates 02/03 to 03/03
9. Inspection Period Identification: Second
10. Inspection Interval Identification: Second
11. Applicable Edition of Section XI 1989 Addenda None
12. Date/Revision of Inspection Plan: December 2002, Revision 2
13. Abstract of Examinations and Tests. Include a list of examinations and tests and a statement concerning status of work required for current interval. Refer to ISI Report
14. Abstract of Results of Examinations and Tests. Refer to ISI Report
15. Abstract of Corrective Measures. Refer to ISI Report We certify that a) the statements made in this report are correct, b) the examinations and tests meet the Inspection Plan as required by the ASME Code,Section XI, and, c) corrective measures taken conform to the rules of the ASME Code,Section XI.

Certificate of Authorization No. (if applicable) N/A Expiration Date N/A Date 6 (1 L 3 20 _ Signed Engineering Manager By Owner Patrick Nugent CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California and employed by H. S. B. . & 1.Co. of Harford. CT have inspected the components described in this Owners' Report during the period 2/03

_______to 3/03 . and state that to the best of my knowledge and belief, the Owner has performed examinations and tests and taken corrective measuresdescribed in this Owners' Report in accordance with the Inspection Plan and as required by the ASME Code,Section XI.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and tests, and corrective measures described in this Owners' Report.

Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this injection.

Ao c--7

-r f Commissions CA 1828. NB 9990 A.N.I.C.

nspectK Signature/Kenny Kim National Board, State, Province and, endorsements.

Date 9 f. 20 C 1/

SECTION C CLASS ONE COMPONENTS

PG&ED DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: REACTOR VESSEL (2Rll)

ASME SECTION XI SYSTEMS - CLASS I PAGE 1 of I CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS B-A B 1.22 Head Welds - RPV 2 1-205C UT 2-14-03

  • Acceptable In-Accordance-With IWB-3510 RI*

Meridional Closure Hd Head Welds - RPV 2 1-205D UT 2-14-03 NRI Meridional Closure Hd B1.40 Head to Flange RPV 2 6-205A MT 2-13-03 NRI Weld (1/3)

Head to Flange RPV 2 6-205A UT 2-14-03 68% Weld Coverage (Relief Request #NDE-5, NRI Weld (1/3) PGE Letter DCL-96-199)

B-G-2 B7.80 CRD Housings: RPV2 Part Length CRDM VT-1 2-21-03 NRI Bolts <2" diam K-4, 6 Bolts CRD Housings: RPV2 Part Length CRDM VT-1 2-21-03 NRI Bolts <2" diam F4, 6 Bolts

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: PRESSURIZER (2R1 1)

ASME SECTION XI SYSTEMS - CLASS 1 PAGE 1 of 1 CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS B-B B2. 11 Shell to Btm Head Pressurizer 2 Girth I UT 2-10-03 NRI Circ Weld (1/3)

B-H B8.20 Support Skirt Pressurizer 2 Girth 10 MT 2-9-03 50% Coverage (MT Performed on Surface Exam NRI Weld (1/3) Area A-B of IWB-2500- 13 AW Relief Request

  1. NDE-26, RI). See Below for remaining coverage.

Support Skirt Pressurizer 2 Girth 10 UT 2-10-03 50% Coverage (UT Performed on Surface Exam NRI Weld (1/3) Area C-D of IWB-2500-13 AW Relief Request

  1. NDE-26, RI). Completing 100% Coverage.

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT (2R11)

MAJOR ITEM: STEAM ASME SECTION XI SYSTEMS - CLASS I GENERATORS CAT STEAM GENERATOR TUBING PAGE I of 1 B16.20 The following percenta es apply to inservice tubes.

SCOPE PROBE TYPE SG 21 SG 22 SG 23 SG 24 Full length (except Rows Bobbin 100% 100% 100% 100%

I and 2 U-bends)

Rows 1 to 46 U-bends Plus Point 100% 100% 100% 100%

Repeat PWSCC Plus Point 100% 100% 100% 100%

indications at dents and top of tubesheet Hot Leg topf tubesheet Plus Point 100% 100% 100% 100%

Cold Leg top-of tubesheet Plus Point 20% 20% 20% 100%

> 5 volt dented TSP Plus Point 100% 100% 100% 100%

intersections

> 2 and < 5 volt dented Plus Point 20% at IH 100% at IH to 5H, 20% at 100% at IH to 3H, 20% at 100% at IH to 3H, 20% at TSP intersections (Note-I) 6H 4H 4H Distorted OD bobbin Plus Point 100% 100% of DOS greater than 100% of DOS greater than 100% of DOS greater than signals (DOS) at TSP 1.2 bobbin volts 1.2 bobbin volts 1.2 bobbin volts intersections Distorted ID bobbin Plus Point 100% 100% 100% 100%

signals (DIS) at TSP intersections

> 5 volt free span dings Plus Point 100% 100% 100% 100%

Baseline TSP ligament Plus Point 100% 100% 100% 100%

indications Tubes plugged . 29 91 10 10 Tubes unplugged NA 150 NA NA Note 1: For each 20% sample, inspected at least 50 dents, or else inspected 100% if there were less than 50 dents.

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: PIPING (2R11I ASME SECTION XI SYSTEMS - CLASS I PAGE I of 2 CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS B-J Pressurizer Surge *-16-14SPL WIB-434 UT 2-18-03 NRI Line Pressurizer Surge *-16-14SPL WIB-436 UT 2-12-03 NRI Line Pressurizer Surge *-16-14SPL Elbow From WIB- UT 2-12-03 NRI Line 436 to WIB-437 Charging Line S6-51-2SPL+ WIB-790 PT 2-13-03 NRI Aux Spray Boron Inj Tk Out S6-1992-1 /2 SPL+ WIB-564 PT 2-18-03 NRI Loop 2 Cold Boron Inj Tk Out S6-1992-1'/2 SPL+ WIB-563 PT 2-18-03 NRI Loop 2 Cold Boron Inj Tk Out S6-1993-1 V2 SPL+ WIB-660 PT 2-19-03 NRI Loop 3 Cold Boron Inj Tk Out S6-1993-1'/2 SPL+ WIB-659 PT 2-19-03 NRI Loop 3 Cold Boron Inj Tk Out S6-1994-1 '/2 SPL+ WIB-736 PT 2-19-03 NRI Loop 4 Cold Boron Inj Tk Out S6-1994-1 '/2 SPL+ WIB-735 PT 2-19-03 NRI Loop 4 Cold

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: PIPING (2R1 f ASME SECTION XI SYSTEMS - CLASS I PAGE 2 of 2 CATEGORY COMPONENT I WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS B-J Pressurizer PWR S6-1171-3SPL+ WIB-410 UT 2-18-03 NRI cont'd. RV PCV 474 Pressurizer RV S6-728-6SPL+ WIB-425 UT 2-18-03 NRI 8010B Inlet Accumulator S6-254-1OSPL+ WIB-168 UT 2-20-03 NRI Injection Loop 2

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: INTEGRAL (2R11) ATTACHMENTS ASME SECTION XI SYSTEMS - CLASS 1 PAGE 1 of I CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS B-K-I B10.10 HL Recirc bef 2V- 2S6-109-14SPL 72-20SL PT 2-18-03 NRI 8702: Weld. Att.

Accum. Injection 2S6-254-IOSPL 2-24V PT 2-20-03 NRI Lp 2: Weld. Att.

Pzr PRV 2PCV- 2S6-1172-3SPL 989-29R PT 2-18-03 NRI 455C: Weld. Att.

  • B10.20 RC Pump 2-1: RCP 2-1 Lug Weld No. I PT 2-19-03 NRI Welded Support Lug Attachment

SECTION D CLASS TWO COMPONENTS

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: STEAM GENERATORS (2R1 1)

ASME SECTION XI SYSTEMS - CLASS 2 PAGE 1 of 1 CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS C-A C1.10 Shell Circ. Welds Steam Generator Girth WI -4 UT 2-12-03 NRI 2-1

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: HEAT EXCHANGERS (2R11)

ASME SECTION XI SYSTEMS - CLASS 2 PAGE 1 of I CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS C-A CL.10 Shell Circ. Welds RHR Heat Girth Weld Item 21 PT 1-28-03 Surface examinations performed in-lieu of 100% NRI Exchanger 2-1 (Shell-to-Flange) volumetric as specified in Relief Request NDE# 17 C-B C2.21 Nozzles in Vessels RHR HX 2-1 to Inlet Nozzle-to-Shell PT 1-28-03 Surface examinations performed in-lieu of 100% NRI NozzleShell Weld 2S1-112-8 Weld Item 24 volumetric as specified in Relief Request NDE# 18

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: INTEGRAL (2R11) ATTACHMENTS ASME SECTION XI SYSTEMS - CLASS 2 PAGE 1 of I CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS C-C C3.20 SIG Stm Out 2-2: Line 2K15-227- 2025-15R MT 2-18-03 NRI Weld. Attachment 28V Attachment S/G Stm Out 2-2: Line 2K15-227- 2022-IV Attachment MT 2-14-03 NRI Weld. Attachment 28V Chg Pp 2-1 Disch: Line 2S6-45-4 23-35R Attachment PT 1-29-03 NRI Weld. Attachment Lugs Chg Pp 2-2 BP Line 2S6-1475-3 23-37R Attachment PT 1-29-03 NRI Sup: Weld. Att. Lugs

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: PIPING (2R11l)

ASME SECTION XI SYSTEMS - CLASS 2 PAGE 1 of 1 CATEGORY COMPONENT I WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS C-F-2 RC Pps Barrier K17-1357-6 WIC-1357B UT 2-10-03 NRI CCW Ret Hdr RC Pps Barrier K17-1357-6 WIC-1357C UT 2-10-03 NRI CCW Ret Hdr C-F-1 Cent Charg Pump S6-464 WIC-46A UT 1-29-03 NRI 2 Discharge Residual Ht Rem Si-1 13-8111 RB-1 13-4 UT 1-29-03 NRI Pp 2 Disch Residual Ht Rem SI-1 13-8111 RB-1 13-5 UT 1-29-03 NRI Pp 2 Disch

PG&E DIABLO CANYON SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT (2R11) MAJOR ITEM: SUPPORTS ASME SECTION XI SYSTEMS - CLASS 2 PAGE 1 of CATEGORY F-A SUPPORTS F1.10 TO F1.70 SUPPORT COMPONENTS The required inservice inspections were performed on 28 Class 2 hangers during the eleventh refueling outage between the dates of 02/06/03 and 02/16/03.

Results were found acceptable. Data reports are on file.

LINE SUPPORT LINE SUPPORT LINE SUPPORT LINE SUPPORT 53 23-43R 54 564-109 746 49-1 OR 1466 923-48 53 24-30A 54 564-155 746 49-113R 1466 923-61 53 414-621R 54 564-199 746 49-191R 1477 949-194 54 564-18 54 564-205 746 414-314R 2046 413-97A 54 564-25 54 1548-45 746 949-28R 54 564-33 54 2216-5 1357 7-29V 54 564-37 54 2216-19 1464 923-55 54 564-65 554 2048-15R 1464 923-91

SECTION E SYSTEM PRESSURE TESTS

PG&E DIABLO CANYON POWER PLANT -

UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT (2R11) MAJOR ITEM: PRESSURE TESTS ASME SECTION XI SYSTEMS - CLASS I & 2 PAGE 1 of 4 TEST CLASS DESCRIPTION EXAM COMMENTS NO. DATE RESULTS 1 1 Reactor Coolant System and Connected Piping 3/15/03 STP R-8A NRI 3 2 Auxiliary Feedwater Pump X- 1 Discharge 3/26/2003 NRI 4 2 RCS Loops I & 4 Hot Leg Sample Lines 3/15/2003 NRI 5 2 Pressurizer Sample Lines 3/15/2003 NRI 6 2 XS Ltdn HX & piping from 8167 to HCV-123 3/15/2003 NRI 7 2 RCP Hi Press Seal Water out & XS Ltdn HX outlet piping 3/15/2003 NRI 8 2 Charging Pumps Discharge Piping 3/26/2003 NRI 9 2 Recip Chg Pump & Disch Piping to 8475 4/11/2003 NRI 10 2 Alt Charging Between 8483, 8147 & 8379A 3/15/2003 NRI 11 2 Charging Injection 8803A & B to 8801A & B 2/20/2003 NRI

PG&E DIABLO CANYON POWER PLANT -

UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT (2R11) MAJOR ITEM: PRESSURE TESTS ASME SECTION XI SYSTEMS - CLASS I & 2 PAGE 2 of 4 TEST CLASS DESCRIPTION EXAM COMMENTS NO. DATE RESULTS 12 2 Charging Injection 8801A & B to 8820 3/15/2003 NRI 13 2 Charging Pumps & Suction Piping 1/31/2003 NRI 15 2 Boric Acid Pumps Disch Piping 3/15/2003 NRI 15A 2 Boric Acid Pumps Disch Piping Between 8104 and 8445 1/8/2003 NRI 16 2 Boric Acid Tanks to Pump Disch Iso Valves 3/15/2003 NRI 17 2 Accumulator Injection Loops 1-4, Sample Lines to 9352A-D, Test 3/15/2003 NRI

& Fill lines to 8878A-D 2 RWST & Supply to RHR, Cont Spray, SI, Refueling Wtr 19 3/10/2003 NRI Purification Pumps & Recirc Line to RHR HX 21 2 Safety Injection Pump Discharge to 8802A & B and Cold Legs 3/15/2003 NRI 22 2 Safety Injection Pumps Discharge to Hot Legs from 8802A & B to 8904A-D 3/15/2003 NRI

SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT (2R11) MAJOR ITEM: PRESSURE TESTS ASME SECTION XI SYSTEMS - CLASS 1 & 2 PAGE 3 of 4 TEST CLASS DESCRIPTION EXAM COMMENTS NO. DATE RESULTS NRI 23 2 RHR Pumps and Discharge Piping 3/10/2003 NRI 24 2 RHR Hot Leg injection from 8703 to 8740A & B 3/15/2003 NRI 25 2 Spray Additive Tank and Unisolable piping 2/5/2003 30 2 CCW Supply & Return to Cont Fan Coolers, RCPs and XS 1/16/2003 NRI Letdown Heat Exchanger NRI 31 2 Steam Generator Nitrogen Supply 2/8/2003 NRI 34 2 PZR Relief Tank Nitrogen Supply (pen 52) 2/8/2003 NRI 35 2 Primary Water Supply to PZR Relief Tank (pen 52) 2/8/2003 36 2 Accumulator Tanks N2 Supply Header. (pen 51) 2/11/2003 NRI 37 2 Accumulators Sample Header 3/15/2003 38 2 Fuel Transfer Tube to Refueling Canal 2/17/2003

SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT (2RI 1) MAJOR ITEM: PRESSURE TESTS ASME SECTION XI SYSTEMS - CLASS 1 & 2 PAGE 4 of 4 TEST CLASS DESCRIPTION EXAM COMMENTS NO. DATE RESULTS 39 2 Auxiliary Steam Containment Penetration 2/10/2003 NRI 40 2 Firewater Supply Before Containment (pen 79) 3/4/2003 NRI 41 2 Refueling Canal Water Inlet (pen 46) 2/25/2003 NRI 42 2 Reactor Coolant Drain Tank N2 Sup. (pen 52) 2/8/2003 NRI 43 2 Reactor Coolant Drain Pumps Disch Header. (pen 50) 2/27/2003 NRI 44 2 Inside Cont Inst Air Supply Header. (pen 54) 2/11/2003 NRI 45 2 Service Air (pen 56) 2/8/2003 NRI

SECTION F PRESERVICE INSPECTION ITEMS

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: PSI (2R11)

ASME SECTION XI SYSTEMS - CLASS 1 & 2 PRESERVICE INSPECTION ITEMS PAGE 1 of 1 CATEGORY COMPONENT f WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS B-G-2 B7.70 Safety Inj Lp I S6-235-6SPL+ 2V-8949A: VT-I 8-14-02 NRI HL: Bolts <2" 12 Studs & Nuts diameter B7.70 Safety Inj Lp 1 S6-235-6SPL+ 2V-8949B: VT-I 1-23-03 HL: Bolts <2" NRI 12 Studs & Nuts diameter B7.70 Safety Inj Lp I S6-235-6SPL+ 2V-8949C: VT-I 1-23-03 HL: Bolts <2" NRI 12 Studs & Nuts diameter Aug RCP Flywheel RCP 2-1 RCP Flywheel UT 2-18-03 Augmented - following replacement NRI

PG&E DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, FIRST REFUELING OUTAGE REPORT MAJOR ITEM: PSI SUPPORTS (2R10)

ASME SECTION XI SYSTEMS - CLASS 1 & 2 PRESERVICE INSPECTION ITEMS PAGE 1 of 1 CATEGORY FA SUPPORTS F1.10 TO F1.70 SUPPORT COMPONENTS The required pre-service inspections were performed on 8 supports duringthe eleventh refueling outage. Results were acceptable.

SUPPORT LINE 7-4V 255 412-143SL 1171 75-15SL 223 78-520SL 56 23-67R 2994 Support Structure RCP 2-4 78-419SL 57 UBOC Support RCP 2-2

SECTION G REPAIRS AND REPLACEMENTS

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Feedwater System (03)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASME Name of Name of Manufactures Nat'l Work Order Other Year Repaired i Coe Component Manufacture Serial No. bd. No No. Ldne No LnNoReplacement Built Replaced, or 2 Stamped (Yes or

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ~

No )

FW-2-369 Weston N/F N/A C0172541 569 N/A Replaced (3) 0 No FW-2-533 Rockwell 456065 N/A CO 176118 By-Pass N/A Replaced (4) _ Yes FW-2-370 Anchor Darling N/F N/A C0l 82321 575 N/A Replaced (4) _ No FW-2-377 Anchor Darling N/F N/A C0182368 569 N/A Replaced (4) 0 No

7. Description of Work (3) Replaced Valve Internals (4) Replaced Valve
8. Tests Conducted: Hydrostatic El Pneumatic Z NominalOperatingPressure El Other Pressure PSIG Test Temp. OF

°_ 0DPressure Test Conducted IAW Code Case N-416-1

9. Remarks CERTIFICATE OF COMPLIANCE We certify' that the statements made j'is report are cvrrecA this Replacement comforms to Sectipn)51 of the ASME Code. Signed \ 21~S Engineering Manager 6 /lO S (Owner or Owner's Designee)-- Patick Nugent/ (Title) (Date)

CERTIFICATE OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & 1.Co. of Hartford, CT have inspected the Replacement described in this Report on { -6 , 200e3 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any person]jjury or propert damage or loss of any kind arising from or connected with this inspection.

%.0---7 ;k _li Inspector 6lg , 42c 3 Commissions CA 1828- NB 9990 A.N.I.C

/Kenny'D. Kim (Title) ' (Date) (State or Province, National Board)

Note: Supflemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 1/2 x II in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Feedwater System (03)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.
7. Description of Work (17) Modified Suppport
8. Tests Conducted: Hydrostatic E] Pneumatic al Nominal Operating Pressure E] Other Pressure PSIG Test Temp. OF El Pressure Test Conducted IAW Code Case N 416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are corret A this Replacement comforms to Section I of the ASME Code. Signed , c& o Engineering Manager 6 x (Owner or Owner's Designee) Patrick Nuge (Title) (Date)

CERTI CATE OF INSPECTION I, the undersigned, holding a valid commission issued by e National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on , 2003 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personajnjury or prop rty damage or loss of any kind arising from or connected with this inspection.

17 e..j Inspector Mg6, 2D 3 Commissions CA 1828 - NB 9990 A.N.I.C

/ Kenny`D. Kim (Title) 6' (Date) (State or Province, National Board)

Note: Su plemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 1/2 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of 2
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Turbine Steam Supply System (04)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

_ ASME Name Of Name of Manufactures Nat'l Work Order Other Year Repaired Code Component Manufacture ..

SNrial No No. Ident. Built Replaced, or 2 Stamped No. Line No Replacement r (Yes or

_ _ _ _ _ _ __ _ __ __ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ~N o)

MS-2-2056 Flowserve Corp N/F N/A C018 1569 1041 N/A Replaced (4) _ No MS-2-PCV-22 Copes-Vulcan N/F N/A C0 173293 1066 N/A Replaced (3) (5) 0 No MS-2-PCV-21 Copes-Vulcan N/F N/A C0 173650 1065 N/A Replaced (3) (5) D No MS-2-PCV-19 Copes-Vulcan N/F N/A C0174252 228 N/A Replaced (6) 0 No MS-2-PCV-20 Copes-Vulcan N/F N/A C0 174253 227 N/A Replaced (6) D No

7. Description of Work (3) Replaced Valve Internals (4) Replaced Valve (5) Replaced Bonnet Bolting (6 )Replaced Flange Bolting
8. Tests Conducted: Hydrostatic El Pneumatic 0 Nominal OperatingPressure El Other Pressure PSIG Test Temp. OF

°_ 0 Pressure Test Conducted IAW Code Case N-416-1

9. Remarks CERTIFICATE OF COMPLIANCE of the ASME Code. Signed (Owner or Owner's Designee) 9)

We certify that the statements made in this report ar corrpict>apd this iA) & t Patrick NugentJ i $

CERTIFICATE OF INSPECTION Repair / Replacement Engineering Manager (Title) comforms to Section 0 l6'//

4 (Datel

-2 I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Repair / Replacement described in this Report on 6 -' 20d 3 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persoralpjuiy or pror damage or loss of any kind arising from or connected with this inspection.

j( jury opo ama Inspector 6..d

, o 3 Commissions CA 1828 - NB 9990 A.N.I.C Kenny D. Kim (Title) t/(Date) (State or Province, National Board)

Note: Spplemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 12 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet 2 of 2
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Turbine Steam Supply System (04)
5. (a) Applicable Construction Code See Work Order 19 _ Edition Addenda. Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

Manufacture Other Repaired - u ASME Name of Name of Manufacture Nat'l Work Order Year R i Code Component Component Manufacture Manufacture Serial No. bd. No No. Ident.

Line No Built Replaced, Replacement or W Stamped Staed ro MS-2-FCV-95 Velan Valves N/F N/A C0174399 593 N/A Replaced (5) 0 No MS-2-PCV-20 Copes-Vulcan N/F N/A C0 174428 227 N/A Replaced (6) 0 No MS-2-3056 FlowServe N/F N/A C0178044 1042 N/A Replaced (5) 0 No MS-2-3056 FlowServe N/F N/A C0178103 1042 N/A Replaced (4) - No MS-2-3056 FlowServe N/F N/A C0178697 1042 N/A Replaced (5) O No MS-2-FCV-43 Schuttle and N690556 N/A C0 181324 226 N/A Repaired (20) 0 No Koerting N690556 N/A C 4.a 2 MS-2-FCV-43 Schuttle and N690556 N/A C0181364 226 N/A Repaired (21) 0 No Koerting _ _ _ _ _ _

MS-2-FCV-43 Schuttle and N690556 N/A ROI159027 226 N/A Replaced (5) 0 No K oerting__ _ __ _ _ __ _ _ _ _ _ __ _ _ _

MS-2-FCV-37 Velan Valves N/F N/A C0178183 593 N/A Replaced (5) 0 Yes MS-2-RV-9 Dresser BN1749 N/A C0 180606 227 N/A Replaced (6) 0 No MS-2-RV-10 Dresser BN1453 N/A C0 180609 227 N/A Replaced (6) O No 0

0

7. Remarks (Applicable Manufacturer's Data Reports to be Attached)

(20) Weld Repair (Anti-Rotation Pin Hole In Disc and Taillink)

(21) Machining (Disc and Taillink)

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Turbine Steam Supply System (04)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

IC ASME Manufactures Other Year Repaired i Code Component Manufacture Serial Wd. No.

Nameor Name of bd. No No No.o.Line Ident.

No Built Replaced, Replacementor a Stamped (Yes or No)49-20R PG&E N/A N/A C0181569 1041 N/A Replaced (18) 0 No 413-422R PG&E N/A N/A C0178103 1042 N/A Replaced (19) a No

7. Description of Work (18) Install Splice Plates (9) Removed Reinstalled Parts By Welding
8. Tests Conducted: Hydrostatic El Pneumatic El NominalOperatingPressure Other Pressure PSIG Test Temp. _ _ OF El Pressure Test Conducted JAW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are th Replacement comforms to Section XI of the ASME Code. Signed FM o S .4er Engineering Manager C.1 /03 (Owner or Owner's Designee) -Patrick Nugent - (Title) (Date )

CERTIFIC E OF INSPECTION 1,the undersigned, holding a valid commission issued by the Na~ nal Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed / H.S.B.I. & I. Co. of Hartford, CT have inspected the Repl~aement described in this Report on /'- , 20 03 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persona i jury or prop-rp damage or loss of any kind arising from or connected with this inspection.

4 Inspector Ae 6 z-oo3 Commissions CA 1828 - NB 9990 A.N.I.C

/ Kenny D. Kim (Title) G/ (Date) (State or Province, National Board)

Note: Spplemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 1/2 x I I in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet 1 of 2
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Reactor Coolant System (07)
5. (a) Applicable Construction Code (See Work Order) 19 Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

IV ASME Name of Name of Manufactures Nat'l Work Order Other Year Repaired i Code Component ComponentManufacture Manufacture Serial No. bd.

No.No No. Ident.

Line No Built Replaced, or Replacement 2 Stamped Wi(es or No)

RCS-2-8000A Velan Valve N/F N/A CO 178091 1171 Unk Replaced (5) 0 Yes RCS-2-8000B Velan Valve N/F N/A C0178092 1172 Unk Replaced (5) 0 Yes RCS-2-8000C Velan Valve N/F N/A C0178093 1195 Unk Replaced (5) 0 Yes RCS-2-RV-801 OA Crosby U2C N/A R0222938 729 1998 Replaced (4) 0 Yes RCS-2-RV-801 OB Crosby UlB N/A R0223172 728 1998 Replaced (4) 0 Yes

7. Description of Work (5) Replaced Bonnet Bolting (4) Replaced Valve
8. Tests Conducted: Hydrostatic 5 Pneumatic 0 Nominal OperatingPressure 5 Other Pressure PSIG Test Temp. OF 0 Pressure Test Conducted IAW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report ar con t d this Replacement comforms to Section XI of the ASME Code. Signed i st z ' ,, Engineering Manager i. /y/ lo3 (Owner or Owner's Designee) Patrick Nugepf (Title) (Date)

CERTIFICATE OF INSPECTION 1,the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & 1.Co. of Hartford, CT have inspected the Replacement descbed inthisReporton , 2003 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal nwry or proppry damage or loss of any kind arising from or connected with this inspection.

Inspector 1 2ae3 N-

- Commissions CA 1828- NB 9990 A.N.I.C

/Kenny D. Kim (Title) (/ (Date) (State or Province, National Board)

Note: Supflemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 1/2 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet 2 of 2
2. Plant Diablo Canyon Power Plant .

Unit 2 P.O. Box 56, Avila Beach, CA 93424 .

3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Reactor Coolant System (07)
5. (a) Applicable Construction Code See Work Order 19 Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

Manufacture OtherReardAM Name of Name of Nat'l Work Order Year -e ASME CodRepaired Component Manufacture Serial bd. No No. Ident. Bul.t Replaced, or St(Ye d No. Line No Bul Replacement (cstampNod RCS-2-RV-8010C Crosby UIC N/A R0222933 727 1998 Replaced (4) Yes

7. R_em_ark

_ s_

X__

(Aplicbl

_ Manufacturer' Dat to

_ be Attached)

Th O5

-5Th _ _

- 5~~~~~~~~~

_ _ _ _ _ _ _ _ -5 _ _ _ ~

_~

_ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ -5 _ _ _ _~~~~~~~~~

_ _ _ -5 _ _ _ _~~~~~~~~~

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -5 _ _ _ _~~~~~~~~~

7. Remarks (Applicable Manufacturer's Data Reports to be Attached)

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Reactor Coolant System (07)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASME Name of Name of Manufactures Nat'l Work Order Year -

Repaired Code Component Manufacture No. W.No.No. Ident.

Line No Built Replaced, or 4 ' Stamped

~~~~~~~~~Replacement (Yes or Serial bd.No.No Line No ~~~~~ ~~ ~

412-143SL Pacific 9098 N/A C0178275 1171 N/A Replaced (10) 0 No

__ __ __ _ _ _ _ _ _ _ _ Sci en t i f i c _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

RCP 2-4 Support Westinghouse N/F N/A C0181255 RCP 2-4 N/A Replaced (17) 0 No

7. Description of Work (10) Replaced Snubber (17) Modified Suppport
8. Tests Conducted: Hydrostatic n Pneumatic E Nominal Operating Pressure a Other Pressure PSIG Test Temp. _ F C] Pressure Test Conducted AW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are c d this Replacement comforms to Section I I of the ASME Code. Signed I2LY7 5 4 0F Engineering Manager 6 6 Iv (Owner or Owner's Designee) ' Patrick Nugent (Title) (Date)

CERTIFICATE OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. o. of Hartford, CT have inspected the Replacement described in this Report on 6-4 ,20 c5 3 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any perso al injury or ro erty damage or loss of any kind arising from or connected with this inspection.

ifEm

):WA-A Inspector (, Ze53 Commissions CA 1828 - NB 9990 A.N.I.C

/ Kenny D.Kim (Title) ( (Date) (State or Province, National Board)

Note: S pplemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 12 x 1 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Chemical and Volume Control System (08)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

_~~~~~~~~~~~~~~~~~~~~~~~

Name O Name of M tanufactures Nat'l Work Order Other Year Repaired q Code Component Name of Manufacture Name of SNrial erial W.No bd. NoNNo No. Ident.

Line No Built Replaced, or Replacement  ; Stamped (Yes or

_ _ _ _ _ _ __ _ _ _ __ __ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ~No)

Centrifugal Pacific Pumps 49189 N/A C0174767 CCP 2-1 N/A Repaired (13) 0 No Charging Pum 2-1__ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Centrifugal Pacific Pumps 49189 N/A C0174848 CCP 2-1 N/A Repaired (15) 0 No Charging Pum p 2-1__ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

CVCS-2-8378A Velan Valves N/F N/A C0179109 50 N/A Replaced (3) 0 Yes

7. Description of Work (3) Replaced Valve Internals (13) Weld Build-Up (15) Machined Seal Housing
8. Tests Conducted: Hydrostatic a Pneumatic El Nominal Operating Pressure a Other Pressure PSIG Test Temp. _F M Pressure Test Conducted AW Code Case N416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made i is report are coyxee and this Repair / Replacement comforms to Sect on of the ASME Code. Signed (Owner or Owner's Designee) -

\ 4  ;  ?

Patrick Nuge9$

Engineering Manager (Title)

G/6 1 a3 I (Date]I CERTIFICATE OF INSPECTION 1, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & 1.Co. of Hartford, CT have inspected the Repair / Replacement described in this Report on S , 20 o 3 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal- ry or rope damage or loss of any kind arising from or connected with this inspection.

K5Z__7 Inspector ,4 , 3 Commissions CA 1828 - NB 9990 A.N.I.C J enny D Kim (Title) / (Date) (State or Province, National Board)

Note: Suppfemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 12 x 11 in., (2) information in items 1 through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Chemical and Volume Control System (08)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-41 6-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASME Name of Name of Manufactures at'l Work Order Other Year Repaired Code Component Manufacture Serial aNo Nor Ident. Built Replaced, or si Stamped No. ~~~~~~~~Line No Replacement (Yes or

__________ ~~~~~~~

78-419SL Anchor Darling 115 NIA C0178251 57 N/A Replaced (I0) E Yes78-520SL Anchor Darling 147 N/A C0178255 56 N/A Replaced (10) 0 Yes

__ __ __ __ __ __ __ __ __ _ 0

7. Description of Work (10) Replaced Snubber
8. Tests Conducted: Hydrostatic E1 Pneumatic El NominalOperatingPressure El Other Pressure PSIG Test Temp. _ _ 'F El Pressure Test Conducted lAW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are corre this Replacement comforms to Sectio XI of the ASME Code. Signed Engineering Manager C> t )

(Owner or Owner's Designee) Patrick Nugent (Title) (Date)

CERTIFICTE OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on I-, ,20 03 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal i or properly d age or loss of any kind arising from or connected with this inspection.

tA , Inspector 9 A, 2A=3 Commissions CA 1828 -NB 9990 A.N.I.C nnyD.Kim (Title) _ (Date) (State or Province, National Board)

Note: Supplemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 1/2 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Safety Injection System (09)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASME Name of Name of Manufactures Ntl Work Order Other Year Repaired M Code Component Manufacture oSerial Nat o Ident. Built Replaced, or l Stamped SeNlod.N o Line No Replacement (Yes or No)

SI-2-8949A Velan Valves N/F N/A C0176755 235 N/A Replaced (5) 0 No SI-2-8949B Velan Valves N/F N/A C0176756 236 N/A Replaced (5) 0 No SI-2-8949C Velan Valves N/F N/A C0176757 237 N/A Replaced (5) 0 No SI-2-214 Contromatics N/F N/A C0179417 3136 N/A Replaced (7) E No

7. Description of Work (5) Replaced Bonnet Bolting (7) Extended ISI Boundary
8. Tests Conducted: Hydrostatic [l Pneumatic El NominalOperatingPressure 5 Other Pressure PSIG Test Temp. _ _ OF 5 Pressure Test Conducted IAW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are correct adhis Replacement comforms to Section4I of the ASME Code. Signed (Owner or Owner's Designee)

I t6&$ ,

Patrick Nugen',

.4 a, Engineering Manager (Title)

L/,

(Date)

CERTIFICATE OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on -4 ,2003 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any person jury or prope damage or loss of any kind arising from or connected with this inspection.

10' G4O 5 Inspector A .Ao aZcs3 Commissions CA 1828 - NB 9990 A.N.I.C Kenny D. Kim (Title) 1 (Date) (State or Province, National Board)

Note: S plemental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 2 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet 1 of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Safety Injection System (09)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

'~ASME Nameof Nameof Manufactures Na' okOdr Other Year Repaired Code Component Name ofManufacture Nol W. N W Nor IdentNo Line l Built Replaced, Replacement or Stamped (Yes or Name of erial bd.NoNNo

_ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ~~~) ~ ~ ~ ~~N 7-4V PG&E N/A N/A C0181210 255 N/A Replaced (17) 0 No 75-15SL Anchor Darling 61 N/A C0178262 223 N/A Replaced (10) 0 Yes

7. Description of Work (10) Replaced Snubber (17) Modified Suppport S. Tests Conducted: Hydrostatic El Pneumatic El Nominal OperatingPressure al Other Pressure PSIG Test Temp. _ _ 'F n Pressure Test Conducted lAW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made intIis report are orr d this Replacement comforms to Sectio XI of the ASME Code. Signed -' LA 5 B Engineering Manager 'l l (Owner or Owner's Designee) Patrick Nugent (Title) (Dat/

CERTIFI TE OF INSPECTION I, the undersigned, holding a valid commission issued by the N ional Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed y H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on -' , 20 03 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any or propertydage or loss of any kind arising from or connected with this inspection.

frszn personal in 4,,, AX;9~

eny D. Kim Inspector (Title) h6w

~2&5 (Date)

Commissions CA 1828 - NB 9990 A.N.I.C (State or Province, National Board)

Note: Suppl nental sheets in the form of lists, sketches, or drawings may be used provided (I) size is 8 1/2 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26,2003 77 Beale Street, San Francisco, CA 94106 Sheet 1 of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Residual Heat Removal System (10)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-41 6-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASME Nameof Nameof ~ Manufactures Na' okOdr Other Year Repaired Code Component Name ofManufacture Nameof SNo Se~~~~Naob.o No oro Ideno Line No Built Replaced, or Replacement li Stamped (YNo)

RHR-2-RV-8707 Crosby RV-1-8707- N/A R0223078 1167 N/A Replaced (4) _ Yes

7. Description of Work (4) Replaced Valve
8. Tests Conducted: Hydrostatic [1 Pneumatic 0 NominalOperatingPressure 2 Other Pressure PSIG Test Temp. _ F 0 Pressure Test Conducted IAW Code Case NA416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are correct and this Replacement comforms to Sectio XI of the ASME Code. Signed Engineering Manager L, /oS (Owner or Owner's Designee) Patrick Ny6ent (Title) (Date)

CERTIFICATE OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on I A , 20e'3 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injtpr property Ymge or loss of any kind arising from or connected with this inspection.

Inspector A, . -- 3 Commissions CA 1828 - NB 9990 A.N.I.C Keyy D. KIm (Title) M (Date) (State or Province, National Board)

Note: Suppleaiental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 12 x 11 in., (2) information in items 1 through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Containment Spray System (12)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N.416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASME Nameof Nameof Manufactures Nat'l Work Order Other Year Repaired Code Component Manufacture No. No. bd. No No. Ident.

~~~~~~~~Line No Built Replaced, or Replacement '~(Yes Stamped or

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ~~~~~~

Containment Spray Goulds Pumps 221 B 174-2 N/A CO 181144 N/A N/A Replaced (8) 0 No P u mp 2 -2 In c. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

CS-2-RV-931 ACF IND N/F N/A R0223097 N/A N/A Replaced (4) 0 No CS-2-RV-930 ACF ND N/F N/A R0223098 N/A N/A Replaced (4) - No

7. Description of Work (4) Replaced Valve (8) Replaced Gland Plate Bolting
8. Tests Conducted: Hydrostatic E] Pneumatic 0 Nominal Operating Pressure I Other Pressure PSIG Test Temp. _ _ OF 10 Pressure Test Conducted IAW Code Case N416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are coreA and this Replacement comforms to Sectjon WI of the ASME Code. Signed (Owner or Owner's Designee)

'SLWJ*.k=,

Patrick Nufent

.4 Engineering Manager (Title) 6 /

(Date)

CERTIFICATE OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on i -,9 20 __

and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injugppropertydajnage or loss of any kind arising from or connected with this inspection.

C-, A5~z~ Inspector 01 d, 2 3 Commissions CA 1828-NB9990 A.N.I.C Kyi(y D. Kim (Title) // (Date) (State or Province, National Board)

Note: Suppleniental sheets in the form of lists, sketches, or drawings maey be used provided (1) size is 8 12 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet 1 of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Component Cooling Water System (14)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASNIE Name of Name of Manufactures Nat'l Wh Oder ther Year Repaired - Code Component Manufacture No. atld.

No No. Ident Built Replaced, or i Stamped No. ~~~~~~~~Line No Replacement (Yes or

_ _ _ _ __ __ _ _ _ _ _ _ _ _ _ _ _ _ ~~~~~~

414-258BSL Pacific 13637 N/A C0178277 321 N/A Replaced (10) a Yes

7. Description of Work I~~~~~~~~~~~~~~~~~~~~~~~

(10) Replaced Snubber DI

8. Tests Conducted: Hydrostatic [] Pneumatic a NominalOperatingPressure [I Other Pressure PSIG Test Temp. _ F El Pressure Test Conducted IAW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in is report are crrect 3 is Replacement comforms to Secton I of the ASME Code. Signed Engineering Manager l C, 6 o >

(Owner or Owner's Designee) Patrick Nugent (Title) (Date)

CERTIFICATC OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on 6- , 20 03 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal inju r property age or loss of any kind arising from or connected with this inspection.

e Inspector 4As.s 3' Commissions CA 1828 - NB 9990 A.N.I.C K9ny D.Kim (Title) 4Date) (State or Province, National Board)

Note: Supple ental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 12 x 1 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 23, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Liquid Radwaste System (19)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-416-1
6. Identification of components Repaired or Replaced, and Replacement Components.

IV ASME Name of Name of Manufactures Nat'l Work Order Other Year Repaired Code Component Manufacture No. W. Noo No. Ident. t Built Replaced, or 9 Stamped Noia.d o Line No Replacement (Yes or

__ _ __ _ __ _ _ _ _ _ _ _ ~~~~~~N Pacific 72-38SL Scientific 7829 N/A C0181507 3729 1976 Replaced (10) 0 Yes

-0

_ _ __ _ _ _ _ __ _ _ _ _ _ _ _ _ -fl

7. Description of Work (10) Replaced Snubber
8. Tests Conducted: Hydrostatic El Pneumatic El Nominal Operating Pressure [l Other Pressure PSIG Test Temp. _F Pressure Test Conducted 1AW Code Case N4 16-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are orrec this Replacement comforms to SectionXI of the ASME Code. Signed 5 P Engineering Manager 6 l) do b (Owner or Owner's Designee) Patrick Nugent (Title) (Date)

CERTIFIC rE OF INSPECTION 1, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & 1.Co. of Hartford, CT have inspected the Replacement described in this Report on /, -, , 20 03 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury, or propertyjia nage or loss of any kind arising from or connected with this inspection.

A~t Inspector 6, 3 2ea Commissions CA 1828 - NB 9990 A.N.I.C Kejyy D. im (Title) / (Date) (State or Province, National Board)

Note: Supplenrental sheets in the form of lists, sketches, or drawings may be used provided (1) size is 8 12 x I l in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

FORM NIS-2 OWNER'S REPORT OF REPAIR OR REPLACEMENT As Required by the Provisions of ASME Code Section XI

1. Owner Pacific Gas and Electric Company Date April 26, 2003 77 Beale Street, San Francisco, CA 94106 Sheet I of I
2. Plant Diablo Canyon Power Plant Unit 2 P.O. Box 56, Avila Beach, CA 93424
3. Work Performed by Owner See Above Repair Org. P.O. No., Job No., etc.
4. Identification of System Vent and Air Conditioning System (23)
5. (a) Applicable Construction Code (See Work Order) 19 _ Edition Addenda, Code Cases N/A (b) Applicable Edition of Section XI Utilized for Repairs or Replacements - 1989, No Addenda, Code Case N-41 6-1
6. Identification of components Repaired or Replaced, and Replacement Components.

ASME Nameof Namoen ofufctr Nameof Manufactures Serial Nat'l bd. No Work Order N.Ident.

Other Year Built Repaired Replaced, or I Code Stamped Component Manufacture No. No Line No Replacement 2 (Yes or No)

VAC-2-FCV-662 Fisher Controls 162028 N/A CO1 81801 647 N/A Replaced (3) 0 No

7. Description of Work (3) Replaced Valve Internals
8. Tests Conducted: Hydrostatic El Pneumatic El Nominal Operating Pressure Other Pressure PSIG Test Temp. _ _ 'F E] Pressure Test Conducted 1AW Code Case N-416-1
9. Remarks CERTIFICATE OF COMPLIANCE We certify that the statements made in this report are corchand this Replacement comforms to Section XI of the ASME Code. Signed  ; Z O f)t Engineering Manager 4A/c-l (Owner or Owner's Designee) Patrick Nug;At (Title) (Date)

CERTIFICATE OF INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of California, employed by H.S.B.I. & I. Co. of Hartford, CT have inspected the Replacement described in this Report on * - , 2003 and state that to the best of my knowledge and belief, this repair or replacement has been constructed in accordance with Section XI of the ASME Code. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair or replacement described in this Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury r property dage or loss of any kind arising from or connected with this inspection.

,inuZ 24r Y o Inspector 3 btt 6; zoz3 Commissions CA 1828 - NB 9990 A.N.I.C Keiy D. Ki'm (Title) 4Date) (State or Province, National Board)

Note: Supplemntal sheets in the form of lists, sketches, or drawings may be used provided () size is 8 12 x 11 in., (2) information in items I through 4 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.

SECTION H CONTAINMENT EXAMINATIONS

PG&ED DIABLO CANYON POWER PLANT - UNIT 2 SECOND INTERVAL, SECOND PERIOD, SECOND REFUELING OUTAGE REPORT MAJOR ITEM: CONTAINMENT EXAMINATIONS (2R11)

CONTAINMENT EXAMS (LINER)

PAGE 2 of 2 CATEGORY COMPONENT / WELD OR EXAM EXAM ITEM DESCRIPTION LINE COMPONENT NO. TYPE DATE COMMENTS RESULTS E-A El. 11 Containment Liner Liner General 2-25-03 NRI E-C E4.11 Containment Liner RHR Sump Visible Surfaces of VT-I 2-17-03

  • AR A0575603 Chipped paint - Maintenance NRI*

Aug. Areas (1/3) work order R0222090 repaired chipped area. No material degradation.

E4.12 Containment Liner RHR Sump Surface Area Grid UT 2-17-03 NRI E-G E8.10 Containment Liner Bolted Pen #58 (Mini VT-1 2-19-03 Connections NRI Equipment) (1/3)

Pen #60 (Mini VT-1 2-19-03 NRI Equipment) (1/3)